[2025] QCAT 532
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-12-16
Original judgment source is linked above.
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
P Somers instructed by Stephen Rudz & Associates Lawyers
Each party usually bears own costs
Other than as provided under this Act or an enabling Act, each party to a proceeding must bear the party's own costs for the proceeding.
(1) The tribunal may make an order requiring a party to a proceeding to pay all or a stated part of the costs of another party to the proceeding if the tribunal considers the interests of justice require it to make the order.
(2) ...
(3) In deciding whether to award costs under subsection (1) or (2) the tribunal may have regard to the following -
(a) whether a party to a proceeding is acting in a way that unnecessarily disadvantages another party to the proceeding, including as mentioned in section 48(1)(a) to (g);
(b) the nature and complexity of the dispute the subject of the proceeding;
(c) the relative strengths of the claims made by each of the parties to the proceeding;
(d) for a proceeding for the review of a reviewable decision -
(i) whether the applicant was afforded natural justice by the decisionmaker for the decision; and
(ii) whether the applicant genuinely attempted to enable and help the decision-maker to make the decision on the merits;
(e) the financial circumstances of the parties to the proceeding;
(f) anything else the tribunal considers relevant.
(1) If the tribunal makes a costs order under this Act or an enabling Act, the tribunal must fix the costs if possible.
(2) If it is not possible to fix the costs having regard to the nature of the proceeding, the tribunal may make an order requiring that the costs be assessed under the rules.
(3) The rules may provide that costs must be assessed by reference to a scale under the rules applying to a court.
Having regard to the objects of the QCAT Act, the discretion to fix costs under s107 is an extremely wide one and is to be exercised robustly.
[33] In these circumstances, I consider it was not appropriate to criticise the [Commission] for being partisan. It was appropriate for it to be defending its decision, since failure to do so would result in its liability to the [homeowners] under the scheme. The builder had an interest in the outcome, because of the existence of a statutory indemnity provided by the QBCC Act s 71, and was therefore properly joined as a party, but in substance this was a fight between an insured and an insurer as to liability under the scheme. ...
...
[68] As I have indicated, although this was in form a review of an administrative decision, I regard it as in substance a commercial matter, namely a claim for assistance under the statutory insurance scheme. Although the quantum of the assistance was not in issue, so that the outcome was not a decision that the appellants be paid a specific sum, their success established an entitlement to receive the amount of assistance properly payable under the terms of the scheme. That gives the matter a commercial element.
[4] ... In deciding whether the interests of justice require me to make an order that the builder pay the [homeowner's] costs I need to consider all the circumstances, but in particular I need to understand the commercial undercurrents in the review for the parties to the costs application, the merits of the review and of the positions taken by the parties in the various issues, and the reasonable expectations of those parties when they made decisions about the review. I need to consider whether the [homeowners] achieved success in the review and if so, whether that success would be eroded if a costs order were not made.
...
[11] When deciding whether the interests of justice require the tribunal to make a costs order there are various factors which can be considered. Some of these are in sections 102(3)(a) to (f) but others come from case law. The various factors identifiable in this way are whether the success of the costs application would be eroded when it was reasonably necessary to be legally represented to achieve that success and whether there are any countervailing considerations, the nature and complexity of the dispute the subject of the proceeding, whether there was a commercial element in the proceedings, the fact that the tribunal gave leave to be legally represented (or lack of such leave), the 'chilling effect' of costs orders on statutory bodies and review applicants (and effect on access to justice), the reasonable expectations of the parties with respect to costs, the aims and objects of the QCAT Act, whether a party to a proceeding acted in a way that unnecessarily disadvantaged another party to the proceeding including as mentioned in section 48(1)(a) to (g), the relative strengths of the claims made by each of the parties to the proceeding, in reviews whether the applicant was afforded natural justice by the decision maker and whether the applicant genuinely attempted to help the decision maker in making the decision on the merits, the financial circumstances of the parties to the proceeding, and anything else the tribunal considers relevant.
(a) eight directions to rectify, referring to multiple items of complaint;
(b) three notices that work had not been satisfactorily rectified; and
(c) various scopes of works under the statutory insurance scheme;
(d) other decisions relevant to these proceedings.
Do the interests of justice require an order for costs to be made in favour of the builder?
(a) by having to prepare for issues which should never have been in contest, i.e.:
(i) by prosecuting GAR617-21 up to the eve of the hearing;
(ii) by not conceding that seven items of work had been satisfactorily rectified until invited to do so by the tribunal;
(b) by altering its approach to issues which were the subject of expert engineering evidence;
(c) by assessing the building work based on deemed to satisfy, not performance requirements, of the National Construction Code.
(a) non-compliance, or late compliance, with many directions to provide evidence;
(b) the very late delivery of the expert report by Mr Fox on the last business day before the hearing was to commence;
(c) late statements from lay witnesses, which it submits were delivered to shore up gaps in material previously filed highlighted in the objections to evidence.
