[2026] NSWSC 940
Supreme Court of NSW
2026-08-06
Hmelnitsky J
Original judgment source is linked above.
Source: NSW Caselaw (www.caselaw.nsw.gov.au). Converted to plain text by ZoeLaw. Not the official version.
Medium Neutral Citation: Reward Interiors Pty Ltd t/as Reward Group v Stream Line Joinery Pty Ltd; Stream Line Joinery Pty Ltd v Reward Interiors Pty Ltd t/as Reward Group [2026] NSWSC 940
Hearing dates: 27 July 2026
Date of orders: 06 August 2026
Decision date: 06 August 2026
Jurisdiction: Equity - Technology and Construction List
Before: Hmelnitsky J
Decision: (1) Summons dismissed.
(2) Cross-summons dismissed.
(3) The plaintiff is to pay the first defendant’s costs as agreed or assessed.
(4) The first cross-defendant is to pay the cross-claimant’s costs as agreed or assessed.
(5) Direct the parties to bring in short minutes of order by 4:00PM on 13 August 2026 dealing with the funds paid into Court pursuant to the order made on 19 March 2026.
Catchwords: BUILDING AND CONSTRUCTION — Adjudication — Judicial review — Where defendant brought payment claim against plaintiff under Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) — Where adjudicator made determinations on payment claim — Where adjudicator decided that payment claim was served within time per s 13(4)(b) of the Act — Whether adjudicator fell into jurisdictional error in his application of s 13(4)(b) — Whether error was material — Whether order in the nature of mandamus is an appropriate form of relief
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW), ss 4, 8, 13(4), 14, 17, 22(5), 26(2)(b), 26E, 32
Civil Procedure Act 2005 (NSW), s 56
Cases Cited: Acciona Infrastructure Australia Pty Ltd v Chess Engineering Pty Ltd (No 2) [2020] NSWSC 1788
Brodyn Pty Ltd (t/a Time Cost & Quality) v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394
Builtcom Construction Pty Ltd v VSD Investments Pty Ltd [2025] NSWSC 250
CPB Contractors Pty Limited v Heyday5 Pty Limited [2020] NSWSC 1625
EQ Constructions Pty Ltd v A-Civil Aust Pty Ltd [2021] NSWSC 1604
Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Pty Ltd (2004) 61 NSWLR 515; [2004] NSWCA 393
Federal Commissioner of Taxation v Futuris Corporation Ltd (2008) 237 CLR 146; [2008] HCA 32
Hossain v Minister for Immigration and Border Protection (2018) 264 CLR 123; [2018] HCA 34
LPDT v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs (2024) 280 CLR 321; [2024] HCA 12
Martinus Rail Pty Ltd v Qube RE Services (No 2) Pty Ltd [2025] NSWCA 49
Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597; [2002] HCA 11
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4
Procon Developments (Australia) Pty Ltd v Hi-Cal Bricklaying [2025] QSC 67
Tomkins Commercial & Industrial Builders Pty Ltd v Starline Interiors Pty Ltd [2026] QSC 21
Tooth & Co Ltd v Council of the City of Parramatta (1955) 97 CLR 492; [1955] HCA 21
TWT Property Group Pty Ltd v Cenric Group Pty Ltd [2020] NSWSC 72
Category: Principal judgment
Parties: Reward Interiors Pty Ltd t/as Reward Group (Plaintiff/First Cross-Defendant)
Stream Line Joinery Pty Ltd (First Defendant/Cross-Claimant)
Ned Mortensen (Second Defendant/Second Cross-Defendant)
Adjudicate Today Pty Limited (Third Defendant/Third Cross-Defendant)
Representation: Counsel:
M Thompson (Plaintiff/First Cross-Defendant)
J Adamopoulos (First Defendant/Cross-Claimant)
Solicitors:
HWLE Lawyers (Plaintiff/First Cross-Defendant)
ERA Legal (First Defendant/Cross-Claimant)
File Number(s): 2026/00069094
Publication restriction: Nil
The plaintiff, Reward Interiors Pty Ltd (Reward), was a contractor for some refurbishment works at the Sofitel Wentworth Hotel at 101 Phillip Street, Sydney. In June 2024, Reward engaged the first defendant, Stream Line Joinery Pty Ltd (Stream Line), as a subcontractor to ‘supply, manufacture and install’ some joinery for the refurbishment.
On 30 September 2025, Stream Line issued a payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) for an amount of $136,106.03 including GST. It lodged an adjudication application on 28 October 2025 with the third defendant, Adjudicate Today Pty Limited (Adjudicate Today), which is an adjudication agency. By its adjudication response, Reward contended (among other things) that ‘all works under the contract’ had been completed by 25 September 2024 and that Stream Line had ‘last carried out construction work to which the claim relates on 25 September 2024’.
It followed, in Reward’s contention, that the payment claim was brought outside the 12-month period for which s 13(4) of the Act provided.
On 18 November 2025, the second defendant (the Adjudicator) made a determination (the First Determination) in which he found that the amount payable to Stream Line by Reward was the amount claimed, being $136,106.03. He specifically rejected Reward’s challenge to jurisdiction based on s 13(4). In so doing, he rejected Reward’s evidence that the final joinery installation work had taken place on 25 September 2024. He instead accepted Stream Line’s evidence that the final installation work had taken place on 1 October 2024 and that certain remediation work had taken place on 9 October 2024.
The Adjudicator made a further determination on 2 December 2025 (the Second Determination) whereby a small correction was made to the First Determination. Nothing turns on the difference between the two determinations (the Determinations) in these proceedings.
Reward contends that the Adjudicator misdirected himself as to the applicable law in determining the s 13(4) point. It contends that the Adjudicator thereby fell into jurisdictional error and that the Court should make a declaration that the Determinations are void and of no effect.
