[2025] VCAT 976
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-10-31
Gillard J
Original judgment source is linked above.
(a) the drafting of Mrs Troise's third witness statement and the discovery of the documents referred to in that witness statement; and
(b) certain costs associated with the evidence of Mr Schmiedel.
(a) Rectification of the Defects: $443,811.00.
(b) Rectification of the vandalism: $46,457.00.
(c) Re-establishment of the boundary: $1,360.00.
(d) Liquidated Damages: $43,821.43.
(e) Credits: $18,897.50.
(f) Loss of rent: $82,800.00.
(g) Other expenses (in the sum of $12,486.16):
Tony Croucher & Associates Invoice dated 0725 21 May: $1,540.00
Inspect Reports Invoice Troise-01 dated 21 September 2020: $2,367.75
Quick Report Invoice dated 21 September 2020: $2,475.00
Vandalism Report Invoice 1266 dated 22 July 2021: $1,155.00
Skills Report Invoice 1274 dated 24 August 2021: $2,994.53
Temporary Fencing (City Wide Invoice) dated 14 May 2021: $1,132.56
On what principal is interest to be calculated?
Damages in the nature of interest are awarded, when it is fair to do so, in order to compensate an innocent party for damage suffered because that party has been deprived of the use of the money.
In essence, damages are awarded in order to compensate a party, wholly or partly, for loss and damage suffered by that party as a result of the offending party's breach of the contract. Damages in the nature of interest are awarded, where it is fair to do so, in order to compensate the innocent party for damage
Interest is awarded to compensate the aggrieved party for having been deprived of the amount awarded from the date that it should have been paid until the date of judgement.
(1) VCAT may make any order it considers fair to resolve a domestic building dispute.
(2) Without limiting this power, VCAT may do one or more of the following -
(a) [Not applicable]
(b) order the payment of a sum of money -
(i) found to be owing by one party to another party;
(ii) by way of damages (including exemplary damages and damages in the nature of interest);
(iii) by way of restitution;
The Court, on application in any proceeding for the recovery of debt or damages, must, unless good cause is shown to the contrary, give damages in the nature of interest at such rate not exceeding the rate for the time being fixed under section 2 of the Penalty Interest Rates Act 1983 as it thinks fit from the commencement of the proceeding to the date of the judgment over and above the debt or damages awarded.
The builder's submission about the relevance of the allowance for inflation on the award for interest
Finding as to the principal sum upon which interest is to be awarded
This is particularly so in the case of the latter, where the discretion is unqualified, except by the requirement that the order be "fair". In my judgment, the Tribunal will usually be assisted both on the question of whether an award of interest is "fair" and the appropriate rate to be applied, by some evidence of how the applicant has covered its expenses pending an award of damages in its favour.
(1) Subject to this Division, each party is to bear their own costs in the proceeding.
(2) At any time, the Tribunal may order that a party pay all or a specified part of the costs of another party in a proceeding.
(3) The Tribunal may make an order under subsection (2) only if satisfied that it is fair to do so, having regard to -
(a) whether a party has conducted the proceeding in a way that unnecessarily disadvantaged another party to the proceeding by conduct such as -
(i) failing to comply with an order or direction of the Tribunal without reasonable excuse;
(ii) failing to comply with this Act, the regulations, the rules or an enabling enactment;
(iii) asking for an adjournment as a result of (i) or (ii);
(iv) causing an adjournment;
(v) attempting to deceive another party or the Tribunal;
(vi) vexatiously conducting the proceeding;
(b) whether a party has been responsible for prolonging unreasonably the time taken to complete the proceeding;
(c) the relative strengths of the claims made by each of the parties, including whether a party has made a claim that has no tenable basis in fact or law;
(d) the nature and complexity of the proceeding;
(e) any other matter the Tribunal considers relevant.
THE OWNERS' SUBMISSIONS AS TO WHY S 109 HAS BEEN ENLIVENED
THE OWNERS' SUBMISSIONS REGARDING THE ENGAGEMENT OF S 109(3)(D).
