[2025] NSWCATAP 133
General information, not legal advice.
NCAT Appeal Panel
2025-06-13
P H Molony, Senior MemberL Andelman, Senior Member
Original judgment source is linked above.
Alexandria Landfill Pty Ltd v Transport for NSW (2020) 103 NSWLR 479; [2020] NSWCA 165
Bimson, Roads & Maritime Services v Damorange Pty Ltd [2014] NSWSC 734
Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98
Bondarek v NSW Land and Housing Corporation [2018] NSWCATAP 299
CEO of Customs v AMI Toyota Ltd [2000] FCA 1343; (2000) 102 FCR 578
Collins v Urban [2014] NSWCATAP 17
Cominos v Di Rico [2016] NSWCATAP 5
Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163
Devel Pty Ltd v Lewis; Lewis v Devel Pty Ltd [2021] NSWCATAP 395
Donau Pty Ltd v ASC AWD Shipbuilder Pty Ltd [2018] NSWSC 1273
Ferella & Anor v Chief Commissioner of State Revenue [2014] NSWCA 378
FVA v Commissioner for Police, NSW Police Force [2024] NSWCATAP 127
Haritos v Federal Commissioner of Taxation (2015) 233 FCR 315; [2015] FCAFC 92
Integrity Homes Pty Ltd v Staniland [2015] NSWCATAP 284
Kostas v HIA Insurance Services Pty Ltd (2010) 241 CLR 390; [2010] HCA 23
Kudrynski v Orange City Council [2024] NSWCA 33
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37
Meacham v Commissioner of Police [2020] NSWCATAP 107
New South Wales Land and Housing Corporation v Orr [2019] NSWCA 231
Orr v Cobar Management Pty Limited (2020) 103 NSWLR 36; [2020] NSWCCA 220
Paraiso v CBS Build Pty Ltd [2020] NSWSC 190
Pholi v Wearne [2014] NSWCATAP 78
Pratt v Hawkins (1991) 32 NSWLR 319
Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69
Re Felicity; FM v Secretary, Department of Family and Community Services (No 3) [2014] NSWCA 226
Ryan v BKB Motor Vehicle Repairs Pty Ltd [2017] NSWCATAP 39
Schwartz Family Co Pty Ltd v Capitol Carpets Pty Ltd [2017] NSWCA 223
Thomas and Naaz Pty Ltd v Chief Commissioner of State Revenue [2023] NSWCA 40
Unique Commercial Group Pty Ltd v Cusumano [2024] NSWCATAP 204
Wilson v Chan & Naylor Parramatta Pty Ltd atf Chan 7 Naylor Paramatta Trust [2020] NSWCA 62
Zahrouni v Vesta Homes Pty Ltd [2023] NSWCATAP 49
(1) The work order dated 4 May 2021 in Tribunal Proceedings No. HB 20/33412 is vacated;
(2) The home building contract dated 29 November 2018 between the Applicant and the Respondent to renovate the Applicant's property at [address] is terminated forthwith;
(3) The Respondent, Dwyer Building Group Pty Ltd ACN 617 566 944, is to pay to the Applicant, Deanna Spicer, of [address], the sum of $251,187.45 on or before 25 September 2024; and
(4) The Respondent is to pay the Applicant's costs of these renewal proceedings on a party/party basis and as agreed or assessed.
In the Owner's Proceedings (HB 20/33412), the Tribunal:
(a) ORDERS that the Builder; in accordance with applicable laws, rules, codes and standards and in a proper and workmanlike manner, complete the works under the contract dated 29 November 2018 within a reasonable time;
(b) NOTES that on 17 July 2020, the Builder proposed an amended project schedule (CB which is Ex Jl vol 2, p578-580) which, inter alia, provided for the completion of the works within 6.5 months of recommencement;
(c) ORDERS that the parties' costs of the Owner's Proceedings be reserved and, if necessary, determined in any renewal proceedings;
(d) NOTES the agreement of the parties to amend the contract dated 29 November 2018 as follows:
(i) With 28 days after date of these Orders, the Owner will pay the balance of the contract price (which will be $119,884.53 incl GST) into the Builder's solicitor's trust account to be dealt with at the Owner's direction;
(ii) The Builder may submit claims for payment on account pursuant to Schedule 2 of the contract;
(iii) Within 5 days of receipt of an invoice, the Owner must provide the Builder with written notice of any specific components of the work the subject of each invoice which she disputes; (iv) 5 business days after receipt of an invoice by the Owner, the Owner will be deemed to have consented to the Builder's solicitor releasing the amount claimed in the Builder's solicitor's trust account to the Builder (except for any specific components the subject of a notice issued by the Owner in accordance with (iii)); and
(v) to the extent that the parties cannot agree on whether the work the subject of a notice by the Owner in accordance (iii) has been completed, the parties agree to use the dispute resolution procedure set out in clause 26 of the contract.
(e) NOTES that the Owner will take all reasonable steps to remove reviews from the Builder's listings on Yellow Pages and Google which she was responsible for publishing.
4. Order that in any renewal proceedings in respect of any of the above orders the parties may rely on without re-filing any of the material filed in HB 20/33412 and/or HB 20/38623 which is notified to the other party in a manner and time frame consistent with the manner and time frame for filing and service of evidence in the renewal proceedings.
(1) incomplete work, being contract works not yet performed (incomplete work);
(2) defective work, being defects appearing in work performed in furtherance of the work order and since the date of the work order (defective work); and,
(3) other defective work, being defects which existed prior to the work order and at the time of the original proceedings were commenced but which were not claimed by the owner in the original proceedings (defects not previously claimed)
"Any internal appeal may be made:
(a) in the case of an interlocutory decision of the Tribunal at first instance - with the leave of the Appeal Panel, and
(b) in the case of any other kind of decision (including an ancillary decision) of the Tribunal at first instance - as of right on any question of law, or with the leave of the Appeal Panel, on any other grounds."
"Those questions of law should be, in our opinion, what are sometimes described as 'pure questions of law.' They should not draw the Court of Criminal Appeal into questions of fact. Moreover, they must be questions whose character as a question of law can be recognised on the face of the question, and not depend upon the answer given to the question. This does not include a question which may ultimately disclose an error of law depending on an analysis of the facts but where this cannot be known without scrutiny of the facts."
(1) Denial of procedural fairness (Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69 at [13](4)); FVA v Commissioner for Police, NSW Police Force [2024] NSWCATAP 127 at [83]- [84]).
(2) A constructive failure to exercise jurisdiction, which includes the failure to consider and address a material issue raised by a party in the proceedings that is within the jurisdiction of the Tribunal to determine (Alexandria Landfill Pty Ltd v Transport for NSW (2020) 103 NSWLR 479; [2020] NSWCA 165 at [8]- [12] and [413]). This category of error also includes a failure by the Tribunal to engage with a clearly articulated argument put to it.
(3) The construction of a statute or contract arrived at by the Tribunal at first instance was wrong in some identified way.
(4) Acting on the application of the wrong legal principle which materially affected the outcome (Bimson, Roads & Maritime Services v Damorange Pty Ltd [2014] NSWSC 734 at [38]- [53]).
(5) No evidence to support a factual finding (Kostas v HIA Insurance Services Pty Ltd (2010) 241 CLR 390; [2010] HCA 23 at [91]).
(6) A failure to provide adequate reasons for decision.
(1) the decision of the Tribunal under appeal was not fair and equitable; or
(2) the decision of the Tribunal under appeal was against the weight of evidence; or
(3) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
"... there was a 'significant possibility' or a 'chance which was fairly open' that a different and more favourable result would have been achieved for the appellant had the relevant circumstance in para (a) or (b) not occurred or if the fresh evidence under para (c) had been before the Tribunal at first instance."
(1) Issues of principles;
(2) Questions of public importance or matters of administration or policy which might have general application;
(3) An injustice which is reasonably clear, in the sense of going beyond merely what is arguable, or an error that is plain and readily apparent which is central to the Tribunal's decision and not merely peripheral, so that it would be unjust to allow the finding to stand;
(4) A factual error that was unreasonable arrived at and clearly mistaken; or
(5) The Tribunal having gone about the fact finding process in such an unorthodox manner or in such a way that it was likely to produce an unfair result so that it would be in the interests of justice for it to be reviewed.
(1) The decision of Senior Member McDonald dated 30 August 2024 (D).
(2) The tender bundle of documents consisting of 4097 pages, in five A4 folders, `which was before the Tribunal when it made the decision (TB).
(3) The Appeal Bundle consisting of 649 pages, in one A4 folder, containing all the documents relating to the appeals, including all submissions made on appeal, as well as a transcript of the hearing and copies of submissions made to the Tribunal below (AB).
1 This is a renewal application of home building proceedings brought by the Owner against the Builder pursuant to Schedule 4, Clause 8 of the Civil and Administrative Tribunal Act 2013 (NSW) in respect of a work order made by consent of the parties on 4 May 2021 in HB 20/33412 (work order).
