[2016] VCAT 2100
Victorian Civil and Administrative Tribunal
2016-12-12
Original judgment source is linked above.
He supported the account given by the next-door neighbour, Mrs Barlow concerning Mr Mann's behaviour towards her at the time of the tree lopping incident. He said that, during a discussion with the Owners about a dumbwaiter that they were asked to install in the cellar, the Owners said: "Money's no issue, just get it done". He was not shaken in cross-examination and I see no reason to doubt what he said.
The figure of $16,000 for appliances was a mistake by Mr Paterson. He had calculated and intended to insert a figure of $8,000. In cross-examination, Mrs Mann acknowledged that it was a mistake.
"The breaches and/or other matters referred to above constitute a repudiation of the building contract on the part of Paterson Constructions, which repudiation is hereby accepted by our clients thereby bringing the building contract to an end at common-law.
This determination of the building contract also operates to revoke the license granted by our clients to Paterson Constructions pursuant to Clause 7.2.1 of the building contract."
"37. Variation of plans or specifications-by builder
(1) A builder who wishes to vary the plans or specifications set out in a major domestic building contract must give the building owner a notice that-
(a) describes the variation the builder wishes to make; and
(b) states why the builder wishes to make the variation; and
(c) states what effect the variation will have on the work as a whole being carried out under the contract and whether a variation to any permit will be required; and
(d) if the variation will result in any delays, states the builder's reasonable estimate as to how long those delays will be; and
(e) states the cost of the variation and the effect it will have on the contract price.
(2) A builder must not give effect to any variation unless-
(a) the building owner gives the builder a signed consent to the variation attached to a copy of the notice required by subsection (1); or
................................................................................................
(3) A builder is not entitled to recover any money in respect of a variation unless-
(ii) can establish that the variation is made necessary by circumstances that could not have been reasonably foreseen by the builder at the time the bontract was entered into; or
(i) that there are exceptional circumstances or that the builder would suffer a significant or exceptional hardship by the operation of paragraph (a); and
(ii) that it would not be unfair to the building owner for the builder to recover the money.
(4) If subsection (3) applies, the builder is entitled to recover the cost of carrying out the variation plus a reasonable profit.
(5) This section does not apply to contractual terms dealing with prime cost items or provisional sums."
"38. Variation of plans or specifications-by building owner
(1) A building owner who wishes to vary the plans or specifications set out in a major domestic building contract must give the builder a notice outlining the variation the building owner wishes to make.
(2) If the builder reasonably believes the variation will not require a variation to any permit and will not cause any delay and will not add more than 2% to the original contract price stated in the contract, the builder may carry out the variation.
(3) In any other case, the builder must give the building owner either-
(i) states what effect the variation will have on the work as a whole being carried out under the contract and whether a variation to any permit will be required; and
(ii) if the variation will result in any delays, states the builder's reasonable estimate as to how long those delays will be; and
(iii) states the cost of the variation and the effect it will have on the contract price; or
(b) a notice that states that the builder refuses, or is unable, to carry out the variation and that states the reason for the refusal or inability.
(4) The builder must comply with subsection (3) within a reasonable time of receiving a notice under subsection (1).
(5) A builder must not give effect to any variation asked for by a building owner unless-
(a) the building owner gives the builder a signed request for the variation attached to a copy of the notice required by subsection (3)(a); or
(6) A builder is not entitled to recover any money in respect of a variation asked for by a building owner unless-
(i) that there are exceptional circumstances or that the builder would suffer a significant or exceptional hardship by the operation of paragraph (a); and
(ii) that it would not be unfair to the building owner for the builder to recover the money.
(7) If subsection (6) applies, the builder is entitled to recover the cost of carrying out the variation plus a reasonable profit.
............................................................."
Variation 1.2 - extension of rear deck - variation of permit
Variation 1.3 - relocate brick wall on the meals laundry area
Variation 1.4 - Merbau deck for extended alfresco area (10.2 m²)
Variation 1.5 - Colorbond roof to extended decking area
Variation 1.8 - relocate laundry trough after rough-in completed
Variation 1.9 - tiled kick board to bathroom vanities
Variation 1.10 - Two-pack finish on front doors
Variation 1.11 - Spotted gum instead of Rose gum
Variation 1.13 - skylights to laundry and stairwell
Variation 1.14 - change of timber for stairwell
Variation 1.15 - solid doors instead of hollow-core doors
Variation 1.19 - brick instead of picket front fence
Variation 1.20 - privacy screens for second-floor windows
Variation 1.21 - increased size of playroom window, wireless connections, water tapping the and energy rating permit
Variation 2.4 - entry ceiling / highlight above door / door painting
Variation 2.6 - changes to en suite/powder room
Variation 2.9 - additional water point for fridge, added bulkhead, relocated ducted vacuum point
Variation 2.11 - and window and additional wall space for TV
Variation 2.14 - sliding door to robe and solid door to bedroom two
Variation 2.18 - selected plumbing in excess of allowance
Variation 2.22 - acoustic insulation garage wall
Variation 2.23 - excavation and concreting for spa
Variation 2.27 - acoustic insulation in ceiling
He said that he kept notes of some of these extra requests.
Provisional sum item 3 - the deletion of the "Vergola"
The claim with respect to the Provisional Sum items
"As you are well aware the project has been delayed due to the various design changes and variations that have been incorporated into the original design."
Can you please send me an email flanking the likelihood proposed amendments A - E being approved by Council.
The only item I am interested in is the Vergola roof as it is included in my contract, I will not be upset if I build what is already approved.
Is it possible to give me an indication when Council may make a decision on these amendments as my handover and client settlement of their home is approaching?"
The heating unit is outside the building adjacent to the side path and below the level of the paving. Mr Anderson said that this would restrict access to the unit for servicing. Fears were also expressed during the hearing that perhaps water might pond in the area and effect the unit. Mr Kier agreed that the installation was inappropriate although he pointed out that the Builder had installed an agricultural drain under the unit to enable any condensate to drain away.
It is common ground that the paving around the unit was laid by the Owners' landscaper and not by the Builder and so I am not satisfied that the height of the surrounding paving, which has caused the difficulty, is the Builder's responsibility. In any case, I noted at the on-site inspection that no water was ponding in the area despite their having been quite heavy rain shortly beforehand.
The outdoor refrigerated condensing unit is less than 200 mm away from the building wall. Mr Anderson said that the manufacturer recommends a minimum clearance of 300 mm unless air deflectors are installed. He costed the installation of air deflectors at $200.
Mr Kier said that the deflectors are only applicable for the discharge side of the condensing unit and so are not relevant. He said that he checked with the manufacturer and was informed that the clearance of the rear of the units will have no appreciable impact on the performance of the unit as long as all other clearances are achieved. He said that the unit was in a reasonably open area and that he did not consider the relocation of the unit was necessary.
