[2024] VSC 679
General information, not legal advice.
Supreme Court of Victoria
2024-11-07
Steffensen AsJ
Original judgment source is linked above.
CORPORATIONS - Application to set aside statutory demand under s 459H by reason of a genuine dispute or offsetting claim - Where the statutory demand states the debt arises from shop drawings delivered pursuant to a contract and subsequently issued payment claim and tax invoice - Whether the defendant is permitted to argue an alternative legal basis of the debt under the Building and Construction Industry Security of Payment Act 2002 (Vic) - CM Luxury Pty Ltd v Menzies Civil Australia Pty Ltd [2023] WASC 340 considered - Where plaintiff claims parties agreed the payment was in the nature of deposit - Where plaintiff issued a payment schedule accepting the payment claim and debt - Where defendant prepared shop drawings but did no further work and did not purchase materials - Where contract terminated and plaintiff issued further payment schedule reducing amount owed by reference to the asserted deposit - Genuine dispute or offsetting claim established as to whether parties agreed the payment was to be a deposit - No genuine dispute established with respect to the second payment schedule - Genuine offsetting claim for legal costs not established - Service of demand not an abuse of process under s 459J(1)(b) - Substantiated amount calculated and demand varied - (Cth) , , ; (Vic) , .
The amount that was previously certified was for a 5% amount being the amount to cover for both shop drawings & deposit. The shop drawings amount assessed is $8,000.00 +GST, as the only approved amount.
A debt that arose in consideration of shop drawings the creditor completed for the debtor company pursuant to a construction contract dated 2 October 2023, and subsequently issued payment claim and tax invoice INV-0210 in the amount of $35,750.00.[10]
In broad terms, the SOP Act provides a relatively expedient process for the recovery of valid 'progress payments' by persons who carry out work or supply goods and services in the construction industry.[16] It does so by granting contractors a statutory entitlement to recover 'progress payments' for work done or goods or services supplied through an established procedure.[17] The procedure involves the making of a progress claim by the contractor claiming payment ('the claimant'), the provision of a payment schedule by the person receiving the payment claim ('the respondent') which must identify any aspect of the claimed amount which is disputed, the referral of any disputed claim to an adjudicator for determination, the payment of the amount of the progress payment as adjudicated and the recovery of the progress payment in the event of a failure to pay.[18]
(a) a claimant serves a valid payment claim on a respondent; and
(b) the respondent provides a payment schedule to the claimant within the time required by the relevant construction contract, or within 10 business days after the payment claim is served (whichever time expires earlier); and
(c) the payment schedule indicates a scheduled amount that the respondent proposes to pay to the claimant; and
(d) the respondent fails to pay the whole or any part of the scheduled amount to the claimant on or before the due date for the progress payment to which the payment claim relates.
recover the unpaid portion of the scheduled amount from the respondent, as a debt due to the claimant in any court of competent jurisdiction...
A statutory demand will contain a defect where the impugned statutory demand is so vague or ambiguous such that it fails to identify, to a reasonable person in the shoes of a director of the debtor company, the general nature of the debt to a sufficient degree to enable the director to assess whether there is a genuine dispute as to the existence or amount of the debt or an offsetting claim. A statutory demand is required to unambiguously put the debtor company on notice of the matters required by the legislation, including the nature of the debt, a statement that the debt is due and payable, and an explanation as to how the amount claimed is composed or calculated.[26]
Although a debtor company can be presumed to have some familiarity with relevant subject matter of the statutory demand, it is not obliged to speculate upon what it is that the creditor demands...whilst a failure to specify in a demand the precise legal basis of the debt claimed may constitute a defect, it will not necessarily be causative of substantial injustice sufficient to justify its setting aside.[28]
...the importance of an accurate description of the debt in the statutory demand, and the injustice that can result if this does not occur, is demonstrated by the manner in which the parties' respective submissions unfolded. When faced with the statutory demand, the affidavit evidence filed by the plaintiff, and their original submissions, were concerned with establishing that there was a genuine dispute as to whether a contract (and therefore a debt) existed at all. The plaintiff's affidavit evidence and submissions did not refer to a claim upon a quantum meruit (or any of the matters that may be relevant to a quantum meruit claim, including the reasonableness of the claimed amount). This is unsurprising as it is not referred to in the statutory demand and a claim in restitution based on a quantum meruit cannot co-exist with a claim based on an existing contract. In the present case a person in the position of the plaintiff would have no knowledge based on the wording in the statutory demand that the alleged basis of the debt was in fact on a quantum meruit. As outlined by Hetyey AsJ in Re Simmoll, a plaintiff should not be expected to guess what the demand relates to or the source of the obligation to pay. This is what has occurred in this case.[35]
C Is there a genuine dispute or offsetting claim?
