[2017] VSC 73
General information, not legal advice.
Supreme Court of Victoria
2017-02-28
Ginnane J
Original judgment source is linked above.
(a) the outstanding amount under the Contract of $65,914.31; and
(b) liquidated damages for delay of $63,304.[8]
12 The appellant stated seven questions of law in the Proposed Notice of Appeal, namely:
13 As previously mentioned, questions of law five and six were not pursued.
14 Each of the questions is answered below in the order of their argument at the hearing, commencing with question of law two.
Question of law two - repudiation of the contract
15 This question was: whether the Tribunal Senior Member misapplied the doctrine of repudiation by wrongly failing to assess the question of repudiation on an entirely objective basis? The key grounds of appeal associated with this question was whether the Tribunal Member erred at law in finding that there had not been a breach of an essential term of the Contract by the Builder which allowed the Plaintiff or the Owner to validly terminate the Contract. Secondly, whether the Senior Member erred at law in failing to consider whether the accumulation of conduct by the Builder, by reference to the effect it would have on a reasonable person, amounted to a repudiation of the Contract. Thirdly, whether having regard to particular facts found by the Senior Member, he ought to found that the cumulative effect of those matters constituted a repudiation of the Contract by the Builder.
16 The applicants submitted that the Senior Member had erred in finding that the Builder had not repudiated the contract by applying a legal test of repudiation by reference to the subjective intentions of the Builder, rather than the objective test of what a reasonable person in Versa-Tile's position would have taken the Builder's conduct to mean.[9]
17 In written submissions, the applicants pointed in particular to the following paragraphs of VCAT's reasons:
18 To succeed in this Court, the applicants must establish an error of law by the Tribunal that affected its decision. I am not persuaded that the Senior Member failed to apply an objective test, in determining whether repudiation had occurred. Before embarking on his analysis of the facts, the Senior Member set out the relevant legal test of repudiation in the following passages by reference to authority:
... repudiation turns upon objective acts and omissions, not on uncommunicated intention, and it is sufficient that, viewed objectively, the conduct of the relevant party has been such as to convey to a reasonable person, in the situation of the other party, repudiation or disavowal either of the contract as a whole or of a fundamental obligation under it.
Gibbs CJ in Sheville & Anor v The Builders Licensing Board likewise observed that a contract may be repudiated where one party renounces their liabilities under it, evincing any intention to no longer be bound by the contract. His Honour further observed that repudiation may also occur when one party demonstrates an intention to fulfil the contract, but in a manner "substantially inconsistent with his [or her] obligations and not in any other way..."
19 These passages identify the relevant legal test as contained in High Court authority that makes clear that the proper test is an objective one. The applicants' counsel in fact relied on Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd as containing the correct test.[11] There is no indication that the Senior Member failed to apply the objective test that he had previously identified in determining whether repudiation of the Building Contract had occurred. The Senior Member's reference to the facts that led to the cessation of the Builder's work does not suggest, when read in the context of his statement of legal principle, that he failed to apply an objective test.
20 There is a second reason why this alleged error of law has not been established. It is clear that the Senior Member found, on the balance of probabilities, that the Builder never said words to the effect that he would not return to the job. The Senior Member was entitled to make that finding. He heard from witnesses and received evidence. The applicants provided no basis for this Court to interfere with the Tribunal's findings of fact on this point.
Question of law four -the Builder's loss and damage
Whether it was open to the Tribunal to find that the Defendant (the Builder) suffered loss and damage in the absence of any evidence to that effect.
22 The primary proposed ground of appeal connected to this question of law was:
Whether the Tribunal Member erred at law in finding that the Builder suffered loss and damage in the absence of any evidence to that effect in circumstances where:
the Tribunal Member erred at law in determining that the Builder suffered loss and damage in the absence of any evidence to that effect.
23 In oral submissions, the applicants did not press an argument that the Tribunal's method of assessing damages had denied them procedural fairness.[12]
24 The applicants attacked the Senior Member's assessment of the Builder's damages on the ground that there was no evidence, or insufficient evidence before him to support the sum that he awarded. In particular, counsel submitted that the following passages in the Reasons revealed error:
(a) $6,545.72 for the Deposit progress claim;
(b) $58,911.44 for the Payment on initial ordering progress claim;
(c) $52,365.72 for the Payment on completion progress claim; and
(d) $13,091.42 for the Handover progress claim.