Stream Line disputes that the Adjudicator made the asserted error. It says that even if he did, the error was not material having regard to the Adjudicator’s factual findings about when the installation work under the contract was completed, namely that it occurred on 1 October 2024, as Stream Line had contended, not on 25 September 2024, as Reward had contended. By cross-summons, Stream Line contends in the alternative that the matter should be remitted to the Adjudicator to determine the s 13(4) question according to law.
On 4 June 2024, Reward entered into a written subcontract titled ‘Purchase Order – Sub Contractor’ (the Contract) with Stream Line for the supply and installation of bespoke banquette seating, counters, bars, tables, a hotel reception desk and wooden building components at the Sofitel Wentworth Hotel.
The Contract detailed the joinery items that Stream Line was subcontracted to complete and the price of each item. Those items added up to a total contract price of $529,635 excluding GST. Of particular relevance here were three items labelled ‘J5.54’ which were the banquette seating components.
Attached to the Contract was a Construction Programme, which set out a schedule for all of the refurbishment works to be completed at the Sofitel Wentworth Hotel.
From June 2024, Stream Line fabricated and installed the various pieces of joinery specified in the Contract. During this time, there were some agreed variations to the scope of the works to be completed by Stream Line as well as some variations which were in dispute before the Adjudicator.
On 29 September 2024, Stream Line served a tax invoice on Reward by email in the amount of $136,106.03, including GST, for what was described as the ‘balance of joinery package’.
On 30 September 2025, Stream Line issued a tax invoice to Reward which was a payment claim under the Act (the Payment Claim). The total amount of the Payment Claim was $136,106.03 including GST for the ‘[b]alance of joinery package as setout [sic] in the attached breakdown’.
The ‘attached breakdown’ was a schedule which set out the details and price of all of the items required under the Contract as well as of the agreed variations (totalling $449,105.00 excluding GST). That schedule included the three ‘J5.54’ banquette items. It then set out the details of all invoices paid to date (totalling $325,372.25 excluding GST) to arrive at the amount to be paid for the balance of the joinery package including 5% retention ($123,732.75 excluding GST).
On 14 October 2025, Reward served a payment schedule (the Payment Schedule) on Stream Line which scheduled a negative amount of $256,899.25 excluding GST. The Payment Schedule set out various grounds for withholding the payment that was claimed by Stream Line, including set-off costs, a purported claim in liquidated damages for delay, and several disputed variations.
Stream Line soon lodged an adjudication application (the Adjudication Application) with Adjudicate Today on 28 October 2025. The Adjudication Application included Stream Line’s written submissions, the Payment Claim, the Payment Schedule and a statutory declaration of Mr Steven Plesa, a director of Stream Line, declared on 28 October 2025 on behalf of Stream Line. It also contained documents said to form the contract between the parties (including the Contract) and correspondence.
Mr Plesa’s statutory declaration contains his account of Stream Line’s engagement by Reward. In relation to the timeline for the completion of the banquette seating, he said the following:
“82. Photos pertaining to the banquette seating that I took during manufacture/internal fabrication are included as follows:
(a) During fabrication by Streamline taken on 26 September 2024 (exhibited at pages 564 to 568);
(b) On completion day by Streamline taken on 1 October 2024 (exhibited at page 569); and
(c) During defect rectification by Streamline taken on 9 October 2024 (exhibited at pages 570 to 582).”
The photographs referred to at paragraph 82(a) of Mr Plesa’s statutory declaration were of an unfinished banquette at various stages of its construction.
I particularly note the following photograph taken on 1 October 2024 of one of the banquettes, being the photograph that Mr Plesa described at paragraph 82(b):
The photographs taken on 9 October 2024 during the defect rectification stage depicted the completed but defective banquettes.
In response to the Adjudication Application, Adjudicate Today issued a Notice of Acceptance on 31 October 2025 to both Stream Line and Reward which identified Mr Mortensen as the Adjudicator.
On 5 November 2025, Reward lodged an adjudication response (the Adjudication Response). That Adjudication Response included Reward’s written submissions, a statutory declaration of Mr Christopher Donohue, the founder and managing director of Reward, declared on 5 November 2025 on behalf of Reward, the Construction Programme, drawings for the joinery works and various correspondence.
The Adjudication Response expressly raised the issue of whether the Payment Claim complied with s 13(4) of the Act. Reward said in its written submissions that the Payment Claim was not validly served in accordance with s 13(4) because it was served more than 12 months after Stream Line completed its installation of all works under the Contract.
Reward claimed that all of Stream Line’s work was completed by 25 September 2024 as follows:
“20. As is established by the declaration of Christopher Donohue, Streamline last carried out construction work to which the claim relates on 25 September 2024.
- The payment claim was issued on the 30 September, which is outside of the 12 month period stated within the Act.
- Accordingly, the tax invoice was not a valid payment claim pursuant to the Act. Based on this the Adjudicator does not have jurisdiction to make a determination for this application. Email Correspondence at Tab 1. Confirm the completion date of Streamline’s work under contract.
- Screenshot of messages sent from George Kalenderian a Site Manager for Reward show all the Banquette seating which was the last items under the contract delivered and installed by 25 September 2024 at Tab 2.”
“3.2 From my recollection of events on site and from reviewing Reward's records related to the Project, including but not limited to the Payment Claim, Streamline last carried out work the subject of the Payment Claim on 25 September 2024.
3.3 I have reviewed the Payment Claim. The Payment Claim does not claim payment for any construction work or related goods and services carried out after 25 September 2024.
…
3.6 Given that Streamline has not carried out any work to which the Payment Claim relates since 25 September 2024, and the Payment Claim does not claim for any work carried out after 25 September 2024, I understand Streamline’s tax invoice is not a valid payment claim pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW).”
“Streamline have finally completed all their joinery installation at Sofitel Wentworth.
I hope we never have to see them again! That was a punish to get it finally done!
Please feel free to contact me to discuss further if need be.”
On 19 November 2025, Adjudicate Today issued to the parties the First Determination, dated 18 November 2025. The First Determination stated that the amount of $136,106.03 including GST was payable as a progress payment by Reward to Stream Line. The due date for payment was 29 October 2025, interest was to accrue pursuant to s 101 of the Civil Procedure Act 2005 (NSW). Reward was to pay all of the adjudication fees and expenses.
