Smith v Quasar Constructions Pty Ltd
[2016] NSWLC 1
At a glance
Source factsCourt
Local Court of NSW
Decision date
2016-02-12
Source
Original judgment source is linked above.
Judgment (18 paragraphs)
Solicitors: Gavin Parsons & Associates (for the applicant) Sewell & Kettle (for the respondent) File Number(s): 2015/47996
Background
- Following a judgment entered in this court on 19 November 2014, Mr Luke Smith, as judgment creditor, became entitled to the sum of $50,786.06 from the judgment debtor Quasar Constructions Pty Limited (herein after referred to as Construction).
- The proceedings now before this court for determination were initiated by the registration of the Certificate of Judgment which was filed on the 4 February 2015. There have been a number of Notices of Motion filed but two are of importance in relation to the bringing of the issues for determination before the court. They are as follows: 1. The first Notice of Motion was issued by AAI Limited wherein this entity sought certain orders. This company had received two demands in respect of monies it owed to the judgment debtor, Constructions. The first of these was in the form of a garnishee order issued in the interest of Mr Luke Smith, so that he could at least obtain part payment of the judgment debt. The second was a letter from Quasar Constructions (Commercial) Pty Ltd (hereinafter referred to as "Commercial") in which it notified AAI of its secured interest in respect of monies advanced to Constructions. In the Notice of Motion it sought orders, inter alia, in the following terms: 1. $25,003.37 being paid into court within fourteen days; and 2. $20,180.94 being paid into court on or before the 26 June 2015. Both these sums were in respect of monies AAI owed to Construction for work Construction had done for AAI. On 4 June 2015 this Notice of Motion was listed before a registrar of the court and the orders sought were made, and monies were duly paid into court pursuant to those orders. 1. The second Notice of Motion, in its amended form, is left to be determined by the court. This motion was filed by Commercial on 9 July 2015. It sought in its final form, the following orders. 1. The sum of $25,003.37 and the sum of $20,180.94 be paid out to the applicant, Quasar Construction (Commercial) Pty Ltd; and 2. Costs.