The Owners bear the onus of proof and since there is a difference of opinion as to whether this is necessary and since the unit does appear to be in an open position I am not satisfied that a defect is established.
Mr Anderson said that the return air grille is undersized, being only 0.2664 m² whereas the manufacturer recommends a minimum size 0.36 m² for a filtered return air grille for heating and a minimum return filter area of 0.48 m² for an add-on cooling system. He said the cost of replacing the existing grille with a larger grille was $380.
Mr Keir said that the required sizing for that particular unit was nominated to be 0.302 m². He said that the grille was undersized but only by a small amount. He said that he did not consider this to be a significant issue and it would not have a measurable impact on the performance of the system.
Since it is acknowledged that the grille is undersized I find a defect and will allow the amount $380 Mr Anderson has assessed `
The circular duct has been brought through a square hole, leaving gaps. Mr Anderson said it will cost $50 to install a starting collar and seal it to the floor. Mr Kier agreed that the connection should be sealed and agreed on the costing. The assessed amount of $50 will be allowed.
Some nuts around the filter grille were found to be loose. Mr Kier pointed out that possession of the unit had been given some time beforehand and it is not established who loosened the nuts. I am not satisfied on this item.
(f) Unit one ground floor dampers Not established
Mr Anderson found that at the time of his inspection a number of ground floor outlet dampers were partly closed, and he suggested that perhaps the system was never balanced properly. Mr Kier said that when he inspected the unit the motorised damper servicing the upper floor was not operational and the airflows will not be able to be achieved to the upper floor until that is rectified. He said that he was informed that the Builder had balanced the system and he suggested that perhaps the air balance had since been carried out in the unit by the Owners or the tenant. Mr Anderson assessed eight hours at a cost of $90 per hour as the cost of rebalancing the system.
Unlike Unit two, this unit was handed over and there is no evidence that the system was out of balance at the time of handover. I am not satisfied on this item.
(g) Unit one - Builders debris supply air boots $495.00
Mr Anderson said that there was Builder's debris seen in a number of supply air boots. He allowed for six hours to clean all ductwork. Mr Kier agreed that there was a very minor debris and allowed five hours. Since one expert is as likely to be as right as the other I will allow 5 ½ hours at $90 per hour.
(h) Unit one - ductwork not adequately suspended $150.00
Mr Anderson said that, although he had not inspected the subfloor, he suspected that the ductwork was not supported because he observed that it had not been in Unit two. Mr Kier agreed with a figure of $150 to install approved flexible duct hangers.
(i) Unit two - location of heating unit $1,490.00
The heating unit is located outside the building and beneath the verandah deck. The deck is constructed of spaced decking boards. The cooling system fan coil unit is outside on the east side of the living/meals area.
Mr Anderson said that the requirement of AS/NZ S5601 Clause 6.3.14 for the installation of a gas heater in an underfloor location requires a minimum clearance of 1.2 m between the lowest part of the floor structure and the ground level. I asked Mr Anderson whether an open external deck could be regarded as an underfloor location in this context and he said that his enquiries of an officer of Energy Safe Victoria suggested that it was. He said that fixed artificial lighting was also to be provided to the appliance. He added that the gas heater does not have a condensate drain fitted but discharges directly into the subfloor space. He costed $600 for materials and six days labour to relocate the unit outside the decking area.
Mr Kier said that it is unclear whether this space is considered to be under a floor. He said that the service manager of the supplier advised that the recommendation was that there be 200 mm clearance over the unit for service access and that this could be achieved by unscrewing the timber decking required. He pointed out that the unit is in an open space in an open area ventilated on three sides with excellent natural light. He said that he was advised by an inspector of Energy Safe Victoria that the location of the unit complies with regulations.
Mr Kier said that, in order to achieve the required gap of 1.2 m below the decking the unit could be lowered by 100 millimetres. Mr Anderson said that it was 2.8 m from the entrance to the subfloor area for servicing whereas it should be no more than 2 m. However the decking is open on all sides and it is a matter of where the access door is located when it is ultimately enclosed.
Mr Pitney suggested that it would take no more than a day to lower the unit by the required amount and Mr O'Brien, whose company installed the unit, agreed with that. Mr Pitney said that it should cost no more than $405 to install a light next to the unit which is also required. After Mr Paterson pointed out that the power point was already there, it was then stated that it would cost $25 to provide the light. A further $25 will be required to provide tubing for the condensate plus an hour and a half's work to install it. If a condensate pump were needed that would cost $200 and an hour's labour for an electrician to install it, but this would only be necessary if the water could not be run away by the natural fall of the land. It is not established that a condensate pump is necessary. It was acknowledged that there is a substantial fall in ground level to the rear fence and a longer tube can be fitted.
Weighing all this evidence up, I will allowed two days labour at $90 per hour and $50 for materials, making $1,490.00.
This is similar to the claim with respect to Unit one and I am not satisfied that a defect is established.
(l) Unit two - Cooling coil etc. not accessible $320.00
Mr Anderson said that the condensate drain that was fitted and the refrigerant pipework installation are incomplete. The condensate drain needs to be trapped and available for inspection. Mr Kier agreed. Mr Anderson had included this cost with the relocation of the unit but since I have not allowed that I need a figure for the necessary work. It appears at the very least that it will be necessary to run another drain tube from the cooling coil unit to a point of discharge.
I am satisfied on Mr Anderson's evidence that there is work to be done and the area appears to be somewhat difficult to access. . I will allow three hours at $90 per hour and $50 for materials, which is $320.00.
(m) Unit two refrigeration piping not adequately supported $410.00
Mr Anderson said that the refrigeration piping between the outdoor condensing unit and the cooling coil was not adequately supported in the subfloor space and that insulation and redundant pipework was left lying under the building. He assessed five hours of labour and $50 in materials to deal with this item.
Mr Kier said that he had a quotation from Mr O'Brien to carry out the necessary work in three hours with $50 in materials. I will allow four hours at $90 per hour and $50 for materials, which is $410.00.
(n) Unit two - connection to return air plenum $230.00
Mr Anderson said that the return air duct is not connected to the return air plenum beneath the staircase and the duct is lying on the ground drawing air from the subfloor space. He costed rectification at two hours labour plus $50 for materials.
Mr Kier agreed with the costing although he pointed out that the duct had been removed in order to commission the trap door hatch to the cellar and that the Contract was terminated before it could be replaced.
Since I am assessing the value of the work and Mr Pitney's valuation assumes that the work is complete I should allow the cost of completing this part of it, which will be $230.00.
(o) Unit two - return air grille irregular and undersized $390.00
Mr Anderson said that the return air grille located below the staircase is an irregular shape and a return air filter is required and has not been installed. He assessed a figure of $120 for materials and three hours labour to rectify the problem.