In contract, damages are awarded with the object of placing the plaintiff in the position in which he would have been had the contract being performed - he is entitled to damages for loss of bargain (expectation loss) and damages suffered including expenditure incurred in reliance upon the contract (reliance interest).
25 The Senior Member then proceeded to assess the Builder's costs to complete particular works.
26 The applicants submitted that the Senior Member, in exercising the discretion contained in s 53 of the Domestic Building Contracts Act 1995, was still obliged to assess damages according to law and accepted practice. They argued that this was not a case where the Builder was unable to lead evidence of its damages. Rather, the Builder had chosen not to adduce evidence of his actual loss and damages and the Court was therefore not obliged to attempt to assess damages to which the Builder may have been entitled. As a result, the Builder was only entitled to nominal damages, if it otherwise proved its case.
27 The applicants also attacked the Tribunal's use of the Owner's experts' reports in determining the amounts to deduct from the contract price in calculating the sum owed to the Builder.
28 The authorities on which the applicants relied suggest that in situations where a plaintiff cannot adduce precise evidence of loss, the Court may engage in some guesswork in assessing damages.[14] Cases where a party cannot adduce evidence of loss are distinguished from cases where a party could have, but has not adduced such evidence.[15] In the latter case where a party has not, and should have, produced evidence, difficulties in the assessment of damages may be resolved against that party.[16] The applicants submitted that the Builder bore the onus of proving actual loss and damage, but had failed to do so. Moreover, the use of the contract price, which the Senior Member identified as neither suitable as a figure of actual loss nor as a contractual entitlement, was an erroneous starting point for the assessment of damages.
29 The legal principles for assessing damages for breach of contract, including proof of loss and damage were summarised by Robson J in NCON Australia v Spotlight Pty Ltd[17], who concluded:
In my opinion, these authorities establish that the plaintiff is obliged to call such evidence as can be reasonably expected in the circumstances to establish the damages which the plaintiff claims. The court's obligation to estimate damage as best it can is only triggered where the circumstances are such that the plaintiff is unable to reasonably establish the damage. McGregor on Damages states that the word 'reasonable' is the controlling one, and the standard of proof only demands evidence from which the existence of damage can be reasonably inferred and which provides adequate data.[18]
30 The Senior Member correctly applied the test for determining expectation damages where a proprietor repudiated a building contract, making it impossible for the builder to complete its obligations under a building contract.
31 In calculating the Owner's damages, the Senior Member referred to the evidence called by each side. There was no error in that approach as all of that evidence was before him. Evidence led cannot be quarantined and restricted to being used only by the party leading it. The Senior Member calculated damages in respect of particular areas of work, such as plumbing and plastering.
32 The Senior Member considered that he should adopt the costings of the experts without adding an amount in relation to contingencies or margins as the risks or contingencies and profit had not been added as a cost against the Builder when the sum required to rectify its own work was determined. He deducted the fixed expenses including Builder's Margins, overhead costs, but added 15% allocated to fixed overheads and supervision. He did not add GST.[19]
33 The Senior Member noted that the Builder claimed the balance of the contract price in the amount of $65,914.30, plus damages because of delay caused to the building work in the amount of $63,304. He dismissed the delay claim. He stated that:
'Doing the best I can with the evidence before me, I assessed the Builder's cost to complete the Works, based on Mr Lorich's and Mr Quick's costings.'[20]
34 The Senior Member then found the cost of that work as $20,803.50, to which he added a margin of 15%, deducting the GST. He concluded:
Therefore, $23,924.03 is to be deducted from $59,922.10 to arrive at a net figure of $35,998.07, exclusive of GST. To this amount, GST is re-added to arrive at a final figure of $39,597.89. I find this amount to represent the Builder's claim for loss and damages, ignoring any cross-claim against the Builder.[21]
35 Assistance on the present point is found in standard texts on the assessment of damages for breach of building contracts. McGregor on Damages states:
On the measure of damages where the owner acts so as to bar completion there is, surprisingly, a dearth of authority. General principles would put the normal measure at the contract price less the cost to the builder of executing or completing the work. In calculating the builder's costs the indirect as well as the direct costs must be included, especially overheads. This measure, however, should be subject to reduction if the defendant can show that the time made available to the claimant by the breach has been, or could have been, used by him in executing other profitable contracts with which he would not otherwise have been able to contend. This is analogous to the cases of manufacturing and erecting machinery dealt with under sale of goods.[22]
36 McGregor does discuss alternative methods of assessing damages to the basic measure outlined in the passage that I have set out. They are the net profit which the builder could have made on the whole contract plus his expenditure in part performance and, secondly, for the work done, such proportion of the contract price as the cost of the work done bears to the total cost of the whole contract, plus, for the work remaining, the profit that would have been made upon it. [23]
Where the proprietor repudiates, the builder may have suffered several losses. Having lost the benefit of the contract, the builder may have suffered a loss of profits on the job. Perhaps the builder had expended moneys in advance on purchases made for the purposes of the contract. In having lost the benefit of the contract, the builder may have lost a commercial advantage which would have been gained had the contract been performed.
