[2000] VSCA 38
General information, not legal advice.
Court of Appeal (Vic)
2000-03-29
TADGELL, ORMISTON and CALLAWAY, JJ.A.
Original judgment source is linked above.
ARBITRATION - Building contract - Notice of dispute to be given "as soon as reasonably practicable" - Delay in giving notice - Application for stay - Whether applicant ready and willing to do all things necessary for proper conduct of arbitration - Commercial Arbitration Act 1984, s.53(1)(b).
"It would seem quite impractical and unreasonable to me to impose any burden upon the plaintiff to give a notice of dispute or difference with respect to the matters covered by the counterclaim prior to the defendant's having given notice of its intention to pursue its claim with respect to such matters by delivering its counterclaim on the 24th April last, particularly given the requirement placed upon the parties by Clause 17.1 to resolve their disputes "to their mutual satisfaction". Following the giving of the notice of counterclaim on 24 April 1998, in my view the plaintiff acted `as soon as reasonably practicable' in giving its notice of dispute or difference on 12 May 1998, immediately following judgment on the summary judgment application."
"One is bound to say that that is not the question which the justices had to decide. What they had to determine was whether the defendant had failed to report the accident at a police station or to a constable as soon as was reasonably practicable. As the accident took place at 1.10 a.m. and was not reported until 11 a.m., it seems to me that no reasonable bench of justices, instructing themselves properly, could possibly, without any explanation, have come to the conclusion that the defendant had failed to report the accident as soon as was reasonably practicable. If they had addressed their minds to the correct question, it seems to me that they would have come to the conclusion that the offence was clearly made out, as in my judgment it was."
"The concept of `a reasonable time' is frequently encountered in the law and life, but thankfully it can seldom be necessary to define it, much less to ascertain the period that the concept connotes. Rather than being concerned to designate a reasonable time, the courts are confronted almost daily with the question whether, within a specific context, a reasonable time has or has not run, when reckoned towards or away from a given point or event. The question is usually answered in the course of a value judgment not calling for much analysis and sometimes, perhaps, intuitively. Often the question answers itself. A reasonable time obviously has no norm or yardstick except that dictated by its own circumstances, including the purpose for which it is to be gauged."
"(1) What was the date on which the contractor completed the works? (2) Is the contractor entitled to have the date for substantial completion of the works extended by any, and if so what, period? (3) What is the date for substantial completion in the events which have occurred? (4) Is the principal entitled to any, and if so what, amount by way of liquidated or pre-ascertained damages for delay in completion?"
As the last sub-paragraph makes clear the issue is clearly whether there was "delay in completion" in the sense of a delay caused by an unjustified failure to complete by the date fixed for substantial completion.
". Liquidated and pre-ascertained damages Minimum nine weeks $45,000"
After stating that they were prepared to release a sum some $40,000 less than that claimed by the respondent, the project manager continued:
"Please note, there are significant incomplete works associated with your contract, which we require completed within (14) days. If these works remain incomplete after this period, we reserve the right to have these works completed by others, with associated payments being deducted from retention moneys held."
A few days later the lesser sum was paid, there being no indication that the respondent accepted the claim, nor that the appellant through its project consultants had abandoned it. As I have said, if there was any further correspondence on the matter, it has not been contained in the Appeal Book.
"By reason of the matters aforesaid the defendant is entitled to set off its entitlement to liquidated and pre-ascertained damages (which exceeds the sum claimed by the plaintiff) against the sum of $40,655.25 claimed by the plaintiff."
"(1) If a party to an arbitration agreement commences proceedings in a court against another party to the arbitration agreement in respect of a matter agreed to be referred to arbitration by the agreement, that other party may, subject to sub-section (2), apply to that court to stay the proceedings and that court, if satisfied -
(a) that there is no sufficient reason why the matter should not be referred to arbitration in accordance with the agreement; and
(b) that the applicant was at the time when the proceedings were commenced and still remains ready and willing to do all things necessary for the proper conduct of the arbitration -
may make an order staying the proceedings and may further give such directions with respect to the future conduct of the arbitration as it thinks fit." (Emphasis added.)
Compare s.5 of the Arbitration Act 1958.