(a) a genuine offsetting claim 'means a claim on a cause of action advanced in good faith, for an amount claimed in good faith'. In this context, 'good faith' means arguable on the basis of facts asserted with sufficient particularity to enable the Court to determine that the claim is not fanciful;
(b) there must be some evidence to indicate the nature of the offsetting claim and the way in which it is calculated, including any loss which is said to arise;
(c) however, it is not necessary to particularise the offsetting claim to the last 'dollar and cent'. The evidence need only be sufficient for the Court to make an estimate of the amount of the offsetting claim, which must be capable of being quantified in monetary terms.
C.2 Is there a genuine dispute or offsetting claim re the payment being a deposit?
If [the defendant] had in the ordinary course commenced Court proceedings against [the plaintiff] to recover the alleged indebtedness, I would have instructed [the plaintiff's] lawyers to seek rectification of the agreement with [the plaintiff] to properly record that the initial payment was by way of deposit, with no amount specific to the drawings, in line with the Contract Quote. I believe that [the plaintiff] would have strong prospects that it would make out such a defence. I would have also instructed the lawyers to bring an Australian Consumer Law claim against [the defendant] for misrepresenting the true nature of the shop drawing claim and seeking to maintain that the sum of $35,750 is a sum due and payable as a whole from [the plaintiff] irrespective of whether any materials have been brought and paid for, work performed, or the like.[49]
During the contract negotiations, Mr McNamara raised with [the plaintiff's contract manager] that it would be difficult to get credit with suppliers and that in order to be able to order materials to start the works, he would need a payment in the nature of a security deposit to assist him with ordering materials...
Mr Karama and I discussed how such a payment could be facilitated. Mr Karama informed me that he had discussed with Mr McNamara, recording in the contract a payment for shop drawings of circa $35,000 to enable a deposit to be paid.[52]
Once this invoice is paid I will be able to order up the materials to get us started. We will face challenges as discussed when getting credit for this job given the issues in the background with payments not being made in the past. I intend to use the shop drawing payment to get us started and from there on all going well we can get some work done and put in another claim and keep pushing forward that way.[53]
The Subcontractor must prepare and obtain at its own cost, shop drawings of the Works as required by the Subcontract Documents or as Directed by the Contractor.
Payment terms (as per PART A - SCHEDULE OF ITEMS TO GENERAL CONDITIONS OF SUBCONTRACT)
The Subcontractor and the Contractor agree that the agreement between them comprises the following documents set out in order of precedence: (a) This Subcontract Formal Instrument; (b) Project Requirements (but only on the basis set out in Item 9 of Part A); (c) Standard Conditions of Subcontract (inclusive of Parts A-H); (d) Specifications; (e) Plans; (f) Scope of Works; and (g) Subcontract Program (collectively, the 'Agreement').
(a) item 7 of the March Payment Schedule, which refers to the amount payable pursuant to the December Payment Schedule, being $32,500.00;
(b) the 'Total Approved Amount' and the 'current payment due' (item 8) of the March Payment Schedule, which both provide the figure '$(24,500.00)'. I infer that the brackets are intended to indicate a negative number, such that the plaintiff has assessed that the defendant owes an amount of $24,500. This could only be the case if the plaintiff was indebted to the defendant in respect of the scheduled amount set out in the December Payment Schedule of $32,500;
(c) item 4 of the March Payment Schedule, which refers to the 'total completed and stored to date' as $8,000, being the value of the shop drawings; and
(d) the explanation set out on page 1 of the March Payment Schedule which states:[61]
The amount that was previously certified was for a 5% amount being the amount to cover for both shop drawings & deposit. The shop drawings amount assessed is $8,000.00 +GST, as the only approved amount.
The [plaintiff] may, without limiting any other right which it may have under the Agreement or at law, at any time and from time to time, deduct from moneys otherwise due, or which may become due, to the [defendant], whether such amounts are included in a Payment Schedule or not: ... ; and
Failure by the [plaintiff, as Contractor] to set out in a Payment Schedule or otherwise an amount which the [plaintiff] is entitled to retain, deduct, withhold or set-off from the amount which would otherwise be payable to the [defendant, as Subcontractor] by the [plaintiff] will not prejudice ... the [plaintiff's] ability or power to set out in a subsequent Payment Schedule an amount which the [plaintiff] is entitled to retain, deduct, withhold or set-off ...