As for Reward’s challenge to his jurisdiction, the Adjudicator decided that the Payment Claim had been served within time in accordance with s 13(4)(b) of the Act. It is this particular aspect of the Determinations which is the focus of the current proceedings. The Adjudicator’s reasons on this issue are contained at paragraphs 6 to 14 of the First Determination, under the heading ‘Jurisdictional Challenge’. These paragraphs are reproduced in full below:
“6 The Respondent has made a submission challenging my jurisdiction, contending that the Payment Claim served by the Claimant on 30 September 2025 is invalid under the Act because it was served out of time.
7 The submission rests on the evidence within the statutory declaration of Christopher Donohue, which asserts that the Claimant last carried out construction work to which the claim relates on 25 September 2024. The precise wording at paragraphs 3.2 and 3.3 of the declaration is that ‘Streamline last carried out work the subject of the Payment Claim on 25 September 2024’ and that ‘The Payment Claim does not claim payment for any construction work or related goods and services carried out after 25 September 2024’.
8 That evidence cannot be applied to the relevant legal test. The time limit for serving a payment claim is established by s 13(4) of the Act, which provides;
(4) A payment claim may be served only within—
(a) the period determined by or in accordance with the terms of the construction contract, or
(b) the period of 12 months after the construction work to which the claim relates was last carried out...
whichever is the later.
9 The test for the final date on which a payment claim can be made prescribed by s 13(4)(b) is not whether the work being claimed for payment was carried out within the preceding 12 months, but rather, if any ‘construction work to which the claim relates’ was carried out within the preceding 12 months. The statutory test of s 13(4) is therefore significantly broader than the reach of the Respondent’s evidence on the point.
10 In this case the payment claim relates to construction work within the meaning of s 5 of the Act, which is the manufacture and installation of joinery within the Respondent’s works at 101 Phillip Street Sydney.
11 The statutory declaration of Steven Plesa, declared 28 October 2025, asserts that joinery installation occurred on 1 October 2024 and that defect rectification works were carried out on site on 9 October 2024. This evidence is supported by photographs which are included by reference within the statutory declaration.
12 Notably, the Respondent has not specifically addressed or provided any evidence to rebut the Claimant’s assertion that it performed ‘construction work’ on 1 and 9 October 2024. In the absence of any challenge to that I determine that ‘construction work’, within the meaning of s 5 of the Act, was last carried out on 9 October 2024. That is the relevant date for determining the final date on which a Payment Claim may be served under s 13(4)(b) of the Act.
13 Applying that determination, the 12 month period in which it was open for the Claimant to serve a payment claim expires on 9 October 2025. The Payment Claim was served on 30 September 2025, which is within the time allowed.
14 It follows that the challenge to jurisdiction on these grounds must fail. I am satisfied that the Payment Claim has been made within time and is a valid claim under the Act.”
On 20 November 2025, Stream Line sent an email to Adjudicate Today requesting that the Adjudicator exercise his power under s 26E of the Act to amend the First Determination so that Reward was directed to provide the identity and contact details of any person who is a principal contractor in relation to the Payment Claim.
Adjudicate Today served the Second Determination made by the Adjudicator on 2 December 2025. The Second Determination was issued in accordance with s 22(5) of the Act to make corrections to the First Determination.
The Second Determination was identical to the First Determination save for the addition of new paragraphs 85 and 86, in which the Adjudicator directed Reward to provide information to Stream Line as to the identity and contact details of any person who is a principal contractor in relation to the Payment Claim, in accordance with s 26E of the Act and as sought by Stream Line.
By its summons and an Amended Technology and Construction List Statement, Reward seeks a declaration that both Determinations are void for jurisdictional error. Making a finding as to whether the Determinations are affected by jurisdictional error requires the Court to answer the following three questions:
First, whether the Adjudicator fell into error in his application of s 13(4) of the Act.
Secondly, if the Determinations were affected by error, whether the Adjudicator’s error in applying s 13(4) is subject to a threshold of materiality.
Thirdly, if a threshold of materiality applies, whether the error was material.
Because the Determinations are relevantly identical, Reward says that to the extent there was an error in the First Determination, that error was repeated in the Second Determination.
If the Determinations are void for jurisdictional error, the issue of relief arises. In its cross-summons, which names Reward, the Adjudicator and Adjudicate Today as the first, second and third cross-defendants respectively, Stream Line seeks an order in the nature of mandamus, namely ‘remittal’ of the Adjudication Application to the Adjudicator to be decided in accordance with law. Reward opposes the grant of this relief.
The Act establishes a regime by which parties to a construction contract can receive progress payments in relation to the work they carry out under that contract.
A ‘progress payment’ is defined in s 4 of the Act as follows:
progress payment means a payment to which a person is entitled under section 8, and includes (without affecting any such entitlement)—
(a) the final payment for construction work carried out (or for related goods and services supplied) under a construction contract, or
(b) a single or one-off payment for carrying out construction work (or for supplying related goods and services) under a construction contract, or
(c) a payment that is based on an event or date (known in the building and construction industry as a “milestone payment”).
(1) A person who, under a construction contract, has undertaken to carry out construction work or to supply related goods and services is entitled to receive a progress payment.
(1) A person referred to in section 8 who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
(1A) A payment claim may be served on and from the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and on and from the last day of each subsequent named month.
(1B) However, if the construction contract concerned makes provision for an earlier date for the serving of a payment claim in any particular named month, the claim may be served on and from that date instead of on and from the last day of that month.
(1C) In the case of a construction contract that has been terminated, a payment claim may be served on and from the date of termination.
(2) A payment claim—
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount), and
(c) must state that it is made under this Act.
(3) The claimed amount may include any amount—
(a) that the respondent is liable to pay the claimant under section 27(2A), or
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.
(4) A payment claim may be served only within—
(a) the period determined by or in accordance with the terms of the construction contract, or
(b) the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied),
whichever is the later.
