[2001] VSC 436
Supreme Court of Victoria
2001-11-23
Byrne J
Original judgment source is linked above.
[2001] VSC 436
BUILDING CONTRACT - Final Payment Claim - summary judgment application - whether Final Payment Claim supported by evidence of the amount due - whether Principal liable to pay the amount claimed in a Final Payment Claim where no Final Certificate issued within time - effect of Final Certificate issued out of time. AS2124-1992 cll. 42.1, 42.7, 42.8
1. Was the Contractor entitled to submit a Final Payment Claim on 15 or 17 May 2001 given that a separate defects liability period which was established on 13 May 2001 had not expired?
2. Was the Final Payment Claim in form ineffective?
3. Does the default procedure for payment under cl. 42.1 apply to a Final Payment Claim?
4. Is the liability of the Principal under the default payment procedure affected by the subsequent issue of a Final Payment Certificate?
"This sum appears to refer to the costs incurred by the [Contractor], payable to Tracey Brunstrom and Hammond Pty Ltd, as part of the [Contractor's] precast variation claim. In this regard I refer to paragraph 113 of the witness statement in chief of David Lindsay Swan in the Arbitration where he refers to the [Contractor] incurring this cost."
Mr Lovett's affidavit of 25 July 2001 does not deal with this item.
"I also gather that those claims, ultimately in the amount of $7,698,951, replicate your earlier payment claims already assessed and certified by me in the sum of $1,180,570 payable by you to the Principal. You are presently disputing my assessment of those claims in your arbitration with the Principal."
These are the Contractor's items upon which the Superintendent was required to form a view within the period for certification. There are two further items which were not supported by evidence: item 10 relating to the interest calculation of $1.1M, and item 11 pertaining to costs of $102,107.
DOES THE DEFAULT PROCEDURE FOR PAYMENT UNDER CLAUSE 42.1 APPLY TO A FINAL PAYMENT CLAIM?
42.1 Payment Claims, Certificates, Calculations and Time for Payment At the times for payment claims stated in the Annexure and upon issue of a Certificate of Practical Completion and within the time prescribed by Clause 42.7, the Contractor shall deliver to the Superintendent claims for payment supported by evidence of the amount due to the Contractor and such information as the Superintendent may reasonably require. Claims for payment shall include the value of work carried out by the Contractor in the performance of the Contract to that time together with all amounts then due to the Contractor arising out of or in connection with the Contract or for any alleged breach thereof. Within 14 days after receipt of a claim for payment, the Superintendent shall issue to the Principal and to the Contractor a payment certificate stating the amount of the payment which, in the opinion of the Superintendent, is to be made by the Principal to the Contractor or by the Contractor to the Principal. The Superintendent shall set out in the certificate the calculations employed to arrive at the amount and, if the amount is more or less than the amount claimed by the Contractor, the reasons for the difference. The Superintendent shall allow in any payment certificate issued pursuant to this Clause 42.1 or any Final Certificate issued pursuant to Clause 42.8 or a Certificate issued pursuant to Clause 44.6, amounts paid under the Contract and amounts otherwise due from the Principal to the Contractor and/or due from the Contractor to the Principal arising out of or in connection with the Contract including but not limited to any amount due or to be credited under any provision of the Contract. If the Contractor fails to make a claim for payment under Clause 42.1, the Superintendent may nevertheless issue a payment certificate. Subject to the provisions of the Contract, within 28 days after receipt by the Superintendent of a claim for payment or within 14 days of issue by the Superintendent of the Superintendent's payment certificate, whichever is the earlier, the Principal shall pay to the Contractor or the Contractor shall pay to the Principal, as the case may be, an amount not less than the amount shown in the Certificate as due to the Contractor or to the Principal as the case may be, or if no payment certificate has been issued, the Principal shall pay the amount of the Contractor's claim. A payment made pursuant to this Clause shall not prejudice the right of either party to dispute under Clause 47 whether the amount so paid is the amount properly due and payable and on determination (whether under Clause 47 or as otherwise agreed) of the amount so properly due and payable, the Principal or Contractor, as the case may be, shall be liable to pay the difference between the amount of such payment and the amount so properly due and payable. Payment of moneys shall not be evidence of the value of work or an admission of liability or evidence that work has been executed satisfactorily but shall be a payment on account only, except as provided by Clause 42.8
The sixth and seventh paragraphs of this clause in AS2124-1992 were replaced in the contract by different terms dealing with the pricing of variations.[5] The eighth paragraph is not relevant for my purposes.
