SWS Lawyers Pty Ltd v Matthew Tumbers
[2022] NSWLC 19
At a glance
Source factsCourt
Local Court of NSW
Decision date
2022-06-28
Catchwords
- [2013] FCAFC 5 Cory Brothers and Company v Owners of Turkish Steamship "Mecca"
Source
Original judgment source is linked above.
Catchwords
Judgment (10 paragraphs)
Judgment
- The Plaintiff is a legal firm seeking to recover the cost of legal services provided in relation to three invoices totalling $35,062.10. Two invoices were issued on 31 July 2019 and the third invoice was issued on 7 July 2020. The invoices were raised under two separate retainers. The plaintiff seeks payment from Mr Matthew Tumbers.
- The first invoice dated 31 July 2019 is for an amount of $4,788.30 and relates to work done in preparing a defence to a statement of claim on behalf of Matthew Tumbers. The second invoice is for an amount of $17,729.10 also dated 31 July 2019 which related to drafting a company information memorandum. The third invoice is for an amount of $20,544.70 dated 7 July 2020 which relates to further work done in relation to the information memorandum and for work done on a shareholding agreement for DBN Solutions Limited. A part payment of $8,000 was appropriated to the second invoice reducing the overall balance due to the amount claimed.
- Matthew Tumbers disputes liability in respect to the provision of legal services. In essence, he denies entering into any agreement to engage the plaintiff for the provision of legal services and denies that he made any request for legal services to be provided.