(1) A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant.
(2) A payment schedule—
(a) must identify the payment claim to which it relates, and
(b) must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount).
(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent’s reasons for withholding payment.
If the respondent does not pay the claimant in accordance with the payment schedule, the claimant may make an adjudication application under s 17 in relation to the payment claim. Part 3, Div 2 of the Act details the process for adjudication of disputes.
Section 32 makes clear that nothing in Pt 3 of the Act affects a party’s rights in civil proceedings arising out of the construction contract:
(1) Subject to section 34, nothing in this Part affects any right that a party to a construction contract—
(a) may have under the contract, or
(b) may have under Part 2 in respect of the contract, or
(c) may have apart from this Act in respect of anything done or omitted to be done under the contract.
(2) Nothing done under or for the purposes of this Part affects any civil proceedings arising under a construction contract, whether under this Part or otherwise, except as provided by subsection (3).
(3) In any proceedings before a court or tribunal in relation to any matter arising under a construction contract, the court or tribunal—
(a) must allow for any amount paid to a party to the contract under or for the purposes of this Part in any order or award it makes in those proceedings, and
(b) may make such orders as it considers appropriate for the restitution of any amount so paid, and such other orders as it considers appropriate, having regard to its decision in those proceedings.
The whole of the Adjudicator’s reasoning in relation to the s 13(4) point is reproduced at paragraph [29] above. I will refer to parts of that passage as D6, D7 and so on, corresponding to the paragraph number.
Reward contends that the Adjudicator’s statement of the test in D9 was erroneous and that the error is apparent not only from the way in which the test was formulated but from the way in which it was applied. Reward draws attention to the statement in D8 that Mr Donohue’s evidence ‘cannot be applied to the relevant legal test’, to the statement in D9 that the test is ‘therefore significantly broader than the reach of’ Reward’s evidence on this point’ and, most especially, to the statement in D12 that Reward had not rebutted Stream Line’s assertion that it performed ‘construction work’ within the meaning of the Act on 1 and 9 October 2024. It submits that these statements reveal the Adjudicator’s understanding of the relevant legal question, namely that it did not turn on evidence of when Stream Line had performed the work described in the Payment Claim, but rather on when Stream Line had performed any construction work even loosely related to the Payment Claim.
Reward also stressed that the finding in D12 was not that the construction work performed on 1 and 9 October 2024 was work to which the Payment Claim related but that it was ‘construction work’ within the meaning of the Act. Thus, when the Adjudicator said in D12 that 9 October 2024 was the relevant date for determining the final date on which a payment claim may be served under s 13(4)(b), he must mistakenly have been referring to the last date on which any construction work under the Contract (or, perhaps, construction work loosely related to the Payment Claim) was performed instead of the last date on which work being claimed for payment was carried out.
Reward thus contends that the Adjudicator fell into a similar error to that identified by Williams J in EQ Constructions Pty Ltd v A-Civil Aust Pty Ltd [2021] NSWSC 1604 (‘EQ Constructions’) and by the Court of Appeal in Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Pty Ltd (2004) 61 NSWLR 515; [2004] NSWCA 393 (‘Estate Property’). It contends that the Adjudicator should have asked himself when ‘any work to which the payment claim relates’ was last performed. Instead, as the foregoing aspects of his reasoning disclose, he asked himself when ‘any construction work’ was last performed. This, Reward contends, is especially apparent from the fact that the Adjudicator attached significance to the remediation works done on 9 October 2024 because those works cannot conceivably (so Reward submits) have been works to which the Payment Claim related. The work done on 9 October could only have been material on an incorrect understanding of the s 13(4) question.
Stream Line submits that the Adjudicator stated and applied the correct legal test. It says that D9 disclosed a correct understanding of s 13(4)(b), in line with the Court of Appeal’s explanation of that provision in Estate Property. On Stream Line’s reading of the Determinations, the Adjudicator accepted at D11 the evidence of Mr Plesa that work was completed on 1 and 9 October 2024, and then noted at D12 that Reward had not presented anything in the Adjudication Response to rebut this evidence. On the basis of these factual findings, he determined that the work performed on 1 and 9 October was work to which the claim related, in circumstances where the Payment Claim was for the ‘balance of [the] joinery package’ including retention.
Stream Line says that the Determinations should not be read with an ‘overcritical or pedantic eye but should be viewed with common sense and without undue legality’: CPB Contractors Pty Limited v Heyday5 Pty Limited [2020] NSWSC 1625 at [35] (Hammerschlag J).
Although I consider the matter to be quite finely balanced, I am not persuaded that the Adjudicator made the error attributed to him. I will explain below my reasons for reaching that conclusion. It is first however appropriate to identify the question which the Adjudicator was required to ask himself.
Section 13(4) is set out at paragraph [39] above. In Estate Property, Hodgson JA (Mason P and Giles JA agreeing) rejected the primary judge’s interpretation of s 13(4)(b) as requiring that only ‘some work under the construction contract’ had to be performed in the 12-month period and held at [17]-[18]:
“[17] In my opinion, s 13(2)(a) of the Act requires that a payment claim identify the construction work for which payment is claimed in the claim, not merely the construction work as a whole that is being carried out under the relevant construction contract. I think this is indicated by the words ‘construction work … to which the progress payment relates’; and strongly confirmed by the consideration that, unless a progress claim identified the particular work for which payment was claimed, it would be impossible for a respondent to provide a meaningful payment schedule supported by reasons. This in turn would make wholly unreasonable s 20(2B) of the Act, which prevents a respondent relying, in an adjudication of a payment claim, on reasons not included in the payment schedule.
[18] Consistently with this, in my opinion ‘construction work … to which the claim relates’ in s 13(4)(b) is also the construction work for which payment is claimed in the claim; and accordingly, the requirement of s 13(4)(b) is that some of that construction work be carried out in the relevant twelve month period. Accordingly, in my opinion, the primary judge’s acceptance of the first of the three interpretations of s 13(4)(b) which he identified, both in this case and in Leighton, was incorrect.”