Damages for loss of profits and damages for expenditure reasonably incurred were said by Mason CJ and Dawson J in Commonwealth v Amann Aviation Pty Ltd to be simply two manifestations of the general rule stated by Parke B in Robinson v Harman. As the decision in the Amann Aviation case shows, the builder may recover so-called reliance damages - 'that is to say, damages equivalent to the wasted expenditure which has been reasonably incurred in reliance upon the assumption that the contractual promises of the [principal] would be honoured'...
It is made clear by the judgments in the Amann Aviation case that recovery of reliance damages is not dependent upon whether the contract, if not repudiated, would have resulted in a profit. But loss of profits is a well-established head of damages. Having found him discharged by breach by a total prevention of performance, Lusher J in Gabriel v Sea & Retaining Wall Constructions Pty Ltd held that the plaintiff in that case was entitled to the damages resulting from the loss of the benefit of the contract - 'ie, the contract price less the cost to him of executing or completing the work ... that is to say, the value of the work performed together with profit lost on the uncompleted work, credit being given for payments ... made'.
In Foley Bros v McIlwee, the Judicial Committee affirmed the decision of the British Columbia Court of Appeal. It held that the measure of damages is the difference between the amount payable to the contractor under the terms of the contract and the amount it would have cost the contractor to carry out the work if the contract had not been cancelled.[24]
38 Far from supporting the applicants' submissions, these passages explain that the starting point for the consideration of a builder's damages claim was the contract price.
39 The Senior Member in assessing damages sought to reach a fair resolution of the dispute as he considered s 53 of the Domestic Contracts Act empowered him to do. The contract price was, albeit hypothetical, a sum that represented what would have been paid to the Builder had the Contract been performed. The Senior Member acknowledged the limitations attaching to the use of that price. [25]
40 The Builder was represented by its director at the VCAT hearing, whereas the Owner was represented by counsel. The material before the Senior Member was not ideal, and, on occasions, he prefaced his assessment with the words: 'Doing the best I can with the evidence before me...'.[26] However imperfect, the contract price was evidence in the dispute and the Senior Member was entitled to use it in his evaluation.
41 The key question is whether the damages awarded by the Tribunal were assessed according to law? The damages awarded were compensatory, in the Builder's case, they were expectation damages and sought to place the Builder in the position he would have enjoyed had the contract not been repudiated. The Senior Member was entitled to have regard to the contract price and the experts' reports, both the Owner's and the Builder's. The Senior Member correctly recognised that to award the full contract price to the Builder would have given it a windfall, because it would have included expenditures and taxes that were not incurred.
42 I do not consider that the Senior Member made the errors in assessing damages that the applicants allege. In the case of the Owner, he considered the amount of damages that it claimed being losses alleged to flow from breach of the contract prior to termination and stated:
Therefore, any assessment of the cost to make good defects found to exist in the works undertaken by the Builder are to be assessed on the basis of what it would cost the Builder. In my view, the most appropriate way to assess the Builder's costs is to subtract GST in the b_uilder's margin_ or a portion of b_uilder's margin,_ from the aggregate cost in order to arrive at a figure that best represents what it would have cost the Builder.[27] What follows are my findings as to whether the works undertaken by the Builder are defective or not, having regard to the evidence before me.[28]
43 Both parties relied on the evidence of their building experts in order to prove or disprove whether the works were defective and the cost of particular works.
