[2020] VCAT 1410
Victorian Civil and Administrative Tribunal
2020-12-11
Original judgment source is linked above.
Scotch College v Boroondara CC [2020] VCAT 1410
Ms Juliet Forsyth SC and Ms Emma Peppler, Counsel, instructed by Mr Tom Callander from Rigby Cook Lawyers.
Mr Craig Murphy, Town Planer from Boroondara City Council.
Mr Nicholas Karageorge, Town Planner from Melbourne Water
Planning permit PP18/00017 was issued by Boroondara City Council on 30 July 2019, for the partial demolition of buildings and construction of buildings and carrying out of works associated with an existing education facility on land affected by the Land Subject to Inundation Overlay and Heritage Overlay, on land at 1 Morrison Street, Hawthorn (the review site). The Planning Permit was issued under the approved Master Plan for Scotch College (DP18/002).
The amendment sought under application PP18/00017.01 provides for the conversion of what was to be a basement storage to car parking, the omission of nominal landscaping and deletion of a window associated with the existing tuck shop.
Application under section 77 of the Planning and Environment Act 1987 - to review the refusal to grant a permit.
Zone and overlays applying to the application[1]
Special Use Zone Schedule 2 (SUZ2) (Private Education Centre) - clause 37.01 & Schedule 2.
Development Plan Overlay Schedule 2 (DPO2) - clause 43.04 and schedule 2.
Heritage Overlay, Schedule 608 (HO608) - clause 43.01.
Land Subject to Inundation Overlay, Schedule 1 (LSIO1) - clause 44.04 - applies to part of the relevant land.
Construct a building or construct or carry out works in the SUZ2 (clause 37.01-4) and the HO608 (clause 43.01-1) and on land subject to a LSIO (clause 44.04-2).
Demolish or remove a building in HO608 (clause 43.01-1)
Clauses 13.01-1S, 13.03-1S, 15.03-1S, 21.03, 21.04, 22.03, 37.01, 43.01, 44.04, 65.01, 66.03 and 71.02.
The review site is located on land described as 1 Morrison Street Hawthorn, being an existing education centre for Scotch College Campus, including a multiple range of education buildings, open space (formal and informal) parking and formal road accessways.
The northern boundary of the campus includes the properties on the northern side of Morrison Street. Glenferrie Road is adjacent to the eastern boundary, the M1 (Citylink) and Gardiners Creek provides the southern boundary. The Yarra River acts as the western boundary. The review site is partly situated on a designated floodplain at the confluence of Gardiners Creek and the Yarra River. Parts of the campus are subject to flooding from both watercourses during large flood events.
The proposed demolition and works occur within the area described in the application as the Keon Cohen building (building 6) within the Scotch College campus.
a) The implementation of the Flood Risk Management Plan which has been approved by the Responsible Authority and Melbourne Water Corporation under this permit.
b) The owner of the Land acknowledges and wholly accepts the risk to human safety and property associated with flooding in the event that the flood plank system fails/faults.
The Flood Risk Management Plan must be implemented to the satisfaction of the Responsible Authority and Melbourne Water.
The Flood Risk Management Plan must include an acknowledgement by the owner of the land that the high flood levels predicted on-site within the Keon Cohen Centre basement from the Yarra River require management of risk in accordance with the Flood Risk Management Plan and that the owner is responsible for the Flood Risk Management Plan implementation measures including the flood plank wall system.
The submissions of Melbourne Water Corporation
Flood risk management under the framework of the planning scheme
Flood risk management and the Guidelines for Development in Flood Affected Areas
Usually the information in the guidelines is sufficient to guide decision making. However, the guidelines cannot cover all the circumstances and aspects of flood behaviour.
Floodplain managers have discretion to vary from the guidelines, considering local circumstances, the nature of the development proposal and the flood risk.
Given the above commentary within the Guidelines and though more a practice document rather than policy, we nonetheless agree with the submissions from Scotch College that the Guidelines are .... a tool to assist decision making, they are not mandatory and nor do they definitively set out measures or circumstances that are acceptable or not.
The flood risk to people (including emergency services personnel) should be kept to acceptable safety thresholds, as per the latest updated Australian Rainfall and Runoff Guidelines.
Any development in a flood affected area, including associated infrastructure, should be planned to avoid or minimise the flood damage potential.
Flood risk is determined by the frequency of flooding and the potential economic, social and environmental consequences to the community. They are interlinked: the less frequent the event, the larger the potential consequences.
Usually, it is not practical to eliminate the flood risk. A challenge for the floodplain management authorities is to determine what flood risk is acceptable to the community.
Future growth in the flood risk can be limited by encouraging development intensification away from areas of high hazard. Where development does occur on flood affected land, the risk must be reduced at the property scale. Examples include elevating the floors of buildings and flood proofing.
Risk reduction solutions are not always appropriate. They need to be considered in terms of the impacts on people, property and the environment.
The nature and understanding of flood risk are not set in stone.
Previous applications of s 173 Agreements
Rather, the control focuses upon minimising the flood damage and allowing development that is 'compatible' with the flood hazard.
Melbourne Water questions whether the FRMP would be effective and would be implemented. We think that sufficient checks and balances can be in put place through the permit conditions to ensure an effective outcome.
(a) Reinstatement of the reference to 'Store 2' in the southern area of the basement.
(a) Identification of the use of any engineered flood warning and protection structures and the ongoing maintenance requirements for the life of the structures, including infrastructure.
(b) The nomination of flood plank wall product or equivalent suitable to the context for which it is proposed with details such as product maintenance and installation instructions.
(c) A maintenance plan for the flood plank systems (including mandatory annual maintenance checks and recording).
(d) Detail of discharge points for submersible pumps.
(b) Two diagonally opposed views of each internal space in the building; and
(c) Architectural design detailing of the building.
(a) The development does not start within two (2) years of the issue date of this permit; or
(b) The development is not completed within four (4) years of the issue date of this permit.
The Responsible Authority may extend the times referred to if a request is made in writing before the permit expires or:
(a) within six (6) months afterwards if the development has not commenced; or
(b) within twelve (12) months afterwards if the development has not been completed.
Council and the Victorian Civil and Administrative Tribunal are unable to approve requests outside of the relevant time frame.
[1] Other planning control provisions apply to the 1 Morrison Street Hawthorn, but do not fall within the area of proposed works and building construction. To avoid confusion, we have not referred to these in this table.
[2] This order now reflects the formal substitution of these amended plans.
[3] Orders of 2 October 2020 made under s 100 of the Victorian Civil and Administrative Tribunal Act 1998.
[4] Those being the plans referred to in order 1 of this decision.
[5] [2020] VCAT 958, at [58].
[9] [2020] VCAT 958, [24].
[10] [2020] VCAT 958, [58].
[11] [2019] VCAT 2058, [52].
Scotch College
Boroondara CC [2020] VCAT 1410