[2019] WASAT 92
General information, not legal advice.
State Administrative Tribunal (WA)
2019-11-27
Original judgment source is linked above.
(a) removal of existing aerial service from pole S84195;
(b) installation of new 25LV cable off existing 240LV cable at the base of the pole S84195. T-Joint 25LV cable to 240LV cable; and
(c) installation of new mini pillar LSH(DCSH U8) of proposed driveway. Approximately 3 metres from common boundary of #128.
This weekend, the sagging of the roof became so bad, the gyprock inside the bedroom closest to the wall, has cracked, and is now at risk of falling. Could you please advise if Todd has made arrangements for this repair soon or not, as we will have to start repairs asap. We have started to call around looking for trades people due to the urgency, but needed to ensure we were not interfering with Todd's works, however given this has been an ongoing issue, we feel we are being left no option but to repair ourselves, to ensure no further damage to the house occurs.
(a) an overrun of the date for practical completion of nearly two years; and
(b) the removal of the air conditioning systems and hot water units, after the date that the respondent claimed practical completion had been achieved.
A person who is a builder or an owner must not, in connection with -
(b) negotiations to vary a contract after execution; or
(c) the circumstances in which a contract or variation of contract is entered into,
WILKINS, MR: ... Todd was like, you know, 'If we remove the side of the house now and drop the power line, we can get in there quick and get it ready for the trucks'. So, to come in and, you know, level out, so it's all ready to go bang, bang, bang, before the finance had come through. So I said, 'Okay, no worries. We'll send the' I said that's right, 'Is that' - you know, 'Is that included in the site works?' 'Yes, it is'. 'Cool. No worries'. 'How will I get that money back?' 'Oh, at the end it will come off'. And so I'm, 'Okay. No worries'. So I said to him, I said, 'Well, if you're going to send me an invoice through for what you're doing'. ...
TRIBUNAL: So when you looked through the contract, did you see anything in there that provided for a payback or deduction for the amount that you've paid? Was there any did you check for any provision?
WILKINS, MR: No. ... I was just going off what he said: that it was part of site works.
TRIBUNAL: Do you see that it says: Demolition not included?
TRIBUNAL: Do you recall looking at that which might have indicated that perhaps the 20,000 was not part of the site works because your contract didn't include demolition?
WILKINS, MR: Yes. I'm just trying to think back. I - I wasn't really that thorough back then.
BUCKLEY, MR: I said, 'You've got a garage on the right or a carport on the right-hand side'. I said, 'So, first of all, you can't get access delivery of the property, so that needs to be demolished. You need to create an access track. Second point is you have a power line that sits outside the house that will create obstruction to trucks in terms of height'. ... I said 'Okay. You're happy you can get all that done?' 'I I'm not I'm not confident. I wouldn't know where to start with Western Power or demolition or anything like that.' I said, 'Not a problem.' I said, 'My company is happy to do it and we can do it but we're going to charge you for it', you know, 'And this is what this is roughly sort of what we're looking at'[.]
... and this quote is here in terms of Western Power, item 1, is purely for Western Power's works. To clarify that, works are sent off to Western Power, they come back with a quote. They say, 'Yes. This is what it's going to cost us to remove this, put in underground power, upgrade the power dome so it can service four one (indistinct) house and three existing units.' They sent back the quote and you pay for those works and then they go and do it. It's not on an account whatsoever, so you pay for it and then they go do the works or book it when they're free. Their subcontractors go and do it. It's not technically Western Power and I have no control over that whatsoever. This was explained to Mr Wilkins. I said, 'Listen, I've got to go away to Western Power, I've got to get quotes to get these power lines removed from overhead to underground.' That was all done. At no stage did I say, 'This is part of the building contract' ... If this invoice or works were part of the contract, it would state in the contract that those works are part of that in this particular contract, so it's clearly a separate agreement and it always has been a separate agreement.
(a) The 19 May 2015 tax invoice was clearly a stand-alone document and did not refer to any set off or anticipated deduction or pay back of the $20,342.
(b) The HBWCs which were entered into by the parties on 22 May 2015 clearly do not include the relevant works identified in the 19 May 2015 invoice.
(c) In particular, the addenda to each of the HBWCs which were executed by the applicant on 24 May 2015 specifically under the heading 'site works' identified that demolition was not included; page 407 of Exhibit 1.
(d) None of the HBWCs executed by the parties contained any provision providing for a refund to the applicant in respect of site works paid upfront.
