[2025] VSC 459
General information, not legal advice.
Supreme Court of Victoria
2025-07-18
Efthim AsJ
Original judgment source is linked above.
BUILDING CONTRACTS - Building and Construction Industry Security of Payment Act 2002 (Vic) ('the Act') - Whether the Adjudication Determination should be set aside - Whether the payment claim meet the requirements of s 14(2) of the Act - Whether the payment claim was served within the time required by s 14 of the Act - Whether the s 18(2) notice was given within the time allowed by the Act - Whether the Adjudication Determination took into account excluded amounts and other matters - Whether there is denial of procedural fairness and apportionment to the plaintiff of the Adjudicator's fee - Adjudicator erred in determining the reference date pursuant to of the Act - The notice was not served within time allowed by the Act.
(i) The payment claim is not a payment claim within the meaning of s 14(2) of the Act;
(ii) The payment claim was not served within the time required by s 14 of the Act;
(iii) The s 18(2) notice was not given within the time allowed by the Act;
(iv) The Adjudication Determination is void under s 23 of the Act, because the Adjudicator contravened s 23(2A)(a) of the Act in that he took into account non-claimable variations and excluded amounts; and
(v) The plaintiff was not afforded procedural fairness by the Adjudicator in apportioning to the plaintiff $24,750 of the Adjudicator's fees to the plaintiff.
Overarching obligation to ensure costs are reasonable and proportionate
A person to whom the overarching obligations apply must use reasonable endeavours to ensure that legal costs and other costs incurred in connection with the civil proceeding are reasonable and proportionate to -
(a) the complexity or importance of the issues in dispute; and
(b) the amount in dispute.
Ground 1 - The payment claim did not meet the requirements of s 14(2) of the Act.
(a) must be in the relevant prescribed form (if any); and
(b) must contain the prescribed information (if any); and
(c) must identify the construction work or related goods and services to which the progress payment relates; and
(d) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount ); and
(e) must state that it is made under this Act.
In respect of the ground that the Payment Claim fails to identify the construction work or related goods and services to which it relates at all or, alternatively, with the required specificity, the Claimant submits that the Payment Claim sufficiently identifies the construction work, variations and services carried out, providing quantities and amounts for each item.
The Claimant points out that, in evaluating the sufficiency of the description of the items claimed in the Payment Claim, regard should be had to the background knowledge and prior exchanges between the parties. That is, it should be understood in the context of previous communications and the parties' ongoing relationship.
It points out that the Payment Claim identifies the work performed and that each of the variations claimed states that the Payment Claim "is firmly grounded on the last Payment Schedule provided by DOMI in relation to Payment Claim 15".
The Act's specific requirements for a valid payment claim are set out in section 14(2). A reading of the Payment Claim states that it is in respect of "Woolworths & Dan Murphy Spotswood". In respect of the Subcontract works, it plainly indicates that it is claiming the balance of the Subcontract value in respect of "T.F. Walls, Walls and Cladding" for Woolworths Spotswood and "Walls and Ceilings" for Dan Murphy Spotswood. It indicates the Subcontract value, the amount previously claimed and the amount claimed to date, identifying the amount claimed in the Payment Claim being the amount calculated by deducting the previous claim from the claim to date. It should be noted that in respect of the Subcontract works, the Claimant asserts they are 100% complete. There is no doubt from a reading of the Payment Claim that the Claimant claims the balance of the Subcontract value in respect of the items claimed.
The Payment Claim also includes claims for 4 variation items asserting that each is 100% complete. All of those variations have been the subject of previous claims, in respect of which the Respondent has previously assessed amounts as payable by it.
The Claimant now claims the balance of what is referred to in the Payment Claim as the "CONTRACT VALUE".
There is a history of claims and payment schedules on the Project prior to the Payment Claim that indicates that the Respondent was quite familiar with the line items claimed in the Payment Claim and would have understood precisely that which was being claimed.
I am left in no doubt that the Respondent, upon reading the Payment Claim, will have been aware that the work claimed in the Payment Claim was the balance of the work to completion of the Subcontract work, together with the balance of the 6 variations partially paid by it following payment claim 15.
The degree of specificity in the Payment Claim in respect of the items claimed was sufficient for the Respondent to understand what was being claimed and to be in a position to identify any grounds upon which it might assert that it was liable to pay less than the amount claimed.
