[2023] NSWCATAP 305
NCAT Appeal Panel
2023-11-06
Blake AM, Cosmarnan Constructions P, Jpqs P
Original judgment source is linked above.
S Robertson and J Nathan (Appellant) T Lynch SC and A Sivanathan (Respondents)
Solicitors: Effective Legal Solutions (Appellant) HWL Ebsworth Lawyers (Respondents) File Number(s): 2023/00280808 Publication restriction: Nil Decision under appeal Court or tribunal: Civil and Administrative Tribunal Jurisdiction: Consumer and Commercial Division Date of Decision: 26 May 2023 Before: D Goldstein, Senior Member File Number(s): HB 20/26413
Overview
The factual background
The history of the Tribunal proceedings
The 15 February 2023 decision
The 26 May 2023 decision
The 22 June 2023 decision
The history of the appeal
The hearing of the appeal
The scope and nature of internal appeals
The issues for determination in the appeal
Issue 1: whether an extension of time to appeal should be granted
Introduction
The 1 September 2023 Gouros affidavit
The 8 September 2023 Gouros affidavit
The 11 September 2023 Gouros affidavit
The 13 September 2023 Little affidavit
The history of the renewal proceedings
The submissions for Redmyre
The submissions for Mr and Mrs Stockman
Consideration
The length of the delay
The reason for the delay
The extent of any prejudice suffered by Mr and Mrs Stockman
Redmyre's prospects of success
Whether the Tribunal failed to consider Redmyre's adverse inference submission
If the Tribunal failed to consider Redmyre's adverse inference submission, whether that failure constituted an error
If the Tribunal failed to consider Redmyre's adverse inference submission and that failure constituted an error, whether the error was material
Conclusion
Issue 2: whether the Tribunal failed to accord natural justice or constructively failed to exercise jurisdiction by failing to respond to a submission of Redmyre relevant to the question of whether there was a contract between Mr and Mrs Stockman and Redmyre to carry out sub floor work and if so whether the Tribunal made an error of law on a material matter
Issue 3: whether the Tribunal erred in failing to consider whether to draw an adverse inference against Mr and Mrs Stockman in light of their unexplained failure to call Mr Stockman to give evidence relevant to the question of whether there was a contract between Mr and Mrs Stockman and the Redmyre to carry out sub-floor work
Issue 4: the costs of the appeal
Orders
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar
Amendments 16 November 2023 - Paragraph [58(1)] amended from 26 June 2023 to 24 June 2023; 66 days becomes 69days DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 16 November 2023
Redmyre Group Pty Ltd
Stockman
[1990] HCA 30
[2003] HCA 48
(2020) 103 NSWLR 479
(2012) 247 CLR 345
(2003) 77 ALJR 1088
(1990) 64 ALJR 458
(1998) 195 CLR 516
(1959) 101 CLR 298
(2010) 247 FLR 140
(2007) 71 NSWLR 61
(2011) 243 CLR 361
(2003) 77 ALJR 1598
(1996) 186 CLR 389
[2011] HCA 11