Within 10 business days of the time for making Payment Claims listed in Item 8 of Part A, the [plaintiff] will assess the claim and shall issue a payment schedule ('Payment Schedule') which: (a) identifies the Payment Claim to which it relates; [and] (b) states the amount of the payment (if any) that the [plaintiff] proposes to make and/or that the [defendant] is required to make to the [plaintiff] ('scheduled amount')...
From my experience, I consider the cost of the shop drawings would have been no more than $2,200 (inclusive of GST). To avoid any dispute however, and to avoid McNamara alleging it was left out of pocket, I decided to make an allowance of $8,000 (plus GST) for the drawings, which is why that sum appears in the second version of the Subcontractor Payment Schedule[.]
C.3 Is there a genuine offsetting claim for costs?
(a) if the Court is satisfied that there is a genuine dispute between the company and the respondent as to the existence of the debt - a nil amount; or
(b) if the Court is satisfied that there is a genuine dispute between the company and the respondent about the amount of the debt - so much of that amount as the Court is satisfied is not the subject of such a dispute; or
(a) make an order varying the demand so that it relates to an amount of $8,000 plus GST; and
(b) declare the demand to have effect, as so varied, from the date on which the demand was served on the company.
[1] Subcontract formal instrument contract dated 27 September 2023 ('Subcontract'), Exhibit TK-1 to Affidavit of Theodore Abel Kerlidis filed on 2 April 2024, 30-78 ('Kerlidis 1').
[11] Defendant's submissions in reply filed on 18 July 2024, [3] ('Defendant's reply submissions'), referring to Graywinter Properties Pty Ltd v Gas & Fuel Corp Superannuation Fund [1996] FCA 822; (1996) 70 FCR 452 ('Graywinter').
[12] The defendant did not read paragraphs 8, 9 and 26 of Affidavit of Nicholas McNamara filed on 28 May 2024. See Transcript dated 18 July 2024, 2, 69 ('Transcript').
[13] See Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91; Re Douglas Aerospace Pty Ltd [2015] NSWSC 167, [91] (Brereton J) ('Re Douglas'); Re J Build Developments Pty Ltd [2022] VSC 434, [37] (Hetyey AsJ) ('Re J Build Developments'); at first instance, Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWSC 1647, [58] (Parker J) ('Grandview - Parker J'), and on appeal, Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2019] NSWCA 60; (2019) 99 NSWLR 397, 399-400 [4]-[5] (Bell P) ('Grandview - Appeal').
[16] See ss 1, 3 of the Building and Construction Industry Security of Payment Act 2002 (Vic) ('SOP Act').
[24] See, for example, Re J Build Developments (n 13), [47]; Diako Builders Pty Ltd v Compfam Pty Ltd [2021] VCC 784, [25] (Woodward J); MKA Bowen v Carelli Constructions [2019] VSC 436, [42] (Digby J); 133 Walsh Street Pty Ltd v BMF Pty Ltd [2020] VSC 650, [37] (Gardiner AsJ); and Re Life Springs Pty Ltd [2022] VSC 406, [59]-[62] (Gardiner AsJ).
[25] Re Douglas (n 13), [93]; Grandview-Parker J (n 13), [12]-[13]; Re J Group Constructions Pty Ltd [2015] NSWSC 1607; (2015) 303 FLR 139, [101], [103] (Robb J).
[26] Re Three Pillars Lynbrook Pty Ltd [2022] VSC 540, [96] (Matthews AsJ) (citations omitted).
[27] [2021] VSC 693 ('Re Simmoll').
[29] Farid Assaf, Assaf's Winding Up In Insolvency (LexisNexis Australia, 3rd Edition 2021), [8.21] ('Assaf's Winding Up in Insolvency').
[30] [2023] WASC 340 (Seaward J) ('CM Luxury').
[33] Ibid, [52]. The term 'defect' is defined in s 9 of the Corporations Act 2001 (Cth) to include a misdescription of the debt.
[39] Plaintiff's submissions in reply filed on 10 July 2024, [10]-[16].
[40] Clause 113 of the Subcontract provides that the plaintiff will pay the scheduled amount in the payment schedule within 30 days of the end of the month in which the payment claim was made.
[43] [2015] VSCA 330, [47]-[51].
[44] [2021] VSCA 178, [28].
[45] [2020] WASCA 31, [35] (Buss P and Vaughan JA) (citations omitted).
[48] Assaf's Winding Up in Insolvency (n 29), [7.19], citing, inter alia Advance Ship Design Pty Ltd v DJ Ryan t/as Davis Collison Cave (1995) 16 ACSR 129 at 139.
[72] [2018] VSC 563, [44]-[62].
[77] Email from the plaintiff dated 19 December 2023, Exhibit NM-2 to the Affidavit of Nicholas McNamara filed on 17 July 2024, 5.