2 The work order arose from mainly incomplete home building work carried out by the Builder at the Owner's residence at [address] (Property).
...
3 On 29 November 2018 the parties entered into a home building contract to undertake renovation work and an addition to the Property in the sum of $358,604.53 including GST (Contract). Work progressed slowly and in 2020 the Owner commenced home building proceedings HB 20/33412 in the Tribunal.
4 The text of the work order appears in the application form to the renewal proceedings in the following terms:
5 The Builder recommenced work at the Property on or about 12 May 2021 following the work order but ceased work and vacated the Property on or about 10 December 2021.
6 The Owner commenced these renewal proceedings on or about 21 January 2022.
7 On 15 June 2022 the Builder issued the Owner with a Notice of Termination of the Contract.
8 By letter dated 20 June 2022 the Owner accepted the Builder's unlawful repudiation of the Contract and elected to terminate the Contract.
9 The renewal proceedings have been brought by the Owner now seeking a money order for the incomplete and defective home building work that the Builder failed to complete either within the time permitted in the work order, or at all.
(1) Reports of Mario Bournelis relied on by the homeowner dated 24 August 2022 (TB 2592-2868), 15 January 2023 (TB 2869-2956) and 13 February 2023 (TB 2957-2972).
(2) Report of Adam Alexander relied on by the Builder by dated 15 November 2022 (TB3013-3388)
(3) A joint expert report and Scott schedule dated 22 February 2023 (TB 3389-3427) prepared by the experts following a conclave held on 25 January 2023.
48K Jurisdiction of Tribunal in relation to building claims
(1) The Tribunal has jurisdiction to hear and determine any building claim brought before it in accordance with this Part in which the amount claimed does not exceed $500,000 (or any other higher or lower figure prescribed by the regulations).
(2) The Tribunal has jurisdiction to hear and determine any building claim whether or not the matter to which the claim relates arose before or after the commencement of this Division, except as provided by this section.
(3) The Tribunal does not have jurisdiction in respect of a building claim relating to building goods or services that have been supplied to or for the claimant if the date on which the claim was lodged is more than 3 years after the date on which the supply was made (or, if made in instalments, the date on which the supply was last made).
(4) The Tribunal does not have jurisdiction in respect of a building claim relating to building goods or services that are required under a contract to be supplied to or for the claimant on or by a specified date or within a specified period but which have not been so supplied if the date on which the claim was lodged is more than 3 years after the date on or by which the supply was required under the contract to be made or, if required to be made in instalments, the last date on which the supply was required to be made.
(5) The fact that a building claim arises out of a contract that also involves the sale of land does not prevent the Tribunal from hearing that building claim.
(6) The Tribunal does not have jurisdiction in respect of a building claim arising out of a building cover contract required to be entered into under this Act if the date on which the claim was lodged is more than 10 years after the date on which the residential building work the subject of the claim was completed.
(7) The Tribunal does not have jurisdiction in respect of a building claim arising from a breach of a statutory warranty implied under Part 2C if the date on which the claim is lodged is after the end of the period within which proceedings for a breach of the statutory warranty must be commenced (as provided by section 18E).
(8) The Tribunal does not have jurisdiction in respect of a building claim relating to -
(a) a contract for the supply of goods or services to which none of subsections (3), (4), (6) and (7) applies, or
(b) a collateral contract,
if the date on which the claim was lodged is more than 3 years after the date on which the contract was entered into.
(9) This section has effect despite clause 5 (Relationship between Tribunal and courts and other bodies in connection with Division functions) of Schedule 4 to the Civil and Administrative Tribunal Act 2013.
18E Proceedings for breach of warranty
(1) Proceedings for a breach of a statutory warranty must be commenced in accordance with the following provisions -
(a) proceedings must be commenced before the end of the warranty period for the breach,
(b) the warranty period is 6 years for a breach that results in a major defect in residential building work or 2 years in any other case,
(c) the warranty period starts on completion of the work to which it relates (but this does not prevent proceedings from being commenced before completion of the work),
(d) if the work is not completed, the warranty period starts on -
(i) the date the contract is terminated, or
(ii) if the contract is not terminated - the date on which work under the contract ceased, or
(iii) if the contract is not terminated and work under the contract was not commenced - the date of the contract,
(e) if the breach of warranty becomes apparent within the last 6 months of the warranty period, proceedings may be commenced within a further 6 months after the end of the warranty period,
(f) a breach of warranty becomes apparent when any person entitled to the benefit of the warranty first becomes aware (or ought reasonably to have become aware) of the breach.
........
(2) The fact that a person entitled to the benefit of a statutory warranty specified in paragraph (a), (b), (c), (e) or (f) of section 18B has enforced the warranty in relation to a particular deficiency in the work does not prevent the person from enforcing the same warranty for a deficiency of a different kind in the work (the other deficiency) if -
(a) the other deficiency was in existence when the work to which the warranty relates was completed, and
(b) the person did not know, and could not reasonably be expected to have known, of the existence of the other deficiency when the warranty was previously enforced, and
(c) the proceedings to enforce the warranty in relation to the other deficiency are brought within the period referred to in subsection (1).
48O Powers of Tribunal
(1) In determining a building claim, the Tribunal is empowered to make one or more of the following orders as it considers appropriate:
(a) an order that one party to the proceedings pay money to another party or to a person specified in the order, whether by way of debt, damages or restitution, or refund any money paid by a specified person,
(b) an order that a specified amount of money is not due or owing by a party to the proceedings to a specified person, or that a party to the proceedings is not entitled to a refund of any money paid to another party to the proceedings,
(c) an order that a party to the proceedings:
(i) do any specified work or perform any specified service or any obligation arising under this Act or the terms of any agreement, or
(ii) do or perform, or refrain from doing or performing, any specified act, matter or thing.
(2) The Tribunal can make an order even if it is not the order that the applicant asked for.
(3) Sections 79R and 79T-79V of the Fair Trading Act 1987 apply, with any necessary modifications, to and in respect of the determination of a building claim.
48MA Rectification of defective work is preferred outcome in proceedings
A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the responsible party) is to have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome.
8 Renewal of proceedings in respect of certain Division decisions
(1) If the Tribunal makes an order in exercise of a Division function in proceedings, the Tribunal may, when the order is made or later, give leave to the person in whose favour the order is made to renew the proceedings if the order is not complied with within the period specified by the Tribunal.
(2) If an order has not been complied with within the period specified by the Tribunal, the person in whose favour the order was made may renew the proceedings to which the order relates by lodging a notice with the Tribunal, within 12 months after the end of the period, stating that the order has not been complied with.
(3) The provisions of this Act apply to a notice lodged in accordance with subclause (2) as if the notice were a new application made in accordance with this Act.
(4) When proceedings have been renewed in accordance with this clause, the Tribunal -
(a) may make any other appropriate order under this Act or enabling legislation as it could have made when the matter was originally determined, or
(b) may refuse to make such an order.
(a) the operation of an order has been suspended, or
(b) the order is or has been the subject of an internal appeal.
Brief outline of the Tribunal's material findings.
(1) Whether the homeowner, on a renewal application, could claim for items that were not alleged to be defective in the original proceedings and which did not arise from work done by the builder under the work order? The Tribunal, relying on "extremely broad terms of the work order" D[273] allowed the homeowner to claim for defective work completed before she made her original claim, which was not alleged to be defective in the original proceedings.
(2) Whether the contract between the parties had been terminated and, if so, by whom, or whether it was still on foot. Both parties contended that the other had wrongfully repudiated the contract (the termination issues) (D[49] - [61]). This included an allegation that by seeking a money order in the renewal proceedings the owner had evinced an intention not to be bound by the contract. The Tribunal concluded that neither party had validly terminated or repudiated the contract and that it remained on foot while the work order was current (D[62] - [70]. The Tribunal made an order terminating the contract.
(3) Whether the work order made by consent on 4 May 2021 still remained on foot, or whether it had been terminated by the conduct of the parties or either of them? The Tribunal found that the work order remained on foot. (D[62] - [70]).
(4) The meaning of the work order, with particular reference to what is a "reasonable time" for the completion of the contracted works and what role the 6.5 months period for completion referred to in point 2 of the order (the note) was to play in deciding what was a reasonable time for the completion of the work ordered.
(5) Whether the extension of time provisions in the contract applied to the assessment of what was a reasonable time under the work order? The Tribunal held that they did not as the work order excluded them (D[69] - [72]).
(6) The Tribunal found that the builder's reasons for not complying with the work order did not constitute a reasonable explanation for the delay. In this regard the Tribunal rejected the builder's explanations relating to delays in complying with the work order being due to:
(a) claimed latent conditions causing delay (D[76] - [79]).
(b) changes to the scope of works (D[80]).
(c) claimed delays by the owner in approving quotes (D[81] - [93].
(d) the owner's failure to complete owner's works (D[94-[105].
(e) Covid-19 restrictions in NSW (D[106] - [107]).
