[2025] WASAT 26
General information, not legal advice.
State Administrative Tribunal (WA)
2025-07-04
Original judgment source is linked above.
(a) in respect of the proceedings in CC 1345 of 2021 and CC 15 of 2023, the builder must pay compensation to the home owners in the total amount of $58,378.81;
(c) in respect of the proceedings in CC 372 of 2023, the Tribunal declined to make any building remedy order; and
(d) each of the related proceedings was otherwise dismissed.
(a) providing for the lodgement of any submissions by the parties to either seek or oppose costs orders; and
(b) that, unless otherwise ordered by the Tribunal, any application or applications for costs shall be determined on the papers pursuant to s 60(2) of the State Administrative Tribunal Act 2004 (WA) (the SAT Act).
(a) the only party seeking any costs to be ordered to be paid to them are the home owners; and
(b) the builder seeks no costs be paid to him and otherwise submits that, contrary to the home owners' position, no costs should be awarded to them and each party should bear their own costs.
(b) the costs of obtaining Transcript of the final hearing on 23, 24 and 25 October 2024 in the amount of $5,113.25; and
(c) the complaint lodgement fees, totalling $358.00, in respect of the original complaints to the Building Commissioner that were ultimately referred to the Tribunal as proceedings CC 1345 of 2021 and CC 372 of 2023.
(a) in Tribunal proceedings, including those under the BSCRA Act, the starting position is that each party ought to bear their own costs;
(b) the home owners' conduct of the related proceedings significantly and unnecessarily delayed and increased the complexity and expenses of the proceedings; and
(c) while the home owners were successful in achieving an award for damages, the builder was successful in reducing the total amount claimed by the home owners by 59.7%.
The Respondent respectfully submits that this is a matter where the Tribunal should declare that both parties have been successful, the Applicants with a modest award and the Respondent by reducing the award for damages resulting in each party paying their own legal costs.
(1) Subject to this section, the Building Commissioner or the State Administrative Tribunal may make such orders for costs as they think fit in relation to proceedings arising from a building service complaint or a HBWC complaint.
(1) The discretionary power is to be exercised judicially; that is not arbitrarily, capriciously, or so as to frustrate the legislative intent;
(2) The power to award costs is to be exercised if it is fair and reasonable in all the circumstances of the case to do so;
(3) The onus is on the party seeking an order in its favour to establish that a favourable order ought to be made;
(4) Every party to proceedings before the Tribunal is taken to be cognisant of the objectives of the Tribunal as expressly provided for in s 9 of the SAT Act. It is therefore necessary for the applicant to establish that the respondent's conduct has impaired the attainment of the Tribunal's objectives to have the proceedings determined fairly and in accordance with the substantial merits, with as little formality and technicality as possible and in a way which minimises the costs to the parties; and
(5) The mere fact that a party ultimately fails on a contention advanced during the course of the hearing does not, in itself, signify that the party has acted inconsistently with the objectives set out in s 9 of the SAT Act.
(5) The rules may deal with the effect of certain offers to settle, and responses, if any, to the offer, on the making of an order for the payment by a party of the costs of another party.
(a) a party to a proceeding (other than a proceeding in the Tribunal's review jurisdiction) gives another party to the proceeding an offer in writing to settle the proceeding; and
(b) the other party does not accept the offer within the time the offer is open; and
(d) in the opinion of the Tribunal, the orders made by the Tribunal in the proceeding are not more favourable to the other party than the offer.
(2) If this rule applies, the Tribunal is to, in determining the costs that may be awarded, take into account that the party did not accept an offer more favourable than the Tribunal's order.
(3) In determining whether its orders are or are not more favourable to a party than an offer, the Tribunal -
(a) must take into account any costs it would have ordered on the date the offer was made; and
(b) must disregard any costs it ordered in respect of any period after the date the offer was received.
...
(a) the stage of the proceeding at which the offer was received;
(b) the time allowed to the offeree to consider the offer;
(c) the extent of the compromise offered;
(d) the offeree's prospects of success, assessed as at the date of the offer;
(e) the clarity with which the terms of the offer were expressed;
(f) whether the offer foreshadowed an application for an indemnity costs in the event of the offeree's rejecting it.
as discussed in Pearce & Anor and Germain [2007] WASAT 291 (S) at [22] [24]; Marvelle Investments Pty Ltd and Argyle Holdings Pty Ltd [2010] WASAT 125 (S) and Hoskins and Daniel Vinci t/as D'Vinci Contracting [2011] WASAT 188.
