It is difficult to imagine a more wholehearted endorsement of a witness's credit. In particular, it will be noted that many of the defects to which Mr Black referred were items which were supposedly 100% completed (e.g. "vanities").
22 Granted his Honour's acceptance of Mr Black's testimony, I can see no escape from the conclusion that the appellant had been negligent.
23 It was urged, against this conclusion, that there was no evidence of reliance by the venturers on the appellant's reports, but I do not see how this submission can be treated seriously in the light of his Honour's specific finding (based on evidence) to the contrary.
24 Again, much was made of the failure by the venturers to call a Mr Nicomede, an employee of one of the venturers. Such failure was said to bring into play the principles outlined by the High Court in Jones v Dunkel (1959) 101 CLR 298 or, as it should more properly be called, the Rule in Armory v Delamirie (1722) 93 ER 664; (1722) 1 Strange 505. The relevant principle is that if a party fails to call a witness whom it might reasonably be expected to call, an inference may be drawn that his evidence, were he called, would not assist that party. It is not easy to see how that principle has anything to do with the present case, and for three reasons. First, it is true that Mr Nicomede had great knowledge of the building trade, but only as a concreter, and it is hard to imagine what he could tell the Court, for example, about vanities or electrical installations. Secondly, when his Honour makes a finding about reliance, the absence of Mr Nicomede is of no moment. Thirdly, (and this is probably doing no more than repeating the previous reason), when a finding of fact has been made in a party's favour by a judge, the fact that an absent witness's evidence, if it were given, would not support that finding, cannot disturb the finding actually made.
25 But there is a further head of negligence raised by the venturers on a statement of contention. This results from the assertion by the appellant of the various degree of completion of the works undertaken. Thus, as I have pointed out, the appellant certified in its Fifth Progress Report (of April 1998) that the contract works were 75% complete, and that in its Tenth Progress Report (of July 1998) that the works were 95% complete. In regard to the last mentioned figure, Mr Black opined that the true figure should have been 75%, not 95%. Although his Honour did not specifically endorse Mr Black's evidence in this regard, in my view his endorsement of Mr Black's evidence is sufficiently effusive to constitute a finding that the work was only 75% complete at the date of the Tenth Progress Report. This conclusion is not negated by the fact that Mr Black did not go through each item in the "Cost Survey", and indicate the proper degree of completion of that item. (Moreover, I do not see how such an effort could have led to a mathematically correct answer, as, presumably, the percentage applicable to each item would differ from that applicable to other items). He was an expert in the field, and as such was capable of estimating correct total percentages.
26 Moreover, it follows that if the Tenth Progress Report was out by 20%, all the other reports from the Fifth Report onwards must also have been out - although not necessarily by the same degree. After all, if one accepts that at the end of the road, at the Tenth Report, the works which had been completed were only 75% of the whole, it is hardly likely that the representation in the Fifth Report that the works were then 75% complete could be accurate.
27 I should therefore uphold the Notice of Contention.
28 As far as damages were concerned, the figure at which his Honour arrived was, before interest was taken into account, $535,005.00. This was computed by aggregating the sum agreed by the experts which was necessary to complete unfinished works ($300,135.00) with the sum necessary for rectifying defective work ($355,690.00), and deducting from that aggregate sum the money still in hand at the Bank ($120,820.00). In this process, the cost of rectifying the results of vandalism were, of course, disregarded. Likewise any discrepancy between values at the date of the tort and values at the date of the order were disregarded.
29 That way of calculating damages seems to me to be unexceptionable. It represents a mode of calculating the amount of money wrongly paid to the Builder as a result of the appellant's negligent representations.
30 Another way of coming to the same result is on the basis of the argument in the Notice of Contention (which, as I have indicated, I would uphold) by calculating the value of 20% (being the difference between the represented and the actual degree of completion) of the contract price of the works.
31 I would dismiss the appeal with costs.
32 BEAZLEY JA: I agree with Meagher JA and the perspicuous remarks of Mason P.