(7) The homeowner's claim for the costs of rectifying defective works. The Tribunal reviewed the evidence with respect to each of the 19 claims and disallowed 5 of them with reasons. It allowed the rest but reduced the allowance for rectification costs in many of them. Of specific interest on the appeal is its consideration of the homeowner's claim for $59,790.00 for repairs to the verandah slab, which was 100 mm below the finish level of the dwelling, as per architectural plans (the verandah slab issue). The Tribunal ultimately allowed $5,000.00 for this: (D[157-167]). The total allowed by the Tribunal for defects was $38,400.00.
(8) The homeowner's claims for the costs of completing incomplete works. There were 21 claims considered by the Tribunal under this heading: D [209-265] . Five were rejected. The Tribunal allowed $214,531.09 for the costs of completion of the remaining sixteen. The builder had argued that these works were not incomplete because the homeowner had wrongfully repudiated the contract, thereby bringing the builder's obligations to an end before completion. As noted above, that argument failed.
(9) With respect to the builder's claim for payment of its unpaid invoices the Tribunal agreed that the builder should recover $46,074.00 for the work charged for in invoice 1323: TB 4079 ($54,484.00 claimed), but was not satisfied with respect to other four invoice: D [110-138].
(1) First, the Builder's invoices which the Tribunal considered appropriate in the sum of an $46,074.00 credit should be set-off against this sum, leaving a sub-total of $322,489.98 due by the Builder to the Owner; and
(2) Secondly, the sum of $46,074.00 must also be deducted from the remaining balance due on the Contract price of $117,376.53 (OCS [the owner's closing submissions] at p.63) as this sum has now been credited to the Builder by way of set-off. The remaining balance then reduces to $71,302.53 which must also be deducted from $322,489.98 leaving a final total payable by the Builder to the Owner of $251,187.45.
269 Both parties acknowledge that a sum of $117,376.53 is currently held in a solicitors' trust account on account of the Builder's fees for performing the work order. The funds appear to be those of the Owner and should be returned to the Owner forthwith. The Tribunal assumes that the parties can resolve that issue without the Tribunal's intervention based on the determinations made above but gives leave to the Owner to relist the proceedings before the Tribunal if that issue cannot be resolved.
(1) Whether, in renewal proceedings, it was open to the Tribunal to determine defects not claimed in the original proceedings?
(2) Whether the Tribunal asked the correct question when it determined that the builder had failed to comply with the work order within 6.5 months and that 6.5 months was a reasonable time within which those works should have been undertaken?
(3) Whether the Tribunal erred in law when it failed to take into account the builder's claimed entitlement to a reasonable extension of time under the contract.
Builder's ground 1 - The Tribunal's decision to treat the proceedings as Renewal Proceedings
23 In paragraphs 2-4 of the OCS [owner's closing submissions], the Owner raised the issue of whether these proceedings should be treated as termination proceedings as an alternative to renewal proceedings.
24 The Builder in its closing submissions submitted that the Tribunal in renewal proceedings was not empowered to consider defect claims that were not part of the original proceedings and were not items that have arisen as a consequence of the orders made in the original proceedings: Zahrouni v Vesta Homes Pty Limited [2023] NSWCATAP 49 at [63].
25 More specifically, the Appeal Panel stated in Devel Pty Limited v Lewis [2021] NSWCATAP 395 at [80]:
"Renewal proceedings are an enforcement mechanism which provides a remedy for non-compliance with Tribunal orders. They are restricted to claims relating to the consequences of the order in the original (sic) not being complied with. This will usually be the costs of undertaking the work specified in the work order. However, where other consequences have arisen as a result of that non-compliance (for example, water damage caused by defective waterproofing work), then the cost of rectifying that damage may be claimed in the renewal proceedings. However, renewal proceedings are not proceedings in which a new claim can be raised that was not raised in the original proceeding."
26 In Devel's case, the Appeal Panel then proceeded to exclude a number of items which were not part of the original claim and which are not items that had arisen as a consequence of the orders made in the original proceedings [81]. These items 'could not be considered as part of the renewal proceedings'.
27 For the avoidance of doubt, the Tribunal proposes to treat these proceedings as renewal proceedings and not as "termination proceedings", the reasons for which will become self-evident.
36 In the original proceedings, the Work Order was made by consent of the parties but in the Tribunal's consideration nothing arises from that.
37 The terms of the Work Order are so broad that it is possible that any work that the Builder was required to undertake under the Contract is within the terms of the renewal application. The only element that the Work Order appeared to add to, or vary, the Contract is a timeframe namely "within 6.5 months of recommencement".
Builder's ground 2 - The scope of the work order - did it extend to defects not previously claimed?
35 In our view, to give the word "appropriate" a narrow construction, so that circumstances or events occurring after the matter was originally determined could not be taken into account, would be inconsistent with the purpose of a renewal application. If, on such an application, the Tribunal could not consider facts and circumstances occurring after the original determination, this might often lead to the conclusion that the Tribunal should refuse to make any other order than that originally made. A renewal application is, however, designed to deal with a situation where there has been non-compliance with the original order that the Tribunal thought was appropriate when the matter was first determined. The circumstances will inevitably have changed since that time, if for no other reasons than because there has been non-compliance with the order that had been made. What was appropriate originally may well not be appropriate at the time of the hearing of the renewal application. To limit the orders that could be made on renewal to those that would have been appropriate when the matter was originally determined would be likely to prevent the Tribunal from doing justice between the parties, having regard to the non-compliance with the original order and to any other circumstances that had changed materially since the proceedings were originally determined. This would render the right to renew proceedings ineffective in a significant number of cases.
52 Our conclusions on the proper construction of cl 8(4)(a) of Sch 4 to the NCAT Act can be summarised as follows:
(1) On a renewal application, the Tribunal can make an order that is materially different from the order made when the proceedings were originally determined.
(2) Such an order must be suitable or fitting in light of the general law principles, whether legal or equitable, and statutory provisions applicable to the type of relief claimed on the renewal application as well as all other relevant circumstances, whether occurring before or after the proceedings were originally determined, including the fact that the order originally made has not been complied with within the time specified in the order and that a renewal application has been made.
(3) Such an order must be one that the Tribunal has authority to make under the NCAT Act or the relevant enabling legislation.
(4) Such an order must be one that the Tribunal had authority to make when the proceedings were originally determined, having regard to the specific legislative provisions under which the original application was made, but the order does not have to be an order that would have been appropriate in the circumstances when the proceedings were originally determined.
43 If we had to find afresh on the basis of the words in clause 8 taken together with their appearance in a Part headed "Special practice and procedure" and interpreted with the assistance of a specific heading "Renewal of proceedings in respect of certain Division decisions", we would come to the view that there is nothing by way of limitation in clause 8 that restricts the Tribunal in a renewal application to the relief claimed in the originating application being renewed, whether or not there was existing evidence to support a new claim for relief already before the Tribunal in relation to the originating application.
44 This interpretative assistance reinforces the purpose, object and context of the renewal power. It is not simply an aid to enforce the Tribunal's existing orders as clause 4(a) makes clear in its reference to "make any other appropriate order". There is no restriction in the clause to the existing material before the Tribunal or its existing findings on that material.
45 Rather, it is to consider what to do next given a non-compliance, but not to rehear the substantive merits already determined, and to do that on the basis of material put forward by the parties relevant to the issue of what to do next. As was said in Akratos v Papadopoulos [2016] NSWCATAP 139 at [36]:
the purpose of the renewal proceedings was to consider, in light of the fact that the original order was not complied with, what other appropriate orders it could have made when the matter was originally determined and not to reconsider the substantive merits of the respondent's building claim.
46 In a residential tenancy context that may mean a termination. In a home building context that may mean substituting a money order for the original work order. The presence of such a broad power is more likely than a narrow reading to achieve the purpose or object of having the Tribunal's original orders complied with in a timely fashion. It also may facilitate a just, quick and cheap resolution, in accord with the guiding principles in CATA s 36, of any difficulty with performance of the original orders.
48 Accordingly, we consider that, on the submissions before him, the primary member erred in law in declining jurisdiction to consider the compensation claim on the basis that it was not in the originating claim and that it was an order that was not "open to the Tribunal at the time of the original orders". The phrase just quoted does not paraphrase the correct meaning of the italicised words in clause 8. Those italicised words mean any order that the Tribunal had jurisdiction and power to make, whether or not such an order was expressly claimed at the time, and the applicable legal principles and evidence permitted it to make.
(1) Arising as a result of the builder carrying out rectification work;
(2) That had been observed subsequent to the Tribunal's orders; or
(3) That were part of the owners' original claim but were not contained in the Tribunal's orders.
There is nothing in Bondarek that is authority for the proposition that in the renewal proceedings the Tribunal could have awarded compensation for an entirely different breach of the tenancy agreement, such as (for example) a failure to repair the kitchen, in circumstances where there had been no claim or orders concerning the kitchen in the original application.
