Siemens WLL v BIC Contracting LLC
[2022] FCA 1029
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2022-08-30
Before
Stewart J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
- Judgment be entered for the applicants against the respondent in the amount of $45,452,098.42.
- Judgment be entered for the first applicant against the respondent in the amount of $2,823,284.32.
- Judgment be entered for the second applicant against the respondent in the amount of $4,209,761.85.
- Interest be payable on the amounts owing under paragraphs 1-3 of these orders at the interest rate prescribed by r 39.06 of the Federal Court Rules 2011 from 31 August 2022.
- The respondent pay the applicants' costs of the application.
- The applicants have liberty to apply for their costs to be assessed on a lump sum basis on the papers. Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Introduction 1 This is an application for judgment enforcing two arbitral awards under s 8(3) of the International Arbitration Act 1974 (Cth) (IAA). That section provides that a "foreign award" may be enforced by the Court as if the award were a judgment or order of the Court. 2 The first applicant, Siemens WLL, is a company incorporated with limited liability in Qatar. 3 The second applicant, Siemens AG, is a company incorporated under the laws of the Federal Republic of Germany. I will refer to the applicants together as Siemens. 4 The respondent, BIC Contracting LLC (BICC), is a company incorporated in the United Arab Emirates. Despite notice of the proceeding, it has not entered an appearance. 5 By amended short minutes of order the applicants seek orders as follows: 1 Judgment in favour of the first applicant and the second applicant against the respondent in the amount of $45,452,098.42. 2 Judgment in favour of the first applicant against the respondent in the amount of $2,823,284.32. 3 Judgment in favour of the second applicant against the respondent in the amount of $4,209,761.85. 4 The respondent pay interest at the interest rate prescribed by rule 39.06 of the Federal Court Rules 2011 (Cth) on each of the amounts in paragraphs 1, 2, 3 above from 31 August 2022. 5 The respondent pay the applicants' costs of and incidental to the application. 6 The applicants have liberty to apply for their costs to be assessed on a lump sum basis on the papers. 6 The amended originating application, which served to give notice to BICC of the relief sought against it, sought judgment in various amounts expressed in currencies other than Australian dollars, namely Qatari riyals, euros, pounds sterling, United States dollars and United Arab Emirates dirhams, "or equivalent". For reasons I will come to, it is proper to give judgment in Australian dollars as sought in the short minutes of order. For present purposes, I am satisfied that the notation "or equivalent" was sufficient to give notice to the respondent that the ultimate judgment may not be expressed in the currencies set out in the amended originating application but that it may be given in equivalent amounts in some other currency, most obviously Australian dollars. 7 There is also one minor respect in which one of the amounts reflected in euros in the amended originating application is less than the amount which is now relied on and converted to Australian dollars. The difference is €50,000 which arose from a "3" having been typed in error in the amended originating application instead of an "8". Not only is that difference trivial in the scheme of what is claimed as a whole, but by reason of other errors in the way in which the prayers in the amended originating application were formulated, the total amounts for which judgments are now sought are materially less than the total amounts claimed in those prayers. In the circumstances, I am satisfied that the amended originating application gave notice of greater claims than those that are now made with the result that there is no prejudice to the respondent in the error. 8 The dispute that led to the arbitrations arises out of a project for the design, construction, maintenance and operation of a people-mover system at Education City in Qatar. The contractor was a consortium of Siemens and Leighton Contracting Qatar WLL under a Consortium Agreement concluded by them in February 2012. Clause 17.2 of the Consortium Agreement required all disputes to be settled by arbitration under the London Court of International Arbitration (LCIA) by a panel of three arbitrators. The seat of the arbitration would be London, UK. 9 In September 2018, Siemens, on the one side, and BICC and Leighton, on the other side, entered into a Mutual Agreement to ensure the financial stability of the project. That agreement recorded that Leighton had cash flow problems in relation to the project and that Siemens had entered into payment diversions in favour of Leighton to overcome those problems. It further recorded that BICC would provide a payment guarantee for a further cash diversion to be made by Siemens in favour of Leighton. 