Proceedings concerning domestic building disputes are normally costly to conduct. Experts' reports are usually required which are expensive. The discovery process of even a modest building dispute is usually arduous and costly involving a large number of documents on both sides. Witness statements are usually ordered and they are most commonly drawn or settled by counsel. There are generally many factual issues involved as well as legal issues, often requiring complex legal argument. The hearing will usually occupy several days. For these reasons, the "nature and complexity of the proceeding" is commonly regarded as warranting an order for costs in favour of a successful party.
...Rectification of the external brickwork over the three units-which had at the date of the inspection not been performed- had been costed by the owners' expert, Mr Schmiedel, at $49,200.00. The brickwork was the largest single category of defect. It was also the defect in respect of which the views of the respective experts were most divergent. In this connection, I note that Mr Schmiedel had assessed the cost of labour to rectify the brickwork in unit 1 at $10,400.00, based on an assessment of 160 hours at $65 per hour. The allowance for replacement of bricks and materials such as sand, cement and lime, inclusive of delivery, was $6,000.00. The total for unit 1 accordingly was $16,400.00. In contrast, the builder's expert, Mr Osborne, had assessed the cost of rectifying the brickwork in unit 1 at $2,637.50.[24]
Mr Schmiedel had, curiously, also assessed the cost to rectify the brickwork in unit 2 at $16,400.00. Mr Osborne's assessment was $85 in total. Mr Schmiedel's assessment of the cost to rectify the brickwork in unit 3 was also $10,400.00. Mr Osborne's assessment for this unit was $3,051.25. It was clear from Mr Schmiedel's costings that he was contemplating the wholesale replacement of thousands of bricks. It was also clear from viewing the brickwork at the site that the brickwork was largely satisfactory, although, there were some blemishes. In these circumstances, it was obvious that Mr Osborne's respective assessments for the three units, which had been based on identification of specific defects in individual bricks and perpends, were much more accurate than Mr Schmiedel's global assessments.[25]
(a) The reality is that a substantial case worth about $280,000.00 was inflated by the owners into an enormous case worth just under $650,000.00. This of itself meant that the case was never going to settle before the hearing.
(b) The upper level of the claim was never going to be made out on the owners' evidence. The owners' primary witness as to quantum, Mr Schmiedel, had prepared a report that the owners and their advisers should have recognised long before the hearing was going to be discredited. Amongst other issues, Mr Schmiedel's findings regarding the brickwork were obviously untenable.
(c) This flaw in the owners' case gave the builder a substantial reason to run the hearing until, at least, the completion of cross examination of Mr Schmiedel.
(d) The manner in which the owners sought to prove their loss changed at the opening of the hearing, as they pivoted from relying on the expert testimony of Mr Schmiedel regarding the cost to rectify those defects which had been rectified to relying in part on the actual cost of rectification as established by invoices issued by Icon. The builder was caught by surprise. The builder could not have taken the new Icon invoices into account in assessing the strength of its case before the hearing started.
(e) Once the hearing got underway, it was very likely to run its course unless Mr Schmiedel's evidence was discarded at an early point, and this did not occur.
(f) I accept the builder's submission that because of the owners' insistence on relying on the evidence of Mr Schmiedel, it was necessary for the builder's barrister, prior to the hearing, to have spent substantial time preparing to cross-examine Mr Schmiedel. Substantial time was also wasted at the hearing while Mr Schmiedel was cross-examined, before his evidence was abandoned. The wasted costs of the builder ought to be taken into account.
(g) The introduction of almost 70 new documents into evidence through Mrs Troise, including what proved to be critical invoices rendered by Icon, delayed the completion of the hearing. The documents should have been discovered well before the hearing. The builder had to assess them 'on the run'. Mrs Troise was in the witness box for longer than she otherwise might have been as she had to give evidence and be cross examined about the documents and about proof of payment of the invoices. This also should be taken into account.
(h) Once the weakness of Mr Schmiedel's evidence was acknowledged by the owners, they attempted to settle the proceeding by making an offer to accept $200,000.00, inclusive of costs, during the course of the hearing. The builder did not accept that offer, but put a counter offer that was close. The counter offer was also rejected, and the hearing continued. The process of making and considering offers, of course, took time, and I consider this delay lies at the feet of the owners.
(i) This episode leads me to conclude that, had the owners put forward a reasonably costed case at the outset, the proceeding could very likely have been settled before the start of the hearing.