80 In our view, there is nothing in the Appeal Panel's reasoning in Blessed Sydney Constructions to support a conclusion that in renewal proceedings the Tribunal can make an order concerning a claim that was not made in the original proceedings. Renewal proceedings are an enforcement mechanism which provides a remedy for non-compliance with Tribunal orders. They are restricted to claims relating to the consequences of the order in the original not being complied with. This will usually be the cost of undertaking the works specified in the work order. However, where other consequences have arisen as a result of that non-compliance (for example, water damage caused by defective waterproofing work), then the cost of rectifying that damage may be claimed in the renewal proceedings. However, renewal proceedings are not proceedings in which a new claim can be raised that was not raised in the original proceedings.
81 As Items 26 to 29 were not part of the original claim and are not items that have arisen as a consequence of the orders made in the original proceedings, they could not be considered as part of the renewal proceedings. We conclude that the Tribunal erred in finding that they could be considered as part of the renewal proceedings on the basis of authorities such as Bondarek and Blessed Sydney Constructions. Items 26 to 29 had to be considered as a new claim, to which the relevant time limitation periods under the HB Act applied.
82 The claim in respect of Items 26 to 29 should have been made in a separate application under the HB Act, rather than on the same application form as the application in the renewal proceedings. There are circumstances in which it would be appropriate for the Tribunal to exercise its discretion to allow both renewal proceedings and a claim for items that were not part of the original claim to be set out in the same application form; for example, if an application in respect of the new claims would be time barred if the Tribunal insisted on a separate application. Allowing the renewal proceedings and the claim in respect of new items to be set out in the same application form in such circumstances would be consistent with the guiding principle under s 36(1) of the NCAT Act; that is, the resolution of the real issues in dispute in a manner that is just, quick and cheap. It would also be consistent with the Tribunal's obligation under s 38(4) of the NCAT Act to act "with as little formality as the circumstances of the case permit and according to equity, good conscience and the substantial merits of the case without regard to technicalities or legal forms.
(i) the date the contract is terminated, or
(ii) if the contract is not terminated - the date on which work under the contract ceased, or
(iii) if the contract is not terminated and work under the contract was not commenced - the date of the contract, ...
... the time limits for statutory warranty proceedings in the Tribunal strictly apply under ss 48K (7), 3B and 18E of the HB Act; and time cannot be extended under s 41 of the NCAT Act. (see the discussion of time limits for breach of statutory warranty claims in Baserite Constructions Pty Ltd v Tanios [2022] NSWCATAP 347 ('Tanios') at [134]-[139] and Onslow v Cullen [2022] NSWSC 1257 at [52]- [62]).
... in proceedings involving the HB Act, the Tribunal is not empowered in renewal proceedings to consider defect claims that were not part of the original proceedings and are not items that have arisen as a consequence of the orders made in the original proceedings.
In determining the meaning of the terms of a commercial contract, it is necessary to ask what a reasonable businessperson would have understood those terms to mean. That enquiry will require consideration of the language used by the parties in the contract, the circumstances addressed by the contract and the commercial purpose or objects to be secured by the contract.
Ground 3 - the Tribunal's conclusion that the work order required completion within 6.5 months.
The only element that the Work Order appeared to add to, or vary, the Contract is a timeframe namely "within 6.5 months of recommencement".
It is also clear from the terms of the Work Order and the notation in paragraph 2 of the Work Order that the parties sought completion of the works under the Contract "within a reasonable time" and that based on the Builder's proposed and amended project schedule, the Builder would provide for the completion of the works within 6.5 months of the Builder's recommencement. This was apparently acceptable to the Builder.
(1) First, it lacks specificity. In one sense it says no more than that the Builder will complete the Contract "within a reasonable time";
(2) Secondly, it notes that the Builder has proposed an amended project schedule for the completion of works within 6.5 months of recommencement. Although this does not appear to be part of the order, it nevertheless notes some informal estimate for completion by the Builder which the Owner apparently accepts and which varies the terms of the Contract;
(3) Thirdly, it does not refer to specific tasks, defects, variations or changes which may have accrued or been considered in the original proceedings under the Contract.
It is apparent on the evidence that the Owner commenced renewal proceedings because the Builder had vacated the Property, the Work Order had not been completed within the agreed 6.5 months, referred to in note 2 of the Work Order.
70 For these reasons, provisions in the Contract in relation to extension of time cannot be imputed into the Work Order either to extend the time for compliance by the Builder with the Work Order or to provide additional time to the Builder in circumstances where the Owner may not have consented.
71 The Tribunal concludes this because first, the Extension of Time provisions in the Contract were not raised upfront or to excuse the Builder's delay; and secondly because the agreement to conclude the work under the Contract was an express variation to the Contract which was contained in the Work Order.
72 For these reasons, the Tribunal finds that the Builder has breached the terms of the Work Order by failing to complete the works under the Contact within the time specified in the Work Order.
38. ... notation D to the 2009 orders, though having no legal consequence, suggested that the magistrate hoped that the attitudes and insight of the applicant would improve over time, with the possibility of unsupervised visits being held out as an incentive.
...
39. This ground is also misconceived on a number of levels. First, the notation did not in terms constitute a "finding", nor did it "reflect" a finding. Secondly, even if the Court had made such a finding, it was open to be reviewed in the light of subsequent events. Thirdly, although it was not, as the applicant suggested, a "mere aspiration by the parties" it may have reflected an aspiration of the magistrate in 2009. It had no legal relevance.
What constitutes a reasonable time is a question of fact which will depend on the context in which the right arises and the circumstances of each particular case: see Cavallari v Premier Refrigeration Co Pty Ltd [1952] HCA 26; (1952) 85 CLR 20 at 26 per Dixon CJ, McTiernan, Fullagar and Kitto JJ. As Brennan J said in Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537, '[i]ts limit is determined by reference to what is fair to both parties' at the time of the exercise of the right: at 567-8; [1982] HCA 29; see also K & M Prodanovski Pty Ltd v Calliden Insurance Ltd [2012] NSWCA 117 at [48] per Meagher JA (with whom Macfarlan JA and Tobias AJA agreed), citing Crawford Fitting Co v Sydney Valve & Fittings Pty Ltd (1988) 14 NSWLR 438 at 444 per McHugh JA (with whom Priestley JA agreed)."
101 One important observation that needs to be made with regard to the primary judge's exposition of principle relates to his statement that the limit of what is a reasonable time is to be determined by what is fair to both parties at the time of the exercise of the right. The passage cited from Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537; [1982] HCA 29 (Perri) does not indicate when the content of what is a reasonable time is to be assessed. It does not stand for the proposition that it is to be assessed at the time of the actual exercise of the right, although that is of course the point of time by reference to which the court will assess whether a reasonable time (within the meaning of the contract on its proper construction) has passed. This is a subtle but important distinction. In my opinion, the relevant time for considering what is in fact a reasonable time is the time at which, under the contract, the right which is to be exercised is first capable of being exercised (just as the time for assessing whether a notice to complete affords a reasonable time for completion is the time of the giving of the notice: see Crawford Fitting Co v Sydney Valve & Fittings Pty Ltd (1988) 14 NSWLR 438 at 444). As I point out at [109] below, the time for ascertaining the legal meaning of "reasonable time" must be the time of contracting.
...
104 What is a reasonable time in any given case may be affected by the nature of the obligation to be performed (for example, whether it is dependent on some third party performance or circumstances outside the control of the party under the obligation) or the right to be exercised (for example, whether the right is dependent upon the provision of some information that may need to be assessed before the right can be exercised or simply upon the happening of an event or the passing of a particular time).
105 In Ellis v Thompson [1838] EngR 85; (1838) 3 M & W 445; 150 ER 1219, cited by Dixon J in Reid, Baron Alderson said (at 456-457; 1224-1225 of ER) that:
"It seems to me the correct mode of ascertaining what reasonable time is in such a case as this, is by placing the Court and jury in the same situation as the contracting parties themselves were in at the time they made the contract: that is to say, by placing before the jury all those circumstances which were known to both parties at the time the contract was made, and under which the contract itself took place. By so doing, you enable the Court and jury to form a safer conclusion as to what is the reasonable time which the law implies, and within which the contract is to be performed." (Emphasis added)
109 The other significant point to note about this passage is that the legal meaning of what is a reasonable time is to be ascertained as at the date of the contract, although what will be reasonable as a matter of fact will inevitably fall to be assessed by reference to circumstances as at the date on which the right is first capable of being exercised (or the date on which the obligation falls to be performed), viewed in the context of the contract as a whole. This accords with the passage from Ellis v Thompson cited above, and is also consistent with the endorsement in Agricultural and Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570; [2008] HCA 57 at [35] by Gummow, Hayne and Kiefel JJ of Lord Reid's statement in James Miller & Partners Ltd v Whitworth Street Estates (Manchester) Ltd [1970] AC 583 at 603 that "... it is not legitimate to use as an aid in the construction of [a] contract anything which the parties said or did after it was made." (Emphasis added).
