[165] I have held that there is betterment to the Macquarie Centre in the amount of $15 million under s 55(f). I have also held that the introduction of controlled parking would not give rise to a reduction in value of the Macquarie Centre, also under s 55(f). I have held that market value is approximately $1,115,000 under s 55(a). I would ask that the parties provide an exact figure shortly. As betterment clearly exceeds the market value and disturbance agreed of $5,745,352 there is no compensation payable to AMP under the provisions of the Just Terms Act for this compulsory acquisition claim. I will reserve costs.
57 Mr Craig submitted that this approach gave no work to s 54(1). He submitted that the case of Brell v Penrith City Council (1965) 11 LGRA 156 was distinguishable, because the applicable legislative provision there was that "the court … shall … give effect to, by way of set-off or abatement, any enhancement in the value" of the other land. He submitted that the decision of the Court of Appeal in Mir Bros Unit Constructions Pty Ltd v Road and Traffic Authority of New South Wales [2006] NSWCA 314, given after the decision of the primary judge, although it dismissed an appeal from the decision referred to by the primary judge, supported a more flexible approach. Such an approach was also supported by Leichhardt Municipal Council v Roads and Traffic Authority of New South Wales [2006] NSWCA 353, 149 LGERA 439 at [37]-[41]. Mr Craig also referred to Walker Corporation Pty Limited v Sydney Harbour Foreshore Authority [2008] HCA 5; (2008) 82 ALJR 489 at [29], [35].
58 Mr Craig submitted, in circumstances where AMP was compelled to spend over $5.7 million in constructing ramps, it could not be considered as justly compensating AMP that it receive nothing, because of an extremely uncertain benefit which it might receive sometime in the future. Also, because of s 3(1)(a) and s 10(1)(a) of the Just Terms Act, the market value of the acquired land must be seen as the bare minimum that AMP should receive. Mr Craig submitted that there was an error by the primary judge in failing to address these considerations.
59 Mr Craig also submitted that there was no reasonable possibility that the case would have been conducted differently below, had this point been taken. It was open on the pleadings, and questions of uncertainty and futurity of the betterment were fully explored in the evidence.
60 Mr Hale submitted that AMP was bound by its conduct of the hearing, and that Coulton v Holcombe applied. Had this matter been in issue, Transport may not have consented to assessment of disturbance at the $5.7 million figure, and may have raised the question of whether the expenditure produced ramps which increased the value of the property, as compared with the previous ramps. Further, had AMP sought to have the increased value under s 55(f) disregarded or discounted because of uncertainty and/or futurity, that issue could have been squarely addressed, and it was not.
61 Mr Hale submitted that it could not be said there was an error of law, where the question had not been raised below. In any event, there was no error of law. Although Mir did not endorse a purely mathematical approach to the various elements of s 55, it accepted the so-called "before and after" approach, which would have the same effect in the present case.
62 In my opinion, s 3(a) of the Just Terms Act is important here. One object of the Just Terms Act is to guarantee that compensation be not less than the market value of the acquired land (unaffected by the proposal), that is, the element of compensation provided by s 55(a). Section 10(1)(a) authorises the giving of a notice, stating that the Just Terms Act does guarantee this. Although this notice is not given in connection with actual negotiations for compensation or proceedings in which compensation is assessed, and although it cannot give rise to a civil cause of action (s 10(3)), it is plainly intended that the notice be truthful and not misleading. In my opinion, these provisions disclose a clear legislative intention that compensation be no less than that provided by s 55(a), even if there is "betterment" under s 55(f) that exceeds the other elements in s 55.
63 I see this as consistent with and supported by s 54(1). Where land is compulsorily acquired, it seems to me just that the acquiring authority pay at least the market value of that land (unaffected by the proposal), even if the person from whom the land is acquired owns adjoining land which is increased in value by the proposal, and even if this increase is greater than the market value of the acquired land. Other persons owning land in the area may benefit equally or more from the proposal; so it seems to me unjust that the acquiring authority should get the acquired land for nothing, and that the person whose land is acquired should get nothing for it, just because of a benefit that may be shared by others. Thus a lower limit of the market value (unaffected by the proposal) seems just; and this is what s 3(a) and s 10 indicate is to be guaranteed.
64 In my opinion, this is not inconsistent with Brell. Whereas s 55 merely requires the Court to have regard only to six matters, including "betterment" under s 55(f), the provision applicable in Brell explicitly required that betterment be given effect to by way of set-off for abatement.
65 There is tension between the view I am suggesting and the "before and after" method of ascertaining compensation, which is sometimes adopted when what is resumed is part of a larger parcel of land owned by the person entitled to compensation. This method takes the value of the whole parcel immediately prior to acquisition (unaffected by the proposal) and subtracts the value, immediately after the acquisition, of what the person is left with (affected by the proposal); and this gives a figure which takes account of the elements of s 55(a), s 55(c) and s 55(f). If it so happens that the "after" value is more than the "before" value, because of "betterment", then the compensation so calculated will be Nil.
66 The "before and after" method was adopted in Mir, and approved by the Court of Appeal in that case. However, Mir did not suggest that the "before and after" method is to be adopted in all cases; and there is no authority to that effect.
67 Mir itself was a case where the approach I am considering could have been adopted, with possibly a more favourable result to the claimant. In Mir, the resumed land had an area of 1.844 hectares, and originally formed part of a larger parcel with a total area of 4.07 hectares. The valuer for the claimant and the valuer for the acquiring authority both agreed that the "before and after" method was appropriate; but the valuer for the acquiring authority expressed the opinion that the value per unit area of the 2.253 hectares with which the claimant was left was, by reason of its smaller area, five per cent more than that of the original 4.097 hectares, and the trial judge accepted that evidence. In the result, compensation for the land acquired turned out to be at a rate per unit area even lower than that of the original parcel, although on evidence accepted by the primary judge it would have been about five per cent more if it had been valued separately.
68 In his judgment in Mir ([2006] NSWCA 314 at [58]-[60]) Spigelman CJ (with whom Handley JA agreed and Tobias JA generally agreed) said this:
[58] By its nature the method encompasses a number of the matters expressly listed in s 55 including market value, loss attributable to severance and the increase or decrease due to the carrying out or proposal to carry out the public purpose. The before and after method is particularly useful in circumstances where the acquired land is difficult to value directly by reason, for example, that it is a non-marketable parcel. It may be preferable, where acquired land can be directly valued, as appears to have been the case in the present proceedings, to do so rather than to adopt the before and after method. Nevertheless, that was not the approach adopted in the present proceedings by either party. It is not appropriate for this Court to reject a methodology that may or may not have been chosen deliberately because of some synergy amongst the different heads of compensation in s 55.