In so holding, his Honour explicitly rejected a proposition accepted by the primary judge, namely that the section requires ‘only that some work under the construction contract had been performed in the twelve month period’: Estate Property at [11].
In EQ Constructions, Williams J identified a similar error that had been made by the adjudicator. In that case, the adjudicator had found that certain ‘demobilisation’ works had occurred during the 12 months preceding the making of the payment claim and that those works were sufficiently ‘related’ to the construction works under the contract that the section was satisfied. At [78], her Honour described the difficulty as being that:
“… the demobilisation activities were the only work that had been carried out within 12 months prior to the service of the payment claim, … the work described in the payment claim (including the schedule and other accompanying documents) did not refer to those demobilisation activities and … the monetary amount claimed did not include any amount for those activities.”
“A payment claim that neither refers to nor includes any monetary amount for the only work identified by the claimant [as] having [been] carried out within that period, is not a payment claim relating to that work.”
It follows that the question which the Adjudicator was required to determine was whether any of the work for which payment was claimed was performed during the 12-month period preceding the Payment Claim.
It is also important to appreciate the material that was before the Adjudicator on this issue.
The issue about s 13(4) arose late in the piece, at least by the standards of the incredibly short timelines prescribed by the Act. The Payment Claim had sought payment for the ‘[b]alance of joinery package as set out in the attached breakdown’. The attached breakdown identified all of the items described in the Contract including three banquettes to be installed on level 5 of the hotel. The banquettes were identified as ‘J5.54’, which was how they were referred to in the Contract itself. The breakdown attached to the Payment Claim set out the total of all items, which corresponded to the total contract amount including retention, and then made deductions for invoices paid. It then identified the balance to be paid excluding GST but including retention of $123,732.75. The Payment Claim was therefore a final claim for the value of all work under the Contract, less only those amounts that had been invoiced and paid.
The Payment Schedule made no mention of the s 13(4) issue. It did however assert Reward’s claim for liquidated damages under the Contract and some other grounds for withholding payment. The liquidated damages were for asserted delay on the part of Stream Line.
In Mr Plesa’s statutory declaration, he responded to the liquidated damages claim. In the course of explaining the delay, he said that the banquette seating had been installed on 1 October 2024 and that 1 October was ‘completion date’. He exhibited a photograph showing that the banquette seating was not completely installed prior to 1 October 2024, which photograph is reproduced at paragraph [19] above. He also said that Stream Line had completed some remediation work on 9 October 2024 and exhibited photographs of the banquettes during the remediation work.
The Adjudication Response was the first time the s 13(4) issue had been raised. The Adjudication Response took the issue up in the way described at paragraphs [22] to [27] above, relying on Mr Donohue’s statutory declaration, some correspondence within Reward and messages from the Site Manager.
It was in this context that the Adjudicator came to the s 13(4) question. The factual issue that had been identified was whether the installation works had been completed on 25 September 2024 as Reward asserted or whether they had been completed on 1 October 2024 as Stream Line asserted. On any view, the final installation of the banquettes was work for which payment was claimed. This was not a case in which the claimant was seeking to rely on ‘construction work’ done during the preceding 12-month period that was not work for which payment was claimed.
What, then, is to be made of the first sentence of D9? That sentence said that:
“The test for the final date on which a payment claim can be made prescribed by s 13(4)(b) is not whether the work being claimed for payment was carried out within the preceding 12 months, but rather, if any ‘construction work to which the claim relates’ was carried out within the preceding 12 months.”
As Mr Thompson, who appeared for Reward, accepted, the test which the Adjudicator was asserting in the second clause of this sentence is drawn directly from the Act. It is not a complete statement of the provision, but it is not wrong so far as it goes. At the same time, the test which the Adjudicator rejected in the first clause – which I infer is the test he believed he was being asked to adopt by Reward – is most certainly not the correct test. It is not necessary for a claimant to show that ‘the work being claimed for payment’ was carried out in the preceding 12-month period, it is only necessary to show that ‘any’ of the construction work to which the claim relates was carried out in that period.
In my view, the Adjudicator’s point was that Reward was wrong to suggest that ‘the work’ (that is, all of the work) had to be performed in the 12 months preceding the Payment Claim.
Reward resisted this characterisation of D9 on the basis that that is not what Reward had argued in its Adjudication Response. But in fairness to the Adjudicator, Reward had done nothing more than assert that Stream Line ‘last carried out construction work to which the claim relates on 25 September 2024’. It was open to the Adjudicator to understand Reward’s argument to be that all of the work had to be carried out within the 12-month period, not just ‘any’ of it.
When the reasons are read as a whole in the light of the limited material with which the Adjudicator was presented on this issue, I think it is unlikely that he was adopting a test akin to that which was rejected in Estate Property. The more likely explanation for what he said at D9 is that he somewhat misapprehended the character of Reward’s objection to jurisdiction. As Payne JA (Gleeson JA and Griffiths AJA agreeing) similarly concluded in Martinus Rail Pty Ltd v Qube RE Services (No 2) Pty Ltd [2025] NSWCA 49 at [101], it may well be the case that the Adjudicator misunderstood the submission made to him, but it does not follow that he fell into jurisdictional error.
Reward submitted that the balance of the Adjudicator’s reasons on this issue only compound the sense that he had adopted an erroneous construction. In particular, Reward pointed to D12 where the Adjudicator found that ‘construction work’ within the meaning of the Act had been carried out on 1 and 9 October 2024. Reward submitted that this showed that the Adjudicator believed the question not to be when work described in the Payment Claim was performed but when any construction work which was loosely ‘related to’ the claim, including rectification works, was performed.
There is force in this aspect of Reward’s argument but I am unable to accept it for two reasons. First, the Adjudicator had made very clear at D9 that the only relevant ‘construction work’ for the purposes of s 13(4) was ‘construction work to which the claim relates’ and, on any view of the material before him, the installation of the banquettes on 1 October met that description. I read his reference to ‘construction work’ in D12 accordingly, namely that he meant ‘construction work to which the claim relates’.