Mr Kier said that the return air grille was located in the position required by the Owners to enable changes in the laundry layout. It seems clear that there is nowhere else to put it. Mr Kier also said that he disputed that the grille was undersized. Mr Anderson said that it could become undersized when the filter was fitted but that if the filter were fitted inside, then the size would be sufficient.
It is acknowledged that this is incomplete work and the cost of completion seems to be agreed at three hours labour $90 an hour plus $120 for materials, which makes $390.00.
(p) Unit two ductwork below floor inadequately supported $510.00
Mr Anderson said that most of the ductwork below the floor was lying on the ground and that additional supports are required. He said that flexible duct supports have been installed that do not comply with the requirements of the relevant Australian Standards.
Mr Kier said that substantial ductwork was removed to enable the installation of the trapdoor and the Contract was terminated before the work could be completed and the ductwork rehung.
Mr Anderson assessed the cost of rectification at 16 hours labour and $150 worth of material. Mr Kier agreed with the materials but said that it would be only four hours labour. Mr Anderson defended his much higher figure by saying that there was not a great deal of space beneath the floor. Mr Kier said that he had a quotation to do the work for four hours labour from Mr O'Brien. Although Mr O'Brien is not a disinterested witness I find it hard to see how it take any more than half a day to do this job. I will allowed four hours and $150 for materials, which makes $510.00.
Mr Anderson said that a number of the ground floor dampers were partially closed. This is a similar situation to what was found in Unit one although in this case it is acknowledged that the Contract was terminated before the system was balanced. Nevertheless, since I am allowing a valuation of all the work on the basis that it was complete and not defective, I should allow the cost of balancing the system.
The cost of balancing the system was assessed by Mr Lorich at $510, by Mr Campbell at $400 and by Mr Pitney at $210. Mr Lorich allowed six hours, Mr Pitney allowed two hours and Mr Campbell said that he obtained the price from Rawlinson's guide. Mr Anderson has assessed it at eight hours labour, which would be $720. Mr Kier allowed only two hours labour.
Precisely what is involved in balancing the system was not clearly explained to me. Obviously it is something that takes a number of hours, the question is, how many? Both the mechanical experts are equally qualified and one is as likely to be right as the other. I will allow five hours at $90 an hour, which is $450, which falls within the scope of the figures assessed by the general experts.
(r) Unit two Builders - debris in supply air boots Not established
Mr Anderson said that builder's debris could be found in many of the supply air boots. However, he inspected the property on 12 March 2016 and by that time the Owners had had their own tradesmen working in Unit two. No such debris was referred to in Mr Lorich's earlier report. The debris Mr Anderson saw at the time of his inspection could have been the result of the Owners' own tradesmen and in any case, it had been removed by the time Mr Kier inspected Unit two on 14 July 2016. I am not satisfied as to this item.
(s) Unit two - additional outlet in play area Not established
Mr Anderson said that, based on his calculations, the air quantity required to condition the play area is more than double that required for either of the upper floor bedrooms. He said that this indicated that there should be either a larger duct and diffuser to service the play area or there should be two outlets, whereas only one has been installed.
Mr Kier said that the system needs to be balanced to suit the loads. He said that the air outlets are in good locations but the Owners have put furniture over the outlet in the play area restricting airflow. He also pointed out that air returning from the two bedrooms will be passing through the play area to reach the return air grille on the ground floor, reducing the loads in the play area. He said that in his opinion, additional air outlets are not required.
There is a difference of opinion between the experts. I would have thought that an assessment of the adequacy of the system could not be made until it has been balanced and that has not been done. I am not satisfied that it has been established that a further outlet is required.
(t) Unit two - the system has three zones instead of four $1,070.00
This was said a number of times during the hearing to be a contractual issue. I was told by Mr Kier that there was a variation to change the system from a four zone system to a three zone system. However, that was not one of the variations referred to in Mr Paterson's witness statement and I can find no other evidence establishing that change. According to the quotation which doubled as the specification, Unit one was to have two zones and Unit two was to have four zones.
There was some discussion between the experts as to whether, when all of the registers are open, that constitutes a zone. If it does, then there are three zones installed in Unit two. Mr Anderson said that it was a "moot point" whether all of the registers being open constituted a zone. Mr Kier said that what was installed was what was required by the Contract. By that I assume he meant that it was a three zone system. Mr Anderson said that the addition of a fourth zone control to shut off the master bedroom will assist in resolving the over-cooling of that room. Mr Kier said that installation of a control could be considered but that it would be a variation.
On this state of the evidence I think that the Contract required an additional zone in Unit two. However, the claim is not under the Contract but is for the value of the work. Mr Pitney has allowed in his valuation for the supply and installation of the systems that were provided but made no mention of zones. I find on the evidence of Mr Anderson and Mr Kier that for the system to operate satisfactorily it should have the additional zone. I therefore treat this as a defect and shall allow the cost of the installation of the additional motorized damper, which is $350 plus 8 hours labour at $90 per hour, making a total of $1,070.00.
This item was acknowledged. Two hours labour and $20 in materials was assessed as the cost of rectification. That amounts to $200.00.
(w) Insufficiency of the system Not established
Mr Anderson said that it would not be practical to install additional outlets to get cooling capacity into the play area and he suggested the installation of three split units for the first floor of Unit two.
Mr Kier said that the system had not been balanced and that there is no evidence that it had insufficient capacity to cool the play area. Mr Pitney said that during discussions on site with Mr Anderson, the latter seemed to agree that a wall outlet could be installed in the plan area. Mr Anderson acknowledged that but said that it was difficult to get the additional ductwork from the subfloor to connect to it.
The specification described the heating system as: "Central heating/air conditioning (refrigerated)". The units to be installed are not identified nor are there any specifications provided as to their intended performance. However the Builder was required to install a system that met this very general description that would be adequate for the purpose.
Mr Kier said that on Mr Anderson's own calculations, both the heating and cooling systems have sufficient capacity. Although he acknowledged that the installation of split systems would improve the performance it was an upgrade beyond the specified requirements. Since I am not satisfied on the balance of probabilities that the units installed were inadequate I do not find any defect.
