[2017] VCAT 1235
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2017-08-10
Original judgment source is linked above.
DOMESTIC BUILDING - application under s75 of the Victorian Civil and Administrative Tribunal Act 1998 - relevant principles - and of the - arguable that a claim against a developer is a - amendments to Points of Claim after limitations period expired - application refused.
View Street Properties (Vic) Pty Ltd (ACN 134 116 117)
Mark Coffey Constructions Pty Ltd (ACN 064 095 370)
Regional Building Surveying Services Pty Ltd (ACN 100 573 831)
Owners Corporation PS 542601 Y v Phenix Holdings Pty Ltd (Building and Property) [2017] VCAT 1235
(1) At any time, the Tribunal may make an order summarily dismissing or striking out all, or any part, of a proceeding that, in its opinion -
(a) is frivolous, vexatious, misconceived or lacking in substance; or
(2) If the Tribunal makes an order under sub-section (1), it may order the applicant to pay any other party an amount to compensate that party for any costs, expenses, loss, inconvenience and embarrassment resulting from the proceeding.
(5) For the purposes of this Act, the question whether or not an application is frivolous, vexatious, misconceived or lacking in substance or is otherwise an abuse of process is a question of law.
"The application is really made to the inherent jurisdiction of the court to stop the abuse of its process when it is employed for groundless claims. The principles upon which that jurisdiction is exercisable are well settled. A case must be very clear indeed to justify the summary intervention of the court to prevent a plaintiff submitting his case for determination in the appointed manner by the court ...".
(a) it must be 'very clear indeed' that the action is 'absolutely hopeless'; or
(b) the action must be 'so clearly untenable that it cannot possibly succeed'.
(c) the strike out power 'may not be invoked where all that is shown is that, on the material currently put before the Tribunal, the complainant may fail to adduce evidence substantiating an essential element of the complaint'; and
(d) the respondent to a complaint has the onus of showing 'that the complaint is undoubtedly hopeless'.
... must be obviously unsustainable in fact or in law, can on no reasonable view justify relief, or must be bound to fail. A claim would be regarded as frivolous or vexatious or misconceived if it is obviously groundless, made by a person without standing, or in respect of a matter which lies outside the VCAT's jurisdiction. A claim may be regarded as lacking in substance if an applicant cannot possibly succeed in establishing its claim, or the respondent has a complete defence. The power to strike out should be exercised with great caution.
... the power to order summary or final judgment is one that should be exercised with great care and should never be exercised unless it is clear that there is no real question to be tried.
(a) The Vendor is not a builder as defined by the Act; and
(b) This Contract is not a Building Contract to which the Act applies.
12.2 The Purchaser acknowledges that the builder building the residence may or the Vendor may direct the builder at any time to make or cause to be made (without reference to the Purchaser) any minor alterations or variations that the Vendor may deem necessary to be made to the residence. The Vendor agrees to notify the Purchaser in writing of any proposed changes to the works relating to the residence which will directly, substantially and detrimentally affect the residence.
12.3 Subject always to special conditions 12.2 & 12.5 the works to the residence will be executed by the builder substantially in accordance with the Project Specifications relating to the residence. The Purchaser acknowledges having received a copy of the Project Plans and Specifications prior to entering into this Contract of Sale from the builder.
12.4 The works will be deemed to be completed by the builder and the builder and the Vendor shall be discharged from any obligations under special conditions 12.2 & 12.3 upon production of an Occupancy Permit for the Property.
12.5 The Vendor or the builder concerned without reference to the Purchaser may make any change to the Project Specifications they deem necessary or which becomes necessary as a consequence of the unavailability of or unreasonable increase in price or failure to meet the Vendor's or the builder's standard of any item, fixture, fitting, or produce referred to in the Project Specifications (unavailable product). In making any change to the Project Specifications the Vendor will ensure the builder replaces any unavailable produce with an item, fixture, fitting or product of equal or similar quality and standard to the unavailable product.