Claim for delay in reaching practical completion
(a) loss of rent in respect of unit A during the period 8 August 2016 to 27 March 2018, being 85 weeks at $300 per week totalling $25,500.
(b) loss of rent in respect to unit B during the period 8 August 2016 to 27 March 2018, being 85 weeks at $300 per week totalling $25,500.
(c) loss of rent in respect to unit C during the period 8 August 2016 to 27 March 2018, being 85 weeks, at $325 per week totalling $27,625.
(d) the applicant also claims interest charged on its mortgage up to 31 January 2018 in the amount of $28,142 plus interest charged on an ANZ credit card held in the name of Mr Wilkins which was used to purchase replacement air conditioning units and on which interest was charged in the amount of $974.
The rule of the common law is, that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.
Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e., according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it. Now, if the special circumstances under which the contract was actually made where communicated by the plaintiffs to the defendants, and thus known to both parties, the damages resulting from the breach of such a contract, which they would reasonably contemplate, would be the amount of injury which would ordinarily follow from a breach of contract under these special circumstances so known and communicated. But, on the other hand, if these special circumstances were wholly unknown to the party breaking the contract, he, at the most, could only be supposed to have had in his contemplation the amount of injury which would arise generally, and in the great multitude of cases not affected by any special circumstances, from such a breach of contract. For such loss would neither have flowed naturally from the breach of this contract in the great multitude of such cases occurring under ordinary circumstances, nor were the special circumstances, which, perhaps, would have made it a reasonable and natural consequence of such breach of contract, communicated to or known by the defendants.
(a) a direct and naturally arising loss which would be within the reasonable contemplation of both parties; and
(b) an indirect or consequential loss which only arises if the party in breach was put on notice prior to or at the time of execution of the contract that this would be a loss suffered if breach occurred.
MARTIN, MR: ... I specifically made topic of that conversation with Todd on the day that I found Mr Wilkins a bit of a hippy and that I had discussed with him the option of doing this development and that from my first appearance from Todd sorry, from Glen being a bit of a hippy, he surprised me with his lack of understanding and his plan to develop as a retirement plan for the future. I made comment of it to Todd, to make him aware that although Glen looks like a bit of a hippy, he's pretty aware and he has got a very clear understanding, and his intention is to use these as part of a retirement plan. And that was a clear conversation we had. There was no intent anyway to sell them. So the fact that Glen had clarified to me that he would be living in the front property and renting the three out, and that was discussed with Todd for the purpose of ...
TRIBUNAL: So your evidence is that you said to Mr Buckley, 'Mr Wilkins intends to live in the existing original property'? - - - Yes. And the three other properties were investment for the purpose of rent? - - - Correct. ... And that is your specific recollection of the conversation? - - - Yes. And did Mr Wilkins at any stage say to you that there was a possibility that he would sell - - - No. - - - the properties? - - - No, and that was not in his plan.
WILKINS, MR: ... So basically, Todd comes round, meets us. He goes, 'What are you going to do?' And I'm just like, 'Hey. This is what I'm going to do. I'm going to build these units and I'm going to rent them out and then live off the difference from the interest only.' And you know, then I won't I won't have to work anymore.
TRIBUNAL: And did you talk about the existing property? - - - Yes. ... I've got a share-house at the front. Yes. And it's basically, you know, I get rent from each one of those rooms and then, you know, I get rent from the units. And the difference in my mortgage will be the income for me. I was quite proud of working it out and all that sort of stuff.
TRIBUNAL: So you told him you were renting out rooms - - - Yes. in the front property? So why did that sort of come up in the conversation? - - - What do you mean?
TRIBUNAL: How did that arise, because - - -? - - I don't know. Like, it just we just I because I was quite proud of what I was doing and I just wanted to tell everyone. ... This is my plan. This is what I'm doing. ... this is how I'm going to do things different from everyone else, you know, instead of working 30 years and like, you know, relying on your super or whatever. So this will be my super. This would be how I retire. This would be a forever thing that I've always got that I can live off that difference. ... So I was quite proud to tell people that that was my plan because in that manner, I've got all this smarter in my head than a lot of other people that don't necessarily think the same way. ... So I just told everyone. I told him multiple times of what I was doing. There's no there has never been any doubt.
We acknowledge and disagree with point 11 of your letter. Yes your client has made Mener Group aware of his intentions to construct these properties as investment properties. However, we dispute the value of weekly rent of each property. Current listings of properties in the area of a similar workmanship and standard are currently being advertised for $251 p/week.