Unit one exterior - Item 1 - Front fence $722.15
Unit one exterior - Item 2 brickwork holes and nails $143.00
Unit one exterior - Item 3 front door $2,073.50
Unit one exterior - Item 6 - gable cladding - $1,801.80
Unit one interior - Item 1 - front entry $536.2
Unit one interior - Item 2 - bedroom one $335.00
**Unit one interior - Item 3 - bedroom one ensuite $**608.00
Unit one interior - Item 4 - bedroom one walk-in robe Not established
Unit one interior - Item 5 - family/living $464.75
Unit one interior - Item 6 - kitchen/meals $357.50
Unit one interior - Item 7 - laundry Not established
Unit one interior - Item 9 - powder room $965.25
Unit one interior - Item 11- first floor bathroom $2,216.50
Unit one interior - Item 12 - first-floor family room $1,101.10
Unit one interior - Item 13 - toilet room $460.46
Unit one interior - Item 14 - bedroom 2 $421.85
Unit one interior - Item 15 - bedroom three $361.79
Unit two external - Item 1 - deck at rear $1,001.00
Unit two external - Item 3 - gas/air-conditioning commissioning
Unit two internal - Item 1 - garage/store $200.20
Unit two internal - Item 3 - lounge room $1,122.55
Unit two internal - Item 4 - the Cellar $5,219.66
Unit two internal - Item 7 - bar area $1,960.00
Unit two internal - Item 8 - powder room $469.04
Unit two internal - Item 10 - bedroom one $117.98
Unit two internal - Item 11 - bedroom one en suite $160.85
Unit two internal - Item 12 - walk-in robe Not established
Unit two internal - Item 13 - staircase handrail $429.00
Unit two internal - Item 14 - play area first floor $679.25
Unit two internal - Item 15 - storeroom $1,018.16
Unit two internal - Item 16 - bedroom two $1,212.50
Unit two internal - Item 18 - bedroom three $78.65
Mr Lorich referred to the two reports prepared by Mr Thompson from the Master painters Association and said that he has estimated the cost to repaint Unit one at $21,195 and the cost to repaint Unit two at $18,840.
Mr Campbell estimated that the cost of rectifying the deficiencies in paintwork identified by Mr Thompson in Unit one was $12,920.05 including margin and GST and that the cost of rectifying the items identified to Unit two, was $8,294.00, including margin and GST. I note that the proportion of the valuation of the project overall attributed to the paintwork was $42,883 (excluding margin and GST).
Unit two has been repainted but the paintwork in Unit one is original and although criticisms were made of some aspects, subject to those criticisms it looked to me to have a satisfactory appearance. Mr Lorich inspected both units and provided a very comprehensive initial report and in that report he did not suggest that the paintwork was so bad that both units had to be repainted.
In essence, Mr Campbell has provided a valuation of the work needed to rectify the defects that have been identified by Mr Thompson whereas Mr Lorich has taken a blanket approach and costed repainting both units.
Mr Pitney said that to provide a further coat of paint to both units would take three painters 11 days at a cost of $17,040 plus margin and GST. Mr Lorich said that the difference between his figures and those of Mr Pitney related to a different hourly rate and the need to subtract $4,300 plus margins to take account of the allowances that he had made in his assessments for painting defects in earlier items referred to above. He said that with this adjustment the figures would be similar.
On this item I prefer Mr Campbell's opinion. I accept his figures, which total $21,214.05 inclusive of margin and GST to rectify the painting defects that were proven. From this figure there must be deducted the amounts that I have previously allowed in assessing the earlier items referred to above with respect to painting.
Mr Lorich and Mr Pitney agreed that, if I were to allow Mr Lorich's figure for repainting both units, the double up to be deducted would be $4,300. However there is no specific evidence as to the amount to be deducted from Mr Campbell's figure to avoid a double up. Doing the best I can with reference to the painting components that were included in the figures I have allowed for the individual items, I will deduct $3,200. The final allowance for defective painting is therefore $18,014.05.
Mr Lorich said that the subfloor insulation does not technically comply with the requirements of the Contract documents. He said that the reflective foil used as insulation has a rating of only R1.97 instead of R2.0. He said that, as the building surveyor accepted it he did not believe that a defect existed. However, since preparing this report he has suggested that, on the advice of Mr Gibney, the engineer, it is in fact defective. Mr Gibney disclaimed any responsibility for saying that it was insufficient but said that he drew it to Mr Lorich's attention. Mr Campbell said that it was not defective and I prefer his opinion.
There are two wall tiles that have come away and were leaning against the wall of the cellar at the time of my inspevction. Mr Lorich suggested that the tiles be re-glued to the wall with a full body of adhesive to make good contact. For that he assessed a figure of $534. Mr Pitney's figure was $180. I have already allowed Mr Campbell's assessment of $220 for the same work which I think is more appropriate because there will be tradesmen replacing the cracked tiles in the cellar at the same time.
During the installation of the water pipe to the refrigerator, a hole was drilled through the bottom plate of a wall and then, accidentally, through a pipe forming part of the ducted vacuum system which had been concealed by the underfloor insulation. This is an acknowledged defect. Mr Lorich has assessed the cost of rectification at $691.00. It was acknowledged that the scope of work was very small. The actual cost of repair appears as part of an invoice dated 19 January 2016 where the plumber charged $175 plus materials and GST. If this invoice is apportioned then the actual cost of this item would appear to be close to Mr Pitney's assessment of $255.
Mr Lorich said that the pump to drain the cellar was not connected into the stormwater system and has assessed the cost of connecting it at $440. Mr Pitney assess the cost at $410. One expert is as likely to be right as the other so I will allow $425. With margin and GST that becomes $607.75.
The drawings included a side gate for Unit one which was not provided. This item has been agreed at $500. With margin and GST the figure becomes $660.00.
The floors had to be sanded in order to remove bubbles. This item has been agreed at $900. With margin and GST the figure becomes $1,287.00
The Owners claim the cost of obtaining remote controls for the Velux windows. Mr Paterson gave evidence that the remote controls were supplied. Since I prefer his evidence to that of the Owners this claim is not established.
The Owners paid $308.00 including GST to clear a downpipe blockage. The amount is part of an invoice dated 6 October 2015. That amount will be allowed. No margin was paid.
Some shower wastes leaked and were repaired at a cost of $240.00. With margin and GST the figure becomes $322.00.
There is a slight difference in height between the polished timber floors and other floor areas which Mr Lorich said was a trip hazard. Mr Campbell disagreed and found no defect. The reason for the height discrepancy in each case was said to be that the floorboards chosen by the Owners are only 14 mm thick. However that was the thickness of the floorboards in the specification and so this problem would have had to have been dealt with by the Builder in any event.
I think that this is an instance of incomplete work. There are five doorways in question and the rectification method involves feathering a small piece of timber in each instance. Mr Lorich's costing allowed eight hours to do that but Mr Pitney said that it should not take that long to fit only 5 m timber and has costed the work at $750. For this item, considering the small amount of work to be done, I prefer Mr Pitney's opinion and will allow his figure. With margin and GST becomes $985.00.
Mr Lorich said that the ceiling joint finish at the rear deck area of unit one was for and requires re-sanding, filling and repainting to make good. This is taken up in Mr Campbell's painting assessment so no further allowance is appropriate.
