[2021] VSCA 122
Court of Appeal (Vic)
2021-05-12
Mr J, French CJ, Bell JJ, Beach JA, Osborn JA
Original judgment source is linked above.
BUILDING AND CONSTRUCTION - Finding relevant to apportionment between concurrent wrongdoers set aside - Whether matter should be remitted to VCAT for apportionment to be redetermined - Osland v Secretary, Department of Justice [No 2] [2010] HCA 24; (2010) 241 CLR 320 applied - Matter not remitted - Civil Procedure Act 2010, ss 7 and 8.
BUILDING AND CONSTRUCTION - Apportionment between concurrent wrongdoers - Allocation of responsibility between building surveyor, architect, fire engineer and smoker who started fire - Extent of respective departures from expected standards of care - Causal potency of each wrongdoer's acts and omissions - Liability reapportioned: fire engineer 42%, building surveyor 30%, architect 25% and smoker 3%.
1 On 26 March 2021, the Court published reasons in the applications for leave to appeal brought by Thomas Nicolas, Gardner Group and Elenberg Fraser against orders that had been made in the Victorian Civil and Administrative Tribunal ('VCAT') in relation to a fire that occurred on 24 November 2014 in the Lacrosse apartment tower.[1] In those reasons, we rejected all of the grounds of appeal advanced by Thomas Nicolas and Elenberg Fraser, and all but one of the grounds of appeal advanced by Gardner Group (ground 3). In relation to ground 3, we accepted Gardner Group's submission that the judge's finding, of a causal link[2] in respect of the second of two bases upon which the judge found that Gardner Group had breached the Gardner Group Agreement, had to be overturned.
2 As a result of our conclusion, the apportionment between Gardner Group, Thomas Nicolas, Elenberg Fraser and Mr Gubitta must be set aside and a fresh apportionment between those parties must be undertaken.
3 Gardner Group contended that this Court should perform the new apportionment, rather than remitting the proceeding to the Tribunal. It submitted that a remittal of the issue to the Tribunal would cause the parties to incur significant additional costs, and delay the resolution of these proceedings. Ultimately, the parties most affected by any reapportionment (Thomas Nicolas and Elenberg Fraser) agreed that it was appropriate for the apportionment to be done by this Court. No party was heard to speak against this proposal.
The appropriateness of this Court performing the reapportionment
4 In Osland v Secretary, Department of Justice [No 2],[3] French CJ, Gummow and Bell JJ said:
The Court of Appeal, in the exercise of its jurisdiction under s 148 of the VCAT Act, may make substitutive orders where only one conclusion is open on the correct application of the law to the facts found by the Tribunal. Such a case arises when no other conclusion could reasonably be entertained. In that event, the Court can make the order that the Tribunal should have made. The language of s 148(7) is also wide enough to allow the Court of Appeal to make substitutive orders in other circumstances. But its powers must, as with the equivalent powers of the Federal Court in relation to the AAT, be exercised having regard to the limited nature of the appeal. Absent such restraint, a question of law would open the door to an appeal by way of rehearing. Where there is a factual matter that has to be determined as a consequence of the appeal, it may be that it is able conveniently to be determined by the Court of Appeal upon uncontested evidence or primary facts already found by the Tribunal. When the outstanding issue involves the formation of an opinion which is, as in this case, based upon considerations of public interest, then it should in the ordinary case be remitted to the body established for the purpose of making that essentially factual, evaluative and ministerial judgment.[4]
5 As has been said many times before, a finding on a question of apportionment involves the weighing of different considerations, and is one as to which there may well be differences of opinion by different minds.[5] Plainly, no apportionment that might be arrived at by this Court, or on remittal to the Tribunal, could be described as being the 'only ... conclusion ... open on the correct application of the law to the facts'[6] that have been found.
6 In Osland, however, their Honours accepted that 'where there is a factual matter that has to be determined as a consequence of the appeal, it may be that it is able conveniently to be determined by the Court of Appeal upon uncontested evidence or primary facts already found by the Tribunal'.[7]
7 Sections 7 and 8 of the Civil Procedure Act 2010 require this Court, in the exercise of its powers, to give effect to the 'just, efficient, timely and cost-effective resolution' of these proceedings. The facts upon which the new apportionment must be conducted have all been found. They are the facts found by the Tribunal, minus the judge's finding on causation at Reasons [565] to which we have already referred. Gardner Group correctly submitted that a remitter of the apportionment issue would likely cause all parties to incur significant further costs and to delay the finalisation of these proceedings. Plainly, taking such a course would be contrary to ss 7 and 8 of the Civil Procedure Act. Accordingly, we propose to accede to the submission that we should not remit the proceeding to the Tribunal.