44 As mentioned, the applicants originally contended, but did not press in final submissions, that the Tribunal had denied them procedural fairness by his method of assessing the Builder's damages. For the sake of completeness, I add that I consider that there was no such denial of procedural fairness, rather the Senior Member applied accepted principle, by reference to all of the evidence that before him.
Question of law seven - denial of procedural fairness
45 The seventh question of law was: Whether the Tribunal Member failed to afford the applicant procedural fairness?
46 The proposed grounds of appeal accompanying this seventh question of law, included some that were really connected with the procedure by which damages were calculated, but, as mentioned, those grounds were not pressed separately as a procedural fairness breach.[29] Save for paragraphs vii and viii and the concluding paragraph, I have set the proposed grounds out as part of question of law four - that related to the assessment of damages. As the procedural fairness question was not pressed in respect of the assessment of damages, I will not set out paragraphs vii and viii and the concluding paragraph.
47 The procedural fairness question, as developed in oral submissions[30], was based upon the Senior Member's determination of the undisclosed principal issue. The determination was that Versa-Tile was an undisclosed principal and that the description of the parties contained in the contract was affected by a mutual mistake. The applicants contended that they had not been given notice of or, the chance to call evidence on, this issue.
48 The proposed grounds of appeal that appear to relate to the Tribunal's dealing with the issue of an undisclosed principal and thus to the procedural fairness ground developed in the hearing, appeared to be stated under the heading 'Wrong Party'. They were:
Whether the Tribunal Member failed to properly apply the test for determining whether the Owner was the undisclosed principal of its agent the Plaintiff.
49 The procedural fairness ground had been outlined in the applicants' written submissions which were prepared some weeks before the hearing in this Court.
50 Question six, which was not pressed by the applicants, might also have been relevant to the undisclosed principal issue. It stated:
Whether section 53 of the Domestic Contracts Act 1995 applies to allow the Tribunal Member to treat the claim made in proceeding BP 354/2014 by the Defendant against Dr Raiz as being a claim made against the Plaintiff and then to set one claim off against the other.
51 The applicants did not ultimately contend that VCAT could not make a final combined order by setting one order off against another when two related proceedings were heard together.
52 The Senior Member sought to identify the parties to the contract because there was an issue whether one party was Dr Raiz or Versa-Tile. The Building Contract described the parties as Dr Raiz and 101 Construction. However, the registered proprietor of the property, and thus the correct contracting party on the Tribunal's findings, was Versa-Tile. The Builder's claim against Dr Raiz was a separate proceeding to that brought by Versa-Tile against 101 Construction. In making final orders, the Senior Member found Versa-Tile to be an undisclosed principal in the proceeding brought by the Builder. In paragraph 14 of the Reasons, the Senior Member found that Dr Raiz's inclusion in the Contract as a party was a 'mutual mistake':
53 The Senior Member then purported to correct the mutual mistake that he had identified, by finding that at all relevant times, Versa-Tile was the undisclosed principal of Dr Raiz, stating under the heading 'Conclusions on Claims':
A person may sue or be sued upon a contract although the other party to the contract did not know that the person with whom he was contracting was acting as an agent, if in fact that person was acting as agent for an undisclosed principal, unless the terms of the contract are inconsistent with the known person being an agent. Either principal or agent may sue or be sued ... The rights and obligations of principal and agent are not joint, but, subject to the superior right of the principal, alternative.
54 The applicants claim that they were not informed that the Tribunal might apply the undisclosed principal rule or make findings that Dr Raiz was an undisclosed principal. Those matters were not raised in the Builder's points of claim and the applicants were not given an opportunity to be heard on those matters and thus denied procedural fairness. Mr Daoud's case was that Dr Raiz was named in, and was a party to, the Building Contract.
55 The applicants submitted that as Dr Raiz was not a party to the Building Contract, the Builder could not claim against him and therefore the Builder's proceeding against Dr Raiz should have been dismissed as the Builder had not sued Versa-Tile.
56 The applicants abandoned the challenge foreshadowed in question of law five to the Senior Member's statement of the undisclosed principal doctrine or its application, but the applicants argued that the Tribunal's application of the doctrine was procedurally unfair.