In addition to this, your client has on two separate telephone conversations to both directors of Mener Group, expressed his concern with the falling rental prices of the Gosnells area due to economic times since he commenced the decision to develop his property. Your client quoted numbers of $250 p/week as the average rent that he would be likely to receive due to the market conditions. This contradicts the numbers indicated in point 11 of your letter.
MR BUCKLEY: ... we had a brief conversation of probably 15 minutes, I would say, at a Dome Café in Leederville. I confirm that. That's true and correct. With regards to him stating that, you know, this is a retirement plan and this is his philosophy on what he wants to achieve in regards to this project. I was never told that. ... Subsequently, I caught up with Mr Wilkins. We had a bit of a chat. He told me, 'Hey, I want to build three units'. He never highlighted to me retirement plans and how he thought this is a wonderful thing and outside of the box. Like, I was never told any of this. I was just told, 'I want to build three units. I've got a tight budget of 600,000. Can you do it?' I said, 'Not a problem. Give me the plans, give me what you want to build, roughly, so I can get an idea of what you're thinking'. ... So this whole premise of, you know, it's my retirement plan and this whole wonderful idea, supposedly, is - I don't - is - is not correct. ... The only conversations that were had were I'm potentially going to look to sell these to - to get some money and I've made that statement previously when Mr Wilkins was in the witness box[.]
Subject to this Contract the Builders shall commence the Works within the number of working days specified in Item 9(a) of the Schedule or as soon thereafter as may be reasonably practicable calculated from the latest of the following dates:
(i) on which the Owner shall have complied with the conditions referred to in Clause 2;
(ii) on which the Owner satisfied all requirements under Clause 3(c), if applicable, and Clause 3(d);
(iii) on which the Builder is satisfied that the boundaries of the Site have been adequately delineated;
(iv) on which the Builder is satisfied that both an adequate water supply and an adequate water supply for the carrying out of the Works are available to the Site;
(v) on which the Builder has received approval from all relevant authorities.
(a) Unit A, 79 weeks at $299 per week totalling $23,621.
(b) Unit B, 79 weeks at $299 per week totalling $23,621.
(c) Unit C, 79 weeks at $325 per week totalling $25,675.
Building service complaint damage to boundary fence
I clearly saw that this fence was not in the best condition. There was obviously a passionfruit vine there overhanging ... There was a number of chips or, you know, small holes. It's a Super Six fence. It's probably the original fence that was done back in 1960. So there was always going to be, you know, minor damage to it. And I agree with Mr Wilkins' statement that the back right-hand corner of the fence as you look at the property had a lean on it. Like, there was a lean, you could see that.
TRIBUNAL: Did you do a pre-site inspection of the site? - - - Yes. Yes.
TRIBUNAL: Is that in any of the documents? So did you an assessment of the site. Photos, report? ---There were photos taken, but not a particular report produced or given to Mr Wilkins. I don't - no. Only for myself.
(a) Despite the respondent being aware of the complaint as early as December 2015, it has never offered to perform any remedial works to the boundary fence. Rather, it has always denied responsibility;
(b) The applicant has submitted to the Tribunal its strong preference for a building remedy order to be made in monetary terms;
(c) The relationship between the parties has irretrievably broken down. They have indeed been involved in highly contested litigation with each other in respect of the construction of the three units since December 2016, a period of almost three years; and
(d) The respondent did not submit to the Tribunal at any stage of the proceedings that it wished to be given an opportunity to perform remedial works to the fence.
Building service complaint rectification costs and consequential loss suffered to the existing property
(a) the cost to rectify the damage sustained to the existing property in the amount of $17,550 plus GST which includes in the master bedroom and second bedroom removing and replacing the ceiling and cornices, sealing and painting the walls, door, doorframe and skirting, in the master bedroom replacing the blind and ceiling fan light, and in respect of both bedrooms, the passage, lounge and kitchen, sanding and sealing the jarrah floorboards; page 235 of Exhibit 2; and
(b) compensation due to the loss suffered by the applicant due to the inability to rent the master bedroom in the existing property from 14 September 2016 onwards at a rate of $190 per week; page 67 of Exhibit 2.
(1) The respondent disputes that it carried out the regulated building service in a manner which was not proper and proficient or which was faulty or unsatisfactory. Rather, the respondent contends that the water damage sustained was unrelated to the performance by it of the regulated building service.