(a) the related proceedings would be settled by way of a payment by the builder to the home owners in the sum of $50,000 in full satisfaction of the home owners' claims in the related proceedings, payable within 21 days of acceptance of the offer;[7]
(b) the offer would remain open for acceptance for 14 days following the date of the offer;
(c) the offer was made in accordance with s 87 of the SAT Act and rules 40, 41 and 42 of the SAT Rules;
(d) the offer will be produced to the Tribunal in support of an application for costs by the home owners in the event that the builder fails to achieve an outcome which is the same or better than the terms of the offer;
(e) if accepted, the offer will be immediately enforceable and binding on the parties, with the terms of the offer to be re-stated in a formal deed of settlement, making provision for confidentiality, non-disparagement and releases in respect of all claims the subject of the related proceedings; and
(f) within seven days of execution of the deed, the parties will execute a memorandum of consent orders for the related proceedings to be dismissed with no order as to costs.
(a) it was set out in a letter stated to be without prejudice save as to costs;[8]
(b) it specifies an amount of money to be paid, together with when and how the money was required to be paid in the event the offer was accepted;[9] and
(c) it was open for acceptance for the minimum required period of 14 days.[10]
(a) within a week of the orders made by the Tribunal on 20 June 2024, by which the related proceedings were listed for a final hearing commencing on 23 October 2024;
(b) almost four months before the first day of the final hearing; and
(c) well after the parties had lodged their respective Statements of Issues, Facts and Contentions and bundles of documents in the proceedings.
(a) The home owners rely upon the conduct of the builder to support their application for costs; and
(b) The builder relies upon the conduct of the home owners to support his position that there ought to be no order as to costs.
The Applicants sought an award from the Tribunal in the sum of $144,765.00 and were awarded $58,378.81, representing 40.30% of their claim. Whilst this can be seen as a "win" for the Applicants, it should also be considered against the reality that the Applicants have taken five (5) years to prosecute the claim with the expense of solicitors. Therefore, the award in this light can hardly be considered a "win" and is hard to justify. The reality is that the Respondent has been successful in reducing the claim by 59.70%.
(c) the costs of obtaining Transcript of the final hearing on 23, 24 and 25 October 2024 in the amount of $5,113.25; and
(d) the complaint lodgement fees, totalling $358.00, in respect of the original complaints to the Building Commissioner that were ultimately referred to the Tribunal as proceedings CC 1345 of 2021 and CC 372 of 2023.
(a) in respect of legal fees, the claimed costs include only legal fees from 10 July 2024; and
(b) in respect of expert fees, this includes the costs of the experts undertaking necessary inspections and preparing their reports, which took place prior to the 25 June Offer, and attending to give evidence at the final hearing in October 2024.
(a) fees being claimed for the attendance of a senior practitioner for the entirety of the final hearing, in addition to counsel but in circumstances where the lawyer appearing as counsel is a principal of the firm representing the home owners;
(b) fees being claimed in respect of two separate senior legal practitioners undertaking work on what appear to be the same tasks and with a risk of inefficiency or overlap, namely preparation for final hearing, preparing the witness statements of each of the home owners and perusing the transcript and preparing written closing submissions;
(c) fees being claimed for a senior practitioner for 3.4 hours to settle/collate the hearing book for the final hearing, in circumstances where much or all of that work could, on the face of it, be undertaken by a clerk or paralegal; and
(d) the likelihood that at least some portion of the work undertaken was associated with the proceedings in CC372 of 2023, in which the Tribunal declined to make any building remedy order.
(c) $5,113.25 for the costs of obtaining transcript of the final hearing on 23, 24 and 25 October 2024;
The Tribunal notes that the following proceedings (the related proceedings) were heard together:
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
[1] Builder's costs submissions at paragraph 18.
[4] See in particular Hippydayze Pty Ltd and Mener Group Pty Ltd [2019] WASAT 92 (S) (Hippydayze (S)) at [4] to [12] and Gileno and Riviera Homes (WA) Pty Ltd [2018] WASAT 48 (S) (Gileno).
[5] Calderbank v Calderbank (1975) 3 All ER 333.
[6] See for example Cairnes and Ventura Home Group Pty Ltd [2024] WASAT 111 (S) at [15] and McLerie and Koleszko [2014] WASAT 160 (S) at [4].
[7] Noting that the heading of the letter includes the proceeding numbers for all four of the related proceedings.
[9] Paragraph 35(b) of the 25 June Offer and r 40(4).
[10] Paragraph 37(a) of the 25 June Offer and r 41(2).
CITATION : PETSOS and JUDD [2025] WASAT 26 (S)
Cairnes and Ventura Home Group Pty Ltd [2024] WASAT 111 (S)
Deshmukh and Distinctive Building Services Pty Ltd [2024] WASAT 62
Giabeni Pty Limited and the Owners of 30 Coode Street Mount Lawley Strata Plan 11321 [2024] WASAT 105 (S)
Gileno and Riviera Homes (WA) Pty Ltd [2018] WASAT 48 (S)
Hazeldene's Chicken Farm Pty Ltd v Victorian WorkCover Authority [No 2] [2005] VSCA 298
Hippydayze Pty Ltd and Mener Group Pty Ltd [2019] WASAT 92 (S)
McLerie and Koleszko [2014] WASAT 160 (S)
Western Australian Planning Commission v Questdale Holdings Pty Ltd [2016] WASCA 32