Secondly, although the Adjudicator found that the defect rectification undertaken on 9 October was relevant to the s 13(4) issue and although this aspect of the Adjudicator’s reasoning is somewhat troubling, it was open to him to find that this was construction work described in the Payment Claim because the claim was for the ‘balance’ of all work under the Contract. I do accept that defect rectification is work that ordinarily would not be the subject of a payment claim. However, if the Adjudicator was wrong about this, it was not a jurisdictional error. It would be ‘an erroneous finding about the question posited by s 13(4)(b)’ and would not constitute jurisdictional error: EQ Constructions at [79].
In my view, D12 shows that the Adjudicator accepted Stream Line’s contention that ‘any’ of the construction work to which the Payment Claim related was carried out within 12 months preceding service of the Payment Claim, albeit that he may well have been mistaken about whether the 9 October work was of that character.
If I am wrong about whether the Determinations are affected by error, it is necessary to determine two further issues: (1) whether there is a threshold of materiality for that error to amount to a jurisdictional error; and (2) if so, whether the error was material.
The notion of materiality was discussed by the High Court in LPDT v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs (2024) 280 CLR 321; [2024] HCA 12 (‘LPDT’). At [7], Gageler CJ, Gordon, Edelman, Steward, Gleeson and Jagot JJ (Beech-Jones J agreeing) explained that in most cases, an error must be material to constitute a jurisdictional error because ‘a statute which contains an express or implied condition to be observed in a decision-making process is ordinarily to be interpreted as incorporating such a “threshold of materiality” in the event of non-compliance’.
At [14]-[16], their Honours explained what it meant for an error to cross the threshold of materiality:
“[14] The question in these cases is whether the decision that was in fact made could, not would, ‘realistically’ have been different had there been no error. ‘Realistic’ is used to distinguish the assessment of the possibility of a different outcome from one where the possibility is fanciful or improbable. Though the applicant must satisfy the court that the threshold of materiality is met in order to establish that the error is jurisdictional, meeting that threshold is not demanding or onerous.
[15] What must be shown to demonstrate that an established error meets the threshold of materiality will depend upon the error. In some cases, it will be sufficient to show that there has been an error and that the outcome is consistent with the error having affected the decision. … Importantly, a court called upon to determine whether the threshold has been met must be careful not to assume the function of the decision-maker: the point at which the line between judicial review and merits review is crossed may not always be clear, but the line must be maintained. This case affords an example.
[16] In sum, unless there is identified a basis on which it can be affirmatively concluded that the outcome would inevitably have been the same had the error not been made, once an applicant establishes that there has been an error and demonstrates that there exists a realistic possibility that the outcome of the decision could have been different had that error not been made, the threshold of materiality will have been met (and curial relief will be justified subject to any issue of utility or discretion).” (emphasis in original)
Reward contended that the error alleged of the Adjudicator here was of a kind that is not subject to a materiality threshold in the sense explained above. It submitted that any mistake in the formulation of the legal test under s 13(4)(b) would amount to a jurisdictional error, regardless of whether or not it deprived a party of the possibility of a better outcome.
In support of this submission, Reward invoked what was said by Nettle J in Hossain v Minister for Immigration and Border Protection (2018) 264 CLR 123; [2018] HCA 34 (‘Hossain’) at [40], which was relevantly as follows:
“… I wish to observe that there may be a number of circumstances in which an error is jurisdictional despite not depriving a party of the possibility of a successful outcome. … [One] such circumstance is where a decision maker is required to make a decision by reference to a single specified criterion and, in error, addresses himself or herself to the wrong criterion. In such a case, the decision maker’s error will be a jurisdictional error – a failure to exercise the jurisdiction of deciding the question according to the applicable criterion – regardless of whether one can say that, if properly directed and having determined the application by reference to the correct criterion, the decision maker would have been bound to make the same decision.”
Reward says that the decision required to be made under s 13(4)(b) was of this character, namely ‘a decision by reference to a single specified criterion’.
I do not agree. In TWT Property Group Pty Ltd v Cenric Group Pty Ltd [2020] NSWSC 72 at [104], Stevenson J said:
“Section 13(4)(b) of the Act posits an enquiry as to whether, as a matter of fact, the payment claim relates to work carried out within a particular period. That involves consideration of the payment claim itself. … It also involves consideration of the factual question of when the ‘construction work’ took place. That factual enquiry might be quite complex.”
In my view, s 13(4) is a provision which incorporates a threshold of materiality in the event of its misapplication.
This conclusion reflects the overall scheme of the Act, which is concerned with providing a ‘speedy and effective means of ensuring cash flow to builders from the parties with whom they contract’: Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4 (‘Probuild’) at [43] (Kiefel CJ, Bell, Keane, Nettle and Gordon JJ). It is also consistent with other authorities considering materiality as an aspect of judicial review of decisions of an adjudicator under the Act. In my view, it is unlikely that Parliament intended immaterial mistakes about s 13(4) to render an adjudicator’s determination invalid.
In Acciona Infrastructure Australia Pty Ltd v Chess Engineering Pty Ltd (No 2) [2020] NSWSC 1788, Henry J dealt with a submission by the first defendant that the determination in that case was not affected by jurisdictional error because the error was not material. In light of the object and scheme of the Act, her Honour reasoned at [36]-[38] that the Act incorporated a threshold of materiality in respect of a failure to determine the amount and timing of a progress payment:
“[36] The SoP Act also makes clear that not every error by an Adjudicator will invalidate a decision. It provides that an error arising from an accidental slip or omission may be corrected on an adjudicator’s own initiative or on the application of the claimant or respondent: SoP Act, s 22(5).