Accordingly, I find that the Payment Claim identifies the construction work or related goods and services to which it relates, with the requisite measure of specificity.[2]
From my review of these authorities, many are of which are appellate authorities, the following principles are clear:
(1) the test of whether a claim is a payment claim for the purpose of the Act is objective;
(2) however, the manner in which compliance is tested is not overly demanding and should not be approached in an unduly technical manner or from an unduly critical point of view;
(3) for the purposes of the identification requirement, it is necessary that the payment claim reasonably identifies the construction work to which it relates such that the basis of the claim is reasonably comprehensible to the recipient party when considered objectively i.e. from the perspective of a reasonable party who is in the position of the recipient;
(4) in evaluating the sufficiency of the identification of the work, it is appropriate to take into account the background knowledge of the parties from their past dealings and prior exchanges of information including correspondence passing between them before and at the time of the payment claim. To that extent, the Court may go beyond the face of the document itself.[4]
It is necessary to decide whether the invoice meets the requirements of s 14. The test is an objective one; that is, it must be clear from the terms of the document that it contains the required information: Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd [2003] NSWSC 266 at [82]. But the terms must be read in context. Payment claims are usually given and received by parties experienced in the building industry who are familiar with the particular construction contract, the history of the project and any issues which may have arisen between them regarding payment. Those matters are part of the context: Multiplex Constructions [2003] NSWSC 1140 at [76].[6]
Base claim to date Variations to date Paid to date Claim ex GST
$537,011 $202,694 $654,330 $85,375
The undemanding standard for compliance with s 14(2)(c) is demonstrated by the following principles:
(a) A payment claim is only required to be bona fide and reasonably purport to identify the particular work in respect of which the claim is made.
(b) A payment claim is only a claim. It is unlike a payment schedule, which is intended to identify the scope of the dispute, and articulate the respondent's case to be determined by the adjudicator.
(c) A payment claim is not required to be as precise or as particularised as a pleading. It need only provide sufficient detail to enable the respondent to identify the subject matter of the claim, not to make its own assessment of the amount payable.
(d) Evidence of what officers did in response to a payment claim is unhelpful and whether they were able to understand the payment claim in fact is not relevant, because 'the focus must remain on the objective circumstances, not the subjective intentions or perceptions of one of the parties'.
(e) The fact that there may be typographical omissions or other errors does not invalidate a payment claim. As was said by the Full Federal Court in Pyneboard Pty Ltd v Trade Practices Commission:
[T]he mere fact that parsing and analysis in the artificial atmosphere of the courtroom can lead to the identification of a number of latent ambiguities will not invalidate what, as a matter of commonsense, is reasonably clear.
(f) To interpret the identification requirement under s 14(2)(c) as imposing a more exacting standard would encourage challenges to the validity of purported payment claims in the courts. The words of s 14(2)(c) do not mandate such an approach. I consider that a more exacting standard would not accord with the legislative intention. As Hodgson JA observed in Nepean Engineering, it cannot be consistent with the scheme of the Act for it to be construed as promoting:
[A] respondent [to] avoid the effect of the Act by not serving a payment schedule, and defending the [s 16] proceedings by raising a question as to identification, which could be as to just one of many items in a claim and could be such as to depend upon a very detailed examination of all the circumstances of the contract.[8]
Hi Sue - we will triple check our end and maybe once we complete the assessment we can meet up and resolve. The numbers you have sent are different from we have previously discussed. We will endeavour to get back to you as soon as possible.
What is a final payment claim is not defined for the purpose of the SOP Act.
Whether a payment claim is a final payment claim is to be determined objectively. The Court should ascertain the meaning that the documentation would convey to a reasonable person having the background knowledge that should reasonably be ascribed to the parties at the time the document was served. The parties' background knowledge is deemed to include experience in the building industry and a familiarity with specific construction project and any issues regarding payment.
The Subcontract provides for two types of payment claims:
(a) periodic progress claims described in cl 12.2; and
(b) final payment claim described in cl 12.4.
A precondition to a final payment claim under cl 12.4 is the expiry of the defects liability period. The timing of the defects liability period is governed by the terms of cl 11.7 and is said to extend for a period of 12 months commencing on the Date of Project Practical Completion.
The defects liability period has yet to expire. Consequently, cl 12.4 has not been engaged and service of a final payment claim under it would be premature.
