[2001] VSC 381
Supreme Court of Victoria
2001-10-26
Byrne J
Original judgment source is linked above.
[2001] VSC 381
BUILDING CONTRACT - final payment claim - summary judgment application - whether separate defects liability period established - whether claim supported by evidence of amount claimed. AS2124-1992 cll. 37, 42.1, 42.7.
"42.7 Final Payment Claim Within 28 days after the expiration of the Defects Liability Period, or where there is more than one, the last to expire, the Contractor shall lodge with the Superintendent a final payment claim and endorse it `Final Payment Claim'. The Contractor shall include in that claim all moneys which the Contractor considers to be due from the Principal under or arising out of the Contract or any alleged breach thereof. After the expiration of the period for lodging a Final Payment Claim, any claim which the Contractor should have made against the Principal and has not made shall be barred."
1. Was the Contractor entitled to submit a final payment claim on 15 or 17 May given that a separate defects liability period which was established on 13 May 2001 had not expired?
2. Was the final payment claim in form ineffective?
3. Does the default procedure for payment under cl. 42.1 apply to a final payment claim?
4. Is the liability of the Principal under the default payment procedure affected by the subsequent issue of a final payment certificate?
"37. DEFECTS LIABILITY ... At any time prior to the 14th day after the expiration of the Defects Liability Period, the Superintendent may direct the Contractor to rectify any omission or defect in the work under the Contract existing at the Date of Practical Completion or which becomes apparent prior to the expiration of the Defects Liability Period. The direction shall identify the omission or defect and state a date by which the Contractor shall complete the work of rectification and may state a date by which the work of rectification shall commence. The direction may provide that in respect of the work of rectification there shall be a separate Defects Liability Period of a stated duration not exceeding the period stated in the Annexure. The separate Defects Liability Period shall commence on the date the Contractor completes the work of rectification. Clause 37 shall apply in respect of the work of rectification and the Defects Liability Period for that work."
"RE SECURITY INSTALLATION Further to my letters dated 2, and 28 February and 11 April 2001, and recent correspondence and on site meetings, I seek your confirmation that the Security System, as installed by Complex Security Management, is complete, is fully operational and conforms with the documents. In particular I also seek your confirmation that the duress alarms and Intruder Detection system is fully operational and can be monitored by Protection Pacific. I also refer you to your letter dated 18 April 2001 in which you advised that as built drawings would be made available by 19 April 2001. At this stage I have not received as built drawings on the Security system. As you are aware, the security system from date of Practical Completion has been the subject of numerous faults, breakdowns and malfunctions. To this time I have not been satisfied that the contracted scope of works for this part of the project has been properly completed. In this regard, in accordance with Clause 37 of the General Conditions of Contract, a separate defects liability period of 12 months shall apply to the security system from the date that the contractor demonstrates that the security system is complete. I have also made you aware that I am not satisfied that the installation of the local control units has been in accordance with the contract documents. I refer you to the Electrical Specification Section 21.15.11 Local Control Units in which specifies that `local control units' be located within equipment rooms/cupboards in approved locations (as shown on drwgs). I find that no instructions were issued during the course of the works to relocate the controllers into ceiling spaces adjacent to or in proximity to the doors. You have indicated that the subcontractors accepted shop drawings did not conform to the contract drawings but in accordance with Clause 8.4 of the general Conditions of contract such non-conformity does not relieve the contractor of the responsibility to comply with the contract. Pursuant to Clause 37, I direct that the local control units are to be located in accordance with the contract documents and that the work of rectification be completed within 14 working days."
"42.1 Payment Claims, Certificates, Calculations and Time for Payment At the times for payment claims stated in the Annexure and upon issue of a Certificate of Practical Completion and within the time prescribed by Clause 42.7, the Contractor shall deliver to the Superintendent claims for payment supported by evidence of the amount due to the Contractor and such information as the Superintendent may reasonably require. Claims for payment shall include the value of work carried out by the Contractor in the performance of the Contract to that time together with all amounts then due to the Contractor arising out of or in connection with the Contract or for any alleged breach thereof."
"Ballarat Police and Courts Complex Amended Final Payment Claim 15th May 2001
Add interest calculated to 15 May 2001 and continuing until the total final payment claim is fully paid
[1] See also cl. 42.2 which makes the final payment certificate not capable of correction.
[2] Minson Nacap Pty Ltd v Aquatec-Maxcon Pty Ltd (2000) 17 BCL 269 at [17].
[3] After hearing further submissions on 1 November 2001, a supplementary judgment [2001] VSC 436 was published on 23 November 2001 which affects certain conclusions in this judgment. This judgment should therefore be read in conjunction with the 23 November 2001 judgment.
Southern Region Pty Ltd
State of Victoria