[2020] VCAT 1339
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2020-11-30
Mr J
Original judgment source is linked above.
IS THE APPLICANT ESTOPPED FROM BRINGING THIS CLAIM?
"exceeded any sum due and payable either at that time or at any time since by the plaintiff to the defendant by the sum of $33,756.57".
the payee cannot justly retain the money paid to him because it would not have come to his hands if it had not been for a false supposition of fact on the part of the payer causing the latter to believe that he was compellable to make the payment or at all events that he ought to make it. [7]
5.2 Except insofar as this subcontract expressly states otherwise, the subcontractor shall also
5.2.1 provide at its own cost and expense all labour, materials, tools, implements and plant and all other things and matters necessary for the proper carrying out and completion of all of its obligations under the subcontract; ...
The respondent would use all appropriate equipment when and where necessary in a timely fashion to complete the work with the minimum expense to the applicant by way of power shutdown, including in particular sourcing and providing a suitable rig.
As per the site meeting held... on the morning of 31/01/17 the below was noted and agreed to as a variation order to the contract:
"The material terms of the Variation were, inter alia, as follows:
(b) the sum of $22,000 would be credited in favour of Platinum on account of an agreed cap of liquidated damages owing to delays from 7 February to 18 February 2017"
The relevant material terms of the Amendment Contract were that:
Whether the respondent has genuinely misunderstood this claim or has knowingly withheld payment, there is no basis for the current submission that no liquidated damages are payable.
LIQUIDATED DAMAGES - SUBCONTRACT WORKS FOR 11-15 MARCH 2017 - $10,000;
As discussed and agreed on site between yourself and I, I will provide assistance to your plumbers, steelers and form workers with minor works such as lifting, cleaning and machine work whilst on site in return for nil penalties on the contract. We are here to work together and assist yourself with catching up on other aspects of the project...
producing photographs (which had not been discovered) which purported to show the state of the works at various dates. In light of the respondent's concession that the completion dates were as alleged by the applicant[15], I do not need to make any findings about the progress of the works as shown in the photographs.
LIQUIDATED DAMAGES - ADDITIONAL DETAILING WORKS - $38,628
WAS THERE AN OVERPAYMENT OF $9833 FOLLOWING THE COUNTY COURT ORDER?
In the event that Straightline is liable to Platinum for any sum at all (which is denied), then Straightline relies on the following facts to establish a set-off in the sum of $9833.88 against that sum:
(a) the sum due and payable by Platinum to Straightline following the County Court Order was $58,849.10. This amount was received by way of garnishee payment.
(b) Platinum made a Further Payment to Straightline in the amount of $56,274.11.
(c) Following the Further Payment Platinum claimed that it had made an overpayment of $30,687 (ex GST) to Straightline.
(d) That calculation was based on subtracting from the Further Payment ($56,274.11) from the retention payment in the amount of $30,690 which Platinum owed Straightline.
(e) that calculation was incorrect. The Further Payment ($56,274.11) less the retention owed ($30,690) equals the sum of $25,584.11, not $30,687.
(f) Straightline paid Platinum the sum of $35,417.99, not $25,584.11. That sum comprises:
(i) $31,430.71 which Straightline paid to Platinum on 15 May 2018; and
(ii) the default judgement dated 29 May 2018 in the amount of $3987.28.
(iii) Straightline therefore made an overpayment of $9833.88 to
[2] The hearing commenced on 19 November 2019, but a successful application for the member presiding to recuse themself was made and the hearing recommenced before me on 20 November 2019.
[3] Solak v Registrar of Titles (No.2) [2010] VSC 146 at [8].
[4] Mr Gulenc witness statement paragraphs 51, 54.
[5] Tutos v State of Victoria [2019] VSC 673 at [26]; Tomlinson v Ramsey Food Processing Pty Limited [2015] HCA 28 at [22].
[6] Paragraphs 170-175; 198-203 of the adjudication decision.
[7] South Australian Cold Stores Ltd v Electricity Trust (SA) [1957] HCA 69; (1957) 98 CLR 65 at 75.
[8] Points of Claim 21 June 2018 and Amended Points of Claim 20 November 2019.
[9] The applicant has used the names Powercor and Citipower interchangeably in their Tribunal documents. I am satisfied that they are the same entity, as the invoice at TB431 has both names in its heading.
[10] At paragraphs 48-57 of his witness statement. I note that Mr Verblun said at paragraph 50 that the shutdowns were on 16, 17 and 23 November 2016. However I take this to be a typographical error as the supporting documents referred to, including the Powercor invoice at TB431, confirm the shutdown on 18 November as well.
[11] Applicant's closing submission paragraph 120.
[12] Outline of Closing Submissions on behalf of the Respondent paragraph 16.
[13] See for example Codelfa Constructions v State Rail Authority of New South Wales [1982] HCA 24; Sumic v Muzaferovic [2013] VCAT 1862; Imerva Corporation Pty Ltd v Kuna [2015] VCAT 2058.
[14] Being $22,000 and $10,000 for the subcontract works, and $666 for 2 weeks for each of break pours 2 and 3
[15] Outline of Closing Submissions on behalf of the Respondent paragraph 3(f)
[16] Outline of Closing Submissions on behalf of the Respondent paragraph 45.
[18] Hawes v Dean [2014] NSWCA 380.
Platinum Construction (Vic) Pty Ltd
Straightline Contractors Pty Ltd
(1977) 180 CLR 266
(1957) 98 CLR 65