Nevertheless, I am required to assess the character of the Payment Claim objectively and by reference to the meaning the documentation served would convey to a reasonable person at the time it was served.
I reject the plaintiff's characterisation of the Payment Claim as a final payment claim.[10]
It is important to observe that the Act allows for the making of a final payment claim for construction work carried out under a construction contract. Subject to s 14(7), which deals with amounts that remain unpaid, once a final payment claim is served, no further payment claim can be served under the Act in respect of the construction contract to which the payment claim relates. It is tolerably clear that the purpose of the final payment claim is to give the builder the opportunity to claim, by way of a statutory entitlement, for all the work done under the construction contract. That is not the same thing as a final accounting of all the contractual entitlements going between the parties, a point that is revealed by the fact that a statutory claim, including a final claim, cannot include excluded amounts.[12]
Ground 2 - The payment claim was not served within the time required by s 14 of the Act
(4) A payment claim in respect of a progress payment (other than a payment claim in respect of a progress payment that is a final, single or one-off payment) may be served only within -
(a) the period determined by or in accordance with the terms of the construction contract in respect of the carrying out of the item of construction work or the supply of the item of related goods and services to which the claim relates; or
(b) the period of 3 months after the reference date referred to in section 9(2) that relates to that progress payment - whichever is the later.
(5) A payment claim in respect of a progress payment that is a final, single or one-off payment may be served only within -
(a) the period determined by or in accordance with the terms of the construction contract; or
(b) if no such period applies, within 3 months after the reference date referred to in section 9(2) that relates to that progress payment.
By s 9(2) progress payments are payable on and from the date, according to the terms of the contract, on which a claim for a progress payment may be made or the date by which the amount of the claim is to be calculated under the construction contract. Progress payments are effectively payments by instalments or periodic payments made over the life of the contract for construction work already completed. A final payment claim may be defined as a "final balancing of account between the contracting parties" (Jemzone (2002) 42 ACSR at 49) or "simply the last of the payment claims" (Southern Region Pty Ltd v State of Victoria (No 3) [2001] VSC 436 at [32]). In substance it is a claim for a payment which, when made, will discharge the principal from further obligations to pay money under the construction contract.[14]
It also notes that Claimant submits that the DLP [defects liability period] runs "at best [...] to November 2024" and more likely until the end of January 2025. The Respondent also does not take issue with that submission.
The Respondent correctly notes that the Claimant characterises the Payment Claim as a progress claim rather than a final, single or one-off payment but it asserts that the payment claim was "well out of time".
It submits that, pursuant to section 14(4) of the Act, a payment claim can only be served within the period determined in accordance with the terms of the contract under which the work to which the claim relates, or 3 months after the reference date, whichever is the later.[15]
In the CNS Submissions, CNS characterises the alleged 19 June 2024 payment claim as a progress claim rather than a final, single or one off-payment (CNS Submissions 7.2, p. 7). Domi Construction does not sufficiently understand the CNS Spreadsheet Printout to be able to agree or disagree with that view, but notes that even if it were a progress payment claim, it would have been made well out of time.[16]
The full value of Retention must be maintained during the term of this Agreement having regard to any right to recourse that the Head Contractor may exercise and shall be reduced by 50% within 14 days of Completion with the balance to be released (subject to any rights of the Head Contractor) upon the expiry of the Defects Liability Period and provision of all documents required under the Subcontract, including pursuant to clause 3.5.
Defects Liability Period means a period of 12 months commencing from the last to occur of:
(a) the date the Head Contractor achieves 'Completion' under the Head Contract; and
(b) the date that the Site is handed over to the Client and or/the date the Client takes possession of the Site.
This Contract does not, however, define or describe such a claim as a 'final claim', a 'final payment claim' or in any way refer expressly to a claim for final payment. Instead, under cls 24, 25.1(d), 26.5 and 28 of the Contract, after Practical Completion relevant entitlements may accrue to both the plaintiff and first defendant, including in relation to defective and incomplete work, and materials to which the first defendant has not attended.
. . .