[37] The object of the SoP Act is to ensure any person who carries out construction work can recover progress payments: SoP Act, s 3. The regime has been described as providing for a unique form of fast track adjudication procedure to enable progress payments to be made promptly, on account, and without prejudice to disputes under the parties’ contract or other rights at law being effected: Style Timber Floor Pty Ltd v Krivosudsky (2019) 100 NSWLR 133; [2019] NSWCA 171.
[38] In my view, the above matters indicate that the SoP Act should be interpreted as incorporating a threshold of materiality in the event of non-compliance by an adjudicator in undertaking their statutory task of determining the amount and timing of a progress payment such that legal force and effect should not be denied to a decision made in the event of every error in undertaking that task: Hossain at [29].”
“The concept of materiality as a requirement for jurisdictional error in the context of the SoP Act is not concerned with whether the Adjudicator acted bona fide or in good faith in seeking to comply with his statutory function: Goodwin Street Developments Pty Ltd v DSD Builders Pty Ltd (2018) 98 NSWLR 712; [2018] NSWCA 276 at [23], [24], [29]. The concept is concerned with the extent of non-compliance; whether an error results in a decision lacking the characteristics necessary for it to be given force and effect by the SoP Act and whether the error is sufficiently insignificant that it could not have materially affected the decision that was made.”
“[144] However, as I pointed out in John Goss at 716 [42], ‘the concept of materiality is inextricably linked to the measure of natural justice that the Act requires parties to be given in a particular case.’ That meant, I said, that the principles of natural justice ‘could not … require an adjudicator to give the parties an opportunity to put submissions on matters that were not germane to his or her decision’.
[145] I see no reason to depart from those views; and neither party submitted that I should. In particular, I think, my insistence on materiality is consistent with the reference by Hodgson JA in Brodyn to ‘substantial denial … of natural justice.’
[146] In this context, Gleeson CJ said in Re Minister for Immigration and Multicultural Affairs; ex parte Lam (2003) 214 CLR 1 at 13 – 14 [37] that fairness is not abstract but practical. His Honour said that ‘[w]hether one talks in terms of procedural fairness or natural justice, the concern of the law is to avoid practical injustice’. To like effect, Kirby J said in Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259 at 291 that the court should not undertake the task of ‘combing through the words of the decision-maker with a fine appellate tooth-comb [sic], against the prospect that a verbal slip will be found warranting’ the intervention of the court.”
Had it been necessary to consider this issue, I would have found that the error in this case was not material. That is because, on the facts found by the Adjudicator, the installation of the banquettes was completed on 1 October 2024, not 25 September 2024.
Reward submitted that the finding about the completion of the banquette installation could not be relied upon because it was arrived at by way of the wrong test. I cannot accept that submission. The factual question for the Adjudicator was entirely straightforward: was the banquette installation completed on 25 September 2024 as claimed by Reward, or was it completed on 1 October 2024 as claimed by Stream Line? The resolution of that issue did not to any degree depend on the correct statement of the s 13(4) test. To the contrary, it was an anterior factual question which was required to be determined before the s 13(4) test could be applied.
The finding by the Adjudicator that the banquette installation was completed on 1 October 2024 is fatal to Reward’s case because that work was work to which the Payment Claim related. Reward’s case before the Adjudicator depended entirely on the proposition that the work was completed on 25 September.
The threshold here is low: could the decision-maker realistically have reached a different conclusion if he had asked himself the correct question? Having found that installation was completed on 1 October 2024, I do not consider that he could. There was no suggestion that the final installation of the banquettes was anything other than work to which the Payment Claim related. As already mentioned, the banquettes were included in the breakdown attached to the Payment Claim. Given the Adjudicator’s conclusion that this work was undertaken on 1 October, it is unrealistic to suppose that he would have reached any different conclusion than the one he did. In the words of the Court in LPDT at [16], that factual finding is a ‘basis on which it can be affirmatively concluded that the outcome would inevitably have been the same had the error not been made’. In my view, even if the Adjudicator did misapprehend the s 13(4) question, he could not realistically have reached any different conclusion by applying the correct test.
These conclusions make it strictly unnecessary to consider the question of whether it would have been appropriate to grant the relief sought in the summons or whether it would instead have been appropriate to grant relief in the nature of mandamus, as sought in the cross-summons. However, because the matter was fully argued, I will at least indicate the conclusions I would likely have reached on this issue.
The consequence of finding that an adjudicator’s determination is affected by jurisdictional error is that there is ‘no decision at all’ (Hossain at [24], Kiefel CJ, Gageler and Keane JJ) and that the decision-maker’s statutory function remains undischarged: Minister for Immigration and Multicultural Affairs v Bhardwaj (2002) 209 CLR 597; [2002] HCA 11 at [53] (Gaudron and Gummow JJ). Reward did not dispute that where that is the case, the Court has the power to make an order in the nature of mandamus requiring the adjudicator to perform his or her function under the Act according to law: see Tackelly No 8 Pty Ltd v Reward Interiors Pty Ltd (t/as Reward Group) [2025] NSWSC 300 (‘Tackelly No 8’) at [116] (Peden J); Builtcom Construction Pty Ltd v VSD Investments Pty Ltd [2025] NSWSC 250 (‘Builtcom’) at [84] (Peden J) and the authorities cited therein. The dispute, rather, was as to whether such an order should be made in the exercise of the Court’s discretion.
Reward submitted that it was generally inappropriate for an order in the nature of mandamus (or as framed in the cross-summons, an order for ‘remittal’) to be made under the Act. It submitted that such an order would significantly prolong the process of dispute resolution for which the Act provides and that it would therefore not be a ‘just, quick and cheap’ outcome for the parties. Reward submitted that Stream Line has an adequate alternative remedy in the form of court proceedings to resolve the parties’ substantive contract dispute, or otherwise that it could lodge an adjudication application afresh under s 26(2)(b) of the Act.
Reward also submitted that to the extent the question had been considered in the context of the NSW legislation, the Court has tended against the making of such an order. It referred me to Tackelly No 8 in which Peden J declined to order relief in the form of mandamus: at [117]-[123]. In that case, her Honour was of the view that civil litigation was a ‘more satisfactory remedy, particularly in circumstances where the contract is at an end’: at [122]. I was also referred to Builtcom, where her Honour expressed a similar view in obiter: at [84]-[85].
