[2025] NSWCATCD 89
General information, not legal advice.
NCAT Consumer and Commercial
2025-06-02
Original judgment source is linked above.
(a) an order that the contractor rectify all defective work within 13 weeks of the date of order;
(b) an order that the contractor was to complete the remaining works under the contract without any delay, free of defects, within seven weeks immediately following rectification of defective work; and
(c) in the alternative, if the builder was unable to comply with the above orders the contractor pay:
(i) $303,349.99 being the amount required to rectify defective works; and
(ii) $133,511.54 being the amount required to complete the work under the contract.
(a) Contractor's tender issued to the owner at the time of entering into the contract;
(b) the architectural plans by Ntach Pty Ltd issued for the construction certificate, referred to at pages 499 - 515 of exhibit A; and
(c) the original structural plans created by Statiker dated 8 February 2024, refer to pages 519 - 520, exhibit A.
(1) In determining a building claim, the Tribunal is empowered to make one or more of the following orders as it considers appropriate -
(a)
(b)
(c) an order that a party to the proceedings -
(i) do any specified work or perform any specified service or any obligation arising under this Act or the terms of any agreement, or
(ii) do or perform, or refrain from doing or performing, any specified act, matter or thing.
"If the owner without reasonable and substantial cause:
denies the contractor or the contractor's sub-contractors access to the site so as to prevent the work from proceeding, or otherwise prevents the contractor from carrying on the work;
the Contractor may, without prejudice to any other rights under the contract, suspend the work by giving written notice to the owner in accordance with Clause 28. (Giving of Notices) specifying the reason."
"If the contract requires or permits a party to give a notice, consent, or other communication in writing to the other party, it must be given by either:
handing it to the other party
leaving it with a person apparently over the age of 16, at the party's business residential address, or
by registered post to the last known address of the other party."
"Suspension of work - Written Direction Notice (WDN)"
(1) The owner was booking inspections by his certifier which were not required by the contractor;
(2) The certifier had gone behind the contractor's back and without any communication had issued a Written Direction Notice.
"On 10 August 2022, Yucel Haydar, who was Ashish's appointed PCA ('Certifier) emailed me."
(1) In 1), "i clearly mentioned that we will be able to call our certifier Yucel by the end of the week"; "Without our consent, Yucel the certifier was gone to the site on the 31 oct." (Emphasis added.)
(2) In 3), "The only reason you booked our private certifier behind our backs is because I ended up replying back to one of your emails very rudely." (Emphasis added.)
(3) In 4) "Yucel our certifier has gone behind our back end without any communication has issued a WDN notice." (Emphasis added.)
(1) At 1), "We have no control of works as you guys are hindering our works past 12 months."; and
(2) At 4), "As you have taken full control of construction site works, you have been demanding the works to be done your way at each and every stage the construction has progressed, our tradies have been intimidated by you day in and day out, there is no room for them to work, but we still we didn't wanted to let go and wanted to finish this project until you went to lodge a claim through ncat, while we were still progressing with the construction."
"We hereby suspend your works as we can not work in an environment where a client like you is getting involved with our tradies day in and day out and jumping on the roof and hosing the roof to check the leak while the works are not done, which has also caused the yellow tongue that we have installed to damage, we understand that you want to get involved every time our tradesmen are conducting works, we understand that you want the job to be perfect but in order for you to hinder our works, we need time to finish your work."
"From the day we have entered your site, every tradesman has complained. And said you are sitting on top of their heads and they are finding it very difficult to work. You don't give them any room to work.
YOU CAN'T BE THERE ON THERE HEADS ALL THE TIME WHILE THEY ARE WORKING.
This has constantly happened since the time we started building the site, while demolishing and after demolition
Now that we have started working on your site again, the behaviour has not changed.
The new brick layer has complained that you are standing all day right beside them and he is not wanting to come back, the new roofer has complained the day before yesterday.
My new Carpenter, who did your roof mentioned " he has he has anxiety coming to your site as you are right there trying to interfere in his work"
We are also having big difficulties to work with you. None of trades wants to go to your site and work and to mention these are all the new trades that are experiencing high level of interference from you."
"From the commencement of this project, Ashish, who would often work from home, constantly interfered with the works. This conduct progressively got worse as the time went by, to the point where he would supervise Manhattan's work at all times, including giving directions to subcontractors on what they should/should not do. This interference got to the point where we would be advised by tradespeople who had visited the property that they no longer wished to return to do any work because of the owner's involvement and constant harassment."
(a) interfered with the building work;
(b) issued directions to subcontractors; or
(c) harassed subcontractors or the builder's workers.
