[2013] VCAT 1683
Victorian Civil and Administrative Tribunal
2013-09-27
Original judgment source is linked above.
Mr Christopher Townshend SC and Mr Peter O'Farrell, instructed by Rigby Cooke Lawyers
Mr Townshend SC and Mr O'Farrell called the following expert witnesses:
Mr Paul Connor of counsel, appeared by direct brief
Ms C Somerville of Norton Rose Fullbright appeared for Little Projects Pty Ltd.
A permit has previously been issued on this site for the construction of a 32 level residential tower above a 6 level podium[1]. The permit authorised a mix of residential, commercial and retail uses.
Amendments to that permit are now sought. The amendments proposed in the application retain the mix of uses including a strong retail presence at the Chapel Street and Toorak Road corner. The podium/tower form of the building is also retained albeit in a modified configuration. The location of the tower on the podium is modified, the number of levels within the building is increased, as is the number of dwellings. There is no increase in height. A change in the office and retail floor space and tenancy mix is proposed. Additional car parking is proposed.
Request under S.87A of the Planning and Environment Act 1987 for amendment of a permit.
Clause 34.01-1; A permit is required to use the land for dwellings as the ground floor frontage exceeds 2.0 metres.
Clause 34.01-4; a permit is required to construct a building or construct or carry out works.
Clause 43.01-1; a permit is required for demolition and to construct a building or construct or carry out works.
Clause 43.02-2; a permit is required to construct a building or construct or carry out works. The schedule to the overlay specifies preferred street wall heights and setbacks. A preferred maximum building height is not specified.
The review site is commonly known as the "Fun Factory" site, and is located on the north west corner of Chapel Street and Toorak Road, South Yarra. Almeida Crescent forms the site's northern boundary. The site has an area in excess of 5600 m2, and is a prominent site within the Principal Activity Centre (PAC).
The Capitol (Vic) Pty Ltd v Stonnington CC & Ors [2009] VCAT 1227.
E A H Batman Pty Ltd v Melbourne CC (includes Summary) (Red Dot) [2011] VCAT 1477
Bestway Group Pty Ltd v Monash CC (Red Dot) [2008] VCAT 860
• Deletion of the green roof to the southern building.
• Modifications to the car park design and parking provision.
Use and development of the site for retailing (4,712 m2), offices (8,036m2) and 204 dwellings. The development has a 32 level residential tower over a six level podium, with a lower commercial office tower above retail and restaurant uses, and car parking. There are two basement car parking levels (137 car spaces) with internalised loading and bicycle parking. There are also an additional five car parking levels above ground (359 spaces). All access to car parking and on-site loading facilities would be from Almeida Crescent. Streetscape works and footpath widening are proposed to Toorak Road, Chapel Street and Almeida Crescent. The residential tower is to the northern part of the site with a curvilinear form to a height of 139.4AHD (including plant). The lower rise component to the south would be 103.1AHD.[3]
A primary gateway to the Forrest Hill Precinct, and prominent site within the wider Prahran South Yarra Principal Activity Centre, with new development expected to act as an architectural landmark.
A prominent corner site, which must strengthen the legibility of the Toorak Road and Chapel Street intersection and reflect the significance of these streets as important access routes.
New development which complements the existing streetscapes of Toorak Road and Chapel Street, largely defined by the podium of the Como Centre and the height of the building on the south-west corner of Toorak Road / Chapel Street.
A large site with potential to make a significant contribution to urban consolidation
To reinforce the primary gateway significance of the Fun Factory site to the Forrest Hill Precinct and Prahran South Yarra Principal Activity Centre.
To ensure the upper levels are designed so as to reduce building mass and bulk and produce a sculptural and slender building outcome.
To provide retail uses and active frontages to revitalise the main street.
To avoid an overbearing presence on Toorak Road, Chapel Street and the Forrest Hill Precinct.
To ensure podium levels complement the existing streetscape of the Toorak Road/Chapel Street intersection and provide a consistent building edge (street wall) along the western side of Chapel Street.