The Vendor agrees to arrange for the completion of the residence on the property and will hand to the Purchaser at or prior to settlement the following documents in respect of the residence erected on the Property:-
(a) Occupancy Permit;
(b) Certificate of Insurance as required by the Building Act 1993 (the Act)
The Vendor will do all things reasonable to ensure the completion of the residence on the property as quickly as practicable. If the said residence is not completed by 31 March 2007 (completion to mean that the documents (a) and (b) immediately above in this Special Condition being available to hand to the purchaser at settlement (the Vendor aor Purchaser may at any time after 31 March 2007 but before both of the said documents are available to hand to the Purchaser at settlement, avoid this sale. [emphasis added]
(c) The Second and/or Third Respondents and/or the First Respondent may make minor alterations or variations to the residence but if so the First Respondent must notify the Second and Third Applicants in writing of the proposed changes which will directly, substantially and detrimentally affect the residence;
(d) The works were deemed "complete" by the provision of an Occupancy Permit, whereupon the Second and Third Respondents and/or the First Respondent were discharged from any further obligations in respect of the completion of the works. This term does not relieve the First Respondent from any contractual obligation in respect of completed works that are not in accordance with the Plans and Specifications in circumstances where the changes are not minor, or where it has not notified the Second and Third Applicants in writing of the changes;
(e) The First Respondent would arrange for the Second and/or Third Respondent to rectify any minor works not completed if notified to it within 3 months from the date of issue of the Occupancy Permit. There is no express terms limited the liability of the First Respondent for incomplete works that are not "minor".
(a) the First Respondent [the developer] failed to ensure that the work to Lot 8 was executed by the Second and/or Third Respondents substantially in accordance with the Plans and Specifications.
(b) The First Respondent and/or the Second and/or Third Respondents made major alterations and variations to the Building Works;
(c) The changes directly, substantially and detrimentally affect the residence and the First Respondent failed to notify the Second and Third Applicants in writing of the proposed changes
The same allegations are pleaded in 50(a) and 52(a) in relation to the contracts of sale for lots 8,9 and 10):
building action means an action (including a counter-claim) for damages for loss or damage arising out of or concerning defective building work;
building work includes the design, inspection and issuing of a permit and respect of building work.
Are the claims in the draft APOC a 'new' cause of action?
In Agtrack, the respondent was the widow of a man who was killed when a Cessna 210, in which he was a passenger on a sight seeing tour in the Northern Territory crashed. Ms Hatfield had brought an action against the appellant which had contracted to carry Mr Hatfield, originally in negligence and in breach of statutory duty. There was no dispute that the proceedings were validly issued. Ms Hatfield later became aware that a claim was only available under Part IV [of] the Civil Aviation (Carriers Liability) Act 1959 and sought to amend to plead a claim under that Act even though the time limit for bringing such an action had expired.
The present case, however, is not a case where a completely new claim, said to have been extinguished by the Act, is sought to be added by way of amendment where no likely claim previously was asserted. As I have previously sought to explain, all that the amendments in the present case sought to achieve was to add to an existing claim, which was already on foot, certain (effectively) jurisdictional allegations, together with an allegation that the proceeding was brought pursuant to Pat IV of the Act.
What is here in issue is an amendment seeking to add or vary a few minor details and to give the existing claim a new characterisation, closely akin and by no means remote from the subject matter of the original claim. That is a true amendment and the very kind, which the Court ought to be free to give effect to. It affects only an action already on foot
Whether the lot owners' claims have no real prospect of success
It must be remembered that in considering an application under s75 I am not required to consider or be satisfied as to the likely success of the Woods' claim. I am required to consider whether the allegations are 'frivolous, vexatious, misconceived or lacking in substance', in other words, whether they are doomed to fail. This does not contemplate a detailed consideration of the evidence. As Senior Member Cremean observed in Johnston v Victorian Managed Insurance Authority [2008] VCAT 402 at [15-17]:
[5] (2003) 7 VR 63, [2003] VSCA 6 - aaffirmed on appeal by the High Court in Agtrack (NT) Pty Limited v Hatfield (2005) 223 CLR 251, [2005] HCA 38.
Owners Corporation PS 542601 Y
Phenix Holdings Pty Ltd
(1949) 78 CLR 62
(2003) 7 VR 63
(2005) 223 CLR 251