[2023] VSCA 182
General information, not legal advice.
Court of Appeal (Vic)
2023-08-11
Leish JA, Niall JA, MacAulay JA
Original judgment source is linked above.
RW & ME Smith Pty Ltd v Boral Resources (Vic) Pty Ltd [2022] VCC 729 (Judge A Ryan)
CONTRACT - Construction - Summary termination - Meaning of 'Cartage Works' in cartage contract - Whether applicant's repair of equipment at respondent's plant fell within meaning of 'Cartage Works' - Whether trial judge erred finding respondent entitled to summarily determine cartage contract due to applicant's alleged default in performing 'Cartage Works' - Error established - Appeal allowed.
CONTRACT - Construction - Scope of release clauses - Whether wide general words of release confined to apply only to specific subject matter - Properly construed relevant clauses only released and indemnified respondent from claims arising from short-term contract made after termination of principal contract - Respondent unable to rely on release in claim against it for breach of principal contract.
Grant v John Grant & Sons Pty Ltd [1954] HCA 23; (1954) 91 CLR 112 applied; Wardman v Macquarie Bank Ltd [2023] FCAFC 13 considered.
1. Cartage Works
1.1 The Contractor must perform the Cartage Works:
(a) in accordance with the terms of this Agreement;
(c) with due care and skill and in a courteous, co-operative and professional manner;
(d) safely, and in accordance with Boral's safety requirements as notified by Boral from time to time;
(e) in accordance with day to day operational directions given by Boral;
(f) in accordance with any direction, policy, procedure or specification (including but not limited to Boral's standard operating procedures) notified by Boral from time to time;
22.2 Boral may, by written notice to the Contractor, immediately terminate this Agreement or any Cartage Works being undertaken by the Contractor if the Contractor commits a material or wilful breach of any of the terms of this Agreement, including:
(a) refusal or failure to perform any Cartage Works;
...
(f) breach of any Applicable Laws, including Chain of Responsibility Laws.
...
22.4 Either party may, at its absolute discretion, terminate this Agreement at any time upon 3 months' written notice to the other party.
22.5 Upon termination by Boral under this clause 23 [sic], except to the extent otherwise required by Applicable Laws, the Contractor's only right to compensation will be for Cartage Works performed up to the time of termination and at the Cartage Rates specified in this Agreement, and the Contractor will not be entitled to any other form of compensation from Boral respect of such termination.
We refer to the meeting held with you on 21st of July 2015 and confirm the decision relayed to you that your Concrete Cartage Agreement has been terminated for reasons of level of conduct (serious misconduct) in relation to the nature of incidents that took place on 9th of July 2015 and your failure to adhere to the standard operating procedures.
Boral has considered your conduct and your responses in relation to these incidents. In our view, we are satisfied that your conduct amounts to serious misconduct in that your driver Tate Pickering and yourself:
Further, Boral considers that your conduct is in breach of:
(a) Terms of your Concrete Cartage Agreement with Boral, and
(b) Boral's policies and procedures relation to occupational health & safety
In the circumstances your conduct has given us no alternative but to terminate your Concrete Cartage Agreement with Boral. Boral will accept the on sale of below mentioned vehicles to an approved party through interview process and approval issued on compliance under the terms of contract. Both parties will be notified via correspondence to advise acceptance. Boral will then permit the sale upon return of a statutory declaration stating that "No Good Will" is involved in the sale ...
A Deed [of] termination will be required to end the Concrete Cartage Agreement ... As agreed this termination is effective on the day of 21st of August 2015.
Boral will conduct an interview with potential contractor and issue approval based on compliance under the term of contract. Both parties will be notified via correspondence to advise expectance. Boral will then permit the sale upon return of statutory declaration stating that "No Good Will" is involved in the sale of the aforementioned vehicles. Deed of Termination will be required to end the Concrete Cartage Agreement ... this will be issued pending an effective start date for on sale.
Background
The Contractor has, as a [sic] independent contractor, provided various transport services to Boral upon certain terms and conditions accepted and performed by the parties over a period of time (Contract).
The parties gave [sic, 'have'] mutually agreed to terminate the contract upon the terms and conditions set out in this deed.
Terms and Conditions
1. Contract Termination
1.1 To enable the Contractor to sell the vehicle within the Boral fleet.
2. Final Payment
2.1 Boral will pay the Contractor the amount due to the Contractor for services provided by the Contractor to Boral for the period from the last payment date to the Termination Date (Final Payment Amount).