"It is true, as McHugh J has pointed out, that for a very long time judges in appellate courts have given as a reason for appellate deference to the decision of a trial judge, the assessment of the appearance of witnesses as they give their testimony that is possible at trial and normally impossible in an appellate court. However, it is equally true that, for almost as long, other judges have cautioned against the dangers of too readily drawing conclusions about truthfulness and reliability solely or mainly from the appearance of witnesses. Thus, in 1924 Atkin LJ observed in Société d'Avances Commerciales (Société Anonyme Egyptienne) v Merchants' Marine Insurance Co (The "Palitana") :
'... I think that an ounce of intrinsic merit or demerit in the evidence, that is to say, the value of the comparison of evidence with known facts, is worth pounds of demeanour.'
Further, in recent years, judges have become more aware of scientific research that has cast doubt on the ability of judges (or anyone else) to tell truth from falsehood accurately on the basis of such appearances. Considerations such as these have encouraged judges, both at trial and on appeal, to limit their reliance on the appearances of witnesses and to reason to their conclusions, as far as possible, on the basis of contemporary materials, objectively established facts and the apparent logic of events. This does not eliminate the established principles about witness credibility; but it tends to reduce the occasions where those principles are seen as critical." (Emphasis added.)
"A device is "designed ... to prevent" copyright infringement when it is the operation of the device (which must incorporate one of the two processes specified in the definition) that makes it impossible to do an act of copyright infringement."
Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2005] NSWCA 248 and Little v J & K Homes Pty Ltd [2017] NSWCATAP 84
"While, on this assumption (the Contract still being on foot), the Council may have been entitled to claim damages for delay arising out of Beckhaus' failure to achieve practical completion by the date for practical completion, it could not sue Beckhaus for defective or incomplete work. As long as the Council maintained that the Contract was alive and had not been terminated, and held Beckhaus to its obligation to complete the work in accordance with the specification, on its contention the work remained lawfully in Beckhaus' possession. In other words, it was an inevitable incident of the Council's argument that the work had not been delivered to and accepted by the Council (Beckhaus - on the Council's argument - being in possession of and obliged to complete the work). While the work was in Beckhaus' possession, the Council suffered no loss by reason of defective or incomplete work; the work, not being in the Council's possession, did not at that stage form part of its patrimony."
"The principle for which the decision of the Court of Appeal stands can have no application to a claim seeking orders that a building contractor perform work required to be undertaken by the terms of a building contract ("specific performance"), or, in relation to work governed by the HBA, to a claim pursuant to s 48O(1)(c) of the HBA for orders that the builder carry out work. A claim for "specific performance" of a building contract can only be brought while the contract remains on foot. Neither the statement of principle set out in [65] to [69] of Brewarrina Shire Council v Beckhaus Civil nor the logic underlying that principle precludes the Tribunal from determining a claim for work orders pursuant to s 48O(1)(c) of the HBA while the contract remains on foot."
"If a builder wrongfully refuses to complete building work governed by the HBA, the Tribunal has jurisdiction pursuant to s 48O(1)(c)(i) to direct the builder to complete that work.
The respondent submitted that the Tribunal could not have made any orders pursuant to s 48O(1)(c) as, at the time of the hearing, the respondent's building licence had lapsed and the Tribunal could not order an unlicensed builder to carry out building work. We accept that it would not be appropriate to make orders requiring an unlicensed builder to carry out building work. Such a builder could not, consistently with the HBA, carry out such work. At the very least, it would involve an inappropriate exercise of discretion to order an unlicensed builder to carry out home building work when the HBA had the effect of proscribing the unlicensed builder's actions in so doing.
However, s 48O(1)(c) is not limited to the making of orders requiring the building contractor to carry out the building work. Section 48O(1)(c) provides:
'(1) In determining a building claim, the Tribunal is empowered to make one or more of the following orders as it considers appropriate:
...
(c) an order that a party to the proceedings:
(i) do any specified work or perform any specified service or any obligation arising under this Act or the terms of any agreement, or
(ii) do or perform, or refrain from doing or performing, any specified act, matter or thing.'
In light of our decision that there was legal error by the Senior Member in applying the Brewarrina principle to the appellants' application, it is strictly unnecessary that we express a concluded view on the point arising under s48O(1)(c) of the HBA. However, it does seem to us that s 48O(1)(c)(i) would permit the making of an appropriately framed order, requiring the respondent builder to perform its obligation to complete the works required by and in accordance with the contract. That obligation could be fulfilled by the respondent retaining a licensed builder to carry out the work." (Emphasis added.)
"the Tribunal is empowered to make one or more of the following orders as it considers appropriate."
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Sharma
Manhattan Custom Homes Pty Ltd [2025] NSWCATCD 89;
(2005) 221 ALR 448