[2017] VCAT 903
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2017-06-21
Original judgment source is linked above.
"Please find attached the amended plans, note the stairs have been amended, as discussed, the butler's pantry, small kitchen has smaller appliances, large sink in main kitchen with 900 wide appliances, bigger 4 car garage below, large showers upstairs bedrooms, available to catch up tomorrow". (sic.)
"We went thru the prices last night with my building partner, are you available this evening about 6 to go through the Contract or if it is easier for you the weekend".(sic.)
He did not say in the email who his business partner was.
"Variation of plans or specifications - by building owner
(1) A building owner who wishes to vary the plans or specifications set out in a major domestic building contract must give the builder a notice outlining the variation the building owner wishes to make.
(2) If the builder reasonably believes the variation will not require a variation to any permit and will not cause any delay and will not add more than 2% to the original contract price stated in the contract, the builder may carry out the variation.
(3) In any other case, the builder must give the building owner either -
(i) states what effect the variation will have on the work as a whole being carried out under the contract and whether a variation to any permit will be required; and
(ii) if the variation will result in any delays, states the builder's reasonable estimate as to how long those delays will be; and
(iii) states the cost of the variation and the effect it will have on the contract price; or
(b) a notice that states that the Builder refuses, or is unable, to carry out the variation and that states the reason for the refusal or inability.
(4) The builder must comply with subsection (3) within a reasonable time of receiving a notice under subsection (1).
(5) A builder must not give effect to any variation asked for by a building owner unless -
(a) the building owner gives the builder a signed request for the variation attached to a copy of the notice required by subsection (3)(a); or
(6) A builder is not entitled to recover any money in respect of a variation asked for by a building owner unless -
(i) that there are exceptional circumstances or that the builder would suffer a significant or exceptional hardship by the operation of paragraph (a); and
(ii) that it would not be unfair to the building owner for the builder to recover the money.
(7) If subsection (6) applies, the builder is entitled to recover the cost of carrying out the variation plus a reasonable profit.
(8) This section does not apply to contractual terms dealing with prime cost items or was in writing provisional sums."
"I am still thinking about the cooling system. Could you please tell me about the type of cooling system before it is installed in the House? Can the cooling system be zoned? We have central cooling system in China, each room has its own control panel to adjust each room temperature. So, I would like to learn some information about cooling system. I hope the cooling system can be zoned as well.
(g) Mr Gurleyen said that, after selections were made for plumbing, electrical, heating and cooling, the Owner requested feature bulkheads throughout the house. The Owner denied that she requested the bulkheads but they are there and there is no complaint in any of the emails that they were built without instructions. I prefer the evidence of Mr Gurleyen.
(h) Mr Gurleyen said that on 16 September 2014, he met the kitchen Contractor with the Owner. He said that, during September, she made further changes to the kitchen.
(i) On 2 October 2014 the Owner gave the Builder details of the tiles she had chosen and the doors and stairs to be used. Mr Gurleyen said that these were later changed.
(j) At a meeting on 9 October 2014 the Owner made further changes to the cabinetry.
(k) On 11 October 2014 the Owners changed her selection of tiles again and sent photographs of the changed tiles that she had chosen to the Builder.
(l) On 16 October 2014 the Owner requested a further sample of timber flooring because she did not wish to go ahead with her previous selection.
(m) Mr Gurleyen said that on 19 October 2014 the kitchen design was finalised. On the following day, the Owner sent an email to the Builder requesting that the kitchen design be changed again and also asking for substantial changes to the cabinetry in the kitchen, butler's pantry and laundry.
(n) On 21 October 2014 the Owner sent the Builder photographs of various exteriors and asked for some landscaping ideas.
(o) Mr Gurleyen said that the selection details of the stairs were not provided until the end of October 2014 and the stairs were installed by mid-November.
(p) A further meeting took place with the kitchen supplier on 7 November.
(q) By an email dated 17 November 2014 to the Builder, the Owner confirmed that she wanted spotted gum flooring and asked him to order tiles, the flooring and the fireplaces. She also asked him to book tradesmen for interior wall painting, plaster for the basement, the plumber, the kitchen supplier and the front yard retaining wall and landscaping.
(r) On about 18 November 2014 the Owner requested Mr Gurleyen to design the front fence. The Builder's design was sent to the Owner on 19 November 2014.
The author of the letter stated that the Owner was entitled to terminate the Contract pursuant to s.41 of the Domestic Building Contracts Act 1995 ("the Act") and said that, unless by 13 May 2015 certain documents were provided and the works were completed, the Owner would have no alternative but to serve a notice of intention to terminate the Contract and would then look to the Builder for any loss or damage suffered by her as a result of the Builder's breach. In the final paragraph it was stated that nothing in the demand was intended to limit or waive the Owner's contractual and common law rights to seek damages.
