[2026] VCAT 93
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2026-02-12
Original judgment source is linked above.
Domestic Building: penultimate determination in proceeding, dealing with outstanding defect claims and the applicants' claim for the cost of completion of incomplete work.
M.T.V. Building & Construction Pty Ltd t/as VoJo Construction
Song v M.T.V. Building & Construction Pty Ltd t/as VoJo Construction (Building and Property) [2026] VCAT 93
(a) make a determination in respect of an outstanding claim made by the owners that there is a defect in a shower in the laundry;
(b) make a determination in respect of a defect pressed by the owners, namely an allegedly defective solar panel, in respect of which new evidence has become available;
(c) make assessments of the cost of completing a number of items of incomplete work which were left outstanding when the contract was brought to an end;
(d) make monetary orders, leaving for resolution at a later time any claim for interest in the nature of damages, and reimbursement of fees.
THE OWNERS' FIRST NOTICE OF INTENTION TO TERMINATE THE CONTRACT
10 On 17 December 2020, the owners gave notice to the builder that the builder was in substantial breach of the contract and demanded the default be remedied within 10 days in accordance with the contract. The builder did not respond by 27 December 2020. Despite asserting an entitlement to end the contract at that point, the owners did not do so even though the builder did not return to work.
THE BUILDER'S INVOICE IN CONNECTION WITH WORK ON THE EXISTING DWELLING
12 On 19 March 2022, the owners issued a further notice to the builder headed 'Notice to the builder of being in substantial breach of the contract again'. The notice referred to clause 43.2 of the contract and asserted that the builder had:
(a) suspended the carrying out of the building works;
(b) delayed the building works for a long time;
(c) caused defects referred to in 'Expert Witness Report for 48 Argyle Street Faulkner' dated 24 February 2022 and 'Expert Witness Supplementary Report for 48 Argyle Street Faulkner' dated 16 March 2022.
13 By notice dated 8 April 2022, the owners gave a further notice to the builder. This referred to both the notices of 17 December 2020 and 19 March 2022 and advised that 'it is with great regret we are sending you this further written notice to end this Contract'.
14 The question of whether the owners had lawfully terminated the contract on 8 April 2022 became an issue in the proceeding.
THE CLAIMS PRESSED BY THE PARTIES AT THE HEARING
(a) who is responsible for the cost of connecting the stormwater drain constructed on the site by the builder to the Melbourne Water stormwater drain in Argyle Street outside the site?
(b) does the contract include the work to the existing dwelling?
(c) did the owners lawfully terminate the contract, and what are the consequences?
(d) is the builder liable to the owners for delay damages, and if so, in what amount?
(e) are the owners entitled to reimbursement of $7,365.78 or any part of that sum?
(f) for what variations is the builder entitled to be paid?
(g) what is the adjusted contract sum?
(h) how much has been paid by the owners under the contract?
(i) are there defects in the builder's work and, if so, what is the cost to rectify them?
(j) are the contract works incomplete and, if so, what is the cost to complete the works?
21 The first hearing began before me on 10 July 2023, and continued on 11, 12, and 13 July 2023. Mr Song and Ms Song appeared in person. They both gave evidence. They called as an expert a building consultant, Mr Andrew White.
(a) (Not relevant here)
(b) the scope of the work under the contract does not require the builder to take the stormwater drain constructed within the site boundary across the site boundary to join the Melbourne Water Stormwater drain in the street;
(c) the scope of the work under the contract includes alterations and additions to the existing house on the site;
(d) the owners' termination of the contract in April 2022 was unlawful;
(e) the owners' claim for liquidated damages for delay must be dismissed;
(f) the builder is entitled to an award in respect of variations of $13,138.00 but its counterclaim is otherwise to be dismissed;
(g) the adjusted contract sum including variations is $403,138.00;
(h) the owners are entitled to have credited against the contract sum, apart from progress payments made against invoices, the following amounts:
(i) $3,000.00 paid in advance in respect of the benchtop variation;
(ii) $2,000.00 paid for kitchen appliances;
(iii) $1,100.00 paid under an order from DBDRV regarding repairs to the front fence; and
(iv) a credit of $4,180.00 in respect of screw piles not installed;
(i) (not relevant here)
(j) the builder is liable to the owners for defects in the sum of $1,813.00.
(a) incorporating an assessment of the liability (if any) in respect of the alleged shower defect at item 13.8 of the White Report; while
(b) maintaining and adopting its liability assessment in respect of the other defects set out at [123]-[140] of its reasons.
(a) the damages to be awarded following the findings made by the Tribunal in the orders of 8 August 2023 and the accompanying reasons;
(b) the assessment of liability for defects referred to at order 1(j) of the Tribunal's orders by incorporating an assessment of the liability (if any) in respect of the alleged shower defect at item 13.8 of the White Report;
(c) any other defect (although the Tribunal noted that there may be an issue as to whether any new defects can be raised at this point);
(d) the final orders the applicants would like the Tribunal to make.
