TRANSPAC CAPITAL PTE LIMITED v BUNTORO
[2008] NSWSC 671
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2008-06-10
Before
Hall J
Source
Original judgment source is linked above.
Judgment (24 paragraphs)
CITATION : TRANSPAC CAPITAL PTE LIMITED v BUNTORO [2008] NSWSC 671
(1) That leave be granted to enforce the Award, that being the Final Award of the Singapore International Arbitration Centre number ARB 057 of 2005, dated 20 August 2007, in this Court as if the Award had been made in this State in accordance with the laws of this State and in the same manner as a judgment of this Court with respect to the amounts set out in paragraph (2) below. (2) That there be an order for judgment for the plaintiff in accordance with the terms of the Award, as follows: (a) US$5,000,000 - being $6,282,196.26 Australian dollars (as at the date of the Award). DECISION : (b) US$531,014.45 - being $667,187.40 Australian dollars (as at the date of the Award). (c) US$1,371,784.13 - being $1,723,563.43 Australian dollars (as at the date of the Award). (d) S$109,461.57 - being $90,143.76 Australian dollars (as at the date of the Award). (3) The total of the amounts in (2)(a) to (d) above is $8,763,090.85 and an order for judgment in that total sum is, accordingly, to be entered for the plaintiff. I order the defendant to pay the costs of this application as agreed or assessed.