NC Refractories Pty Ltd -v- Consultant Bricklaying Pty Ltd [2013] NSWSC 842
[2013] NSWSC 842
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2013-06-20
Before
Hammerschlag J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Introduction 1HIS HONOUR: By its Further Amended Summons filed 13 May 2013 the plaintiff (or respondent) seeks an order quashing an adjudication determination ("the determination") made by the second defendant on 23 January 2013, purportedly under s 22 of the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act"), in favour of the first defendant (or claimant) for $41,463.60, including GST.
Factual background 2The first defendant is a specialist bricklaying company which was retained by the plaintiff to carry out brickwork on a furnace in Wagga Wagga in the State of NSW belonging to Renewed Metal Technologies. The payment under the contract was to be calculated on an hourly basis, plus expenses. 3By all accounts there were problems which brought about delays, amongst others, because bricks supplied to the plaintiff from a supplier in India to be used by the first defendant were not cut properly. Ultimately, the principal directed the plaintiff to engage another contractor (Beroa Australia) to complete or, on one view of things, redo the work. 4On 11 December 2012 the first defendant served on the plaintiff a payment claim (in the form of a tax invoice number 654) for a total of $56,995.60 derived from 1,082 man hours at $70 ($75,740), 106 travel hours at $40 ($4,240), expenses of $8,197.82, making a total of $88,177.82 plus GST of $8,817.78, less $40,000 previously paid. 5There was then an exchange of emails between the plaintiff and the first defendant. Two of them are critical. In an email at 5:07pm on 11 December 2012, Mr Naresh Sharma of the plaintiff wrote to the first defendant: Mick I am very disappointed with the out come (sic) of this project. You worked through the difficult part of the project, Dome. However the lack of attention to man-power and lack of continued supervision led to crises from RMT/Turnkey which resulted in the final outcome. This has significant monetary burden on us and effect (sic) our reputation as supplier and installer. Regardless of above, the guys have to paid (sic). I expect you to provide me actual costs incurred by you + 10% (not @$70 per hour). I do not intend to drag on the issue but you have to be realist (sic) under the situation. We will pay @$50 for Ord Hour, @$60 for OT1.5 and @70 for OT2. Consider the above in view that none of these are recoverable are 100% our costs. Await your response Naresh 6It is possible that Mr Sharma was not in possession of full information about the standard of the works at this time. 7Mr Mick Mulligan of the first defendant responded at 12:34am on 12 December 2012. Relevantly, he said: Attached revised invoice reflecting reduction in rates. Would ask that this be settled as a matter of urgency. 8The attached revised invoice was numbered 654/1 and dated 11 December 2012. It claimed a reduced amount of $41,463.60. The travel hours and expenses were unchanged, but the man hours claim was reduced. 9This is the payment claim which forms the foundation of this dispute. 10On 13 December 2012 the plaintiff served payment schedules in respect of both invoices asserting a nil balance on the grounds that "works not completed, and due to poor workmanship, all installed brickwork removed & replaced by others". 11In paragraphs 2 and 4 of its adjudication application (undated but apparently of 3 January 2013) the first defendant described the contract as a verbal contract, having been agreed in or about Monday 12 November 2012. 12In its adjudication response (also undated but apparently of 11 January 2013) the plaintiff responded to paragraphs 2 and 4 with the words "no contest". 13It contended that it was an implied term of the contract that works must be completed prior to full payment being made. 14In its adjudication response the plaintiff asserted poor workmanship. It contended that "It became apparent only when Beroa Australia was directed to remove all installed brickwork that the quality of the workman ship (sic) would have led to a catastrophic failure". It stated that the payment schedule was valued at nil "due to the fact that the contractual obligations of the Claimant were not met, and the quality of workmanship was substandard". It included photographs of allegedly defective work and it referred to air gaps shown in the pictures which it said "would not have provided any resistance to molten metal and hence would have cause (sic) a failure in the steel shell resulting in substantial metal leak and potential risk to human life". 15The adjudicator rejected the implied term contended for as being not necessary to give business efficacy to the contract. That finding is not challenged. 16Under the heading "Defective Works" the adjudicator determined as follows: 30. The Respondent submits that it ought not pay the Claim because of defective works. 31. This ground requires some analysis of what happened on site. 32. It is not in dispute that there were issues with the lining bricks which were provided to the Claimant and that therefore there was a need to carefully consider measures to allow those bricks to be used on the project. This caused delay. That delay and debate about methodologies apparently led to friction between the Respondent and the Principal and pressure on the Respondent to complete within a short time frame. 33. That pressure in turn was applied by the Respondent onto the Claimant. 34. The Claimant's principle, Mr Mulligan, left the site on 4 December 2012 at a time when there was particular pressure to complete the works. 35. The Respondent treated this as "abandonment" and in any event the Respondent was directed (see attachment 2 to the Response) to engage others to complete the Claimant's work by the Principal on the same day (4 December 2012). 36. The Claimant treated the email of Mr Faunt (for the Respondent) as termination of the contract and did not return to the site. 37. The Respondent says that when the replacement installer (Beroa ) commenced work it found that there were defects in the work of the Claimant. There is no report on the extent of the defects and indeed they are only set out in the most generalised way in the Response to paragraphs 47 and 48 of the Application. 38. The Claimant accepts that the works were not "perfect" and indeed in an email on 12 December 2012 expresses "shame" about the works. 39. The Claimant, however, also describes the defects as minor and complains that it was not allowed to rectify them before others took over at which time any such opportunity was lost. 40. While it may be that there is defective work there is no attempt by the Respondent to fix a value to that work in circumstances where it engaged (at the direction of the Principal) a new subcontractor to complete the works. 41. That may be because the Respondent has, itself, been terminated by the Principal so that it is unaware of the costs. 42. Without evidence of what the defects were (rather than a generalisation) and without costings arising from the rectification it is not, in my view, a valid operation of the terms of the contract that the Respondent is entitled to simply withhold payment generally. There is no such term of the contract and indeed the Respondent does not attempt to imply that term. 17Under the heading "Valuing the Claim" the adjudicator determined as follows: 48. There is no dispute as to the number of hours claimed and other costs claimed by the Claimant. So much is clear from the Respondent's response to paragraph 37 of the Application set out in the Response. The Respondent relies on the failure to complete but does not dispute the actual time or costs. In response to paragraph 38 of the application the Respondent's submission is, "no contest". 49. I note that the Claimant has reduced its rates, from those in the earlier claim which it made on the same day and effectively withdrew, at the behest of the Respondent. The rates applied are those sought by the Respondent. 50. Having determined the entitlement of the Claimant above and without evidence or submissions to the contrary, I accept the Claimant's valuation set out in the Claim. 51. Accordingly, I determine that the value of the Claimant's Claim is $41,463.60.