(i) the drafting of Mrs Troise's third witness statement; and
(ii) the discovery of the documents referred to in that witness statement.
(i) the preparation of Mr Schmiedel's expert reports;
(ii) the time the owners' solicitors spent in retaining and briefing Mr Schmiedel; and
(iii) the time that the owners' counsel spent in reading Mr Schmiedel's reports and conferring with him.
(1) This section applies if -
(a) a party to a proceeding (other than a proceeding for review of a decision) gives another party an offer in writing to settle the proceeding; and
(b) the other party does not accept the offer within the time the offer is open; and
(c) the offer complies with sections 113 and 114; and
(d) in the opinion of the Tribunal, the orders made by the Tribunal in the proceeding are not more favourable to the other party than the offer.
(2) If this section applies and unless the Tribunal orders otherwise, a party who made an offer referred to in subsection (1)(a) is entitled to an order that the party who did not accept the offer pay all costs incurred by the offering party after the offer was made.
(3) In determining whether its orders are or are not more favourable to a party than an offer, the Tribunal -
(a) must take into account any costs it would have ordered on the date the offer was made; and
(b) must disregard any interest or costs it ordered in respect of any period after the date the offer was received.
WHAT IF I HAD FOUND THAT S 112 HAD BEEN ENGAGED?
a party who has substantially succeeded against another party in a proceeding to which this section applies is entitled to an order under section 115B that the other party reimburse the successful party the whole of any fees paid by the successful party in the proceeding.
(a) the nature of, and issues involved in, the proceeding; and
(b) the conduct of the parties (whether occurring before or during the proceeding), including whether the successful party has caused unreasonable delay in the proceeding or has failed to comply with an order or direction of the Tribunal without reasonable excuse.
[3] (Building and Property) [2021] VCAT 1080.
[6] (Building and Property) [2018] VCAT 680, [16]-[18].
[8] (Building and Property) [2019] VCAT 468, at [8].
[20] [2007] VSC 117, [22].
[21] [2014] VCAT 1126, [15].
[22] [2007] VSC 117, [22].
[29] [2005] VSCA 298, [23].
[30] (Building and Property) [2014] VCAT 1274, at [54].
Troise
Blue Key Properties Pty Ltd
INTEREST: The Tribunal's power to award interest under ss 53(2)(b)(ii) of the Domestic Building Contracts Act 1995 (Vic) ('DBC Act') discussed; s 53 of the DBC Act contrasted with s 60(1) of the Supreme Court Act 1986; the compensatory principle explained and Ewin v Siemerin (Building and Property) [2021] VCAT 1080, Khan v Kimitsis trading as Quest Building [2009] VCAT 912; Douglas v Kelso [2018] VCAT 680; an award of interest under s 53 of the DBC Act must be fair; the role of evidence in considering an order for interest; Owners Corporation No.1 of PS613436T v LU Simon Builders Pty Ltd (No. 2)(Building and Property) [2019] VCAT 468 discussed;
COSTS: general principles discussed including Gillard J's observation in Vero Insurance Ltd v Gombac Group Pty Ltd [2007] VSC 117, [22] that "it is important that the Tribunal consider all the matters [in s 109(3) of the Victorian Civil and Administrative Tribunal Act 1998 ('VCAT Act')] together and determine whether it is fair to make an order for costs"; held, at [61] "the claimant's conduct of the proceeding, when assessed against the criteria established by 109(3), may justify a finding by the Tribunal that it is not fair to award costs, or that it is fair to reduce an award of costs which might otherwise have been made"; regarding s 109(3)(d) of the VCAT Act, Hyndman v Hurtob Homes Pty Ltd [2014] VCAT 1126, [15] considered; regarding assessment of efficacy of a s 112 offer made on a 'costs inclusive' basis, Metricon Homes Pty Ltd v Saw_y_er [2013] VSC 518 referred to; as to efficacy of a Calderbank offer, Hazeldene's Chicken Farm Pty Ltd v Victorian Workcover Authority (No. 2) [2005] VSCA 298 considered.
FEES: regarding the question of whether the applicants had been substantially successful in percentage terms, Ferdinands v 3D Homes Pty Ltd (Building and Property) [2014] VCAT 1274, at [54] referred to.