57 While the concept of 'undisclosed principal' was not directly referred to, the issue of who were the contracting parties was clearly before the Tribunal. Indeed, the first issue the Senior Member identified in the Reasons was: 'Who are the contracting parties?'[31]
58 Because the Builder did not participate in the proceedings in this Court, no one submitted that the Tribunal erred in finding that Versa- Tile and not Dr Raiz was the 'Owner' party to the Contract.
59 Versa-Tile's claim in both VCAT proceedings addresses the issue of who were the contracting parties. In its Points of Claim in proceeding BP311/2014, Versa-Tile referred to the Building Contract and stated:
The [Building Contract] was entered into by Dr Danny-Glen Raiz, on behalf of [Versa-Tile]. Dr Raiz is the sole director and sole shareholder of [Versa-Tile].[32]
60 In his Points of Defence to proceeding BP354/2014, Dr Raiz, in response to 101 Construction's reference to the Building Contract stated:
(a) He denies that he is a party to the [Building Contract].
(b) He says that in entering into the [Building Contract], he did so on behalf of, and in his capacity as, the sole director of Versa-Tile Pty Ltd.
(c) He admits that Versa-Tile Pty Ltd entered into a contract with [101 Construction]...[33]
61 At the commencement of the Tribunal hearing, the identity of the contracting parties was raised as follows:
MR RYDE: ...Perhaps it is relevant to start by saying whether the tribunal has had an opportunity to look through these documents but although there are two claims here. They really were talking about the one dispute. The reason, as I understand it, that Mr Daoud brought a separate proceeding is that he brought the proceeding against Dr Raiz in his personal capacity rather than against the company.
SENIOR MEMBER: Yes.
MR RYDE: So really for the purpose of this hearing - - -
SENIOR MEMBER: This is a dispute, isn't it, as to who the contracting party is, whether it is Versa-Tile Pty Limited or whether it is Dr Raiz.
MR RYDE: Dr Raiz. Yes, sir. I must say on that point that it is not clear to us yet what the issues in dispute are. This is no criticism of Mr Daoud, given he is representing himself but as I said, his pleadings were filed there has been some movement... [34]
62 Similarly, during examination-in-chief, Dr Raiz gave evidence about signing the contract:
MR RYDE: (To witness) Doctor Raiz, I'd just like to ask you about entering into the contract with Mr Daoud in relation to the work that was done at your premises at Fitzroy?---Yes.
Who entered into that contract?---My company did, and I did as a director of my company.[35]
63 Given that Dr Raiz admitted that he was acting on behalf of Versa-Tile and that Versa-Tile 'pleaded' a contract with 101 Construction, Versa-Tile's case in respect of question of law seven was really directed to a perceived deficiency in 101 Construction's points of claim and its failure to sue Versa-Tile. However, the reason why 101 Construction, represented by Mr Daoud, sued Dr Raiz, is clear enough - the Building Contract named 'Danny Raiz' as Owner and not Versa-Tile, who is not mentioned in it.
64 Where there is an issue about the identity of the parties to a contract and who the plaintiff should have sued, the court can make findings that depart from the pleading of the claim. Wilson J in Reardon v Stokes Contractors Pty Limited,[36] dealt with an appeal on the ground that:
The learned Magistrate entered judgment against the plaintiff, notwithstanding the contract pleaded to have been breached was between the defendant and [the plaintiff's company].
65 In dismissing this ground, Wilson J noted that the Magistrate 'identified the issue of the contracting parties as a primary issue of concern'.[37] Later, her Honour explained:
The identities of the contracting parties was clearly an issue in the proceedings before the Magistrate and, despite the imprecision of the original pleading[38], the issue appears to have been recognised by both the court and the parties. Indeed, the matter was conducted by the parties on that basis.
Despite that, Mr Reardon relies upon the failure to plead an action in contract against him in the pleadings filed by Stokes as a basis upon which to impugn the conclusions of the Local Court.
...
In oral submissions in court, the plaintiff stated:
'I should say, your Honour, as a matter of frankness, that it wasn't disputed ultimately that there was a contract as between the plaintiff and the second defendant; what was disputed was whether the plaintiff had brought any action in respect of that contract.'
The present plaintiff also relies upon the failure of Stokes to make an application to amend the pleadings so as to bring an action against Mr Reardon for breach of contract.[39]
Where there is a contention that a matter was determined on a basis other than one raised in the pleadings, attention must be given to both the pleadings and the manner in which the case was conducted.