If any question, difference or dispute whatsoever shall arise between the Principal and the Contractor, upon or in relation to or in connection with the Contract, which cannot be resolved by the contracting parties to their mutual satisfaction, either party may, as soon as reasonably practicable, by notice in writing to the other party clearly specify the nature of such question, difference or dispute and call for the point or points of issue to be submitted for settlement by arbitration." (Emphasis added.)
The "Principal" is the appellant and the "Contractor" is the respondent.
"Clause 17.1 of the building agreement stipulates that notice requiring arbitration be given 'as soon as reasonably practicable'. The defendant submits that since the plaintiff pleads that the works required under the building agreement were completed in July 1997, an invoice in respect of them was delivered on the 28th October 1997 and the last payment for the building works was made by the defendant to the plaintiff on 1 December 1997, the plaintiff, in waiting until 12 May 1998, did not give notice requiring arbitration 'as soon as reasonably practicable'. I do not accept this submission. The matters in dispute here are those referred to in the defendant's counterclaim which was delivered on 24 April 1998. It would seem quite impractical and unreasonable to me to impose any burden upon the plaintiff to give a notice of dispute or difference with respect to the matters covered by the counterclaim prior to the defendant's having given notice of its intention to pursue its claim with respect to such matters by delivering its counterclaim on the 24th April last, particularly given the requirement placed upon the parties by Clause 17.1 to endeavour to resolve their disputes 'to their mutual satisfaction'. Following the giving of the notice of counterclaim on 24 April 1998, in my view the plaintiff acted 'as soon as reasonably practicable' in giving its notice of dispute or difference on 12 May 1998, immediately following judgment on the summary judgment application."
[3] [1991] VicRp 77; [1991] 2 V.R. 367, at 378.
[5] This date seems largely a matter of inference since the date of payment appears only in paragraph 8 of the statement of claim, not denied in the defence, and there is otherwise no evidence as to conversations or correspondence at or about that time. One may assume that the respondent plaintiff was not content to accept that sum for it issued its proceedings for the balance on 11 March 1998. It appears uncertain, indeed unlikely, that the delay between the end of November and the ultimate giving of the notice was originally relied upon before the learned County Court judge, but equally there is little doubt, having regard to his reasoning at pp.180-181, that it was argued before him on that basis as one of the two alternative reasons for saying that the submission was not made as soon as reasonably practicable.
[6] I shall hereafter use the word "dispute" to cover all aspects of the expression "question, difference or dispute".
[7] Other than in Brunswick N.L. v. Sam Graham Nominees Pty. Ltd. [1990] 2 WAR 207 per Malcolm, C.J. at 208-209. The case was cited to the Court, but not this passage. It is not difficult to see why, for, although one would not wish to disagree with the outcome, the passage does not analyse the expressions, but merely expresses factual conclusions.
[8] The relevant provisions of that clause are set out later in this judgment.
[9] Neither counsel appearing before us appeared below.
[10] [1950] HCA 43; (1950) 81 C.L.R. 502 at 508-509.
[11] Unreported, Full Court, 4th May 1993 at 4.
[12] See, for example, Bell v. Sun Fire Insurance Office (1927) 29 Ll.L.Rep. 236 at 238; H.P. Brady Pty. Ltd. v. Kirsch [1936] VicLawRp 5; [1936] V.L.R. 44 at 47 and Carracher v. Colonial Mutual Life Insurance Society Ltd. [1968] V.R. 605 at 611. A commonsense approach is nevertheless required. A defendant, for example, may not be ready or willing to initiate an arbitration until it learns that proceedings have been commenced, or perhaps until it is served with the writ, but that does not mean that it was not ready and willing "at the time when the proceedings were commenced".
[13] [1975] VicRp 10; [1975] V.R. 108 at 116. Those observations must now be read subject to PMT Partners Pty. Ltd. v. Australian National Parks and Wildlife Service [1995] HCA 36; (1995) 184 C.L.R. 301. Moreover, it is not necessary that a notice of dispute have been given when the proceedings are commenced but only, if it has not, that the applicant then be ready and willing to give it.
[14] (1995) 35 N.S.W.L.R. 596 at 620 and 625-626. See also Manningham City Council v. Dura (Aust.) Constructions Pty. Ltd. [1999] VSCA 158 at [17] per Phillips, J.A.
Royal Society for the Prevention of Cruelty to Animals (Victoria) Incorporated
Marson Constructions Pty Ltd [2000] VSCA 38