The authorities indicate that the meaning of the payment claim is determined objectively. The Court should ascertain the meaning that the documentation would convey to a reasonable person having the background knowledge that should reasonably be ascribed to the parties at the time the document was served. The parties' background knowledge is deemed to include experience in the building industry and a familiarity with the specific construction project and any issues regarding payment. [18]
(2) In this section, "reference date", in relation to a construction contract, means -
(a) a date determined by or in accordance with the terms of the contract as -
(i) a date on which a claim for a progress payment may be made; or
(ii) a date by reference to which the amount of a progress payment is to be calculated -
in relation to a specific item of construction work carried out or to be carried out or a specific item of related goods and services supplied or to be supplied under the contract; or
(b) subject to paragraphs (c) and (d), if the contract makes no express provision with respect to the matter, the date occurring 20 business days after the previous reference date or (in the case of the first reference date) the date occurring 20 business days after -
(i) construction work was first carried out under the contract; or
(ii) related goods and services were first supplied under the contract; or
(c) in the case of a single or one-off payment, if the contract makes no express provision with respect to the matter, the date immediately following the day that -
(i) construction work was last carried out under the contract; or
(ii) related goods and services were last supplied under the contract; or
(d) in the case of a final payment, if the contract makes no express provision with respect to the matter, the date immediately following -
(i) the expiry of any period provided in the contract for the rectification of defects or omissions in the construction work carried out under the contract or in related goods and services supplied under the contract, unless subparagraph (ii) applies; or
(ii) the issue under the contract of a certificate specifying the final amount payable under the contract a final certificate ; or
(iii) if neither subparagraph (i) nor subparagraph (ii) applies, the day that -
(A) construction work was last carried out under the contract; or
(B) related goods and services were last supplied under the contract.
(a) per sub-section 9(2)(d)(i), the date immediately following the expiry of the defects liability period - i.e. a date in January 2025; or
(b) per sub-section 9(2)(d)(iii), the date after the day that construction work was last carried out under the Subcontract, which the first defendant has deposed in this proceeding as being 10 November 2023.
Unless otherwise agreed in writing between the parties or as agreed and set out in the Scope Documents, and except for the month of December, the Subcontractor may claim payment progressively at the times identified in the Schedule for work carried out in the preceding month by issuing a written claim for payment to the Head Contractor (Progress Claim). Where the Works relate to works performed on Site, a Progress Claim must:
(a) be supported by evidence of the amount due to the Subcontractor and such information as the Head Contractor may reasonably require;
(b) set out the work and the value of work carried out by the Subcontractor in the performance of the Works to the date of the claim;
(c) set out the work and the value of work of any Variations;
(d) set out the amounts (otherwise due from the Head Contractor to the Subcontractor and the Subcontractor to the Head Contractor);
(e) set out the amounts previously paid by the Head Contractor to the Subcontractor in respect of the Works;
(f) set out the amounts previously claimed under this Subcontract;
(g) set out the retention moneys to be deducted pursuant to this Subcontract;
(h) set out the amount which the Subcontractor asserts is payable to the Subcontractor in accordance with this Subcontract;
(i) be accompanied by a statutory declaration prepared by an officer of the Subcontractor approved by the Head Contractor stating that:
(i) all moneys included in previous progress payments in respect of work carried out or materials supplied by subcontractors or suppliers to the Subcontractor or employees of the Subcontractor have been paid by the Subcontractor to those subcontractors, suppliers and employees; and
(ii) any other monies which are payable by the Subcontractor to its employees or subcontractors which have become payable as at the date of the statutory declaration have been paid where those monies relate to time spent on the Works by employees of the Subcontractor; and
(iii) be accompanied by all relevant documentation evidencing (to the satisfaction of the Head Contractor) the Subcontractor's full compliance with any industrial requirements or agreements.
From the preceding analysis of the Act, it follows that: the question whether the document served by Lewence on Southern Han on 4 December 2014 answered the description of a payment claim in s 13(1) turns on whether Lewence was on that date entitled under s 8(1) to a progress payment in relation to work carried out to 27 October 2014; and the question whether Lewence on that date had that entitlement under s 8(1) turns on whether a reference date under the Contract had then come to exist in relation to that work under s 8(2).[21]
I adhere to the view I expressed in Transgrid v Siemens Limited [2004] NSWCA 395, (2004) 61 NSWLR 521 at [35] and John Holland Pty Limited v Road and Traffic Authority of New South Wales [2007] NSWCA 19 at [38], to the effect that "calculated in accordance with the terms of the contract" in s 9(a) of the Building and Construction Industry Security of Payment Act 1999 (the Act) does not engage contract mechanisms determining what is due under the contract, independently of calculations referrable to the work performed.
