[2026] NSWCATAP 15
General information, not legal advice.
NCAT Appeal Panel
2026-01-21
P H Molony, Senior MemberR C Titterton AM, Senior Member
Original judgment source is linked above.
Al-Daouk v Mr Pine Pty Ltd t/as Furnco Bankstown [2015] NSWCATAP 111
Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98
Bondarek v NSW Land and Housing Corporation [2018] NSWCATAP 299
CEO of Customs v AMI Toyota Ltd [2000] FCA 1343; (2000) 102 FCR 578
Collins v Urban [2014] NSWCATAP 17
Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163 at 179; [1995] HCA 58
Devel Pty Ltd v Lewis; Lewis v Devel Pty Ltd [2021] NSWCATAP 395
Dwyer Building Group Pty Ltd v Spicer; Spicer v Dwyer Building Group Pty Ltd [2025] NSWCATAP 133
Ferella & Anor v Chief Commissioner of State Revenue [2014] NSWCA 378
Haritos v Federal Commissioner of Taxation (2015) 233 FCR 315; [2015] FCAFC 92
Kudrynski v Orange City Council [2024] NSWCA 33
Orr v Cobar Management Pty Limited (2020) 103 NSWLR 36; [2020] NSWCCA 220
Pholi v Wearne [2014] NSWCATAP 78
Ryan v BKB Motor Vehicle Repairs Pty Ltd [2017] NSWCATAP 39
Schwartz Family Co Pty Ltd v Capitol Carpets Pty Ltd [2017] NSWCA 223
Secretary, Department of Family and Community Services v Smith [2017] NSWCA 206; (2017) 95 NSWLR 597
Unique Commercial Group Pty Ltd v Cusumano [2024] NSWCATAP 204
Wilson v Chan & Naylor Parramatta Pty Ltd atf Chan & Naylor Paramatta Trust [2020] NSWCA 62
Zahrouni v Vesta Homes Pty Ltd [2023] NSWCATAP 49
1 By consent of parties, Consent orders are attached to the file.
Scope of works.
1 Protect surrounding surfaces.
2 Install full protection to perimeter of roof.
3 Remove and dispose of existing roof sheeting & Cappings.
4 Remove and re-use gutters and down pipes
5 Install additional roof insulation and sarking where required.
6 Provide tarp to cover roof over night
7 Install new lysaght Klip Lok 0.48 roof sheeting, capping and flashing.
8 Reinstall gutter and downpipes.
9 Install additional 2 downpipes.
10 Owner to connect new downpipes to stormwater.
11 Clean and tidy area affected by work.
12 Work to be in accordance with NCC, Manufacturer's specification and relevant standards.
13 Work to commence from 6 weeks from order.
14 Work to be completed within 4 weeks of commencement.
15 Work is subject to weather conditions, contractor to notify owner of weather delay within 1 day (of delay arising)
16 Once work is commenced on site it must continue to completion.
signed by both parties 1/03/24.
1. The decision is reserved.
2. On or before 13-Oct-2025, the respondent is to file and serve submissions on the "relevant standards" referred to in par [12] of the consent orders of 1 March 2024 in proceedings 2023/00377524 and 2023/00370588, in particular as to whether the Fair Trading NSW Guide to Standards and Tolerances is incorporated by the consent orders. The submissions are to be limited to five pages.
3. The appellant may reply on or before 20-Oct-2025, such submissions being limited to two pages.
"Any internal appeal may be made":
(a) "in the case of an interlocutory decision of the Tribunal at first instance - with the leave of the Appeal Panel", and
(b) "in the case of any other kind of decision (including an ancillary decision) of the Tribunal at first instance - as of right on any question of law, or with the leave of the Appeal Panel, on any other grounds".
"An Appeal Panel may grant leave under section 80 (2) (b) of this Act for an internal appeal against a Division decision only if the Appeal Panel is satisfied the appellant may have suffered a substantial miscarriage of justice because:
(a) the decision of the Tribunal under appeal was not fair and equitable, or
(b) the decision of the Tribunal under appeal was against the weight of evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with)."