10 A payment guarantee was provided by BICC in favour of each of the Siemens companies. The payment guarantee contained an arbitration clause to the effect that any dispute under the guarantee would be finally settled under the Rules of Arbitration of the International Chamber of Commerce (ICC) by three arbitrators in accordance with the ICC Rules. The venue of the arbitration would be Dubai, UAE. Further, BICC irrevocably consented to the enforcement of any award or judgment issued pursuant to the guarantee in any court of competent jurisdiction. 11 I infer that it was sometime in 2019 that Siemens commenced an LCIA arbitration against Leighton, as first respondent, and BICC, as second respondent, under the Consortium Agreement and the Mutual Agreement. On 29 March 2020, Siemens commenced an ICC arbitration against BICC under the payment guarantee. The same three-person arbitral panel was appointed in both arbitrations, namely Professor Doug Jones AO (Siemens nominated), Stephen Furst QC (Leighton and BICC nominated) and Nicholas Dennys QC (presiding). 12 The LCIA arbitral tribunal published a final award on 10 August 2021 at London, UK. The award records that it is based on the arbitration clause in the Consortium Agreement and it records the finding that the arbitration agreement binds BICC on account of BICC's assent to the Mutual Agreement, which incorporated the Consortium Agreement by reference. On that basis, the tribunal found that it had jurisdiction to determine the claims against BICC and to determine disputes arising under the Mutual Agreement. 13 Insofar as is relevant to the judgment sought in the present proceeding, the LCIA final award, as corrected by an amending memorandum by the tribunal dated 23 September 2021, makes a final award in the following terms: The Tribunal awards and declares as follows: … (7) The First Respondent will pay the Claimants the sums of QAR 19,591,228.14 and €5,747,529 for repayment of the cash diversions; (8) The First and Second Respondents are jointly and severally liable to pay the Claimants the sum of QAR 74,512,517.47 for the Claimants' costs in completing the balance of Leighton's scope of work; (9) The First Respondent will pay the Claimants the sum of QAR 16,661,079.90 for prolongation costs resulting from delays for which Leighton is responsible, representing 143 days of delay in 2016 and 2017; (10) The Second Respondent is jointly and severally liable with the First Respondent for payment of QAR 2,031,477.32, representing 49 days of delay to the works in 2019; (11) The First and Second Respondents are jointly and severally liable to pay the Claimants the sum of QAR 729,514 for Leighton's share of the CAR Insurance premiums; (12) The Respondents shall pay the Claimants the sum of QAR 7,715,383.30 and €80,373.81 for the damage to the works, purchase of materials, PORR costs and failure to provide warranties; (13) The First Respondent will pay the Claimants interest at the rate of 8.1% per annum on the amounts awarded for repayment of the cash diversions from 31 December 2018 to 28 days from the date of this Award; (14) The First and Second Respondents will pay to the Claimants interest at the rate of 2.5% in respect of the claims for completion costs, prolongation costs, CAR Insurance repayment, damage to the Point Machines, damage to 11kV cables, damage to OCL, and Leighton's subcontractor claims, amounting to QAR 94,508,991.90 and EUR 80,373.81 from 1 January 2019 to 28 days from the date of this Award; (15) The First and Second Respondents will pay the Claimants' Legal Costs in the following sums: QAR 100.00; AED 3,066,106.50; £12,848.00 and €2,463,239.50, within 28 days of the date of this award; (16) The First and Second Respondents will pay the Arbitration Costs in the sum of £292,334.00 within 28 days of the date of this award. (17) All sums ordered to be paid by the First and/or Second Respondents to the Claimants shall be paid within 28 days of the date of this Award; (18) The First and Second Respondents will pay to the Claimants interest at 8.1% per annum, on a simple interest basis, on any sums that remain unpaid pursuant to this Award after 28 days of the date of this Award to the date of payment; (19) All other claims and counterclaims made in these proceedings are dismissed. 14 The ICC arbitral tribunal published a final award on 6 October 2021 at Dubai, UAE. The award records that it is based on the arbitration clause in the payment guarantee. The terms of the award are relevantly as follows: The Tribunal directs and awards as follows: … (2) The Respondent shall pay the First Claimant, Siemens AG, the sum of €2,701,615 as repayment of its portion of the third cash diversion; (3) The Respondent shall pay the Second Claimant, Siemens W.L.L., the sum of QAR 6,657,317 as repayment of its portion of the third cash diversion; (4) The Respondent shall pay the Claimants interest at the rate of 2.5% per annum from 31st July 2019 to the date of payment of the sums awarded above; (5) The Respondent shall pay the Claimants the sum of: (i) US$ 320,000 for arbitration costs; (ii) € 225,000 and AED 16,430 for legal costs; (6) All other claims for relief made by the Parties in this arbitration are denied.