Grounds 1 and 2 - Severance
7 In determining compensation Sheahan J found that had the resumed land not been required for the public purpose for which it was resumed, it would have been zoned Residential 2(a3), as was the retained land.
8 His Honour concluded that the highest and best use of the resumed land was potentially that of a retirement village. Before the Court was a retirement village concept for 88 units on the resumed land devised by Mr Geoffrey Twibill, architect. The appellant had submitted that such a proposal would have been approved by the Council in 1984. This was referred to as Scenario 1.
9 With regard to this scenario, his Honour said that he did not accept that it could be compared with what happened in Lasseter v Blacktown City Council (Court of Appeal, unreported 5 December 1996), where the landlocked condition of the land was a direct and actual consequence of the subdivision which was seen to be a step in the resumption process.
10 Sheahan J said:
Here, the link is far more tenuous. There is no guarantee that consent would have been granted in 1984 for the 88 units, even with a strong recommendation from Minnaard. There was in fact no application in 1984. The specific proposal for the 88 units was not even devised until 1996. The Court cannot assume so speculative a proposition. The "consentless" condition does not bear a sufficiently direct connection to the resumption process.
11 Accordingly, his Honour turned to Scenario 2 of the appellant's case, in which it was maintained that a hypothetical purchaser would obtain development consent in 1995 to extend the existing retirement village onto the resumed land. Under Scenario 2 his Honour considered whether this concept would have been likely to receive development approval and whether it was economically viable.
12 His Honour considered the evidence of various constraints on the development and concluded that he accepted the opinion of Mr Minnaard (former town planner with the Council) that the constraints would not preclude the Council granting consent to the hypothetical development.
13 However, his Honour found that such a proposal was not financially viable. Accordingly, Sheahan J concluded that a hypothetical purchaser would not have viewed the Twibill proposal as 'within the realm of probability'. Rather, it would have been seen by a prudent purchaser as speculative. It could not, therefore, be regarded as the highest and best use of the resumed land.
14 The finding on the financial viability of Scenario 2 is a finding of fact and cannot be challenged on appeal. Accepting this situation, the appellant properly makes no challenge to the finding.
15 His Honour then went on to find that the highest and best use of the resumed land was for a single dwelling site. This he valued at $105,000, to which he added $81,031.54 for disturbance, making a total award of compensation of $186,031.54.
16 The appellant had also claimed compensation based on severance under s 55(f) of the Act for the lost development potential of the retained land. This is the subject of grounds 1 and 2 of the appeal.
17 Section 55 of the Act provides that in determining compensation regard must be had to:
(c) any loss attributable to severance;
…
(f) any increase or decrease in the value of any other land of the person at the date of acquisition which adjoins or is severed from the acquired land by reason of the carrying out of, or the proposal to carry out, the public purpose for which the land was acquired.
18 Section 58 defines 'loss attributable to severance' of land as meaning 'the amount of any reduction in the market value of any other land of the person entitled to compensation which is caused by that other land being severed from other land of that person'.
19 It may be that the claim for severance would have been more appropriately made under s 55(c), but it matters not.
20 His Honour recited what he understood to be the submission of counsel for the appellant. He said that the appellant claimed to have lost the benefit of being able to develop the retained land for additional units up to a maximum of 128. His Honour said that he rejected the claim for severance for 'similar reasons to those underpinning my rejection of the applicant's Scenario 1'.
21 In addition he said:
The land must generally be valued at the date of resumption in its then existing condition ( Yates ). The acquisition of the acquired land did not decrease the value of the retained land at the date of the acquisition.
As outlined in the discussion of the Scenario 1, the Yates principle is subject to the San Sebastian rule, as applied in Lasseter , so that the Court must set aside conditions of the land which are the direct consequence of the resumption process and which affect the land's value.
Here, there is not a sufficiently direct connection between the condition asserted by the applicant - the lost development potential of the retained land - and the resumption process. The Court cannot assume a higher development potential as a basis for awarding compensation when a development application for the additional units was never lodged and where there is no evidence before the Court that it was likely to have been approved . (emphasis added)
22 The severance case was based upon the evidence of the appellant's valuer, Mr John Robertson. In his valuation report he argued that the taking of the resumed land severed the lands and reduced the value of the retained land. In para 15.14 of his report he stated that if the resumed land had not been severed from the retained land, the owner would have had the opportunity to develop 292 units on the combined land. That is 88 units on the resumed land (the Twibill concept) and 204 on the retained land. This last figure is made up of 164 units approved in 1984 plus 40 additional units on the retained land. The figure of 292 units resulted from a mathematical calculation of one unit per 100m2 of site area provided under the Bankstown Planning Scheme Ordinance, (cl 62(3)).
23 The complaint made by the appellant is that his Honour did not deal with its alternative severance claim of the loss of development potential for 40 additional units on the retained land.
24 Mr Robertson's report stated that:
The owner has lost the development potential of 40 units which could have been accommodated on the upper level had the land not been designated for County Open Space.
25 The valuer assessed this loss of 40 units at $1,680,000 or $1,400,000 depending on a unit value assigned of either $42,000 or $35,000.
26 In his report in chief, Mr Minnaard, the appellant's planner, did not refer to any suggestion that the resumption caused a potential loss in the development of 40 additional units on the retained land, or for that matter, to any other severance claim.