On the other hand, I note that orders in the nature of mandamus have been made in the context of the analogous Victorian and Queensland legislation. In Queensland, orders to remit adjudication applications for determination have been made under s 101(3)(b) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (the Queensland Act). Section 101(3)(b) is relevantly identical to s 32(3)(b) of the Act.
In Procon Developments (Australia) Pty Ltd v Hi-Cal Bricklaying [2025] QSC 67, Bowskill CJ made an order that the application be remitted and that the timeframes under the Queensland Act would follow from the date of remittal: see [43]-[45]. Her Honour envisaged that a different adjudicator would determine the matter.
In Tomkins Commercial & Industrial Builders Pty Ltd v Starline Interiors Pty Ltd [2026] QSC 21, Muir J made an order that the application be remitted to the same adjudicator and that the time limits would run from the date the adjudicator was given notice of the order. In making that order, her Honour specifically addressed an argument that remitter would upset the ‘mandatory and jurisdictional time requirements in sections 85 and 86 of the [Queensland] Act through the use of legal fictions’: see [45]. This was essentially the same as one of the arguments put to me, namely that an order for remittal would prolong the dispute and be inconsistent with the very strict time limits set by the Act.
Muir J rejected this argument. At [46], her Honour said:
“But this submission overlooks that the time limits in the [Queensland] Act are concerned with the adjudication process and not with a court determination if an adjudication decision made within those time constraints is declared invalid. That is where s 101 has some work to do. I am satisfied that s 101 is plainly a remedial and plenary section which ‘should not be unduly read down.’ …”
In my view, there is force in this reasoning.
I also tend to doubt that the ability to sue a head contractor for damages under the contract represents an adequate alternative remedy for what the Act provides. The right to receive an interim progress payment under the Act is not in the nature of a right to sue for damages for breach of contract, nor does it represent the enforcement of the contract: Brodyn Pty Ltd (t/a Time Cost & Quality) v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394 at [82] (Hodgson JA, Mason P and Giles JA agreeing); Probuild at [38]. Although the ability to sue on the contract is undoubtedly an alternative to pursuing rights under the Act, and although it is a matter to be taken into account in determining whether to make an order in the nature of mandamus, it is not in my view something that amounts to an adequate alternative remedy of the kind envisioned by Dixon CJ in Tooth & Co Ltd v Council of the City of Parramatta (1955) 97 CLR 492; [1955] HCA 21 at 498, where his Honour spoke of a statutory appeal as being ‘an equally convenient, beneficial, effective and appropriate remedy’ to prerogative relief: see also Federal Commissioner of Taxation v Futuris Corporation Ltd (2008) 237 CLR 146; [2008] HCA 32 at [91]-[92] (Kirby J). In this regard, I bear in mind that the raison d’ê**tre of the Act is to create an entitlement to interim payment that is ‘determined informally, summarily and quickly, and then summarily enforced without prejudice to the common law rights of both parties’: Probuild at [44]; s 32 of the Act.
I am also not inclined to attach much significance in the context of the present dispute to the fact that the Contract is now at an end. The legislation does not seem to me to draw any particular distinction between progress payments to which a claimant is entitled while the contract is still being performed and those to which they may be entitled on completion of the contract. The definition of ‘progress payment’ in s 4 of the Act expressly includes ‘the final payment for construction work carried out … under a construction contract’. That is not to say that the completion of the Contract is irrelevant. It may well be that in the ordinary run of cases, disputes about completed contracts can and should be pursued through the courts in the usual way. Here, however, Stream Line was brought on late in a project to perform work on short notice and is yet to be paid a significant portion of the Contract sum.
I would also have been unwilling to accept the proposition that it would not be ‘just, quick and cheap’ to remit the matter to the Adjudicator. I would not have accepted that the more ‘just, quick and cheap’ resolution of the dispute between these parties was all-out civil litigation as opposed to a fresh determination of the parties’ rights under the Act by the Adjudicator. In any event, the notion of what is ‘just, quick and cheap’ (s 56 of the Civil Procedure Act) will ordinarily have little bearing on whether a final order in the nature of mandamus should be made in the Court’s discretion.
Reward also submitted that an order in the nature of mandamus may be appropriate in the case of a tribunal or court but was inappropriate in the case of an individual such as the Adjudicator who may or may not be able to comply with the timelines, which would necessarily have to run again. However, I note that the Adjudicator is a party to the proceedings and that the relief sought in the cross-summons is directed to him. He has filed a submitting appearance. In these circumstances I would not have attached any weight to Reward’s submission on this point.
Had it been necessary to decide the point, I would therefore have been inclined to order the Adjudicator to determine the application according to law.
The summons and cross-summons will be dismissed. Reward will be ordered to pay Stream Line’s costs, both of the claim and the cross-claim.
It is appropriate for Reward to pay Stream Line’s costs of the cross-claim, because, had I been of the view that the Adjudicator had made a jurisdictional error and that that error was material, I would have made the order sought in the cross-summons.
The orders of the Court will be as follows:
Summons dismissed.
Cross-summons dismissed.
The plaintiff is to pay the first defendant’s costs as agreed or assessed.
The first cross-defendant is to pay the cross-claimant’s costs as agreed or assessed.
Direct the parties to bring in short minutes of order by 4:00PM on 13 August 2026 dealing with the funds paid into Court pursuant to the order made on 19 March 2026.
**********
[2002] HCA 11
(2004) 61 NSWLR 421
(2004) 61 NSWLR 515
(2008) 237 CLR 146
(2018) 264 CLR 123
(2024) 280 CLR 321
(2002) 209 CLR 597
(2018) 264 CLR 1
(1955) 97 CLR 492
(2019) 100 NSWLR 133
(2018) 98 NSWLR 712
(2003) 214 CLR 1
(1996) 185 CLR 259