(a) a statutory declaration concerning incomplete work filed by Mr Song made 28 August 2023 ('Incomplete Work Declaration');
(b) an affidavit sworn by Mr Song on 21 March 2025 in respect of a defective solar panel ('March affidavit');
(c) written submissions prepared for the final hearing dated 2 May 2025 ('May submissions');
(d) a further affidavit sworn by Mr Song on 2 May 2025 ('May affidavit');
(e) the schedule of incomplete work prepared by their expert Mr Andrew White, which appears at pages 28-31 of the White Report.
THE BUILDER'S SUBMISSIONS ABOUT INCOMPLETE WORK
38A One of the annexures to the September submissions was a public notice titled 'Proclamation of Peace and Integrity' which had been witnessed by a public notary on 5 July 2023. This document is not relevant to the proceeding and is put to one side.
38B Another annexure was headed 'Fee structure: Terms and Conditions' which appeared to be a statement of a claim being pursued by Mr Tony Mitevski pursuant to 'Canon Law 5057'. This document is irrelevant to the proceeding, and is disregarded.
38C Another schedule was headed 'Court Appearance Schedule' and was followed by the following demand:
These fees must be paid immediately after my case is finished. Failure to pay fines and fees will have an additional fee of $50,000 for breach of contract.
38D A schedule of fees was then sent out, which began with a claim for fees in respect of appearance 'Under protest and duress-Hourly fee $75,000.00'. There were about 18 other claims relating to use of tradename material, the provision of private information or time used in court appearances. These fees appear to be personally claimed by Mr Tony Mitevski. That is the case, the claim is misconceived on the basis that he has no standing in the proceeding. If the fees are claimed on behalf of the builder, then the claim must be pressed at the appropriate time under s 109 of the VCAT Act. For these reasons, this annexure is set aside.
38E The penultimate schedule was headed 'Trespass-Fee Schedule'. The first item claim was 'Failure to Honour God Given Rights' in respect of which are stated fee was $20,000.00. There were about 36 other categories of fee. No basis was given for how these fees were claimed. The schedule is put to one side.
38F The final schedule related to 'Services to others and/or Corporation(s)'. The fees included an hourly rate of $500.00 for each of studying, analysing, research, preparing documents, answering questions and providing information. The fees claimed increased to $75,000.00 per hour 'While under threat, duress, coercion'. It is conceivable that these were fees which Mr Tony Mitevski proposed to charge the builder for the assistance he rendered in connection with this proceeding. If that is the case, he must take the issue of fees up with the builder. No explanation was otherwise given as to why the fees were set out or why they were relevant to the case. This schedule is also set aside.
39A The first was dated 20 June 2025 and was headed 'Prerogative Directive and Notice of Equitable Supersession'. It is addressed not only to the principal registrar of the Tribunal, but also to myself, to Justice Quigley of the Supreme Court and to the Attorney-General of Victoria. In the document an alleged objection to a procedural irregularity was raised. This seemed to relate to the fact that the hearing on 1 July 2025 had initially been scheduled for 4 July 2025, and that this was an irregularity. Putting aside the fact that there is nothing in the complaint, the notice was supported by references to a number of relevant documents including an ATO Tax File number Declaration and Withholding Declaration and also Form 5A-Writ of Execution (Supreme Court of Victoria). I put this document to one side.
39B The complaint that the hearing had irregularly been rescheduled from 4 July 2025 to 1 July 2025 was repeated in a further document filed on 27 June 2025 by Mr Tony Mitevski, who described himself 'De Jure Crown in Right for the Magna-Mater Society: House of Zita-Makedon Charitable International Trust (MMZMCIT), acting for, acting for M.T.V Building & Construction Pty Ltd, on the land of the Wurundjeri Woi-warrung people of Kulin Nation, whose sovereignty has never been ceded'. The notice went on to assert, amongst other things, MMZMCIT's equitable interest in assets involved in this proceeding, demanded fiduciary disclosure, rebutted the 'plaintiff's' claims, and sought procedural relief at the 1 July 2025 hearing including under the Trustee Act 1958 (Vic). This document was discussed briefly at the hearing on 1 July 2025. I ruled the hearing would not be adjourned and explained why the document was irrelevant to the issues in the proceeding.