2.2 The parties agree that payment by Boral to the Contractor of the Final Payment Amount is in full and final settlement of all payment obligations of Boral to the Contractor under the Contract to the intent and with the effect that no further claim for any payment may be made by the Contractor against Boral.
2.3 The parties agree that the Final Payment Amount includes but is not limited to any and all claims, costs, fees, fines, third party claims, claims for property and personal damage and expenses howsoever arising and in any way related to the transport services provided by the Contractor to Boral and the vehicles, equipment and drivers used or engaged by the Contractor when providing those transport services.
3. Indemnity and Release
3.1 By its execution of this Deed, the Contractor agrees that, subject to payment by Boral to the contractor of the Final Payment Amount due for the period to the Termination Date, the Contractor will indemnify and release Boral from any and all liabilities, losses, claims, damages and expenses howsoever arising which may, directly or indirectly, arise from the Contract and the vehicles, equipment and drivers used and engaged in the provision by the Contractor of the transport services.
3.2 The Contractor acknowledges and agrees that effective on the termination date the Contract between Boral and the Contractor is at an end and the Contractor has no further claims or entitlements against Boral either now or in the future and hereby releases and indemnifies Boral against any and all such claims.
4. General Conditions
...
0.0 [sic] Entire Agreement
This deed embodies the entire agreement and understanding between the parties concerning its subject matter and succeeds and cancels all another [sic] agreements and understandings concerning the subject matter of this deed and any warranty, representation, guarantee or other term and condition of any nature not contained in this deed is of no force or effect.
5. Legal advice
The Contractor confirms that it has been advised by Boral to obtain independent legal advice concerning the terms of this deed and has been provided with an opportunity to obtain that advice.
(a) Do the following implied terms form part of the cartage agreement: > > (i) implied terms of good faith and cooperation as pleaded by the plaintiff; and > > (ii) an implied term that the plaintiff would comply with its own and Boral's work, health and safety obligations, as pleaded by Boral? > > (iii) If so, did either party breach the implied terms? > > (b) Did the plaintiff breach any express terms of the cartage agreement, including clauses 1.1(d), (f) and (h)? > > (c) Was the plaintiff was acting at the request, supervision or direction of Boral on 9 July 2015, and if so, was Boral estopped or otherwise prohibited by law from terminating the cartage agreement? > > (d) Did Boral wrongfully terminate the cartage agreement? > > (e) In relation to the effect and construction of the Deed: > > (i) Do clauses 2.2, 3.1 and 3.2 of the Deed, separately or in combination, constitute an indemnity and release in favour of Boral from the claim that is the subject of this proceeding? > > (ii) If so, is Boral estopped from relying on the indemnity and release as provided under the Deed as to do so would be unconscionable? > > (iii) If not, pursuant to the principle of circuity of action, should the Court decline to grant the relief sought by the plaintiff in this proceeding? > > (f) Is the plaintiff entitled to an amount representing loss of goodwill, being the alternative head of damages claimed? > > (g) If so, has the plaintiff suffered loss and damage as a result?
(a) the rating of the seriousness of the incident by Boral as "Extreme" and a "Serious Harm Event; > > (b) the fact of the earlier disciplinary incident involving the plaintiff in 2014; > > (c) the fact that Boral sacked its own employee Mr Congram over the incident; and > > (d) Boral's oft stated concerns and requirements about ensuring safety procedures being followed at all times, in effect a zero-tolerance policy for unsafe work practices.
Whether a truck was being loaded at the time of the incident
Did the applicant breach the Agreement and enliven Boral's right of summary termination?
Was Boral precluded from terminating the Agreement for some other reason?
Did the applicant release Boral from the claim for wrongful termination?
3. Indemnity and Release
3.1 By its execution of this Deed, the Contractor agrees that, subject to payment by Boral to the contractor of the Final Payment Amount due for the period to the Termination Date, the Contractor will indemnify and release Boral from any and all liabilities, losses, claims, damages and expenses howsoever arising which may, directly or indirectly, arise from the Contract and the vehicles, equipment and drivers used and engaged in the provision by the Contractor of the transport services.