(2) If the respondent is unsuccessful in respect of its position in (1) above, the respondent contends that the estimated rectification costs are excessive and not reasonable.
(3) If the respondent is unsuccessful in its contention in (1) above, it also contends that the rental claim is not a recoverable loss because the respondent was not made aware that the master bedroom of the existing property was intended to be rented; and further that the applicant has failed to mitigate its loss by not undertaking the requisite remedial works so as to enable the room to be rented at an earlier time.
It is obvious that the poorly secured tarpaulins have allowed water ingress into the roof space. The water has found its way onto the ceiling below where the tarpaulins are located near the gable end that was sheeted with HardiFlex. This has saturated the installation on the plasterboard ceiling and caused the ceiling to drop and crack.
It is our opinion the damage to the ceiling was caused by water penetration due to the long exposure to the weather after the car port was removed and the inadequate protection by the tarpaulins while the roof was re-roofed.
FIELD, MR: ... So it seemed to me it was pretty obvious that, you know, the water damage was caused from water getting in through - in a lack of sealing or whatever of the - the roof that had been exposed, you know. So that seemed pretty obvious. I know.
... Well, there was nothing else that I could think of that would possibly have caused it. You know. So unless, you know, someone had gone up there and physically caused it.
... All I could judge on - well, I could see the damage, I could see the works and the state of what it was and that's how I assessed it.
TRIBUNAL: And you waited that period of time. Why was that? - - -No money.
What was happening during that 12 months? - - - I've been keeping my head above water through this whole contract. I've had no money to get building insurance. To get, like, the gas hot water systems installed, I had to get credit cards and all that sort of stuff. The banks weren't helping with any more money. I was having problems with tenants not paying as well as lawyer fees as - it just - there was - and I'm trying to do it all on a - - - on a small wage and - - -
TRIBUNAL: So financially you were restricted from doing any substantive works? - - - Financially crippled. Yes. Yes. I was - there was no way. Yes.
An order that a person who carried out a regulated building service pay to an aggrieved person a sum of money specified in the order to compensate the aggrieved person for the failure to carry out the building service in a proper and proficient manner or for faulty or unsatisfactory building work.
HBWC complaints various breaches of the home building works contracts
Costs for supply and installation of new locks and keys
Costs for supply and installation of clothes lines
Costs for supply and installation of termite barrier replacement system
Termite treatment I.D.: Durable sticker to be installed to the inside of the meter box door specifying the method of protection provided against Termite infestation including, a) date of installation, b) the life expectancy of the chemical barrier as listed on the National Registration Authority label, c) the need to maintain and inspect the building on a regular basis, d) any other maintenance requirements.
There are no signs of termite treatment as required (no sticker in the meter box and an inlet for a replenishment irrigation system could not be found).
Costs for removal of single bowls and replacement by double bowls
Costs for supply and installation of mailboxes, bricked and rendered
Proceedings CC 1436, CC 1438 and CC 1439 of 2017
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
CITATION : HIPPYDAYZE PTY LTD and MENER GROUP PTY LTD [2019] WASAT 92 (S)
Costs - Building dispute - Exercise of discretion - Parties to act in accordance with Tribunal's statutory objectives - Respondent failed to act in a way so as to minimise costs to parties
Chew and Director General of the Department of Education and Training [2006] WASAT 248
Gileno and Rivera Homes (WA) Pty Ltd [2018] WASAT 48 (S)
Hippydayze Pty Ltd and Mener Group Pty Ltd [2019] WASAT 92
Marvelle Investments Pty Ltd and Argyle Holdings Pty Ltd [2010] WASAT 125 (S)
Mener Group Pty Ltd and Hippydayze Pty Ltd [2019] WASAT 37
Perth Central Holdings Pty Ltd and Doric Constructions Pty Ltd [No 2] [2008] WASAT 302
Western Australian Planning Commission v Questdale Holdings Pty Ltd [2016] WASCA 32
Subject to this section, the Building Commissioner or the State Administrative Tribunal may make such orders for costs as they think fit in relation to proceedings arising from a building service complaint or a HBWC complaint.
We take the view that in proceedings under the Act, the Tribunal should not generally make an award for costs unless a party has conducted itself in such a way as to unnecessarily prolong the hearing; has acted unreasonably or inappropriately in its conduct of the proceedings, has been capricious; or the proceedings in some other way constitute an abuse of process. The Tribunal might also make an order as to costs where a matter has been brought vexatiously or for improper purposes.