Ground 4 - The completion date required by the work order.
The question for determination by the Appeal Panel is whether the Tribunal should have found that the builder was required to complete the work under the contract within 6.5 months or whether the builder was required to complete the work under the contract within "a reasonable time".
Grounds 5 in part, 6, 7, 8 in part, and 9 - Whether the homeowner had repudiated the contract having regard to the surrounding circumstances.
50 As stated above, there was no vacation of the Work Order at that time (it remains on foot to this day) and any intention to bring the Contract to an end must be express and clear, not implied as the Builder suggests.
51 Cases proffered by the Builder in support of this submission including Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98 where, at [68]-[69], the Appeal Panel stated:
"It is inherent in the making of this renewal application, in which a money order is sought in lieu of the work order, that the homeowner was no longer holding the builder to performance of the contract that was the subject of that work order. By her renewal application, the homeowner was seeking in effect to terminate the contract because of the builder's breach of the contract, which is also of value to comply with the work order."
52 But when is the contract terminated or brought to an end? The Appeal Panel states 'when the original work order is vacated': see Blessed at [69]. Also at [60] in Blessed, the Appeal Panel states that contract is terminated 'when the Tribunal made the order for payment of money on 30 October 2017 in consequence of the renewal application'. That is yet to occur in these proceedings and will only occur when final orders are made in this decision.(Original emphasis).
The Tribunal accepts the Owner's submissions at paragraph 26 of the OCS namely that:
(a) The Contract cannot be terminated whilst it is the subject of a work order, especially in the broad terms of this Work Order which embrace the Contract;
(b) The Work Order continues to operate until it is complied with or vacated either by the Tribunal or by consent of the parties; and
(c) The Builder cannot relieve itself of its contractual obligations by purporting to terminate the Contract, especially on the specious grounds alleged in the notice of termination dated 15 June 2022.
40. ... When such an order is vacated on a renewal application, the builder is no longer required to comply with the contract and termination of the contract can then occur. By seeking to replace the work order with an order for payment of money by way of damages, the owner has in effect exercised the right to terminate the contract, subject to the Tribunal's deciding to relieve the builder from complying with the contract. ...(Our emphasis)
41 Taking this approach in renewal proceedings does not, in our view, inappropriately restrict the Tribunal's ability to enforce its work orders. A similar approach applies where a Court with equitable jurisdiction has made an order for specific performance of a contract and there has been non-compliance with that order. The approach taken in such cases is explained in Spry (at 677-8) as follows:
"... when, for example, an order for specific performance has been made but the defendant does not comply with it, it is unnecessary to commence new proceedings for damages and it is sufficient to apply to the court for dissolution of the order for specific performance and for permission to accept the defendant's repudiation and for an order declaring the contract to be terminated; and an award of damages may thereupon be made. ... Where however the order for specific performance is dissolved, and damages are substituted, in the absence of special equitable considerations the measure of damages is determined by reference to the ordinary basis on which legal damages are calculated." (footnotes omitted)
42 In this context, it should be noted that, under s 48O(3) of the HB Act, s 79U of the Fair Trading Act 1987 (NSW) (the FT Act), among others, applies, with any necessary modifications, "to and in respect of the determination of a building claim". Section 79U requires that "the Tribunal must be satisfied that the orders will be fair and equitable to all the parties to the claim." By these provisions in s 48O of the HB Act and s 79U of the FT Act, the Tribunal is empowered and required, in effect, to give effect to both legal and equitable principles which are applicable to the type of relief sought in a home building matter. This continues, in our view, to be the case, when the Tribunal is determining which orders are "appropriate" on a renewal application under cl 8 of Sch 4 to the NCAT Act in respect of such a matter.
As after a decree of specific performance there can be no termination without the leave of the court, the only appropriate method of procedure is to write a letter to the party allegedly in default indicating that a notice of motion seeking termination will be filed if there is no action by the opponent.
Grounds 10 and 11 - Builder's explanation for delay in complying with the work order
(1) The homeowner's refusal to sign the "approval of quotes" (variations) for quotes 293, 296, 299, 300, 301, 302.01 and 303.01 which form the basis for to extensions of time # 8, 9 and 10 relate. The Tribunal rejected the builder's explanation, at D [82] - [93], accepting that the homeowner had reasonable grounds for rejecting the proposed variations.
(2) COVID-19 delays which form the basis of extension of time # 3. The Tribunal at D[106] -[108], wrote:
106 The Builder also claimed that restrictions associated with the COVID-19 pandemic delayed the contract works. Although this claim is broad and unspecified, the Owner submits that only one extension of time notice dated 15 July 2021 refers to a delay caused by the pandemic and seeks an extension of 20 business days.
107 In addition, although it was not the subject of specific evidence, it was known at the time that first, the building industry was generally regarded as an exemption to COVID-19 restrictions in NSW and secondly, that the impact of the pandemic in regional areas was generally less severe than in urban areas.
108 For the above reasons, and on a review of the relevant evidence, the Tribunal concludes that the Builder has not made out grounds to justify his failure to comply with the Work Order.
... This Court has said on a number of occasions that, although there can be no universal rule, it is important for intermediate courts of appeal to consider whether to deal with all grounds of appeal, not just with what is identified as the decisive ground. If the intermediate court has dealt with all grounds argued and an appeal to this Court succeeds, this Court will be able to consider all the issues between the parties and will not have to remit the matter to the intermediate court for consideration of grounds of appeal not dealt with below.
159 The Owner submits that:
(1) The stamped and certified plans (202, 204 - 228) show a 100 mm step down between the verandah and bedroom 4 and 5 (211);
(2) Detail 3 on sheet 9B of the stamped and certified plans (214) also show the 100 mm step down as does sheet 9C (215). Section 4.16(12) of the Environmental Planning and Assessment Act 1979 (NSW) (EPA) states the construction certificate and any approved plans and specifications issued with respect to that construction certificate are taken to form part of the relevant development consent;
(3) Section 4.2(1)(b) of the EPA provides that a person must not carry the development out other than in accordance with the development consent, so the Builder has contravened this section;
(4) In constructing the concrete slab in contravention of s. 4.2 of the EPA Act, the Builder has contravened s. 18B(1)(c) of the HBA; and
(5) The Builder is therefore liable to compensate the Owner for the loss suffered by reason of this building defect in the sum of $59,790.00, the sum assessed by Mr Bournelis in the JER.
160 The Builder by contrast submits:
(1) This item was not claimed in the original proceeding (although it existed at that time) and is therefore beyond the permissible scope of renewal proceedings;
(2) A contravention of s. 18(1)(c) of the HBA was not specifically pleaded and should not be allowed now when the Builder had no warning prior to the close of evidence;
(3) The only available evidence from Broken Hill City Council (Council) is that the slab as constructed is compliant with the development consent;
(4) The Builder claims that the Owner expressly instructed and directed the allegedly non-compliant slab to be constructed.
161 The matter is also complicated by the existence of several reiterations (sic) of plans being:
(1) The 2018 Plans (3619 - 3639) showing a pier and joist foundation system which runs consistently flat across the dwelling and verandahs (3626). The Builder's quote Q1004 was based on these plans (2976);
(2) The 2018 Plans Rev 2 (3687) showing a slab system which runs consistently flat across the dwelling and verandas, and which was provided by the Owner's draughtsman, Paul Bessel (2978);
(3) The 2019 Plans (3721) showing a slab system which has a 100 mm drop down at the verandahs (2982), but the Builder alleges the Owner directed it not to build to these plans but rather to construct the slab as per the 2018 Plans Rev 2 (2981 - 2).
162 The Builder's expert, Mr Alexander, relies on uncertified 2018 Plans to support his conclusion that the slab is not defective (3396), which is itself unsatisfactory.
163 In all the circumstances, the Tribunal concludes that the concrete slab is in breach of the development approval and therefore in breach of s.18B(1)(c) of the HBA; see The Owners - Strata Plan No. 66375 v King [2018] NSWCA 170 at [402] Shanahan v Erwin Fornasier [2021] NSWCATAP 158 at [63] - [69].
164 The Tribunal dismisses the evidence of the Builder that the concrete slab was constructed in the manner in which it was based upon the Owner's express instructions. Although the oral evidence on this issue was uncertain, there is no written document or communication which supports such a claim or such instructions.
165 The Tribunal acknowledges that the concrete slab as constructed is 100 mm below the verandah flooring and in breach of the development approval. However, it is unclear what flows from that.
166 The Owner has resided, and continues to reside, in the Property. There was no evidence at the hearing to suggest that the occupancy of her or her family members had been impeded because of this defect. If this does became an issue between the Owner and the Council, then it is open to the Owner to apply to the Council for an amended Development Consent. This appears to be a more efficient and cost-effective way of dealing with this issue than tearing up and replacing the slab with one 100mm higher.
167 The Tribunal allows the Owner the sum of $5,000.00 for this contingency and to cover her costs of applying for an amended development consent.