This item is also included in the figure for repainting.
Mr Lorich said that the skirtings in the Unit one living room are loose on the walls. I observed this on site and I will allow the amount of $756 assessed by Mr Lorich. With margin and GST becomes $990.80.
Mr Lorich said that the plaster on the laundry wall was drummy and requires additional fixing for which he assessed a figure of $225. With margin and GST that becomes $321.75
The paint on the privacy screens has rust spots and it was not suggested that the cost of repainting them is included in the allowance for painting. Mr Lorich's figure for repainting them was $900 and Mr Pitney allowed $650. There are five screens and they will require three coats. Since one expert is as likely to be right as the other I will allow $775. With margin and GST that becomes $815.00.
Mr Gibney said that a significant amount of timber framing in the kitchen subfloor area around the circular staircase to the cellar had been cut away and that the existing particle board had been removed to expose the underside of the hardwood flooring. He said a series of floor joists had been totally removed to allow the support mechanism to be placed and that the mechanism was inadequately supported. He said that, without pulling off the ceiling lining or removing the floor above it was not possible to ascertain what framing had been used and whether any modifications and structural steel had been inserted in the subfloor space. In his evidence he said that the framing around the mechanism was incomplete and that there was significant work to do.
Mr Blackwood agreed that some of the framework needed attention but said that it was only a couple of square metres that needed to be addressed and that it would only require a couple of hours work for a carpenter. Mr Gibney said that the torsional loads of the hatch were taken by the floor but Mr Blackwood pointed out that the mechanism was bolted to the core filled block work walls and that the majority of the load went into the block work. The photographs produced confirmed that, at least one side of it was connected to the wall.
Mr Gibney pointed to a loose screw but there was a dispute as to whether it was in that condition when the Owners took possession of the site. Certainly, when I inspected it the mechanism worked satisfactorily but it appears that some work was done to the floor after the Builder left the site and both before Mr Gibney's inspection and between then and the time of Mr Blackwood's inspection. The state of the floor at the time the Owners took possession of the unit is impossible to assess with any confidence because others have worked on it in the meantime. That is always the problem when rectification work has been carried out before all parties have had the opportunity to have the site inspected and recorded by an independent expert in the state the Builder left it. The earliest experts' report that I have does not mention these matters.
In considering the structural capability of the floor, Mr Gibney had assumed that the strip flooring was a floating floor placed over the underlying yellow tongue sheeting. However Mr Paterson was recalled and he gave evidence that the strip flooring was in fact glued to the yellow tongue below it.
On this state of the evidence I am satisfied there is some work to be done by a carpenter but that it is not as extensive as Mr Gibney initially believed. As to the scope of rectification, I prefer Mr Blackwood's opinion.
Mr Gibney said that he was informed that the metal component supporting the access lid to the cellar had cracked and had to be replaced. That had already been done by the time the experts saw it. The Owners paid $481.25 to replace the metal component that is claimed to have cracked and failed.
In her witness statement, Mrs Mann said that the Owners also paid $2,906, to their landscaping contractor, Four Seasons Landscaping & Paving, in respect of "necessary rectification works" to the cellar but in the absence of some evidence as to what was done, the reasonableness of the amount charged and whether it was to address an identifiable defect, no claim for that sum is established.
Mr Gibney suggested that the spiral staircase was only tack-welded to the surrounding collar. Mr Blackwood disagreed. I was shown photographs by the experts and I had a careful look at it on site. I saw one tack weld but I also saw the areas that Mr Blackwood pointed out which he said were proper welds. I prefer Mr Blackwood's opinion and I accept that the welding is sufficient and that no further work is required in regard to that. Apart from the cost of the welding, the major consequence of that, and the finding in regard to the floor structure, is that the ceiling of the cellar does not have to be removed in order to carry out the limited scope of works that are required to the subfloor.
In regard to the rectification of the cellar opening I accept the opinion of Mr Blackwood and the costing of his scope of works of $1,380 which, with margin and GST, is $1,973.40. In addition, the amount paid by the Owners of $481.25 will be allowed, making a total figure for this item $2,454.65.
A note on the plans required that retaining walls below ground level be tanked. The wall on the eastern boundary forming part of Unit two is a cavity brick wall that has not been tanked. It is also not been core filled, which Mr Gibney said was necessary. He said that the cavity should be filled with concrete with a waterproofing admixture in it. Mr Blackwood agreed that the cavity should be filled but said that there was no requirement for base brickwork to be tanked.
In his report of 10 June 2016, Mr Lorich costed the rectification of the boundary wall, only with a much wider scope of works that I have found is warranted. From his calculations in Attachment 'B' to this report, I find that the cost to fill the cavity with mortar is $2,610 which, with builders margin GST becomes $3,732.30.
Mr Gibney said that the wall within the property should also be tanked because it is below ground level. Mr Blackwood said that tanking a subfloor is not common practice and there was no requirement that this wall be tanked. Mr Gibney suggested the possibility of edge heave if there should be any water penetration into the soil beneaththe footing. Mr Blackwood pointed out that the wall is supported on piles because of the angle of repose of the walls of the cellar. On this state of the evidence I am not satisfied that it has been demonstrated that this wall needs to be tanked.
It was not suggested that the masonry code requires such a wall to be tanked. The general note on drawing A00 to which Mr Gibney refers relates to requirements for waterproofing. It deals with internal wet areas, balconies, perimeter floor drains and other applications that one would expect to be waterproofed and then states that for "retaining walls and walls below ground level" a named waterproofing agent is to be installed.
Mr Gibney interpreted that as meaning that any wall at all that was below ground level needed to be tanked which would have included all base brickwork. As a matter of interpretation, I think that the note provides the manner of waterproofing that is to be adopted for retaining walls and walls below ground level where those walls need to be tanked but it does not intend to impose a requirement that all walls below ground level necessarily need to be tanked. As a consequence I prefer Mr Blackwood's opinion.
There was a dispute between the two engineers as to whether this wall needs to be tanked. Mr Blackwood pointed out that the site slopes to the rear boundary and that as a consequence, water will not pond against the wall. Mr Gibney pointed to a photograph showing dampness on the inside of the wall but it appeared that the bricks in the photograph were sitting on the strip footing so that if anything were to be tanked it would only be the bottom one or two courses. Mr Blackwood said that when he was under the floor he found the ground was dry. Mr Gibney said that he found that it was wet. I am not satisfied that it has been demonstrated that this wall will need to be tanked.
Mr Gibney suggested in his report that a prop under the floor should be replaced with a proper stump. It appears however that it was a piece of timber left there by mistake. It is non-structural and can simply be removed. Mr Gibney agreed in evidence that an additional stump was not required.