3.2 The Contractor acknowledges and agrees that effective on the termination date the Contract between Boral and the Contractor is at an end and the Contractor has no further claims or entitlements against Boral either now or in the future and hereby releases and indemnifies Boral against any and all such claims.
The Learned Trial Judge erred in concluding that the Deed, and in particular clause 3.2, released Boral from claims for wrongful termination in circumstances in which:
(a) the works performed were not Cartage Works within the meaning of the Concrete Cartage Agreement (see Ground 1) such that any release is inoperative; or
(b) the terms of the release ought to have been construed to be insufficient to encompass the wrongful termination (including statutory claims for unconscionability) of the Concrete Cartage Agreement.
[T]he general words of a release may be limited by the particular matter out of which the release springs and the particular intent of the parties by whom the release is executed.[31]
This first principle may be seen as an emanation of the more general principle that the words of a contract are to be construed as a whole having regard to the purpose or objects to be secured by the contract. The first principle operates on the premise that there are express objects evident from recitals.
The second and differently expressed common law principle of construction referred to in the joint judgment in Grant ... is that the general words in a release are limited to those things which were in contemplation of the parties at the time when the release was given.
...
The second principle may also be seen as an emanation of the more general principle that in the construction process regard be had to the purpose to be secured by a contract, objectively ascertained. To the extent that such an examination extends to mutually known circumstances that are extrinsic to the words of the contract, the principles referred to by French CJ, Nettle and Gordon JJ in Mount Bruce Mining at [48]-[49] will apply -
- [48] Ordinarily, this process of construction is possible by reference to the contract alone. Indeed, if an expression in a contract is unambiguous or susceptible of only one meaning, evidence of surrounding circumstances (events, circumstances and things external to the contract) cannot be adduced to contradict its plain meaning.
- [49] However, sometimes, recourse to events, circumstances and things external to the contract is necessary. It may be necessary in identifying the commercial purpose or objects of the contract where that task is facilitated by an understanding "of the genesis of the transaction, the background, the context [and] the market in which the parties are operating". It may be necessary in determining the proper construction where there is a constructional choice ...
(a) on 22 July 2015, Boral purported to immediately terminate the Agreement by giving the applicant notice of such termination under cl 22 of the Agreement; > > (b) despite the termination of the Agreement, the parties agreed that the applicant would continue to provide concrete delivery services to Boral in return for the payment of fees, under restricted driver arrangements, until such time as the applicant had secured a purchaser for its trucks with the agitators affixed and Boral had approved such purchaser; and > > (c) after 22 July the applicant continued to provide such services until 13 October 2015 when an approved purchaser bought the applicant's trucks and, as required by Boral, the applicant signed both a statutory declaration (declaring that it had not added any goodwill to the sale price of the vehicles) and the Second Deed.
Was it unconscionable for Boral to rely upon the release in the Second Deed?
Would Boral have terminated the Agreement on three months' notice?
...the indicative value of the Business Goodwill at 21 July 2015 is in the range of $353,000 - $424,000.
Total Value of the Business as a going concern at 21 July 2015 inclusive of physical property is between $638,000 - $709,000.
(a) Whether the correct basis upon which to assess the loss of bargain is to assess the net present value of the income the applicant would have earned for the life of the contract. > > (b) If so, how long should the entitlement to income be projected? What facts should be taken into account on that analysis? > > (c) Should Mr Jensen's figures be accepted as correct?
(a) Boral breached the Agreement by wrongfully purporting to exercise a right of immediate termination; > > (b) Boral's breach prevented the applicant from performing the Agreement and earning revenue from that performance; > > (c) Boral failed to prove that it would have terminated the Agreement upon three months' written notice; > > (d) the applicant is entitled to judgment, with costs, with damages to be assessed; and > > (e) the parties led the evidence at trial upon which they intended to rely for the assessment of loss and damage should the applicant succeed on its claim.
(a) the applicant have leave to appeal and the appeal be allowed; > > (b) the orders made by the County Court on 3 June 2022 be set aside and in their place there be judgment for the plaintiff (applicant in this Court) for a sum of damages to be assessed; > > (c) the proceeding be remitted to the County Court for the assessment of damages and orders as to costs; and > > (d) the respondent pay the applicant's costs of the appeal, including the application for leave to appeal.
[1] Competition and Consumer Act 2010 (Cth), sch 2.
[2] Described as the Second Deed because, as explained below, the parties entered into a prior identical deed.