....This means that the amendments before us should be assessed on their own merits. We agree with Mr Townshend's submission that the exercise of our discretion must not become a 'beauty contest' between the Elenberg Fraser plans considered in the previous decision by the Tribunal and the proposal now before us (the amended plans). We also agree with Mr Townshend that the focus of planning decision-making generally is about achieving acceptable outcomes rather than best or better outcomes. Accordingly, our consideration of the amended plans is a consideration of the particular merits of those plans.[10]
241 & 257 Toorak Road and 625 Chapel Street, South Yarra
Demolition of the existing building, use and development of the land for shops, restaurants, offices, broadcasting and telecommunications equipment, and dwellings and associated car parking dispensation, altered access to a Category 1 Road and public realm works in accordance with the endorsed plans and subject to the following conditions.
(f) Details of the location and finishes of security doors to the vehicle accessway into the loading/residential area car park. This treatment must be of a high quality and to the satisfaction of the Responsible Authority.
(g) Splay to the service room, convex mirrors or punched openings to the wall between loading areas as required to provide for adequate sightlines within the loading areas.
(h) The proposed staging of development;
(i) the podium wall on the western boundary of the land as a solid concrete wall;
(j) the notation on drawing 2.06 regarding screening to the west amended to state "1800 high perforated or slatted metal screen - 25% permeability - refer TP02.29";
(k) a notation on the western boundary of the southern building, at the northern bedrooms of levels 4-10 of "Void. No Balcony";
(l) a notation on drawing 5.05 (Section 5) of "Aluminium fins (nom. 75x300) fixed to façade at approx 1500mm centres to extent indicated on elevations, for levels 2 to 9 of the southern building";
(m) the notation on drawing 2.12 regarding acoustic screening to state "Acoustic treatment installed in accordance with a report prepared by a suitably qualified acoustic consultant to demonstrate compliance with relevant acoustic standards";
(n) the installation of bollard or low wall treatment (less than 1 metre height) in accordance with the "North West Corner Plan" dated 8 August 2013.
Before the development starts, a schedule of materials and finishes must be submitted for the approval of the Responsible Authority. The schedule must include adequate detail for comparison with the elevations. While acknowledging that the detailed design will further evolve, the schedule of materials and finishes must demonstrate how the development will achieve at least the degree of materiality as represented in the computer images prepared by Bates Smart and contained in the evidence statement of Ian Potter in VCAT Proceeding P281/2013. When approved, the schedule of materials and finishes will be endorsed and will then form part of the permit.
(a) Details of proposed staging;
(b) A requirement that the endorsed plans for that stage must show compliance with the conditions of the permit as appropriate to that stage;
(c) The timing for construction of public works in relation to that stage and/or the completion of the development;
The Waste Management Plan must be approved by the Responsible Authority prior to commencement of construction of that stage and all waste storage and collection must be carried out in accordance with the approved Waste Management Plan.
(a) Show how the 553 car spaces will be designated to the individual tenancies/dwellings.. Spaces are to be allocated as follows:
- (i) Maximum of 1 space per 1 bedroom unit.
- (ii) Not less than 1 space per 2 bedroom unit.
(iii) Not less than 26 spaces for the retail or office uses.
(b) Detail the signing and line marking of parking spaces;
(c) Detail where and how loading and unloading will occur;
(d) Detail any access controls to the parking area, such as boom gates which shall take into account the required queue length required as per section 3.4 of AS 2890.1.
8 Prior to the commencement of any buildings or works, a suitably qualified person must undertake a comprehensive wind tunnel test of the entire development and a Wind Climate Assessment Report must be provided for the written approval of the Responsible Authority. Any modifications required to the development in order to ensure acceptable wind conditions must be submitted to and approved by the Responsible Authority. The design details of any wind mitigation works must receive the endorsement of the owner(s) wind climate experts and preference should be afforded to the use of architectural features and planting.
The owner and or developer of the particular stage must incur all the costs associated with these works and such works must be carried out prior to the commencement of the use allowed by this permit;
(c) The owner and/or developer of the particular stage must incur all costs associated with the construction of all infrastructure including footpaths, traffic management works and the paving materials and construction of the footpath adjacent to the site of the particular stage that must be to the satisfaction of the Responsible Authority;
(d) The payment of a supervision fee by the owner and/or developer of a particular stage where works in relation to that stage are supervised by the Responsible Authority.