There was an area where some floor joists were notched over bearers, which Mr Gibney said was structurally inadequate. He said that it might involve about six or seven joists. In forming his opinion, Mr Gibney assumed that the joists were 90 mm x 45 mm but Mr Paterson said that in fact they were 140 mm x 45 mm.
Mr Blackwood said that it was a standard joist carrying a small amount of load and he would imagine that it is almost certainly not going to be a problem. He said that it was quite common to notch joists a small amount over bearers and that a 90 mm joist would definitely work. Both engineers said that calculations would be required but none were available at the time. Mr Gibney said that if it were a 90 mm joist and it were checked, it would not work as a continuous joist but Mr Patterson's evidence is that it is a 140 mm joist. I am not satisfied that a defect has been demonstrated.
Mr Gibney pointed out that some of the internal bricks in the base brickwork were wire cut bricks lying on edge. He did not say that there were structurally inadequate for the task but he said that they this was not in accordance with the Code. Mr Blackwood said that they were very lightly loaded and there was no problem. Since this is base brickwork and it is structurally sound I am not satisfied that it has been demonstrated that there is a defect.
(g) Protective board around the cellar Not established
Mr Gibney produced a photograph to the effect that the protective board has moved away slightly from the tanked wall of the cellar. He acknowledged that it was "a fairly minor thing" but said that the board should be continuous to protect the tanking. It was acknowledged that there were no signs of the membrane having been breached and no indication that any of the scoria has fallen down between the protective board and the wall.
Mr Blackwood acknowledged that it is possible that, over time, pieces of scoria could fall down between the wall and the protective board and could penetrate the membrane but he also pointed out that there was a drain at the bottom of the outside of the wall connected to a pit, designed to take away any water and that there was also the scoria to direct water away from the wall. He said that the photographs show a very wide scoria section which water would have to somehow get through. Since this is apparently a fairly minor thing and there is no evidence that there is in fact any scoria between the board and the wall I am not satisfied that a defect has been demonstrated.
At the front porch area of unit two there is a low brick wall of a few courses of bricks separating the porch from the driveway. The height of the driveway is above the height of the porch and it is suggested that water is penetrating through the wall. Water tests by the experts show that the fall of the concrete of the driveway is away from the wall and so it directs surface water away from the wall but Mr Gibney said that the issue is not just surface water but rather, water in the soil behind the wall because the wall is not tanked.
Mr Gibney said that a segment of concrete in the driveway should be cut out and the wall should be excavated to the base of the footing and be tanked and backfilled and a trenched grate should be put around it to pick up any surface flows.
I asked about the wall of the unit which this low wall abuts, which is also not tanked. Mr Paterson said that there was an agricultural drain there. If there is an agricultural drain and I do not understand why there would be any sub-soil water to be concerned about.
Reference was made to efflorescence said to be on the bricks. Mr Blackwood said that he could not see any. A faint white mark on a brick was pointed out to me on-site that might have been efflorescence but it was too faint for me to be sure what it was. Mr Gibney acknowledged that there was no efflorescence in the mortar.
Mr Blackwood did not agree that there was any requirement for a trench drain for this section of wall. He said that the whole area was covered by a roof and that all the water went into drainage. Since there are agricultural drains behind the wall to take away any subsoil moisture and the driveway is graded away from the wall I am not satisfied that it has been demonstrated that this wall should have been tanked.
Mr Gibney said that one of the joists above the cellar is acting as a beam rather than a joist. He said that the joists run parallel across the cellar and then one of them picks up the jack joists spanning at right angles to it.
Mr Blackwood said that these joists are cantilevered and the connection was made to avoid any local differential movement. He said that the fact they were joined did not mean that they were not cantilevered.
Mr Gibney agreed that, as a cantilever, the jack joists would have sufficient capacity but he said that as soon as you fix them to another member they are not a cantilever anymore. I find it difficult to understand why the floor structure would be sufficient if the joists were unconnected and yet deficient simply because they were connected. I prefer the opinion of Mr Blackwood because it appears to me to make more sense.
This matter is dealt with in part (a) of the last paragraph.
(b) Void under the rear of the Unit two garage floor slab Not established
There is an opening at the rear of the garage to Unit two. According to the plans there were to be mass concrete steps formed in this location but the landscaping was excluded from the Contract. There is a small void under the edge of the slab that Mr Lorich said was due to the absence of a retaining wall, allowing some washing and falling away of the underlying gravel and sand fill. He said that rectification will require the construction of a concrete formed edge to act as a retaining wall and he has assessed the cost of that, including margin and GST at $2,337.00. Mr Campbell costed rectification $1,523.00 including margin and GST.
This matter was not identified as a defect in Mr Lorich's initial report. Mr Campbell agreed that the face edge of the slab is not neatly finished but said that there is no evidence showing any subsidence or erosion. He said that the landscaping of the area behind the rear of the garage remains incomplete and the matter is purely aesthetic.
The complaint is really about the absence of a retaining wall but the construction of such a wall was not within the Contract scope of works. I think that the Builder was entitled to assume that the area would be landscaped in accordance with the plans by the Owners. It seems to me that if that had been done the escape of the underlying gravel and sand fill could not have occurred. I note that no landscaping has been included in Mr Pitney's valuation of the work. Since the construction of the steps in accordance with the plans was the responsibility of the Owners I do not find that the construction was defective.
Mr Lorich said that there was a bow in the wall around the corner from the powder room. The wall has been straightened but the acute angle of the skirting board is noticeable. Mr Lorich proposes to strip off the architrave and skirting, pack the plaster out and refit and repaint. Mr Campbell said that only the skirting needs to be removed which he costed at $303.73 with margin and GST.
I prefer Mr Lorich's opinion and will allow his figure of $1,080.00. That figure includes painting but this item is not included in Mr Campbell's painting assessment and so there should be no deduction. With margin and GST the figure becomes $1,414.00.
The two architraves were not quite at the same level although the difference is not easy to see. When Mr Campbell put a 2 metre level on them they appeared to be level. Mr Lorich said that that was because they were level in the centre. Mr Campbell said that there was a slight kick in the left-hand side and that it would only be necessary to adjust the architraves. Mr Lorich said that it was unsightly and would require demolition of the door to the walk-in robe unit as well as the inbuilt robe shelving and the removal of plaster linings. Mr Lorich has reduced his costing of this item to $800 for one side only. I accept that assessment. He indicated that he was prepared to reduce it further to take account of the painting but that seemed to be on the basis that I allowed his costing for repainting the unit and I have not done that so I should allow the whole $800. With margin and GST it becomes $1,050.00.
(c) Robe drawers and shelving - bedroom one Not established
This is an addition to Mr Lorich's earlier assessment of the cost of replacing the drawers and shelving because, he said, some very expensive quotations had been received by the Owners. Since I have not allowed this item in the first place there is no allowance to increase.