27 Nor was there any direct mention of the loss of the potential to develop an additional 40 units on the retained land in Mr Minnaard's lengthy report in reply. At the very end of this report, the planner mentions (para 10.11) that a density of 1 unit per 100 sq m of site area would have meant that it would have been possible to provide up to an additional 132 units. That is, one assumes, the 88 units in the Twibill concept plan and 40 additional units on the retained land, although there is a discrepancy of 4 units which may be explained by the 1992 modification.
28 In para 10.12 of the report Mr Minnaard said that if a development application in the form of the Twibill plan had been before the Council in 1984, he as the then Chief Town Planner of the Council, would have recommended approval. Again, this is a reference to Twibill's concept plan of 88 units on the resumed land.
29 The last paragraph of Mr Minnaard's report in reply (10.14) deals with 'the same application' as at the date of the compulsory acquisition in 1995, viz a hypothetical application to approve 88 units on the resumed land, and states that he would have supported it.
30 Mr Minnaard then adds a final sentence:
I also consider that, due to the unit entitlement possible for the site that Council would also have considered allowing the additional entitlement added to the existing development above the escarpment. (emphasis added)
31 A number of observations may be made about this sentence. First, it was the only town planning evidence adduced on the question of additional units on the retained land. Second, Mr Minnaard refers to the possible unit entitlement wholly on the basis of the theoretical maximum mathematical entitlement under the planning scheme. Third, he says that having regard to the arithmetic, 'Council would also have considered' allowing the expansion of the existing development. No specific number of units is mentioned.
32 The appellant accepts that this material (Mr Robertson and Mr Minnaard) is the sum total of the evidence called by it to support the severance claim. Mr Minnaard was not cross-examined on the part of his report in reply which has been referred to above.
33 We have been referred to the written submissions of counsel for the appellant at the trial, in particular to page 22. His Honour's judgment closely followed the wording of the written submissions. Speaking for myself, it does not leap out of the page that a separate severance claim was being put forward in relation to 40 additional units lost on the retained land.
34 Counsel for the appellant returned to the matter in his oral address at the trial. At pp 1116 - 1117 of the transcript, Mr Webster referred to the lost development rights of 128 units. In this submission, counsel did refer to his client losing the benefit of being able to develop 'the top part of the land for the additional units'. He added, however, that just how this would have been achieved was 'difficult to imagine'.
35 This last comment was clearly appropriate given that there was no plan before the court as to how the existing approved development on the retained land would have been able to be re-designed to accommodate an additional 40 units. Forty units were still to be erected on the periphery of the residential land and 40 additional units would have to be added to this part of the uncompleted development. Thus a new development application would have had to have been lodged in 1995 for 80 units on the remainder of the retained land where stages 5 and 6 of the 1984 development approval were yet to be constructed. About this scenario there was no town planning evidence whatsoever. No evidence of how it could be achieved or whether there was any likelihood of it being approved. The town planning evidence from Mr Minnaard provided no support for the proposition, except perhaps on a simple arithmetic basis. In any event, the highest his evidence reached was that the Council 'would have considered' allowing the construction of additional units to the existing development, not that they would have been likely to approve an additional 40 units. It is unsurprising that the respondent chose not to cross-examine Mr Minnaard on what appeared to be little more than a throwaway comment at the end of a lengthy report in reply. Mr Robertson, of course, is a qualified valuer and his evidence provides no town planning opinion.
36 In so far as Sheahan J rejected the severance claim regarding the 1984 situation, 128 units (that is 88 plus 40), his Honour's conclusion is unassailable as involving no error of law. This leaves the severance claim of 40 lost units on the retained land. But the 40 units were included in the 128 unit submission rejected by his Honour.
37 In this respect, his Honour's notation of the concession by counsel that 'a density to comply with this criteria on the retained land would have been difficult to justify' speaks volumes as to the likelihood of approval being forthcoming. The fact of the matter is that the appellant never made any application for additional units on the retained land and there was no evidence that if it had, it was likely to have been approved. As I have said, Mr Minnaard's evidence provides no assistance in this regard. It may also be noted that notwithstanding that 160 units were approved in 1984 on the retained land (plus an extra four in 1992) only 124 had been built by 1995. This makes it wholly unlikely that an application for additional units would have been made in 1995, let alone approved.
38 Notwithstanding the perhaps elliptical reasons given by his Honour on the severance claim, promoted I think by the somewhat confused nature of the appellant's submission and the dearth of relevant evidence, his Honour's conclusion was open. His Honour was entitled, as regards the claim for the lost development potential for 40 units on the retained land, to find that there was no sufficient connection between it and the resumption process. His Honour was also entitled to conclude that the court was unable to assume a higher development potential when no application for additional units had been lodged and when there was no evidence that any such application was likely to be approved. The first proposition is undoubtedly correct. The second proposition was one which was open to his Honour. Indeed, it was probably the only conclusion which was open. That is, I think, an end of the matter. Mr Minnaard's evidence, referred to earlier, provides no evidence to the contrary.
39 Nor do I think that any inference favourable to the appellant on this issue can be drawn from his Honour's earlier acceptance of Mr Minnaard's opinion that the constraints on development on the resumed land would not preclude Council from approving the hypothetical development. This was a reference to Scenario 2, being the potential in 1995 for approval to extend the existing village onto the resumed land by the addition of 88 units thereon. It was not a reference to an additional 40 units on the retained land promoted in the severance claim. Mr Minnaard's evidence in this regard was directed to the earlier issue of the highest and best use from the perception of a hypothetical purchaser.
40 In any event, the crucial findings of his Honour are findings of fact and it is difficult to see how they can be transformed into questions of law.
41 I would reject the grounds of appeal going to severance.