"While the total construction period including delay days in the new homes contract stipulated 321 days, the work that you have done has taken much longer than this time period and the contract is still yet to be completed. The time you have spent on the contract already exceeds one and a half times of the original construction period and accordingly, our client hereby ends the contract in accordance with section 21.1 of the contract and section 41 of the Domestic Building Contracts Act 1995." (sic.)
"Pursuant to your letter dated 20 August 2015, despite our continued frustration in your client's failure to undertake further fruitful productive discussions and numerous attempts by us to progress works in good faith with our continued wish to bring works to a successful conclusion, it appears that your client is resolute in instruction to terminate our contract, under section 41 of the Domestic Building Contracts Act, for building works at [address of House given].
Please note that it is with the utmost disappointment and regret that as a result, and at your explicit instruction, we have made arrangements for the keys to site to be handed to you and for our plant and equipment to be removed from site.
If you could please make prompt arrangements to remit to us all unpaid invoices within 7 days with final accounts for Building Works to follow.
We reserve all our rights and entitlements for works both on and off site also for any loss and damage suffered as a result of your/your client's actions in this matter." (sic.)
Water proofing of above ground areas - $40,800.50
He also said that the brick sill under the laundry window has been laid too flat and needs to be re-laid in order to achieve an appropriate water run-off.
Brickwork and subfloor ventilation - $5,779.00
Weep holes to external masonry walls - Included in next item
Driveway entry gate pillars and garage - $1,501.50
"26. ...A person is said to have a right of election when events occur which enable him to exercise alternative and inconsistent rights, i.e. when he has the right to determine an estate or terminate a contract for breach of covenant or contract and the alternative right to insist on the continuation of the estate or the performance of the contract. It matters not whether the right to terminate the contract is conferred by the contract or arises at common law for fundamental breach - in each instance the alternative right to insist on performance creates a right of election.
It is also pleaded that the Builder failed to complete the work within the construction period.
"For the purposes of section 40(4) of the Act, when parties to a major domestic building Contract agree that sections 40(2) and (3) of the Act do not apply to that Contract, the manner of agreement is to include in the major domestic building Contract -
(a) a warning in the form of Form 1 in the Schedule which is signed by the building Owner before the execution of the Contract; and
(b) a Clause in the form of Form 2 in the Schedule."
"Repudiation is not ascertained by an inquiry into the subjective state of mind of the party in default; it is to be found in the conduct, whether verbal or other, of the party in default which conveys to the other party the defaulting party's inability to perform the contract or promise or his intention not to perform it or to fulfil it only in a manner substantially inconsistent with his obligations and not in any other way."
"An election to not rescind for failure to deliver the excavated site on the due date could not deprive that failure of all significance. When a second breach occurs, the two combined may have a significance which it might not be legitimate to attach to the first alone".
Termination under Clause 21 and s.41 of the Act
"Ending a Contract if completion time or cost blows out for unforeseeable reasons
(1) A building Owner may end a major domestic building Contract if -
(i) the Contract price rises by 15% or more after the Contract was entered into; or
(ii) the Contract has not been completed within 1½ times the period it was to have been completed by; and
(b) the reason for the increased time or cost was something that could not have been reasonably foreseen by the builder on the date the contract was made.
(2) For the purposes of subsection (1), any increased time or cost that arises as a result of a prime cost item or a provisional sum or that is caused by a variation made under section 38 is to be ignored in calculating any price rise or increase in time.
(3) To end the Contract, the building Owner must give the Builder a signed notice stating that the building Owner is ending the Contract under this section and giving details of why the Contract is being ended.
(5) If a Contract is ended under this section, the Builder is entitled to a reasonable price for the work carried out under the Contract to the date the Contract is ended.
(6) However, a Builder may not recover under subsection (5) more than the Builder would have been entitled to recover under the Contract."
"It is a fundamental principle that one party may not rely upon the failure of the other party to perform the contract where it is the former who has prevented the performance. Or, as it was would in Panamena Europea Navigacion (Compania Limitada) v. Frederick Leyland & Co Ltd [1947] AC 428 at 436:
'...... No person can take advantage of the non-fulfilment of a condition the performance of which has been ended by himself'.
Whether the delay was reasonably foreseeable by the Builder on the date the Contract was made
"The Contract did not adequately specify the scope of the works, specifications, prime cost items or provisional sum allowances. Variations were not adequately documented or authorised."
Shao
A G Advanced Construction Pty Ltd
(1964) 111 CLR 41
(1953) 89 CLR 327