There were holes in the brickwork from where the heating system was relocated. There is also a loose piece of material to be removed. This was agreed at $135. With margin and GST that becomes $193.05.
There is a small piece of trim hanging off the bottom of a window upstairs and an articulation joint needs to be caulked. Mr Lorich has assessed a gross cost of $1,705 for this item, $1,200 of which is for a scaffold. It was acknowledged that, if the roofing items are to be allowed, that figure can be saved because the roof will be scaffolded already. As a result, I can remove that from the calculation which reduces Mr Lorich's assessment to $505. It was also suggested that it might be possible to do the job from the window. On this item I accept Mr Pitney's assessment of $170 which, with margin and GST becomes $243.10.
Mr Lorich said that when he was there, the area around the tank was flooded. It appears that it was necessary for it to be installed with flexible connections. The tank holds 2000 litres and is seated on crushed rock.
Mr Campbell said that he found a small amount of water there but found that the pump had been disconnected and that the water appeared to come from where the pump had been.
According to Mrs Mann's witness statement, the toilets were blocking up and they suspected that the filtration and pump system were not working properly. I do not have enough evidence to find a defect in regard to this item.
This issue has already been dealt with. I am not satisfied that the insulation used is insufficient.
(b) Repairs to plaster in Unit two by Mr Frogley, $3,718. Allow $300.00
The invoice and proof of payment have been produced and the invoice contains some detail but insufficient to determine what should be allowed. The plastering over of the power point blanks seems to have been a substantial item but the evidence established that this should not have been done. The only one of the items of work that was referred to in expert evidence was the straightening out of the plaster wall near the powder room in Unit two but although this was referred to in connection with the powder room, no evidence was given as to how much that work should reasonably have cost. Nevertheless it ought to have cost something and doing the best I can I will allow $300.00. Since this was done by someone hired directly by the Owners there was no margin.
This was with respect to undetailed repairs to a shower screen and sink in Unit one and a mixer tap and sump pump and commissioning of the gas appliances and the water connection to the fridge in Unit two, all for a total cost of $594 including margin and GST. The connection of the sump pump has already been disallowed and the other items in regard to Unit two are probably completion items. However since I am allowing the value of the completed work then the cost of commissioning the appliances should be allowed.
It is impossible to ascertain how this invoice should be apportioned but doing the best I can I will allow $400.00 for the remaining items.
(d) Spiral staircase balustrade $2,695.00 Allow nil
(f) Supply/replacement of remote controls $950.00 Allow nil
(g) Heating/cooling repairs $1,245.00 Allow nil
There was a report from a contractor called Coldflow dated 15 May 2015 that makes some criticisms of the installation and recommendations for improvement. There is an invoice for $750 for replacing the "condensate kit, flue, thermister and vent" but no expert evidence to the effect that this resulted from any defect. I cannot find any evidence to substantiate the balance of this amount. It appears to have been a charge made for inspecting the system rather than rectify any defect.
(h) Paintwork to front fence $1,630.76 Allow nil
The valuation of the work did not include paintwork to the front fence and so there is no allowance that needs to be reduced.
(i) Repainting of Unit two $35,484.48 Allow nil
(j) Electrical repairs Dean Mack $3,700.00 Allow $50.00
This claim is supported by a detailed invoice dated 17 June 2015. It shows that virtually all of this work was for substantial upgrades to what had been provided by the builder. No expert evidence has been led to the effect that any of this work was done in order to rectify any defect and that does not appear to be the case on the face of the invoice. The only allowable item is the connection of the wall oven and no separate charge has being made for that in the invoice. In the absence of any evidence as to an appropriate allowance I will allow $50.00. This item is allowed because Mr Pitney's valuation assumed that the oven would be connected.
All I have in support of this claim are two cash register invoices from Bunnings but I have no explanation of why the hinges were required. This claim is not established.
According to the invoice, this is for sanding and coating the flooring in Unit two. That complaint has already been dealt with and allowed.
(m) Faulty bi-fold door seals $137.50 Allow $137.50
This was for the provision of four bi-fold door seals on 30 July 2015 to replace those that had been painted over. That amount will be allowed.
(n) Replacement of air-conditioning unit $8,130.00 Allow nil
This is a claim for the split system air-conditioner the Owners purchased for Unit one because they claimed that the system installed by the Builder did not have sufficient capacity. This has already been considered above and rejected for the reasons given.
(o) Defective vacuum system $1,433.00 Allow nil
This claim comprises a service call on 30 October 2000 of $198 including GST to locate the cause of the low suction in the pipe. An amount of $130 was subsequently paid to the supplier. I have no evidence to explain the balance of the claim. This claim has already been allowed above.
Landscaping was not included in Mr Pitney's valuation of the work, perhaps because landscaping was excluded from the scope of works under the Contract. The total paid to Mr Korke, the landscaper, was $9,900.00. In paragraph 400 of Mrs Mann's witness statement in reply, she says that his invoice included charges he had made for assisting the Owners to identify defects and for liaising with experts. She acknowledged that some of that was not appropriate to claim from the Builder in this proceeding and so the Owners only claimed half of the amount they paid him. This seems a rather arbitrary claim without any expert evidence to establish that it represents a loss the Owners have suffered as a result of any defect in the work and materials that Mr Pitney has valued. There does not seem to me to be any basis for reducing Mr Pitney's valuation on this account.
(q) Seal/paint garage Unit one $310.00 Allow nil
The sealing and painting of this floor was excluded from Mr Pitney's valuation. He only made an allowance for sealing and painting the garage floor of Unit two. There is therefore no figure to reduce.
This item has already being considered and rejected.
(u) Balustrade to cellar opening $2,970.00 Allow nil
This item has already being considered and rejected.
(v) Seal spiral staircase treads $660.00 Allow nil
This was the balustrade for the alfresco area in Unit two that the Owners installed when they took possession of the site. The contract documents did not provide for the installation of a glass balustrade and no allowance for that cost was included in Mr Pitney's valuation of the work. Accordingly, there is nothing to be deducted on this account.
(y) Retractable fly screens bi-fold door $2,501.40 Allow nil
These have not been included in Mr Pitney's valuation. All that he has allowed for are screens for the windows.
(z) Velux in stairwell - remote & programming $734.80 Allow nil
This item has already being considered and rejected.
According to Mrs Mann's witness statement, part of this claim relates to Mr Gibney's charge for the certification of the retaining wall and the rear fence and part relates to advice that he gave them in regard to the operating mechanism of the cellar hatch.
In paragraph 236 of her first witness statement Mrs Mann refers to an invoice from Mr Gibney dated 11 June 2015. I have found Mr Gibney's certifications of the design and construction of the fence and retaining wall which bear that date in the Tribunal Book but I cannot find any invoice from him to show me how this amount is divided.