"Those questions of law should be, in our opinion, what are sometimes described as 'pure questions of law.' They should not draw the Court of Criminal Appeal into questions of fact. Moreover, they must be questions whose character as a question of law can be recognised on the face of the question, and not depend upon the answer given to the question. This does not include a question which may ultimately disclose an error of law depending on an analysis of the facts but where this cannot be known without scrutiny of the facts."
"An Appeal Panel may grant leave under section 80 (2) (b) of this Act for an internal appeal against a Division decision only if the Appeal Panel is satisfied the appellant may have suffered a substantial miscarriage of justice because:
(a) the decision of the Tribunal under appeal was not fair and equitable, or
(b) the decision of the Tribunal under appeal was against the weight of evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with)."
"... there was a 'significant possibility' or a 'chance which was fairly open' that a different and more favourable result would have been achieved for the appellant had the relevant circumstance in para (a) or (b) not occurred or if the fresh evidence under para (c) had been before the Tribunal at first instance."
"During the hearing, Mr Xue gave sworn evidence, including that:
(1) He is a licensed builder and registered surveyor; he has worked in the industry for around 20 years and has his own construction team currently engaged in five projects across Sydney.
(2) He was first contacted by the Owners in around July 2023, regarding defective roofing work.
(3) He attended the site on 12 July 2023 and prepared a report identifying various defects.
(4) He was then contacted around a year later in relation to concerns about rectification work.
(5) He attended the site on 05 September 2024 and produced a further report on 06 September 2024, a copy of which has been provided to the Tribunal.
(6) He has included both information about defects as well as incomplete work, and recommendations about the work required to remediate. Recommended work is accompanied by costings.
(7) He has attempted to engage in a conclave with the Builder's expert, and has left two voicemail messages with the number listed on the website for the Builder's expert, but has not received any call back."
"19 The Builder argues that:
(1) The work required by the Consent Orders is substantially complete and not defective;
(2) While items 9 and 10 required by the Consent Orders are not complete, this is due to a failure by the Owners to provide information; and
(3) Given the above, the Builder has no liability to compensate the Owners."
"21 ... the Builder argued that the guttering is a "Triline Stiffened Back Gutter" (identified at the bottom right of the image in section [9.4] in the Owner's Expert Report) and that the profile or shape of this guttering is such that Mr Xue's own observations can be contradicted by measurements which and accompanying photographs which appear in the Builder's Expert Report. I have understood this as a complaint about the methodology Mr Xue has used to assess compliance with NSW Standards and Tolerances.
...
23 In his evidence, Mr Kumar stated that the reason for water ingress into the parts of the premises was due to the choice of design and building material made by the Owners. He stated, "we just did whatever they asked" and made a statement to the effect that if the roof was leaking, it was the Owners fault and not the Builders.
24 Mr Kumar also argued that leaks in the roof were not due to a problem with the sarking, but were instead due to insulation. He argued that for relatively flat roofs, when installing fascia there is a high risk of water ingress due to a capillary action. He referred to his written material in relation to this submission."
"29 The nature of renewal proceedings has been addressed by the Appeal Panel in Zahrouni v Vesta Homes Pty Ltd [2023] NSWCATAP 49 including at [63] holding:
"[I]n proceedings involving the HB Act, the Tribunal is not empowered in renewal proceedings to consider defect claims that were not part of the original proceedings and are not items that have arisen as a consequence of the orders made in the original proceedings."
More generally, the principles relevant to determination of renewal proceedings, including what constitutes "appropriate" orders on renewal, has been considered by the Appeal Panel in Minifie v Maxwell [2020] NSWCATAP 30 at [38] - [40]."
"35 The Owner's Expert Report reaches significantly different conclusions to the Builder's Expert Report. I consider that the Owner's Expert Report must be given more weight because it meets the criteria set out in Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR 705; [2001] NSWCA 305 at [59]. It provides clear evidence of the scope and assumptions that form the basis for Mr Xue's work, the investigative process is discussed and where he has volunteered a finding that work described in the Consent Orders is defective or incomplete is generally supported by a clear explanation and/or photographic evidence.
36 By contrast, the Builder's Expert Report does not contend with the issues raised in the Owner's Expert Report and has not been prepared in a way that enabled me to understand the basis for the preparation of that report, nor the conclusions reached.