9 The relevant facts may now be summarised as follows:
(1) Gardner Group breached the Gardner Group Agreement by failing to exercise due care and skill in issuing the Stage 7 Building Permit and, in so doing, approving the ACP Specification, which specification did not comply with the BCA. This breach was a cause of LU Simon's loss and damage (being the damages payable by LU Simon to the Owners).
(2) Elenberg Fraser breached the Elenberg Fraser Agreement by failing to exercise due care and skill in:
which failures were also a cause of LU Simon's loss and damage.
(3) Thomas Nicolas breached the Thomas Nicholas Agreement by failing to exercise due care and skill in:
which failures were again also a cause of LU Simon's loss and damage.
(4) Mr Gubitta failed to exercise reasonable care in the disposal of his smouldering cigarette, and to ensure that it was fully extinguished before leaving it in the plastic container on a table on the balcony of the apartment he was staying in.
10 Gardner Group submitted that on a proper assessment of the factual findings of the Tribunal, its relative culpability should be reduced by one third of that determined by the Tribunal - that is, from 33 per cent to 22 per cent. It was submitted that this reduction acknowledges that the finding in relation to the negligent issuing of the Stage 7 Building Permit was responsible for two thirds of the original assessment of liability against it, and is accordingly consistent with the Tribunal's assessment that the Fifth FER negligence finding was 'one of considerably less force than the issue of the Stage 7 Building Permit'.
11 Gardner Group contended that if its liability was reduced by one third (or by some other percentage as determined by this Court) the relevant reduction could be reallocated in one of two ways:
12 Elenberg Fraser submitted that an apportionment performed by this Court should be performed 'afresh, having due regard to the reasons of the Tribunal'. It submitted that performing the exercise afresh would not necessarily result in Gardner Group's share of the apportionment being reduced. It also submitted that if there were to be a new apportionment then any alteration to the proportions should be made chiefly between Gardner Group and Thomas Nicolas - the finding on causation which has been set aside by this Court having involved only the conduct of those parties.
13 Elenberg Fraser contended that it was open to this Court to find that no adjustment to the proportions allocated by the Tribunal should be made. If an adjustment were to be made, Elenberg Fraser submitted that it should be 'extremely minor - less than a few percentage points'. By way of example, it submitted that this Court could decrease Gardner Group's share from 33 per cent to 31 per cent; decrease Elenberg Fraser's share from 25 per cent to 24 per cent; and increase Thomas Nicolas' share from 39 per cent to 42 per cent.
14 Thomas Nicolas submitted that there should be no reduction in Gardner Group's liability as determined by the Tribunal. It contended that, on a 'complete reading' of the Tribunal's Reasons, Gardner Group's success on ground 3 of its appeal and the 'removal of that aspect of culpability' would not have changed the Tribunal's conclusion as to the relevant apportionment between each of the consultants and Mr Gubitta, 'in any manner whatsoever'.
15 In support of its submissions, Thomas Nicolas asserted that in that part of the Reasons dealing with the amounts to be apportioned between the consultants and Mr Gubitta, no reference was made to Gardner Group's failure to identify deficiencies in the Fifth FER. Thomas Nicolas submitted that the amount apportioned to Gardner Group by the Tribunal was justified by the Tribunal, in its Reasons, by reference only to Gardner Group's breach of the Gardner Group Agreement as identified at Reasons [564].[10]
16 Thomas Nicolas contended that the Tribunal had carefully considered the 'complex factual matrix and responsibility of the parties' in its Reasons and 'none of those reasons have been shown to be wrong'. Therefore, it was submitted, the proportions as determined by the Tribunal should not be changed, and there is 'no basis to support a de minimis reduction and consequential changing in the Tribunal's findings'.