It is apparent from the certification that both the design and the construction of the fence and retaining wall that was erected by the Builder were sound and no defect is suggested. In discussions with the Builder at the time of construction the Owners undertook the responsibility of attending to any requirements of the Council and also, obtaining any permits that might have been necessary. That would have included any certifications the Council might have required.
As to advice given by Mr Gibney in regard to the cellar hatch mechanism, that might have been a disbursement to be included in any claim for the costs of this proceeding but there is no evidence establishing that it is an amount claimable against the Builder by way of damages or reduction of the valuation of the works.
This amount was said to be the cost of preparing the as-built plans. Since these were the necessary result of Owner variations I do not think that this was payable by the Builder. The Contract was also determined before the expense was incurred and it is now at an end. I cannot see any contractual basis for this claim and the cost of preparing such plans has not been included in Mr Pitney's valuation so I cannot see any reason to deduct it from his valuation.
(c) Proteck building surveying $1,650.00 Allow nil
This was said to be the amount charged by the building surveyor for carrying out further inspections and issuing a conditional permit on 1 September 2015. Again, this expense was incurred after the termination of the Contract and there is no evidence establishing that it is an amount claimable against the Builder.
This amount was said to have been charged by the Council for a secondary consent on 21 June 2015. It was after the Contract came to an end and there is no evidence establishing that it is an amount claimable against the Builder.
(e) DT Electrical & Data $750.00 Order to produce
According to Mrs Mann, the Owners have obtained a quotation from a company, DT Electrical & Data, of "approximately $750" in order to provide a certificate for the solar panels that the Builder installed so that they would be able to claim a solar rebate. It does not appear that any such expense has been incurred to date. She said that the Builder gave the Owners no paperwork relating to the installation.
Mr Paterson said that the Owners never requested any solar power paperwork. He said that other certificates, which were requested, were provided to them through their solicitors. In the Tribunal's order of 18 August 2015, there is a list of certificates that the Owner's solicitors had sought and the Tribunal ordered the Builder to provide them if they were in its possession. It appears that these were provided.
There is no clear evidence as to what the documents that are sought would be. I think the appropriate course is to make an order that any certificates relating to the solar panels that the Builder installed that are in its possession or control must be provided to the Owners.
(f) Matthew Shepard Plumbing $1,520.00 Not established
Mrs Mann attached to her witness statement in reply, a letter from a plumber, Matthew Shepard, quoting an amount of $1,520 for a scope of works directed to replacing the pump from the water tank to the toilets, installing a filtration system, installing a pump cover with a sound deadening cover to eliminate noise and commissioning the new pump to the toilet system. There is no accompanying report from Mr Shepherd to explain why this work is necessary and he was not called to give evidence.
Mrs Mann said that the Owners had experienced blockages and Mr Shepherd had told her that the reason was that the pump and filtration system from the tank were defective. There is no expert evidence to establish that is the case. In his opening, Mr Hellyer said that the Owners had to pay $583.00 to rectify the toilet. He said that the tank had been disconnected from the toilets because they kept "blocking up".
Mr Paterson said that he tested the toilets before he left the site and that they were all working. He said that any adjustment would have been a maintenance item. Mr Laird complained that this was a late inclusion in the claim that the Builder's advisers had not had an opportunity to look at and consider.
There is insufficient evidence to establish this claim.
"Repudiation of a Contract is a serious matter and is not to be lightly found or inferred: Ross T. Smyth & Co., Ltd. v. T.D. Bailey, Son & Co. (1940) 3 A11 ER 60, at p 71. In considering it, one must look to all the circumstances of the case to see whether the conduct "amounts to a renunciation, to an absolute refusal to perform the Contract_": Mersey Steel and Iron Co. v. Naylor, Benzon & Co._ (1884) 9 App Cas 434, at p 439."
"Repudiation is not ascertained by an inquiry into the subjective state of mind of the party in default; it is to be found in the conduct, whether verbal or other, of the party in default which conveys to the other party the defaulting party's inability to perform the Contract or promise or his intention not to perform it or to fulfil it only in a manner substantially inconsistent with his obligations and not in any other way."
Conclusion concerning the alleged repudiation by the Builder
"When a party commits a breach going to the heart of the contract or repudiate his obligations then the situation arises under which the so-called innocent party has to elect whether or not to put an end to the contract. The time for making an election will not arise until a reasonable time has elapsed for the matter to be properly considered... After that time the innocent party must do one of two things, either elect to affirm the contract or to put an end to it. That election can be made by an intentional statement or by action or by conduct. That election must be communicated and is not complete until it is communicated.... All that is meant by "communication" is that the fact of election must come to the repudiating party's attention. It matters not whether the communication came from the innocent party or from a third party."
"12 The right of a builder to sue on a quantum meruit following a repudiation of the contract has been part of the common law of Australia for more than a century. It is supported by decisions of intermediate courts of appeal in three States, all of which postdate McDonald and two of which postdate Pavey & Matthews. If that remedy is now to be declared to be unavailable as a matter of law, that is a step which the High Court alone can take."
"25 The proper approach to assessment of a quantum meruit claim is, as the trial judge said, to ascertain the fair and reasonable value of the work performed. Axiomatically, the measure of the restitutionary remedy is the value of the benefit conferred on the party which received it. Once it is accepted that the quantum meruit claim is available independently of the contract, then it follows - as Meagher JA said in Renard - that it would be 'extremely anomalous' if the defaulting party could invoke the contract which it has repudiated to impose a ceiling on the amounts recoverable. [emphasis added]
26 Nor is the contract price 'the best evidence' of the value of the benefit conferred. As counsel for Kane pointed out, the contract price is struck prospectively, based on the parties' expectations of the future course of events. The quantum meruit, on the other hand, is assessed with the benefit of hindsight, on the basis of the events which actually happened."
"35 The existence of the entitlement to a profit margin seems entirely consistent with the restitutionary objective of measuring the value of the benefit conferred. The inclusion of a margin for profit and overhead means that the calculation approximates the replacement cost of the works. As we have said, it is an appropriate index of value to ascertain what it would have cost the Principal to have had these works carried out by another builder in comparable circumstances. The answer to that question must necessarily include that other builder's margin." [emphasis added]
"43 If the work the subject of the variations has been carried out - and there was no dispute here that it had been - the only question is the fair and reasonable value of the work. It is irrelevant whether or not the work fell outside the original contractual scope. All that matters is that the performance of the work has conferred a benefit on the owner, for the reasonable value of which the Builder should be remunerated."
Value of the work assessed without defects $1,722,611.00
less rectification of defects as above $ 116,297.59
Value of the benefit conferred upon the Owners $1,606,313.41
Paterson Constructions Pty Ltd
Mann