37 In forming this view, I've considered the photographic evidence which Mr Kumar relied on in relation to the overhand of the sheet roofing relative to the gutter. This photographic evidence is equivocal. The photographs appear to show that the roofing overhangs in at least some sections by less than 50mm. This supports the conclusion offered by Mr Xue including at 9.3 of the Owner's Expert Report.
38 I do not accept Mr Kumar's evidence that the Builder has simply indulged any design whim or choice made by the Owners. Mr Varga's evidence given at the hearing, which I accept, is that he is not an expert in this type of work. The Owners are, by operation of s 18B(1) of the HBA [Home Building Act 1989], entitled to expect that a Builder will perform work in a manner that meets applicable standards and is fundamentally fit for purpose. This is consistent with s 18F(1) of the HBA which provides for a mechanism whereby a builder can depart from such standards if they provide a written advice to a client. This is plainly to ensure clients are making properly informed decisions, and to ward off the prospect of unnecessary litigation. Such a disclosure has not occurred here.
39 I accept that the works required by the Consent Orders are defective as set out in Section 8 of the Owner's Expert Report and accept find that the Builder has failed to comply with the statutory warranties in ss 18B(1)(a) and (in respect of the downpipes) s 18B(1)(d) of the HBA.
40 In reaching the conclusion that the Builder has failed to comply with s 18B(1)(d) of the HBA, I am satisfied that the reasonable time for performance of the works was the time period agreed by the Builder in the Consent Orders."
(1) was beyond the power of the Tribunal on a renewal application;
(2) failed to take into account a relevant consideration, namely that the replacement was not raised at first instance; and
(3) took into account an irrelevant consideration, namely the replacement not being previously claimed?
(1) was not fair and equitable; and
(2) was against the weight of evidence and involves a factual error unreasonable arrived at and clearly in error.
"Speed and efficiency, in the sense of minimum delay and expense, are seen as essential to a just resolution of the proceedings... It cannot therefore be said that a just resolution requires that a party be permitted to raise any arguable case at any point in the proceedings, on payment of costs".
... a 90 mil fall in the roof gutter. So which was definitely over 50 mil. or 65 mil. but we have to accept that, because we were talking on the books. If we're talking by books, then I was wrong, because roof sheet fall was more than 65 mil. and I have to accept that. I cannot cut the roof sheets because the risk of the corrosion. So there was no other option for me.
"A new point cannot be taken on appeal where, had the issue been raised in the court below, evidence could have been given which "by any possibility" could have prevented the point from succeeding... If on the other hand there is a pure question of law, even one which was not even obliquely raised at first instance, there are occasions when it is appropriate to let that be advanced for the first time on appeal."
"...Consent orders, like contracts, need to construed having regard to their text, context and purpose: As the majority explained in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37 (Mount Bruce) at [47]:
"In determining the meaning of the terms of a commercial contract, it is necessary to ask what a reasonable businessperson would have understood those terms to mean. That enquiry will require consideration of the language used by the parties in the contract, the circumstances addressed by the contract and the commercial purpose or objects to be secured by the contract."
Consent work orders should be read in the context of the proceedings they relate to and in the light of their purpose. That is usually, as here, to resolve proceedings between the parties. While we agree that the interpretation adopted by the Tribunal was a possible interpretation, the construction of orders should have regard to the context in which they were made . That was one in which proceedings were on foot, as is made plain by the orders themselves. The clear focus of the homeowner's proceedings was on the completion of the works. Both parties were legally represented. The homeowner had obtained an expert report. The consent order should be construed objectively in that context and have due regard to the fact that the order was intended to resolve the original proceedings. Such a construction leads to the order being one intended to complete the disputed works in accordance with the contract. It did not extend to or require the builder to revisit already completed works. The fact that the text of the order required the builder to "complete" the works made that clear. If the purpose was for the builder to rectify and remedy already completed works, one would have expected that to be stated explicitly, and likely the to be subject of specific agreement."
Ground 1 and 2 - Was the Tribunal's order for replacement of the aluminum roof on renewal beyond power?
"8 Renewal of proceedings in respect of certain Division decisions
(1) If the Tribunal makes an order in exercise of a Division function in proceedings, the Tribunal may, when the order is made or later, give leave to the person in whose favour the order is made to renew the proceedings if the order is not complied with within the period specified by the Tribunal.