Its not at the stage where an OC can be obtained. Senior Member, your question is to what the issue may be. The issue may be that the OC is not issued because the slabs not built in accordance with the construction certificate, council approved plans.
"... In the present case, the respondent was entitled to have a building erected upon her land in accordance with the contract and the plans and specifications which formed part of it, and her damage is the loss which she has sustained by the failure of the appellant to perform his obligation to her. This loss cannot be measured by comparing the value of the building which has been erected with the value it would have borne if erected in accordance with the contract; her loss can, prima facie, be measured only by ascertaining the amount required to rectify the defects complained of and so give to her the equivalent of a building on her land which is substantially in accordance with the contract.
The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt. No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of demolishing the walls and re-erecting them in second-hand bricks. In such circumstances the work of demolition and re-erection would be quite unreasonable or it would, to use a term current in the United States, constitute "economic waste". (See Restatement of the Law of Contracts, (1932) para 346). We prefer, however, to think that the building owner's right to undertake remedial works at the expense of a builder is not subject to any limit other than is to be found in the expressions "necessary" and "reasonable", for the expression "economic waste" appears to us to go too far and would deny to a building owner the right to demolish a structure which, though satisfactory as a structure of a particular type, is quite different in character from that called for by the contract. Many examples may, of course, be given of remedial work, which though necessary to produce conformity would not constitute a reasonable method of dealing with the situation and in such cases the true measure of the building owner's loss will be the diminution in value, if any, produced by the departure from the plans and specifications or by the defective workmanship or materials.
As to what remedial work is both "necessary" and "reasonable" in any particular case is a question of fact. But the question whether demolition and re-erection is a reasonable method of remedying defects does not arise when defective foundations seriously threaten the stability of a house and when the threat can be removed only by such a course. That work, in such circumstances, is obviously reasonable and in our opinion, may be undertaken at the expense of the builder. As we have already said the appellant does not seek to challenge the finding of the learned trial judge that the existing foundations are such as to threaten the stability of the building and the question which arises in this case is therefore whether demolition and rebuilding is the only practicable method of dealing with the situation that has arisen. This was followed in Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8 where the Court explained, at [19] that:
The "qualification" referred to in the passage quoted above that the "work undertaken be necessary to produce conformity" meant, in that case, apt to conform with the plans and specifications which had not been conformed with. Applied to this case, the expression "necessary to produce conformity" means "apt to bring about conformity between the foyer as it would become after the damages had been spent in rebuilding it and the foyer as it was at the start of the lease"...
186 The general principle on which damages are recoverable by a building owner for breach of a building contract is the cost of making the work or building conform to the contract, subject to the qualification that not only must the work be necessary to produce conformity, but it must also be a reasonable course to adopt: Bellgrove at 617-618; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; [2009] HCA 8 at [15]. In the latter case, the court indicated that the test of unreasonableness is only to be satisfied by fairly exceptional circumstances: at [17].
Works Completed, currently outstanding - To be paid by client
Works completed (that have not been invoiced but are part of the remaining stage claims):
- slab battens installed through out
- ceiling battens installed through out
- wall & ceiling insulation on site
- internal built in robe framing for cavity sliding door unit openings
- internal brick openings cut through out
- internal steel lintels installed above brick openings
- first coat of hard set plaster to openings
- laundry door install inc. lock set
- internal wet areas niches framed
- external timber fascia primed and painted
- external verandah framing primed
- decorative timber fascia installed to front gable
- installation of 4 x dorma vents to roof
- external down pipes installed
- All materials & labour associated with above completed tasks.
- Builder supervision & mark up + 15%
133 In relation to the third item listed in the invoice, wall & ceiling insulation onsite, Mr Bournelis was apparently instructed that the insulation had been removed from the site however photographs clearly show insulation installed to the wall cavity (2614) which Mr Bournelis subsequently confirmed in cross-examination [10761-10770] .In his later report of 15 January 2023 Mr Bournelis had asserted that the Builder "did not bring the project to the point where insulation could be fitted" (2890).
134 Mr Alexander for the Builder reviewed the work purportedly undertaken in the invoice more carefully and allocated a percentage completed to each of the 15 or so items listed in the invoice. He then applied estimates for those that were not 100% completed of the cost to complete those tasks and allocated the sum of $8,410 to this.
135 The Builder acknowledged some discount was appropriate.
136 In respect of this item the Tribunal prefers the better and more considered evidence of Mr Alexander on this item and awards the Builder a set off in the sum of $46,074.00.
137 Accordingly, the Tribunal calculates in respect of each of the Builder's invoice the amounts which should be permitted to be set off against the Owner's claim as follows:
...
138 The Tribunal notes that if there is any issue about the circumstances of the Builder invoicing these amounts or whether the Contract was on foot at this time, the Builder would be in any case entitled to these amounts on a quantum meruit claim as the balance of evidence suggests that the above work was done by the Builder in that sum and the Owner has received the benefit of that work in that sum. In these circumstances, it is only fair and equitable that the Builder be reimbursed for these amounts.
(1) Given the builder's representatives concessions in cross-examination that four of the fourteen items in the invoice were improperly included in the invoice, and one had been paid, there was no basis upon which the amount owning could be calculated. The items the builder conceded should not be included in the invoice were:
wall & ceiling insulation on site
internal brick openings cut through out
internal steel lintels installed above brick openings
first coat of hard set plaster to openings
(2) The works for the final stage were not completed and therefore payment was not due.
(4) In addition, the practice and procedure of the Tribunal should be implemented so as to facilitate the resolution of the issues between the parties in such a way that the cost to the parties and the Tribunal is proportionate to the importance and complexity of the subject-matter of the proceedings.
2A. Joint Responsibilities of the Builder and Owner
The Parties acknowledge the fact that the amount payable by the Owner under this contract and the time taken to carry out the work is subject to change for various reasons, As at the date of the contract the work detailed in Schedule 3 is work which can be carried out for the contract sum.
The contract sum will be affected by the impact of choices made and work done under the provisional sum and prime cost allowances as well as the various other matters listed on the page 1 warning as to matters which may change the contract price. The Parties agree that:
a) they will conduct regular meetings in order to:
i) review the work done and money paid under the contract; review the work to be done and the amount payable for such work; and iii) make decisions and choices regarding work under the contract covered by "allowances" (see Schedule 2 point 11) and required by variations (see Clause 14) so that the work to be paid for by the Owner is consistent with the Owner's capacity to pay.
b) any adjustments to the work to be done under the contract are to be recorded in writing and signed by both parties. If such adjustment comprises a variation under Clause 14, the variation should be valued under that clause and the contract price adjusted Builder accordingly.
c) they will act co-operatively and in a manner which progresses the works.
d) either party may require a meeting to be held within five (5) days of a written request for a meeting. Both parties must attend such a meeting. The party if the calling the meeting will identify issues to be covered at the meeting.
The Builder will provide a report on the matters raised at the meeting within a reasonable time but no later than ten (10) business days after the meeting.
d) provide written instructions to the Builder, where required, in a timely and proper manner so as to avoid delay to the works. This specifically relates to variations, directions and instructions in relation to work under the contract.
11 . Delays and Extensions of Time
a) Should the progress of the works be delayed by any of the following matters, conditions or consequences resulting from them:
i) variations;
ii) suspension of the works under Clause 21;
iii) latent conditions affecting the site, the ability to carry out work or requiring work;
iv) ...
v) any act, default, delay or omission on the part of the Owner including, but not limited to, providing instructions, making payment or doing a thing necessary to allow the works to proceed (including signing instructions concerning variations);
vi) delay in having a mandatory inspection carried out by the PCA or an authorised person;
vii) an instruction by the Owner to stop the works;
viii) ...
ix) civil commotion or industrial dispute affecting any of the trades employed upon the works or the manufacture or supply of materials for the works;
x) inclement weather and the effect of weather on site access, site safety or the ability to do the work;
xi) ...
xii) any other cause, thing or matter beyond the reasonable control of the Builder, such as trade shortages or material shortages, which affect the Builder's ability to do the work;
then in any such case the Builder must receive a fair and reasonable extension of time to the Construction period.
Builder to Advise of Matters Causing Delay
b) i) The Builder is to notify the Owner in writing of any matters which cause delay, within a reasonable time of becoming aware of their occurrence, together with an extension of time to the Construction Period, if it is known .
ii) If the period of delay referred to in Sub-Clause (i) is not known at the time of that notice then the Builder shall issue a further notice after the period of delay is determined stating the extension of time to the Construction Period.
c) Should the Owner not dissent, in writing from the above notification within five (5) days, the Construction Period will be extended by the period claimed in the notification under Sub-Clause (b).
d) Delay in notifying or a failure to notify a delay will not of itself prohibit an extension of time provided the matter which is claimed to cause delay is shown to cause delay to the works.
e) The Builder must use his best endeavours to minimise any delay.