This means that contractors are not deprived of entitlement to payment under the Act because a condition precedent, such as the obtaining of a superintendent's certificate, has not been satisfied; and it means equally that contractors are not ipso facto entitled to payment because of the operation of a deeming provision such as cl 37(2) of the contract in this case.[24]
(1) The provisions of this Act have effect despite any provision to the contrary in any contract.
(2) A provision of any agreement, whether in writing or not -
(a) under which the operation of this Act is, or is purported to be, excluded, modified or restricted, or that has the effect of excluding, modifying or restricting the operation of this Act; or
(b) that may reasonably be construed as an attempt to deter a person from taking action under this Act -
(8) A claimant cannot serve more than one payment claim in respect of each reference date under the construction contract.
(9) However, subsection (8) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim if the amount has not been paid.
Ground 3 - The s 18(2) notice was not given within the time allowed by the Act.
(2) An adjudication application to which subsection (1)(b) applies cannot be made unless -
(a) the claimant has notified the respondent, within the period of 10 business days immediately following the due date for payment, of the claimant's intention to apply for adjudication of the payment claim; and
(b) the respondent has been given an opportunity to provide a payment schedule to the claimant within 2 business days after receiving the claimant's notice.
Initially, the Respondent did not serve a payment schedule in response to the Payment Claim.
Based on cl 13.2 of the Subcontract and s 15(4)(b) of the Act, the payment schedule was due by 3 July 2024, being 10 business days after the date the Payment Claim was served.
On 5 August 2024, the Claimant served on the Respondent a s 18(2) notice by email, by which it gave notice of its intention to proceed to adjudication and giving the Respondent a second chance to serve a payment schedule within two business days. I note that the s 18(2) notice has 1 August as the date printed on it, but the parties agree that it was served on 5 August 2024.
The Claimant's s 18(2) notice was required to be served within 10 business days following the due date for payment.
The Claimant submits that the due date for payment is 31 July 2024. Section 12 of the Act provides that the due date for payment is the date on which payment becomes due in accordance with the terms of the contract or, if the contract makes no express provision with respect to the matter, within 10 business days after a payment claim is made.
Clause 13.3 of the Subcontract provides that the time for payment is the last business day of the subsequent month in which the payment claim was issued, which in this case is 31 July 2024, which accords with the Claimant's submission.
Therefore, I am satisfied that the due date for payment is 31 July 2024 and that the s 18(2) notice was served within the period allowed under s 18(2)(a).
On 7 August 2024, the Respondent served its Payment Schedule, which was within 2 business days of the s 18(2) notice, within the period permitted under s 18(2)(b).
(1) A progress payment under a construction contract becomes due and payable -
(a) on the date on which the payment becomes due and payable in accordance with the terms of the contract; or
(b) if the contract makes no express provision with respect to the matter, on the date occurring 10 business days after a payment claim is made under Part 3 in relation to the payment.
Subject to the Subcontractor issuing a valid tax invoice for the Certified Amount and the Subcontractor's compliance with clause 3.5(a) and any other precondition set out in this Subcontract, the Head Contractor shall pay the Subcontractor the Certified Amount (Progress Payment) or the Subcontractor shall pay the Head Contractor the Certified Amount (as the case may be) on the last business day of the subsequent month in which the Progress Claim was issued.
The Head Contractor shall, within 10 business days after receiving a Progress Claim, assess the claim and issue a progress certificate stating the moneys due to the Subcontractor or the Head Contractor as the case may be (Certified Amount) and details as to how the Certified Amount was calculated including reasons if the Certified Amount is different to the amount claimed.
Ground 4 - The Adjudication Determination took into account excluded amounts and other matters.
(2A) In determining an adjudication application, the adjudicator must not take into account -
(a) any part of the claimed amount that is an excluded amount; or
(b) any other matter that is prohibited by this Act from being taken into account.