(1) The discretionary power is to be exercised judicially; that is not arbitrarily, capriciously or so as to frustrate the legislative intent; Questdale per Murphy JA (with whom Martin CJ and Corboy J agreed) at [48];
(2) The power to award costs is to be exercised if it is fair and reasonable in all the circumstances of the case to do so; Questdale per Murphy JA (with whom Martin CJ and Corboy J agreed) at [49];
(3) The onus is on the party seeking an order in its favour to establish that a favourable order ought to be made; Questdale per Murphy JA (with whom Martin CJ and Corboy J agreed) at [51];
(4) Every party to proceedings before the Tribunal is taken to be cognisant of the objectives of the Tribunal as expressly provided for in s 9 of the SAT Act. It is therefore necessary for the applicant to establish that the respondent's conduct has impaired the attainment of the Tribunal's objectives to have the proceedings determined fairly and in accordance with the substantial merits, with as little formality and technicality as possible and in a way which minimises the costs to the parties; Questdale per Murphy JA (with whom Martin CJ and Corboy J agreed) at [54]; and
(5) The mere fact that a party ultimately fails on a contention advanced during the course of the hearing does not, in itself, signify that the party has acted inconsistently with the objectives set out in s 9 of the SAT Act; Questdale per Murphy JA (with whom Martin CJ and Corboy J agreed) at [55].
(a) The parties have been involved in multiple proceedings which have taken a number of years to reach final determination;
(b) The respondent took no steps to reduce the costs incurred or the length of the proceedings, for example, by failing to concede complaints where there was no proper defence available. Rather, the respondent put the applicant to proof in respect of every complaint;
(c) The applicant brought a multitude of complaints against the respondent and was largely successful;
(d) The respondent's sole director was dishonest in his evidence before the Tribunal and attempted to mislead the Tribunal; and
(e) If the respondent had acted reasonably and in good faith, it would not have been necessary to incur the large quantum of costs incurred in the proceedings.
(a) The respondent met all of its obligations in the proceedings and did not delay by filing late or not complying with the Tribunal's orders;
(b) The respondent attempted to resolve the proceedings with the applicant and it was the applicant's choice to proceed by refusing the respondent's offers to resolve the dispute on a 'walk away' basis;
(c) Some of the delay in the related proceedings was due to the conduct of the applicant in failing to file documents in accordance with the Tribunal's orders and a failure to attend a mediation which resulted in the parties incurring increased costs; and
(d) The respondent was entitled to defend itself and refute the allegations made by the applicant in the proceedings.
(a) There was legal complexity in a number of the complaints raised by the applicant which required it to seek legal advice and representation;
(b) The applicant was almost entirely successful as against the respondent and many of the complaints were clearly meritorious and ought to have been conceded by the respondent but were not;
(c) The respondent did not act in a manner which was cognisant of the s 9 SAT Act objectives given that it did not conduct itself in a way which minimised the costs to the parties. By strongly refuting every complaint item, in a number of instances without a proper foundation and in the absence of corroborating lay or expert evidence, the respondent forced the applicant to incur both legal and expert costs in pursuing those complaints;
(d) Any offers to settle made by the respondent were not reasonable given the ultimate orders made by the Tribunal in the applicant's favour; and
(e) The respondent's director gave evidence to the Tribunal which was found to lack credibility; Hippydayze at [107].
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
Briginshaw v Briginshaw [1938] HCA 34; (1938) 60 CLR 336
Burns v MAN Automotive (Aust) Pty Ltd [1986] HCA 81; (1986) 161 CLR 653
Butcher v Lachlan Elder Realty Pty Ltd [2004] HCA 60; (2004) 218 CLR 592
Clark v Macourt (2013) 253 CLR 1; [2013] HCA 56
Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64
Gemmill Homes Pty Ltd and Sanders [2018] WASC 179
Mener Group Pty Ltd and Hippydayze Pty Ltd [2019] WASAT 37
Mener Group Pty Ltd and Hippydayze Pty Ltd [2019] WASAT 58
Mener Group Pty Ltd and Hippydayze Pty Ltd [2019] WASAT 91
Trengove and Celebration Nominees Pty Ltd [2012] WASAT 65
Vouzas v Bleake House Ptd Ltd [2013] VSC 534
(1938) 60 CLR 336
(1986) 161 CLR 653
(2004) 218 CLR 592
(1991) 174 CLR 64
(2013) 253 CLR 1
(2013) 249 CLR 435