39C Mr Tony Mitevski filed a second document dated 27 July 2025, headed 'Consolidated Notice of Equitable Interest, Fiduciary Disclosure, Rebuttal Pendente Lite and Motion to Stay'. On this occasion he described himself as Attorney-in Fact In -Trust (EIN 98-6124802), Executor-in-Trust, Bona Fide (Protected) Purchaser, Beneficial Entitlement Holder as Settlor, De Juror Crown in Right, MMZMCIT. He sent the document to a number of individuals including the Tribunal CEO, myself, Acting Senior Member Nash, Justice Quigley, the Attorney General (Victoria) and the Attorney-General (Commonwealth), and to a number of institutions including the Sheriff's Office, Victoria, the High Court of Australia, the Magistrates Court of Victoria, the Australian Human Rights Commission, the United Nation's Human Rights Committee and the International Criminal Court. The document comprised 13 different sections including a notice of equitable interest pendente lite, a written demand for a new agreement, a notice of fiduciary disclosure and an accounting demand, payment terms, instructions to the sheriff, and 'Multi-Jurisdictional Considerations'. I put this document to one side on the basis that it is irrelevant to the proceeding.
The builder installed solar panels on the roof. The owners' complaints are that they do not know what brand has been installed, and that the solar panels are not connected to the hot water system. The parties will have leave to provide further evidence about this issue concerning both liability and the cost to complete.
THE TRIBUNAL'S DECISION CONCERNING TERMINATION OF THE CONTRACT
THE OWNER'S ENTITLEMENT TO CLAIM REASONABLE DELAY DAMAGES
THE OWNERS' ENTITLEMENT TO CLAIM REASONABLE DAMAGE ABOUT THE UPGRADE OF THE BENCHTOP
THE OWNERS' ENTITLEMENT TO CLAIM REASONABLE DAMAGE ABOUT THE STAIRCASE BALUSTER
THE OWNERS' ENTITLEMENT TO CLAIM REASONABLE DAMAGE ABOUT A VARIATION TO SHOWER ON THE GROUND FLOOR
THE OWNERS' ENTITLEMENT TO CLAIM $2,365.78 INTEREST FOR LATE PAYMENT BY ORDER MADE BY THE DBDRV
THE BUILDER'S LIABILITY FOR DEFECTIVE FLOORBOARDS
In my view, bearing in mind the rates were used in an assessment of damages prepared in February 2022, these rates are reasonable.
TREATMENT OF BUILDER'S MARGIN, CONTINGENCY AND GST
COST OF COMPLETION TO BE ASSESSED FROM POINT OF VIEW OF THE BUILDER
(a) the oven: $800.00 expended against an allowance of $800.00;
(b) hotplates: $600.00 expended against an allowance of $600.00;
(c) range hood: $800.00 expended against an allowance of $400.00.
Summary of damages allowed for incomplete work in the new house
Summary of awards made for incomplete works in the existing house
FINAL CONTRACT RECONCILIATION AND SUMMARY OF FINAL ORDERS
(a) the contract made between the owners and the builder includes four pages of civil design prepared by BCE;
(b) the scope of the work under the contract does not require the builder to take the stormwater drain constructed within the site boundary across the site boundary to join the Melbourne Water Stormwater drain in the street;
(c) the scope of the work under the contract includes alterations and additions to the existing house on the site;
(d) the owners' termination of the contract in April 2022 was unlawful;
(e) the owners' claim for liquidated damages for delay must be dismissed;
(f) the builder is entitled to an award in respect of variations of $13,138.00 but its counterclaim is otherwise to be dismissed;
(g) the adjusted contract sum including variations is $403,138.00;
(h) the owners are entitled to have credited against the contract sum, apart from progress payments made against invoices, the following amounts:
(i) $3,000.00 paid in advance in respect of the benchtop variation;
(ii) $2,000.00 paid for kitchen appliances;
(iii) $1,100.00 paid under an order from Domestic Building Dispute Resolution Victoria ('DBDRV') regarding repairs to the front fence; and
(iv) a credit of $4,180.00 in respect of screw piles not installed.
(i) the amount paid or deemed to be paid under the contract by the owners is $361,280.00 leaving a balance due of $41,858.00;
(j) the builder is liable to the owners for defects in the sum of $1,813.00;
(k) the liability of the builder to the owners for damages in respect of incomplete work remains to be assessed at a further hearing;
(l) the liability of the builder to the owners for damages in the nature of interest remains to be assessed.
(a) $3,000.00 paid in advance in respect of the benchtop variation;
(b) $2,000.00 paid for kitchen appliances;
(c) $1,100.00 paid under an order from DBDRV regarding repairs to the front fence; and
(d) a credit of $4,180.00 in respect of screw piles not installed.
[1] [2025] VCAT 79, [130].
[5] These payments were listed at [112] of the Reasons dated 8 August 2023, save that the last payment of $97,500.00, which was for the fixing stage, was erroneously described as the frame stage.
Song
M.T.V. Building & Construction Pty Ltd t/as VoJo Construction