Total claimed amounts outstanding in respect of variations
"Paid to date" per First Defendant (and Adjudicator)
(1) An adjudicator may correct a determination made by him or her if the determination contains -
(a) a clerical mistake; or
(b) an error arising from an accidental slip or omission; or
(c) a material miscalculation of figures or a material mistake in the description of any person, thing or matter referred to in the determination; or
Ground 5 - Denial of procedural fairness and apportionment to the plaintiff of the adjudicator's fee
There is no evidence that the plaintiff's fees are well in excess of the adjudication fees normally charged. I suspect they might be due to the nature of the submissions put to the Adjudicator.
The complaint is that the adjudicator determined that the respondent was liable to pay 100 percent of the adjudication fees without affording the parties [Brambles in particular] the opportunity to address on the issue. This is said to offend the rules of natural justice which it is said require in this context each party to be given the opportunity to present an informed case to the adjudicator to be considered. Brambles submission includes:
"While it may be that an adjudicator has a discretion as to how to award the costs of any determination, there is a presumption inbuilt into sections 28(4)(b) and 29(3) that those fees will be split equally - albeit the parties will remain jointly and severally liable to the adjudicator therefore - unless that adjudicator determines to the contrary. In the present case no submissions were made by any party, nor were they sought by the Adjudicator, to suggest a costs determination on any particular basis, let alone a 100% liability to Brambles.
An adjudication is amenable to review on the basis of a purported denial of natural justice; Musico at [107], Transgrid v Walter Construction Group Ltd [2004] NSWSC 21 at [60] ff. The Adjudicator's approach to this issue meant that Brambles was denied a reasonable (indeed, any) opportunity of presenting a case on this matter; Russell v Duke of Norfolk [1949] 1 All ER 109 at 188 per Tucker LJ. The Adjudicator failed in the circumstances to adopt and follow a reasonable and fair procedure before exercising his statutory discretion, see for example (in a trial sense) Kioa v West [1985] HCA 81; (1985) 159 CLR 550 at 627 per Brennan J; Rose v Bridges (1997) 79 FCR 378 at 386 per Finn J. His Honour's approach offended the notion of a contest or debate between parties before a detached and essentially passive tribunal, refer; Judicial Review of Administrative Action , Aronson & Dyer, LBC (2nd Ed) at 403."
The content of the obligation to afford natural justice to the parties plainly depends upon the circumstances of the particular case and here, the legislative scheme. The parties are aware as soon as an adjudication application is served that the adjudicator has the power to determine the proportions in which the claimant and respondent are to be liable to contribute to the payment of the adjudicator's fees and expenses. The legislation sets up a fast track tightly regulated set of procedures which, as earlier mentioned, have recently been the subject of extensive judicial consideration. The width of the discretion given to the adjudicator and the whole of the relevant legislative scheme, importantly, fixing a time limit within which the adjudication application is to be determined, appears to me to require that the parties, if they wish to put any particular matter to the adjudicator, do so in the course of and as part of their submission of the documents stipulated for by the Act: that is to say the payment claim, the payment schedule, the adjudication application and the adjudication response. In the absence of any submission of any type by either party in relation to the adjudicator's fees and expenses, the adjudicator may proceed to exercise, as here, his/her discretion to determine the issue. In that circumstance the adjudicator, in exercising that discretion, may take into account such matters as to the adjudicator appear relevant to the exercise. Whilst the discretion is not entirely at large, almost every matter which relates to the circumstances in which, and manner in which, the adjudication application has come forward and then been dealt with by the parties, may be taken into account.[31]
[1] The Adjudication Determination at [89]-[90].
[2] The Adjudication Determination at [79]-[88].
[15] The Adjudication Determination at [49]-[51].
[16] The plaintiff's written submissions to the Adjudicator at [24].
[22] The Adjudication Determination [70].
[26] See Endeavour Constructions Pty Ltd v Down Under Piling Australia Pty Ltd [2023] VSC 424.
[28] See Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; [2015] 256 CLR 104.
[29] Cl 3 (5) of the Subcontract provides:
(a) within 2 days of executing this Agreement, provide the Head Contractor with a duly executed Deed of Guarantee and Indemnity in the form provided at Annexure A of this Agreement, to be given by the Subcontractor's director; and
(b) as a condition precedent to Completion, provide the Head Contractor with a duly executed Deed of Collateral Warranty in the form provided at Annexure B of this Agreement.
Domi Construction Pty Ltd
CNS Linings Pty Ltd [2025] VSC 459
(2004) 61 NSWLR 521
(1985) 159 CLR 550
(1997) 79 FCR 378