Whilst the pleadings may be determinative of the matter, that is not always the case. Where neither the pleadings nor the evidence advanced and argued by the parties gives rise to determination of the matter on a basis other than that which was pleaded, there is likely to be a denial of procedural fairness to one or both parties in determining the trial by reference to a matter not argued before the court. That will not be the case, however, where the evidence adduced by the parties and the issues argued by them legitimately gives rise to determination of the matter pleaded on a different basis to that pleaded, and upon which the trial may be determined.
As stated in Gould v Mount Oxide Mines Ltd (in liq)]:
Undoubtedly, as a general rule of fair play, and one resting on the fundamental principle that no man ought to be put to loss without having a proper opportunity of meeting the case against him, pleadings should state with sufficient clearness the case of the party whose averments they are. That is their function. Their function is discharged when the case is presented with reasonable clearness. Any want of clearness can be cured by amendment or particulars. But pleadings are only a means to an end, and if the parties in fighting their legal battles choose to restrict them, or to enlarge them, or to disregard them and meet each other on issues fairly fought out, it is impossible for either of them to hark back to the pleadings and treat them as governing the area of contest.
See also Banque Commerciale SA (in liq) v Akhil Holdings Ltd; Dare v Pulham; Ingot Capital Investments Pty Ltd v Macquarie Equity Capital Markets.
Here, his Honour clearly took the view that, whilst breach of contract was pleaded against Nessfield[40] alone, the evidence adduced by both Stokes and Mr Reardon established the existence of a contract between the two at the material time, and the parties had argued the matter in a manner consistent with that evidence.
That conclusion was, in my view, open to his Honour, and does not represent a denial of procedural fairness to Mr Reardon.[41]
67 However, in that case the party found to have been a contracting party was a co- defendant to the proceeding. That was a critical feature not present in this case as 101 Construction did not sue Versa-Tile, but sued Dr Raiz.
68 The applicants' submissions contained suggestions that Mr Daoud knew that Dr Raiz was the agent for Versa-Tile, but 101 Construction only named Dr Raiz as the contracting party in its proceeding. It is unclear if Mr Daoud, for 101 Construction, did argue in the Tribunal hearing that Versa-Tile was the 'Owner' party to the building contract, but the question is not whether 101 Construction was denied procedural fairness, but whether Versa-Tile was.
69 A case based on a denial of procedural fairness can only succeed if the claimant establishes that it has suffered a practical injustice.[42]
70 VCAT is not a Tribunal of pleadings, although points of claim and defence are commonly ordered by VCAT, and it:
must conduct each proceeding with as little formality and technicality, and determine each proceeding with as much speed, as the requirements of this Act and the enabling enactment and a proper consideration of the matters before it permit.[43]
71 In performing that statutory role and in exercising the jurisdiction conferred by s 53 of the Domestic Contracts Act insofar as it was relevant, VCAT had to act in accordance with procedural fairness.
72 The identity of the contracting parties was raised as an important issue. Versa-Tile could not have obtained the Senior Member's order in BP311/2014 without his finding that it was the real contracting party, because the contract only named Dr Raiz. If 101 Construction had sued Versa-Tile being the entity that Dr Raiz contended was the party to the contract, then on the Tribunal's findings, which I have not disturbed, Versa-Tile would still have been held liable to 101 Construction in the amount of $39, 597.89.
73 The Senior Member, in performing the Tribunal's obligations to a self-represented litigant, in this case the Builder, may have been able to inform Mr Daoud, the director who was representing the Builder, of its right to apply, if it so chose, to join Versa-Tile to the proceeding and of the possible consequences for it, if he found that Versa-Tile was the 'Owner' party to the Building Contract, when it had not been joined as a party.[44] It is likely that any such application would have been granted. One feature of the proceeding was that submissions were made in writing including by the self-represented Builder and as a result, the Tribunal was unable to raise with the parties orally during submissions the orders that it might make.
