[2014] VCAT 1126
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2014-09-05
Mr P
Original judgment source is linked above.
Domestic Building dispute - costs applications - Victorian Civil and Administrative Tribunal Act 1998 - s.109 - whether fair to make an award of costs - offers of settlement - s.112 - whether offer capable of acceptance by offeree - whether any costs should be awarded - partially successful claim by both parties - many claims by both parties unsuccessful - relevant considerations - apportioning costs according to success - difficulty of
Hyndman v Hurtob Homes Pty Ltd (Building and Property) [2014] VCAT 1126
"109 (1) Subject to this Division, each party is to bear their own costs in the proceeding.
(2) At any time, the Tribunal may order that a party pay all or a specified part of the costs of another party in a proceeding.
(3) The Tribunal may make an order under subsection (2) only if satisfied that it is fair to do so, having regard to -
(a) whether a party has conducted the proceeding in a way that unnecessarily disadvantaged another party to the proceeding by conduct such as -
(i) failing to comply with an order or direction of the Tribunal without reasonable excuse;
(ii) failing to comply with this Act, the regulations, the rules or an enabling enactment;
(iii) asking for an adjournment as a result of (i) or (ii);
(v) attempting to deceive another party or the Tribunal;
(b) whether a party has been responsible for prolonging unreasonably the time taken to complete the proceeding;
(c) the relative strengths of the claims made by each of the parties, including whether a party has made a claim that has no tenable basis in fact or law;
(e) any other matter the Tribunal considers relevant."
"112. Presumption of order for costs if settlement offer is rejected
(a) a party to a proceeding (other than a proceeding for review of a decision) gives another party an offer in writing to settle the proceeding; and
(b) the other party does not accept the offer within the time the offer is open; and
(c) the offer complies with sections 113 and 114; and
(d) in the opinion of the Tribunal, the orders made by the Tribunal in the proceeding are not more favourable to the other party than the offer.
(2) If this section applies and unless the Tribunal orders otherwise, a party who made an offer referred to in sub-section (1)(a) is entitled to an order that the party who did not accept the offer pay all costs incurred by the offering party after the offer was made."
"The scheme of the Act is that an offer pursuant to s.112 must be "to settle the proceedings". An offer to settle only on the condition that a certain requirement is fulfilled is not in my view an offer to settle the proceedings. It is an offer to settle that will only become effective if something should happen in the future. Further, if the condition attaches to the offer, rather than to any agreement arising from its acceptance, then it would not seem that it was "open for acceptance" within the meaning of s.114(1). Finally, I would have to determine for the purposes of s.112(1)(d) whether or not the orders that I ultimately made were more favourable to the Applicant than the terms of the offer. I think the scheme of the Act is that the offer must be able to be evaluated and assessed at the time it is made not at some later time looking back at the offer with the benefit of hindsight. At the time the offer was made the Applicant did not and could not know whether the proceedings would be settled or not and so he could not be certain that the acceptance of the offer would settle the proceedings. For all these reasons, I do not think that the offer satisfies s.112 of the Act."
Hyndman
Hurtob Homes Pty Ltd