(e) Identify the apportionment and responsibility for works and payments for any stage of the development.
(f) The cost of provision of the land and public works be set off against any future public open space requirement.
With the agreement of the Responsible Authority, the Section 173 Agreement may be removed from any title once the requirements within the Agreement for any part of the land) are satisfied.
A memorandum of the Agreement is to be entered on the relevant title and the cost of the preparation and execution of the Agreement and entry of the memorandum on title is to be paid by the owner.
(as shown on the endorsed plans) are set aside as roads so that upon registration of such plan, those portions of the site will vest in the Responsible Authority as roads pursuant to Section 24(2)(b) of the Subdivision Act 1988.
When approved, the plans and schedules shall be endorsed to form part of the permit. The location of the restaurants or the number of seats provided within each tenancy shall not be altered without the written permission of the Responsible Authority.
(a) Full work schedule/construction management plan for each individual stage to ascertain impacts on surrounding properties.
(b) Public/worker access and safety issues;
(c) Hours of construction activity (including at what stage "out of hours works" are proposed and what type of works are to be conducted outside the hours of operation;
(d) The location of hoardings, hoists and workers' amenities;
(e) The location of public precautions, loading zones, site sheds, materials, cranes and crane/hoisting zones, gantries and any other construction related items or equipment to be located in any street;
(f) Details as to how traffic and pedestrian safety and amenity will be controlled within the vicinity of the site and its surrounds;
(g) The provision of a traffic management plan, including detailed plans that show the areas required for and the nature of items to be placed on any street during all stages of construction in accordance with approval by the responsible Building Surveyor, entry and exit points for construction vehicles (including temporary and permanent vehicle crossings), traffic management during construction including road closures/road occupation/footpath closures, work zones/construction zones to accommodate vehicles and deliveries;
(h) Service connections/road and footpath openings and anticipated impact on public land during the connection of different services;
(i) Measures to be used to protect Council infrastructure from damage;
(j) Existing services and environmental management;
(k) A list of all environmental hazards that the activities on-site pose i.e.; contaminated soil, materials and waste, dust, stormwater contamination from run-off and wash-waters sediment from the site on roads, construction noise, hours of operation, vibration, washing of concrete trucks and other vehicles and machinery, spillage from refuelling cranes and other vehicles and machinery etc;
(l) Protection measures that will be undertaken to minimise the risk of the above hazards being realised;
(m) Regular monitoring/inspections of the above protection measures;
(n) Identification as to who will be responsible for managing all of the above issues; and
(o) Measures required for interim or temporary site management; including temporary site access; car parking provision; treatment and/or screening of vacant spaces;
All activities associated with the construction of the buildings and works hereby permitted must be carried out in accordance with the approved Construction Management Plan. The Construction Management Plan may be amended to the satisfaction of the responsible authority.
In accordance with Section 69 of the Planning and Environment Act 1987, an application may be submitted to the Responsible Authority for an extension of the periods referred to in this condition.
[1] The Capitol (Vic) Pty Ltd v Stonnington CC & Ors [2009] VCAT 1227.
[2] Following the gazettal of Planning Scheme amendment VC100, the land has been rezoned from Business 1 to Commercial 1.
[4] [2009] VCAT 1227, paragraph 11.
[5] [2009] VCAT 1227, paragraph 18
[6] [2009] VCAT 1227, paragraph 54.
[7] Mr Hutson considers the internal amenity of the dwellings to be acceptable, and acknowledges that the building would not imposes unreasonable shadowing of the public realm. Mr Czarny considered the proposal to be broadly in line with the parameters identified in the planning scheme for the Forest hill Precinct.
[8] Bestway Group Pty Ltd v Monash CC (Red Dot) [2008] VCAT 860
[9] [2008] VCAT 860, paragraph 19.
[10] E A H Batman Pty Ltd v Melbourne CC (includes Summary) (Red Dot) [2011] VCAT 1477
PT Capitol Development Partnership Pty Ltd
Stonnington CC [2013] VCAT 1683