74 The practical reasons for the Tribunal's orders are apparent, but, in my respectful opinion, before making any such orders, it should have first informed the parties that, if it found that Versa-Tile was the other or 'Owner' party to the Building Contract and not Dr Raiz, that it might make an order against it in the Builder's proceeding. While procedural fairness is a practical matter, the outcome of the Builder's proceeding is that the Builder obtained an order against Versa-Tile although it was not a respondent to the Builder's proceeding and the Builder had never sued it. Versa-Tile was before the Tribunal as an applicant in its own proceeding and it was not sued by the Builder. The fact that the two proceedings were heard at the same time does not alter the fact, that if Versa-Tile was to be found liable to the Builder in its proceeding, it needed to be joined as second respondent, perhaps in the alternative, in that proceeding. This is not a mere technical issue, as neither a Court nor a Tribunal can make an order for damages against a person who is not a party to the proceeding in which the damages are ordered. This is a matter of jurisdiction, as well as in the circumstances of this case, a matter of procedural fairness. I do not consider that this deficiency can be corrected in this Court on these applications for leave to appeal as they are limited to consideration of questions of law, in circumstances where the Builder is not represented and in now in liquidation. It is possible to speculate what, if any, difference, would have resulted from the Tribunal providing the applicants with notice of the course that it proposed to follow, but I do not consider that it is appropriate to do so on an application for leave to appeal on questions of law.
75 Question of law seven is established. The proposed grounds of appeal that relate to this question are those that appear under the heading 'Wrong Party'.
Question of law one - breach of an essential term
76 Question of law one was whether the Tribunal has misapplied the test for validly terminating a contract following the breach of an essential term of the contract. This question was connected with the second question of law which concerned repudiation. The Grounds of Appeal connected with this question were whether the Tribunal Member had failed to apply the test for breach of an essential term of the Building Contract:
the Tribunal Member erred at law in finding that there had not been a breach of an essential term of the Contract by the Builder which allowed the Plaintiff or the Owner to validly terminate the Contract.
77 The applicants argued that implied in the Senior Member's reasons was a finding that the building contract included a 'time is of the essence' clause, and thus, due to the delays in construction, an essential term of the contract had been breached entitling Versa-Tile to terminate the contract. The applicants claimed that paragraph 24 of the reasons, in particular the phrase 'especially where time is made of the essence', was a finding by the Tribunal that completing construction on time was an essential term of the building contract.
78 Paragraph 24 of the Tribunal's reasons and the associated paragraphs, which are contained in a section of the reasons dealing with 'Delays' are as follows:
79 The applicants have not established any error of law by the Tribunal in the terms raised in this question of law or the associated proposed grounds of appeal. First, the reasons themselves do not support their argument. A fair reading of the part of the reasons on which they rely reveals that the Senior Member did not consider that the contract contained a 'time is of the essence' condition. Secondly, the Senior Member on the evidence was entitled to make a finding that the term alleged by the applicants did not form part of the Building Contract.
80 Building contracts generally do not include 'time is of the essence' clauses because of the vicissitudes of construction.[45] Generally speaking, if that term is to be included in a building contract, it must be unequivocally expressed, and even then, courts may be hesitant to treat such clauses as making time of the essence.[46]
81 The terms and context of the Building Contract in these proceedings are consistent with the general approach that 'time is of the essence' clauses are not readily implied in domestic building contracts. In this case, of particular importance is clause 8.4 of the Building Contract, which refers to the Builder's rights to extend the completion date, whether 'entitled under the Contract or otherwise'.[47]
Question of law three - The 'scope of works' question
Whether the Tribunal Member failed to take into account relevant evidence of what was agreed between the parties as to the scope of the roofing works, and took into account irrelevant opinions of the Defendant's roofing subcontractor, when construing the terms of the relevant contract.
83 The scope of works question depended on the Court upholding the question that challenges the Tribunal's finding about repudiation.[48]
84 The applicants contend that the Senior Member made an error of law in identifying the terms of the contract, by failing to find that they included an oral term that guaranteed that the roofing works to be performed by the Builder would be 'watertight'. The proposed grounds of appeal in respect of question 3 were that: The Tribunal Member failed to take into account relevant evidence of what was agreed between the parties as to the scope of the roofing works, and took into account irrelevant evidence of what the plaintiff's [builder's] experts said in their reports about the roofing works, when construing the contract.
(a) The Tribunal Member made an error of law when he determined the scope of the roof plumbing work required under the Contract by reference to the expert reports rather than evidence of what was agreed by the parties [Reasons at 61-62].
