[2014] NSWSC 1565
Supreme Court of NSW
2014-11-07
Garling J
Original judgment source is linked above.
(2)The plaintiff has leave to file and serve an amended statement of claim and any statement of particulars on or before 13 February 2015.
(3)Amended Notice of Motion of first defendant filed 5 November 2014 otherwise dismissed.
(4)Notice of Motion of second defendant filed 19 September 2014 otherwise dismissed.
(5)Notice of Motion of third defendant filed 17 September 2014 adjourned to 17 April 2015.
(6)The plaintiff to serve any expert report concerning dam operations upon which it proposes to rely at the hearing on or before 13 February 2015.
(7)Each defendant to file and serve its defence, verified in accordance with r 14.23 of the UCPR, together with a statement of the questions of law or fact which the defendant identifies as common to the claims of the group members on or before 10 April 2015.
(8)The matter be listed for a case management conference at 9.30am on 17 April 2015.
(9)The plaintiff is to serve on or before 29 May 2015:
(a)all written statements, in accordance with r 31.4 of the UCPR, of the oral evidence which it intends to adduce in chief at the hearing, on any and all questions of fact relevant to that hearing; and
(b)all expert reports, in accordance with r 31.27 of the UCPR, of all expert evidence which it intends to adduce in chief at the hearing, on any and all questions of expert opinion relevant to that hearing.
(10)Each defendant is to serve on or before 25 September 2015:
(a)all written statements, in accordance with r 31.4 of the UCPR, of the oral evidence which it intends to adduce in chief at the hearing, on any and all questions of fact relevant to that hearing; and
(b)all expert reports, in accordance with r 31.27 of the UCPR, of all expert evidence which it intends to adduce in chief at the hearing, on any and all questions of expert opinion relevant to that hearing.
(11)The plaintiff is to serve all lay and expert evidence in reply to the defendants lay and expert evidence on or before 29 October 2015. Such evidence to accord with the provisions of the UCPR referred to in Order 9 above.
(a)on or before 27 February 2015 (in the case of the second and third defendants); and
(b)on or before 10 April 2015 (in the case of the first defendant)
to provide discovery, in accordance with r 21.2 of the UCPR, of all documents relating to the control, operation and management of Somerset Dam and Wivenhoe Dam (including, without limitation, all documents sent to or received by the Flood Engineers in connection therewith) in the period 1 December 2010 to 19 January 2011, excluding:
(c)any document created after 19 January 2011, unless bearing a date within the period;
(d)any document previously provided to the plaintiff by any of the defendants; and
(e)any document received in evidence at the Queensland Floods Commission of Inquiry and currently publically available on the Commission's website
(13)The matter be listed for hearing commencing on 18 July 2016.
(14)The parties have liberty to apply, on 3 days' notice, to restore the matter for directions.
(15)The plaintiff will circulate a proposed document management protocol to the defendants with a view to the parties agreeing the same in advance of discovery being provided.
(16)Orders will be made in due course which provide for:
(a)conclaves of expert witnesses, and the production of joint reports during the period November 2015 to February 2016;
(b)the process of consensual, or else court-ordered mediation, during the period March 2016 to April 2016; and
(c)the undertaking of final pre-trial preparation during the period May 2016 to 15 July 2016.
(17)Order that the costs of the amended notice of motion of the first defendant and the notice of motion of the 2nd defendant be costs in the cause.
(18)Costs of the notice of motion of the 3rd defendant be reserved. Catchwords: PROCEDURE - civil - summary disposal - strike out statement of claim; application to - Uniform Civil Procedure Rules 2005, r 14.28 - representative proceedings - negligence - pleading - Civil Liability Act 2005 (Qld), s 9 - risk of harm - requirement to specifically plead - erroneous references in pleading - group members - closed class - geographically defined - pleading of group members deficient, whether - need to be more specifically pleaded as to geography and time, whether - proof of damage - common question of fact properly determined at hearing - pleading of foreseeability - defective, whether - greater specificity needed as to time at which damage was foreseeable and to whom, whether - not required - causation a matter for factual proof - breaches of duty - particulars - acts and omissions - acting unreasonably - failure to act reasonably - causation - pleading afforded defendants a fair opportunity to meet the case, whether - need to specify minimum available capacity by reference to dam height level - greater precision required in phrase 'greater flooding', whether - greater specificity in geography of flooding required - formulaic and repetitive allegations, whether - matter of convenience - claim extends over six weeks - many possible combinations of breach of duty - re-pleading Legislation Cited: Civil Liability Act 2003 (Qld) Civil Procedure Act 2005 Uniform Civil Procedure Rules 2005 Cases Cited: Council of the Shire of Wyong v Shirt [1980] HCA 12; (1980) 146 CLR 40 Forrest v Australian Securities Investment Commission [2012] HCA 39; (2012) 247 CLR 486 Gould v Mount Oxide Mines Ltd (in liq) (1916) 22 CLR 490 Sullivan v Moody [2001] HCA 59; (2001) 207 CLR 562 Young v Hones [2013] NSWSC 580 Category: Procedural and other rulings Parties: Rodriguez & Sons Pty Ltd (P) Queensland Bulk Water Supply Authority t/as Seqwater (D1) Sunwater Ltd (D2) State of Queensland (D3) Representation: Counsel: S Finch SC / N Owens / R Yezerski (P) B O'Donnell QC / D Klineberg (D1) D Williams SC / N Neal (D2) G H Thompson QC / E Morzone / J Horton (D3)
Solicitors: Maurice Blackburn (P) King + Wood Mallesons (D1) Norton Rose Fulbright (D2) Crown Solicitors (D3) File Number(s): 2014/200854
Judgment
The Statement of Claim
Notices of Motion
Uniform Civil Procure Rules
Principles to be applied
Submissions of Sunwater
Submissions of Seqwater
Summary
Orders
Amendments 20 March 2015 - Format amendment DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 20 March 2015
Rodriguez & Sons Pty Ltd
Queensland Bulk Water Supply Authority t/as Seqwater
(1980) 146 CLR 40
(2012) 247 CLR 486
(1916) 22 CLR 490
(2001) 207 CLR 562
(2000) 170 ALR 487
[2001] HCA 59