[2023] NSWSC 723
Supreme Court of NSW
2023-06-22
Rees J, Stevenson J
Original judgment source is linked above.
Solicitors: HWL Ebsworth Lawyers (Plaintiff) Roberts Legal (Defendant) File Number(s): 2023/188806
Judgment
Construction contracts
Default Notice
Termination
Payment claims
Were the contracts terminated?
Is the claimant entitled to issue further payment claims?
Orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 27 June 2023
Taylor Construction Group Pty Ltd
Adcon Structural Group Pty Ltd
[2014] WASCA 127
(2022) 406 ALR 632
(1993) 176 CLR 300
(1953) 89 CLR 327
(2003) 128 FCR 1
(1940) 64 CLR 221
(1976) 136 CLR 444
(1974) 131 CLR 634
(1989) 168 CLR 385