(a) the builder's ill-health;
(b) the terminal cancer diagnosis of Mr Bowman's brother, requiring Mr Bowman to focus on his brother, not these proceedings;
(c) the challenges faced by Mr Rudz, who is a sole practitioner;
(d) actions by the QBCC which resulted in hardship to the builder;
(e) Mr Fox's cataract operation, making it difficult for him to review material;
(f) late provision of statements from the QBCC;
(g) challenges faced by the builder in funding his solicitor, counsel and Mr Fox.
Relative strengths of the claims made by each of the parties to the proceeding
(a) The builder was directed to repair a dent in a roof sheet on the rear deck roof. The repair was done. It was so well done that when the QBCC inspector inspected the rectification work on 6 January 2021 he concluded that the sheet had been replaced.[20] The homeowners did not share the inspector's view about the quality of the initial repair. They thought it was 'a dodgy patch job'.[21]
(b) The homeowners made a fresh complaint about the roof sheets. A QBCC officer carried out an inspection on 6 April 2021. He observed kinks in one sheet and another sheet that had signs of corrosion and rusting.[22] Mr Bowman (who attended the site because the homeowners would not permit the builder to be present) inspected the whole of the rear deck roof. He did not observe any corrosion.[23] I resolved the conflict in the evidence by preferring contemporaneous evidence which did not support a finding that there was visible corrosion in April 2021.[24]
(c) On 20 September 2021 the homeowners requested an internal review of initial scope of works, asking that the scope be amended to include replacement of roof panels that had corroded due to poor quality rectification work. They submitted that the rusting roof should have been classified as a structural defect as the rust would affect the durability and strength of the roof over time.[25] (This was the only basis upon which they could recover under the statutory insurance scheme.) Initially their request was rejected.[26]
(d) The homeowners persisted in their efforts to have two roof panels replaced under the statutory insurance scheme until they received advice from the QBCC that the question might be re-investigated while the rectification works were carried out.[27]
(e) Mrs Price complained to the QBCC that she had been fobbed off and the inspector did not want a bar to do with it.[28]
(f) The QBCC changed the classification of the defect in the corroded roof sheet from non-structural to structural, despite the absence of evidence that the roof could collapse if the rust continued, leaping from a failure to follow the manufacturer's recommendations for repair to the surface of the panel, to the likelihood of surface rust affecting the structural performance of the building.[29]
(g) The rectifying builder supplied a variation for the cost of removing and replacing a damaged insulated roof panel ($4,174.85).[30]
(h) None of the QBCC's witnesses challenged Mr Bowman's evidence that surface corrosion on a sandwich panel could not be a structural defect.[31]
(a) On 13 December 2019 the builder told the homeowner that the roof should have been designed as a skillion roof and was told that under no circumstances would any variation to the works be approved.[32]
(b) The QBCC inspector decided that rectification was required as the valley gutter had not been installed in accordance with industry standard SAA HB 39 or the NCC.[33]
(c) The builder argued that the design was reason for the water ingress that caused the initiating complaint that the roof valleys were not in accordance with NCC requirements.
(d) At the hearing the QBCC argued that the builder had a responsibility to raise concerns about design issues with relevant parties during the course of construction,[34] despite having evidence that the builder told the owner about the problem on 13 December 2019.
(e) The inadequacy of the original design was also identified by the rectifying builder in 2021.
(f) The experts agreed that the original design was inadequate.[35]
Whether the builder was afforded natural justice by the decisionmaker for the decision
Whether the builder genuinely attempted to enable and help the decision-maker to make the decision on the merits
(a) in FY 2025/2026 the builder had one job valued at $25,000;
(b) in FY 2024/2025 the builder had one job valued at $60,000;
(c) in FY 2023/2024 the builder had three jobs valued at $978,000;
(d) in FY 2022/2023 the builder had one job valued at $465,872.91;
(e) in approval year 2024/2025 two claims were approved under the statutory insurance scheme totalling $400,000;
(f) in approval year 2023/2024 two claims were approved under the statutory insurance scheme totalling $98,404.55;
(g) in approval year 2021/2022 three claims were approved under the statutory insurance scheme totalling $75,441.90.
(a) to give a direction to rectify (GAR617-21, GAR055-23);
(b) that building work undertaken at the direction of the commission was not of a satisfactory standard (GAR255-21, GAR557-21, GAR631-23); and
(c) about the scope of works to be undertaken under the statutory insurance scheme to rectify tribunal work (GAR109-22).
[1] [2016] QCAT 111, [49].
[14] Manwin v Queensland Building Services Authority [2007] QDC 298, [16].
[36] Those criticisms have already been dealt with above.
[40] [2023] QCAT 360, [24].
O'Donnell
Queensland Building and Construction Commission [2025] QCAT 532
Cowen v Queensland Building and Construction Commission [2021] QCATA 103
Cruceru v Medical Board of Australia [2016] QCAT 111
Health Ombudsman v du Toit [2024] QCA 235
Marzini v Health Ombudsman (No. 4) [2020] QCAT 365
Rosecove Pty Ltd v Queensland Building and Construction Commission [2024] QCAT 520
Van Dorssen v Queensland Building and Construction Authority (No. 2) [2025] QCAT 140