Compensation to Builder for Delay not caused by Builder
f) ...
14. Variations - How to Deal with Changes to the Work
a) The works may be varied by such things as:
i) execution of additional work;
ii) decreases in or omissions from the works;
iii) changes in the character or quality of any material or work such as may be necessary due to the existence of a latent condition;
iv) changes in the levels, lines, positions or dimensions of any part of the works.
b) For the sake of clarity, a variation is established by:
i) written instructions from the Owner or the Owner's representative; and or
ii) the supply to the Builder of post contract details such as drawings; and or
iii) the discovery of an otherwise unknown or latent condition; and or
iv) ...
c) The Builder is not obliged to vary the Contract works or carry out any extra work unless the Builder consents. Such consent will not be unreasonably withheld.
d)
i) If the Builder agrees to undertake a variation requested or required by the Owner, the variation is to be detailed in writing and signed by the Owner (or the Owner's agent) and the Builder. Documents detailing the variation, including as appropriate, amended drawings or specifications, become contract documents.
ii) The Builder may require, prior to the execution of any variation that the Owner produce evidence, satisfactory to the Builder, of the Owner's capacity to pay for the variation.
Builder to Advise Value of Variations
e) The Builder, within a reasonable time of receipt of instructions to execute a variation (i.e. an instruction signed by the Owner or Owner's agent), is to notify the Owner, in writing, of the value of the variation.
Less Work due to a variation
f) ...
Additional work due to a variation
g) Where the work to be done is increased, the cost of the extra work is to be added to the contract price. The Builder can choose when and how often to claim payment for variation work and is not required to wait until the next stage claim.
h) Where a price has not been previously agreed for additional work, the Builder may proceed with the variation work and the price to be paid for the work will be the cost as calculated in accordance with Sub-Clause (i) below, together with the allowance specified in Item 1 of Schedule 2 for supervision, overhead and profit.
i) The cost referred to in Sub-Clause (h) above, unless otherwise agreed, will be calculated as follows:
i) for work by the Builder's employees, the rates for such labour are those set out in Item 2 of Schedule 2. If no rates are shown, then the rates to be used are the rates published by the Master Builders Association of NSW current at the time the variation is made; ii) where the work or some part of it is executed by a sub-contractor, the cost to be paid under Sub-Clause (h) above is the amount properly paid or payable to the sub-contractor which will be established by provision of a proper tax invoice from the sub-contractor engaged to do the extra work.
iii) the price for materials is the cost of the materials to the Builder. The Builder is not entitled to any discount other than a discount for prompt or cash payment.
All Directions Concerning Work are to be Given to the Builder
j) Neither the Owner nor any duly appointed representative will give or are entitled to give at any time directions to the Builder's workers or subcontractors concerning the works or any part thereof. All instructions are to be given to the Builder and are to be in writing.
(2) Any agreement to vary this contract, or to vary the plans and specifications for work to be done under this contract, must be in writing signed by or on behalf of each party to this contract.
In cll 2A(b) and 14(d)(i) the parties agreed upon the manner in which any requested or required variation would become contractually binding, namely by bringing into existence written details signed by both of them. They also agreed at cl 3(d) that, apart from any terms implied by statute, "the whole of the terms, conditions and warranties of this Contract are set out in the Contract". They bound themselves not to make agreements varying the works to be performed except in accordance with cl 14 and in particular sub-cl (d)(i). If the contract left it open to the parties to make separate simple contracts to vary the works, without complying with sub-cl (d)(i), that would be inconsistent with the statutory term referred to above and would be unenforceable.
21 . Suspension of Work
a) Should the Owner:-
i) fail to pay or cause to be paid any payment or any part thereof including an amount for GST within the time required by Item 4 of Schedule 2;
ii) fail to confirm in writing instructions regarding an Owner requested or required variation to the works;
iii) fail to provide written instructions in a manner and time so as to reasonably avoid delay to the progress of works;
iv) ...;
THEN the Builder may, without prejudice to his right to determine this Contract, suspend the works.
Suspension pursuant to this clause will act as a bar to any claim for damages, compensation or offset by the Owner against the Builder which relates to the period of suspension or consequences of such suspension.
b) The Builder is to give notice in writing of any suspension under sub-clause (a) to the Owner.
c) Should the Owner direct the Builder to not proceed with the works then without prejudice to the Builder's right to terminate this Contract or to claim delay costs pursuant to Clause Il(f), the Contract is automatically suspended.
d) The parties must, in relation to a dispute as to payment or otherwise, conduct a meeting pursuant to Clause 26. Please refer to Clause 26.
(1) Delays due to variations/adjustments where the builder claimed an extension of time due to the homeowner not providing written instructions - extensions of time # 1, 2, 4. 5 and 7.
(2) Delays due to COVID which were beyond the reasonable control of the builder - extension of time # 3.
(3) Delays due to latent conditions - extensions of time # 5 and 8.
(4) Material supply delays - extension of time # 9 and 12.
(5) Delays due to owners work being incomplete - extensions of time # 9, 10, 12, 13, 14, and 15
Delays due to no instructions being given for variations/adjustments
In regard to the rear entrance door, thanks for providing a quote on the variation I requested in March 2020, however the variation to change the design of the back door is no longer required. The rear door is to be constructed as per the contract. The contract refers to the council approved plans and quote 1004, the rear door is detailed in these documents.
Thanks for providing the quote and confirming those details.
While I'll still go ahead with the cavity sliding doors for the 4 x wardrobes and get you to purchase those from Barriers using some of the PC allowance allocated for wardrobes, I won't proceed with your quote to install them. Due to the price you've quote, I'll find an alternative to carry out these tasks which you've identified aren't in quote 1004:
• Install selected cavity sliding door units x 4 and hang the 4 doors
• supply & install architraves around 4 x wardrobe openings
• pack wall to bedroom 2 due to extra wall thickness and plaster that 1 wall
• paint 4 x wardrobe doors, 1 wall in bedroom 2 where plaster is patched, paint architraves around the 4 wardrobe door openings
On 2 September 2021, I asked that you order the cavity units and doors from Barrier can you please confirm these have been ordered?
Robes have not been ordered, as we were waiting for confirmation and directions from you regarding Quote 288. We do not order materials until directions regarding variations or allowance changes have been supplied.
Please see attached Allowances Agreement. Once this has been signed and returned, we will order materials as per your supplied Barrier Timber Suppliers Quote 17486.
I changed some of the contents of the supposed "Allowance Agreement" provided by the Builder. I did not agree to its original wording because it does not reflect what I agreed to. I changed the document to include the words "expenditure of allowance" rather than "reduction of allowance" as it wasn't my intention to reduce the allowance but to spend it on certain items. Given the previous history with the Builder, I was wary about what the Builder was insisting I sign.
(1) While the contract required that any adjustment to it be recorded in writing and signed by the parties, the contract did not require that the necessary writing be as required or stipulated by the builder. Any adjustment was to be agreed between them. While the homeowner had a duty to act cooperatively under cl 2A(c), that did not require that she obey the builders directions as to the form and wording of adjustments. They were to cooperate in agreeing to proposed adjustments, so that the written record reflected their agreement, not how one party saw it.
(2) The homeowner was not required by the contract to agree to the builder's formulation of any changes to Prime Cost items or variations.
(3) The homeowner rejected the builder's quote, which it purported to treat as constituting a requested variation, on the day she received the quote.
(4) The homeowner's obligation under cl 15(b) of the contract was to provide "written directions regarding the selection" of prime cost items "in sufficient time that no delay is occasioned in the progress of the works." On 2 September 2021 and again on 17 September 2021 the homeowner gave express written instructions to the builder about the wardrobe doors she wished to have fitted and requested they be ordered. It is difficult to conceive of clearer written directions.
(5) It is clear from the correspondence that the builder required the homeowner to sign an allowance agreement relating to the wardrobe doors, as drafted by the builder, without amendment or dissent.
(6) There was therefore no act, default, delay or omission on the part of the homeowner in refusing to agree to a variation, or in issuing a written direction as required by cl 15(b), to which cl 11(a)(v) of the contract applies.
(7) Even if that were not the case, there is no coherent evidence that that the works could not otherwise proceed.
(1) Full electrical layout.
(2) Selections for all fittings and patterns to all wet areas.
(3) Full detailed cabinetry design and layout/working drawings for kitchen/ laundry/store room/W.I.R to be costed against your remaining allowance to that dedicated area including ALL fittings & fixtures, appliances to areas as per Q1004.
(4) That outstanding owners work be completed ASAP.
As of 30.9.21 - No client works completed on site, works are unable to progress.
Further extensions of time will apply if further delays caused by Client.
106 The Builder also claimed that restrictions associated with the COVID-19 pandemic delayed the contract works. Although this claim is broad and unspecified, the Owner submits that only one extension of time notice dated 15 July 2021 refers to a delay caused by the pandemic and seeks an extension of 20 business days.