(b) The Tribunal Member ought to have found that it was a term of the contract or the collateral contract that the builder was to ensure that the roof of the applicant's building would be 'water tight'.
(c) The Tribunal Member found, in reliance of the evidence of Mr Williams (being the builder's roofing subcontractor) rather than by reference to what the parties agreed that:
85 There then followed 14 subparagraphs that were not pressed. The matters contained in subparagraph 12(c) of the proposed grounds of appeal were not pressed in submissions.
86 The Senior Member addressed the issue of whether a condition of 'watertightness' formed part of the Contract, and found that it did not in the following passage:
87 Plainly evident in the above passage is a finding of fact by the Senior Member that the scope of works to be carried out by the Builder were contained wholly in the written terms of the Contract. That is hardly a surprising conclusion. The issue of whether a 'watertightness' condition was inserted by an oral variation of the written terms of the contract was a question of fact and no question of law arises from the Senior Member's finding on that question of fact. It is unnecessary to decide whether a failure to take into account relevant evidence, as is alleged in question three, in the circumstances of these proceedings could be an error of law, as the evidence does not support the conclusion that the Tribunal did fail to take any such evidence into account.
88 The applicants have established an error of law by the Tribunal as described in their question of law seven. The other questions of law that the applicants pressed have not been established and do not identify any other error of law by the Tribunal.
89 The question then arises as to the order that the Court should make taking into account the liquidation of the Builder, the liquidators' admission of the amount of $3,933.06, which VCAT awarded against the Builder to Versa-Tile and the provisions of s 500(2) of the Corporations Act 2001 (Cth).
90 I will give the parties, or in the case of the Builder, its liquidator, the opportunity to make any submissions they wish about the form of orders.
[1] BP311/2014 Versa-Tile Pty Ltd v 101 Construction Pty Ltd (Building and Property) [2015] VCAT 1472 ('Reasons').
[2] BP354/2014 101 Construction Pty Ltd v Raiz (Building and Property) [2015] VCAT 1473.
[3] Transcript of Proceedings, Versa-Tile Pty Ltd v 101 Construction Pty Ltd and Danny Raiz v 101 Construction Pty Ltd (Supreme Court of Victoria, S CI 2015 05336 & 05338, Ginnane J, 1 September 2016) 32, 46 ('T').
[4]. The history of the proceedings is set out in the affidavits of Alexander Collins, the applicants' solicitor, sworn 23 December 2015 in proceeding SCI 05336 of 2015 and sworn 9 March 2016 in proceeding SCI 05338 of 2015.
[5] [2005] VSCA 217; (2005) 13 VR 381, 387 [17].
[7] Christ Church Grammar School v Bosnich & Sehr [2010] VSC 476, [40] (citations omitted).
[14] Longdon v Kenalda Nominees Pty Ltd [2003] VSCA 128, [33] (Chernov JA).
[15] Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd (2003) 196 ALR 257, [38] (Hayne J).
[16] NCON Australia Ltd v Spotlight Pty Ltd [2012] VSC 604, [291] (Robson J).
[17] [2012] VSC 604, [281]-[296].
[22] Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 18th ed, 2009), 995-6 [26-022] (emphasis added).
[24] Damien Cremean et al, Brooking On Building Contracts (LexisNexis, 5th ed,2014) 282-283.
[27]. Reasons [58] (Italics in the Reasons).
[32] BP311/2014 Points of Claim, [3] Particulars.
[33] BP354/2014 Points of Defence, [3].
[36] Reardon v Stokes Contractors Pty Ltd [2015] NSWSC 960.
[38] Which only pleaded an action against the company.
[39] Ibid, [31]-[32] and [34]-[35].
[41] Ibid, [36]-[41] (citations omitted).
[42] Re Minister for Immigration and Multicultural and Indigenous Affairs (2003) 214 CLR 1, 14 [38] (Gleeson CJ).
[44] See the VCAT Fair Hearing Obligation Practice Note.
[45] Nicholas Dennys QC and Robert Clay (eds), Hudson's Building and Engineering Contracts (Sweet & Maxwell, 13th ed, 2015) 706 [6-006].
[47] Contract Ex 13 - Dr Raiz affidavit.
Versa-Tile Pty Ltd
101 Construction Pty Ltd [2017] VSC 73