17 Neither LU Simon nor the Owners sought to be heard in relation to the reapportionment between Gardner Group, Elenberg Fraser, Thomas Nicolas and Mr Gubitta.
18 In any apportionment between concurrent wrongdoers, the matters that need to be considered are: first, the degree of departure by each wrongdoer from the standard of care reasonably expected of that wrongdoer; and secondly, the causal potency of each wrongdoer's negligent acts or omissions. The judgment required involved a synthesis having regard to the whole of the conduct of each wrongdoer.[11]
19 In dealing with the apportionment issue now before this Court, there is no challenge by any party in respect of the 3 per cent attributed by the Tribunal to Mr Gubitta. The apportionment issue in this Court now falls to be considered by us on the basis of the facts found by the Tribunal, but absent the causal finding against Gardner Group in relation to its failure to identify deficiencies in the Fifth FER.
20 In arriving at its conclusion on apportionment, the Tribunal made the following findings and conclusions:
21 On the facts found by the Tribunal, and which are no longer in dispute, there is no basis for interfering with the Tribunal's findings and conclusions to which we have just referred. Having set aside the causal finding in relation to Gardner Group's negligence in failing to identify deficiencies in the Fifth FER, and having considered all of the remaining facts for ourselves by reference to the consultants' respective departures from the standards of care expected of them and the causal potency of each of their acts and omissions, we conclude that the appropriate apportionment for each consultant is:
22 In arriving at this apportionment, we have rejected Gardner Group's submission that the apportionment attributed to Mr Gubitta of 3 per cent requires a reduction in Gardner Group's apportionment by more than 3 per cent. First, while no party sought to overturn the finding against Mr Gubitta, having regard to the limited area of damage for which he was found responsible,[20] it might be thought that the apportionment in respect of Mr Gubitta was higher than it ought otherwise have been.
23 Secondly, in any event, there is no ready comparison between the amount apportioned to Mr Gubitta on the one hand and the amount apportioned to Gardner Group on the other hand, given the very different amounts of damage attributed to each of them by the Tribunal.[21]
24 Thirdly, as was submitted by Elenberg Fraser, the apportionment required to be performed by this Court is one which is to be performed afresh, having due regard to the Tribunal's findings and conclusions. It would be contrary to principle to engage in some mathematical rectification, without properly considering relevant degrees of departure from the particular standards of care expected of each consultant, and the respective causal potencies of each consultant's negligent acts and omissions.
25 While it might appear that we have simply assigned the reduction in Gardner Group's share of the apportionment to Thomas Nicolas without increasing Elenberg Fraser's share, the figures we have arrived at reflect the views we have formed about each party's relative responsibility. As the Tribunal correctly found, Thomas Nicolas sits at the top of the hierarchy by a clear margin from Gardner Group and Elenberg Fraser, but Gardner Group bears a not insignificantly greater responsibility than Elenberg Fraser. The figures which we have arrived at reflect our views in relation to these matters.
26 The orders made by the Tribunal will be varied to the extent necessary to accord with our conclusion that the damages payable by LU Simon to the Owners should be apportioned:
[1] Tanah Merah Vic Pty Ltd v Owners' Corporation No 1 of PS613436T [2021] VSCA 72 ('Appeal Reasons'). We shall use the same abbreviations in these reasons as in the Appeal Reasons.
[3] [2010] HCA 24; (2010) 241 CLR 320 ('Osland').
[5] See, eg, Podrebersek v Australian Iron and Steel Pty Ltd [1985] HCA 34; (1985) 59 ALJR 492, 493-4 ('Podrebersek').
[6] Osland [2010] HCA 24; (2010) 241 CLR 320, 332 [20].
[7] Ibid 333 [20]. See also Leeda Projects Pty Ltd v Zeng [2020] VSCA 192; (2020) 61 VR 384, 386-7 [3] (Tate JA), 387 [4] (Kaye JA) and 432-4 [193]-[201] (McLeish JA).
[8] See div 3 of pt 3 of the Victorian Civil and Administrative Tribunal Act 1998 ('the VCAT Act').
Tanah Merah Vic Pty Ltd
Owners Corporation No 1 of PS613436T [No 2] [2021] VSCA 122
(2020) 61 VR 384
(2010) 241 CLR 320
(1985) 59 ALJR 492
(2016) 50 VR 129