107 In addition, although it was not the subject of specific evidence, it was known at the time that first, the building industry was generally regarded as an exemption to COVID-19 restrictions in NSW and secondly, that the impact of the pandemic in regional areas was generally less severe than in urban areas.
Dwyer Building Group failed to adequately protect the property and the wall was exposed to rain for an extensive period of time.
Any damages caused, such as the render crumbling and cracking, are to be rectified by you. I'm seeking you make good of the damages caused during your possession from the internal wall's continual exposure to the elements by way of replacing the entire wall with plaster board or repairing it using the same materials as the existing.
My instructions are as follows: carry out the contract works and make good of the damages you've caused.
Builder requested directions by 7.10.21 to avoid further delay in progress of works.
Builder to request direction regarding latent conditions supplier to Builder by close of business 13.10.21.
Further Extension of Time Notices will apply if Client further delays the progress of works.
76 In respect of the uncovered latent conditions and variations to repair the pre-existing damage to the walls, the Owner submits that the damaged bedroom wall was not a latent condition, it was damaged by the Builder when he left the works unprotected from the weather: (2022 and 1480-1481).
77 At [7045-7053], Mr Dwyer accepted he left the Property exposed to the weather but did not consider the exposure would cause water damage. Even though Mr Dwyer was shown during the hearing the Owner's video of water streaming through the Property, Mr Dwyer refused to accept that he failed to protect the Property from water damage.
78 Mr Bournelis, the Owner's expert, considers that the damage to the bedroom wall was caused by water damage.
79 Weighing up this evidence, the Tribunal considers that there were material grounds for the Owner to refuse to pay for variations to repair the water damage to the bedroom wall.
Extensions of time # 9, 10, 11, 13, 14, and 15.
Owners failure to organise trades to complete ceiling framing to Bedroom 3 due to latent condition of existing framing. Builder cannot progress with works to this area until completed.
Owners failure to provide adequate directions regarding Bedroom 3 Wall Linings. Builder has notified Owner of issues with existing wall linings. Builder cannot progress with works to this area until completed.
82 In respect of quote 293, Bedroom 3 wall linings in the sum of $1,925.00, this appears at (2000). The Builder asserts that the Owner failed to approve quote 293. The Owner relies upon paragraph 226 of her 24 August 2022 statement at (1481-1482).
83 As outlined above, the Owner submits that the bedroom wall lining was damaged by the Builder's failure to protect the Property from water ingress.
84 As a result of that, it follows that the Builder caused this damage, and the Owner was acting reasonably when she refused to pay for the quote/works/variation referred to in quote 293.
(1) Installing flooring in the kitchen/living area. There was no dispute that this work had not been done. How it is said to have resulted in a 5 day delays - totalling 45 days - is not explained and is difficult to understand. When considering whether this provided a reasonable excuse for non-compliance the work order the Tribunal wrote, at D [103]:
103 In respect of the section of the flooring in the existing dwelling to be installed for the Builder to match, the Owner states in her email dated 7 October 2021 (2135) that the Builder was the cause that this work was not performed because the Builder was required to:
(1) rectify the defective kitchen subfloor;
(2) install a timber floor from the bifold door back to the hallway; and
(3) order Tasmanian oak floorboards.
In response (TB 2134) the builder disputed the condition of the sub-floor and said it would prepare a variation for the floor timber and complained about the homeowner's delay. The owner replied four days later (TB 2123) with photographs of the condition of the subfloor showing non-compliance with a PCA report and emphasizing the need for the bifold doors to be completed.
It is clear that the Tribunal accepted the homeowner's explanation. Having reviewed the materials, we are of the same view. We are not satisfied that there was any act, default, delay or omission on the part of the homeowner which would entitle the builder to any extension of time under cl 11(a)(v) of the contract.
(2) The AC works. When considering whether this provided a reasonable excuse for non-compliance the work order the Tribunal wrote, at D [95]:
95 The evidence shows that Mr Dwyer was told by Mr Tavian on 20 March 2020 and on 6 November 2021 that the air conditioning unit had been sufficiently installed to allow the Builder to continue with his works. In cross examination Mr Dwyer expressed some uncertainty as to whether the installation was complete [8009-8014]. There appears to be little substantive evidence to support his assertion that the Owner's failure to install the air conditioning unit prevented the Builder from complying with the Work Order
We can see no reason to disagree with that conclusion on reconsideration. We note the suggestion that ducting was incomplete. If that were the case, we do not see and there is no evidence as to how complete ducting was necessary for the other work to proceed. We are not satisfied that there was any act, default, delay or omission on the part of the homeowner which would entitle the builder to an extension of time under cl 11(a)(v) of the contract.
(3) The gas HWS. In its decision the Tribunal, at D [100]-[102], noted that the builder's principal, when cross-examined, was uncertain whether or not the gas installation had been completed in June 2021. When shown a gas supply certificate dated 29 October 2021, he remained of the view that the HWS had not been installed. We note that there was no explanation in the notices as to how or why the absence of a HWS would delay the work. We are not satisfied that there was any act, default, delay or omission on the part of the homeowner which would entitle the builder to an extension of time under cl 11(a)(v) of the contract in relation to the HWS. In particular, we are not satisfied that the absence of an HWS would prevent the work otherwise proceeding, or that five days - cumulatively 45 days - would be a fair and reasonable allowance for any delay caused.
Owners failure to provide adequate directions regarding supplied electrical quote. Builder cannot progress with works to this area until completed.
Laundry, Kitchen, Flooring, Bathroom, WC & Ensuite quotes in regards to allowances made in Quote 1004 have been supplied to Owner with requests for directions by 18.10.21. Builder cannot progress with works to these areas until directions and signed documents received.
85 In respect of quote 296, electrical in the sum of $15,396.70 and ... both quotes are presented in a lump sum and are not particularised in any manner. The Owner explained her objection at (1612-1614) which was in summary that both these quotes form, at least in part, an inclusion under the Contract.
(1) Quote 300 dated 12 October 2021 which relates to the kitchen and is a lump sum quote for $58,500.00 including GST. It expired on 26 October 2021.
(2) Quote 301 (TB 3933 - 3934) dated 12 October 2021 which relates to the flooring and is a lump sum quote for $22,852.50 including GST. It expired on 26 October 2021.
(3) Quote 302 (TB 3929 - 3930) dated 13 October 2021 which relates to the bathroom and WC and is a lump sum quote for $69,700.40 including GST. 302.01(TB 3931- 3932), following it, and undated, is itemized. It shows a cost for materials of $28,516.23 and labour of $36,004.17 totalling $64,520.40. It notes that the allowance amount in the contract was $17,041.92. Quote 302 expired on 27 October 2021.
(4) Quote 303 (TB 3935 - 3936) also dated 13 October 2021 relates to the ensuite and is a lump sum quote for $49,656.20 including GST. Quote 302.01(TB 3931- 3932), follows quote 303 in the tender bundle. It is undated and itemized. It shows a cost for materials of $18,811.20 and labour of $28,700.00 totalling $47,511.20. It notes that the allowance amount in the contract was $17,041.92. Quote 302 expired on 27 October 2021.
Owners failure to provide adequate directions regarding Master Bedroom Wall Linings. Wall linings show existing damage before works at the property commenced. Builder cannot progress with works to this area until completed.
Barrier Timber Suppliers Quote 17486. Items ordered as per Owners request, advised unavailable until late November 2021 by supplier. Builder cannot progress with works to this area until completed.
Had time for completion of the works expired on 21 January 2022?
(1) Both appeals are allowed.
(2) Order 3 made by the Tribunal on 30 August 2024 is set aside and the following order made in its place:
The Respondent, Dwyer Building Group Pty Ltd ACN 617 566 944, is to pay to the Applicant, Deanna Spicer, the sum of $241,305.74, less any amounts paid since 30 August 2024 .
(3) Order 4 is set-aside pending further order of Appeal Panel.
(4) If either party wishes to make an application for costs with respect to (a) these appeals, and (b) the costs order made by the Tribunal on 30 August 2024, they shall file and serve an application with supporting submissions (not exceeding 2,000 words) and materials within 42 days of the publication of these reasons.
(5) The other party may file and serve submissions (not exceeding 2,000 words) and materials in response within 56 days of the publication of these reasons.
(6) Any submissions in reply (not exceeding 1,000 words) are to be filed and served within 63 days of the publication of these reasons.
(7) Any submission relating to costs are to address whether or not the Appeal Panel should dispense with a hearing on the costs issues under s 50 of the Civil and Administrative Tribunal Act 2013.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
(2020) 103 NSWLR 479
(2000) 102 FCR 578
(1995) 184 CLR 163
(2015) 233 FCR 315
(2010) 241 CLR 390
(2015) 256 CLR 104
(2020) 103 NSWLR 36
(1991) 32 NSWLR 319
(1952) 85 CLR 20
(1982) 149 CLR 537
(1988) 14 NSWLR 438
(2008) 238 CLR 570
(2009) 236 CLR 272