(2) If an order has not been complied with within the period specified by the Tribunal, the person in whose favour the order was made may renew the proceedings to which the order relates by lodging a notice with the Tribunal, within 12 months after the end of the period, stating that the order has not been complied with.
(3) The provisions of this Act apply to a notice lodged in accordance with subclause (2) as if the notice were a new application made in accordance with this Act.
(4) When proceedings have been renewed in accordance with this clause, the Tribunal -
(a) may make any other appropriate order under this Act or enabling legislation as it could have made when the matter was originally determined, or
(b) may refuse to make such an order.
(a) the operation of an order has been suspended, or
(b) the order is or has been the subject of an internal appeal."
"... in proceedings involving the HB Act, the Tribunal is not empowered in renewal proceedings to consider defect claims that were not part of the original proceedings and are not items that have arisen as a consequence of the orders made in the original proceedings."
". Renewal proceedings are an enforcement mechanism which provides a remedy for non-compliance with Tribunal orders. They are restricted to claims relating to the consequences of the order in the original not being complied with. This will usually be the cost of undertaking the works specified in the work order. However, where other consequences have arisen as a result of that non-compliance (for example, water damage caused by defective waterproofing work), then the cost of rectifying that damage may be claimed in the renewal proceedings. However, renewal proceedings are not proceedings in which a new claim can be raised that was not raised in the original proceedings."
(1) Was not fair and equitable.
(2) Was against the weight of evidence and involves a factual error unreasonable arrived at and clearly in error.
(1) We are not satisfied that the decision was not fair and equitable. The only error upon which the builder relies for this leave grounds is that the Tribunal wrongly considered the additional defects reported by Mr Xue. We have already explained why we reject that proposition and see no error of law in the Tribunal doing so. Similarly, we can see no error of fact.
(2) The conclusions reached by the Tribunal, with respect to the defective work done by the builder in undertaking the works under the consent order, were clearly open to it. There is no error evident in the Tribunal preferring the expert evidence of Mr Xue over that of the builder and its expert. The Tribunal provided clear, cogent and persuasive reasons for doing so. The decision is not against the weight of the evidence.
(3) Having reviewed the decision in detail we are not satisfied that the any of the matters complained of by the builder in grounds 1 and 2 give rise to a significant possibility, or a real chance, that the builder may have suffered a substantial miscarriage of justice because the decision was not fair or equitable or was against the weight of the evidence. There is no injustice apparent.
(4) The appeal does not give rise to a question of importance or matters of administration or policy which might have general application.
(5) There is no issue of principle at stake. The contention that defective work done pursuant to a consent order is not claimable on renewal if the same defect was not previously claimed, does not give rise to an issue of principle. It is without merit.
(1) The builder's appeal against the order made in the renewal proceedings that it pay the owners' costs fixed at of $10,507.00.
(2) The issue of costs of this appeal.
(1) Leave to appeal refused.
(2) Appeal dismissed.
(3) The sum of $19,547.60 held in the respondent's solicitors trust account is to be paid to the respondents.
(4) It is noted that the parties have consented to the issue of the costs of this appeal and the appeal against the costs order made by the Tribunal on 5 May 2025, being determined, without a hearing, on the papers to be provided by them.
(5) The appellant is to notify the Tribunal and the respondents within 14 days if it wishes to continue with its appeal against the costs decision made by the Tribunal, or whether it wishes to withdraw that appeal. If the appellant wishes to proceed with the appeal, the Appeal Panel will then make orders for the filing of submissions.
(6) If either party wishes to make an application for costs with respect to this appeal they shall file and serve an application with supporting submissions (not exceeding 2,000 words) and materials within 21 days of the publication of these reasons.
(7) The other party may file and serve submissions (not exceeding 2,000 words) and materials in response within 42 days of the publication of these reasons.
(8) Any submissions in reply (not exceeding 1,000 words) are to be filed and served within 49 days of the publication of these reasons
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Sydney Roof Construction Pty Ltd
Varga [2026] NSWCATAP 15;
(2000) 102 FCR 578
(1995) 184 CLR 163
(2015) 233 FCR 315
(2020) 103 NSWLR 36
(2017) 95 NSWLR 597
(2001) 52 NSWLR 705
(2009) 239 CLR 175
(2015) 256 CLR 104