"42.7 Final Payment Claim Within 28 days after the expiration of the Defects Liability Period, or where there is more than one, the last to expire, the Contractor shall lodge with the Superintendent a final payment claim and endorse it `Final Payment Claim'. The Contractor shall include in that claim all moneys which the Contractor considers to be due from the Principal under or arising out of the Contract or any alleged breach thereof. After the expiration of the period for lodging a Final Payment Claim, any claim which the Contractor should have made against the Principal and has not made shall be barred." 42.8 Final Certificate Within 14 days after receipt of the Contractor's Final Payment Claim or, where the Contractor fails to lodge such claim, the expiration of the period specified in Clause 42.7 for the lodgement of the Final Payment Claim by the Contractor, the Superintendent shall issue to the Contractor and to the Principal a Final Payment Certificate endorsed `Final Certificate'. In the certificate the Superintendent shall certify the amount which in the Superintendent's opinion is finally due from the Principal to the Contractor or from the Contractor to the Principal under or arising out of the Contract or any alleged breach thereof. Unless either party, either before the Final Certificate has been issued or not later than 15 days after the issue thereof, serves a notice of dispute under Clause 47, the Final Certificate shall be evidence in any proceedings of whatsoever nature and whether under the Contract or otherwise between the parties arising out of the Contract, that the Works have been completed in accordance with the terms of the Contract and that any necessary effect has been given to all the terms of the Contract which require additions or deductions to be made to the Contract Sum, except in the case of - (a) fraud, dishonesty or fraudulent concealment relating to the Works or any part thereof or to any matter dealt with in the said Certificate; (b) any defect (including omission) in the Works or any part thereof which was not apparent at the end of the Defects Liability Period, or which would not have been disclosed upon reasonable inspection at the time of the issue of the Final Certificate; or (c) any accidental or erroneous inclusion or exclusion of any work, plant, materials or figures in any computation or any arithmetical error in any computation. Within 14 days after the issue of a Final Certificate which certifies a balance owing by the Principal to the Contractor, the Principal shall release to the Contractor any retention moneys or security then held by the Principal. 42.9 Interest on Overdue Payments If any moneys due to either party remain unpaid after the date upon which or the expiration of the period within which they should have been paid then interest shall be payable thereon from but excluding the date upon which or the expiration of the period within which they should have been paid to and including the date upon which the moneys are paid. The rate of interest shall be the rate stated in the Annexure and if no rate is stated the rate shall be 18 percent per annum. Interest shall be compounded at six monthly intervals."
The last date for the Superintendent to direct rectification or completion work.[20]
The last date for the Contractor to lodge its final claim[21]
and the date upon which any claim by the Contractor not previously made is barred[22].
The last day for the Contractor to dispute a direction of the Superintendent to carry out rectification or completion work[23]
The last day for the Superintendent to issue the Final Certificate[24]
The last day for release of security[25]
If no notice of dispute pursuant to cl. 47 has been given, the Final Certificate becomes evidence that the works have been satisfactorily completed and that all adjustments to the contract sum have been duly made, subject to three specified exceptions[26]
"42.1... the Superintendent shall issue to the Principal and to the Contractor a payment certificate stating the amount of the payment which, in the opinion of the Superintendent, is to be made by the Principal to the Contractor or by the Contractor to the Principal. 42.8... the Superintendent shall issue to the Contractor and to the Principal a final payment certificate endorsed `Final Certificate'. In the certificate the Superintendent shall certify the amount which in the Superintendent's opinion is finally due from the Principal to the Contractor or from the Contractor to the Principal under or arising out of the Contract or any alleged breach thereof."
The fact that these matters are dealt with separately in cl. 42.8 suggests that this part of cl. 41.2 has no function where cl. 42.8 operates.
What is the effect of a late Final Certificate?
[2] The claim is set out in my October judgment at [2001] VSC 381 at [28].
[3] At least with respect to the provisions with respect to payment, deductions and set-off: Merritt Cairns Constructions Pty Ltd v Wulguru Heights Pty Ltd [1995] QCA 273; [1995] 2 Qd R 521 at 527, per McPherson J. See Daysea Pty Ltd v Watpac Australia Pty Ltd [2001] QCA 49 at [19].
[4] Compare "any claim" in cl. 42.7, third paragraph and in cll. 42.6 and 42.8.
[6] Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) 14 BCL 215 at 219, per Rolfe J (NSW).
[7] Modified in this contract by Annexure 1 cl. B2.9.
[11] [2001] QCA 49 at [17].
[12] CMR Builders (Vic) Pty Ltd v Rosebud Hotel Pty Ltd (1996) 13 BCL 55 (SC, Vic, Byrne J); Algons Engineering Pty Ltd v Abbey Group Pty Ltd (1997) 14 BCL 215 (SC, NSW, Rolfe J).
[13] Daysea Pty Ltd v Watpac Australia Pty Ltd [2001] QCA 49 at [31]; Zauner Construction Pty Ltd v No. 2 Pitt Street Pty Ltd (2001) 17 BCL 357 at [18] per Byrne J (SC, Vic).
[14] Compare cl. 42.1, fifth paragraph (progress certificate not evidence of quality).
[15] Compare cl. 42.1, fourth paragraph.
[16] See cll. 42.8, third paragraph and 5.8, third paragraph.
[19] Subject only to the establishment of a separate defects liability period pursuant to cl. 37, third paragraph.
[23] Clause 46.2, as modified by Annexure 1 cl. B2.10.
[25] Clause 42.8, third paragraph, cl. 5.8, third paragraph.
[28] Walker v Black [1879] VicLawRp 94; (1879) 5 VLR(L) 77, referred to without disapproval in Ian Delbridge Pty Ltd v Warrandyte High School Council [1991] 2 VR 544 at 552.
[31] See Devaugh Pty Ltd v Lamac Developments Pty Ltd (1999) 16 BCL 378 (FC, WA) at [126], per Parker J.
[32] (1999) 16 BCL 378 at [134], per Parker J (FC, WA).
[33] It may be otherwise in cl. 42.6 which has not been amended since AS2124-1986 notwithstanding the re-introduction of the finality provisions in the 1992 revision.
[37] See NPWC3 cl. 42.5; JCC cl. 11.12.
[39] Ian Delbridge Pty Ltd v Warrandyte High School Council [1991] VicRp 91; [1991] 2 VR 545 at 550, per Murphy J, Fullagar and Vincent JJ concurring.
[45] [2001] QCA 49 at [16].
Southern Region Pty Ltd
State of Victoria