[3] RW & ME Smith Pty Ltd v Boral Resources (Vic) Pty Ltd [2022] VCC 729 ('Reasons').
[4] In these reasons, proposed grounds of appeal are referred to as grounds of appeal.
[22] Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165, [40]; [2004] HCA 52.
[25] Gibb v Commissioner of Taxation [1966] HCA 74; (1966) 118 CLR 628, 638 (Barwick CJ, McTiernan and Taylor JJ); [1966] HCA 74; Kelly v The Queen [2004] HCA 12; (2004) 218 CLR 216, [84], [103] (McHugh J); [2004] HCA 12; Halford v Price (1960) 105 CLR 23, 26-28 (Dixon CJ; Menzies and Windeyer JJ agreeing), 32 (Fullagar J); [1960] HCA 38; Segelov v Ernst & Young Services Pty Ltd [2015] NSWCA 156; (2015) 89 NSWLR 431, [88] (Gleeson JA, Meagher and Leeming JJA agreeing); [2015] NSWCA 156; Craig Williamson Pty Ltd v Barrowcliff [1915] VicLawRp 66; [1915] VLR 450, 452; The Registrar of Titles of the State of Western Australia v Franzon [1975] HCA 41; (1975) 132 CLR 611, 618 (Mason J, Barwick CJ and Jacobs J agreeing); [1975] HCA 41; Parmar v Minister for Immigration and Citizenship [2011] FCA 760; (2011) 195 FCR 186, [18]; [2011] FCA 760.
[26] Grant v John Grant & Sons Pty Ltd (1954) 91 CLR 112; [1954] HCA 23 ('Grant').
[27] Grant [1954] HCA 23; (1954) 91 CLR 112, 123 (Dixon CJ, Fullagar, Kitto and Taylor JJ), citing Payler v Homersham [1815] EngR 1083; (1815) 4 M & S 423; 105 ER 890.
[28] Grant [1954] HCA 23; (1954) 91 CLR 112, 123 (Dixon CJ, Fullagar, Kitto and Taylor JJ), citing Lampon v Corke (1822) 5 B & Ald 606, 611 106 ER 1312, 1314 (Best J).
[29] Grant [1954] HCA 23; (1954) 91 CLR 112, 123-4.
[30] Upton v Upton (1832) Dow PC 400; 36 RR 817.
[31] Upton v Upton (1832) Dow PC 400, 406; 36 RR 817, 821.
[32] Grant [1954] HCA 23; (1954) 91 CLR 112, 123 (Dixon CJ, Fullagar, Kitto and Taylor JJ).
[33] Wardman v Macquarie Bank Ltd [2023] FCAFC 13 ('Wardman').
[34] Reid v Commonwealth Bank of Australia [2022] NSWCA 134.
[35] Burness v Hill [2019] VSCA 94 ('Burness').
[36] Wardman [2023] FCAFC 13, [290].
[37] Wardman [2023] FCAFC 13, [207]-[209]. See also Burness [2019] VSCA 94, [71]-[72] (Kaye, McLeish and Hargrave JJA).
[38] Citing Australian Securities and Investment Commission v Kobelt (2019) 267 CLR 1, 39 [92] (Gageler J); [2019] HCA 18.
[39] Berry v CCL Secure Pty Ltd [2020] HCA 27; (2020) 271 CLR 151, 175 [36] (Bell, Keane and Nettle JJ); [2020] HCA 27 ('Berry').
[40] Wills Australia Group Services Pty Ltd v Mitchell-Innes [2015] NSWCA 318, [122] (Macfarlan JA) ('Wills').
[41] Berry [2020] HCA 27; (2020) 271 CLR 151, 176 [38] (Bell, Keane and Nettle JJ).
[42] Warren v Coombes (1979) 142 CLR 531; [1979] HCA 9.
[43] Wills [2015] NSWCA 318, [122].
RW & ME Smith Pty Ltd
Boral Resources
(1954) 91 CLR 112
(1959) 101 CLR 298
(2004) 219 CLR 165
(1966) 118 CLR 628
(2004) 218 CLR 216
(1960) 105 CLR 23
(2015) 89 NSWLR 431
(1975) 132 CLR 611
(2011) 195 FCR 186
(2019) 267 CLR 1
(2020) 271 CLR 151
(1979) 142 CLR 531