[2022] VCAT 1086
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2022-09-16
Original judgment source is linked above.
(a) $2,175 in respect of shower base tiles defects; and
(b) $882 in respect of timber doors defects.
(a) Mr Mark Temming, building manager of the builder, by witness statements dated 22 June 2020 and 5 March 2021;
(b) Mr Danny Martin, dated 4 September 2017 in relation to defects; and
(c) Mr Andrew Maroun, a director of A&S Carpentry Pty Ltd, who provided quotations dated 26 February 2021 for the carrying out of work respectively set out in the Thorne report and the Love report.
Damages not only necessary, but also reasonable
...the respondent [owner is] entitled to have a building erected upon her land in accordance with the contract and the plan and specifications which formed part of it, and her damage is the loss she has sustained by the failure of the appellant [builder] to perform his obligations to her. This loss cannot be measured by comparing the value of the building which has been erected with the value it would have borne if erected in accordance with the contract; her loss can, prima facie, be measured only by ascertaining the amount required to rectify the defects complained of and so give to her the equivalent of a building on her land which is substantially in accordance with the contract.[5]
The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt. No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of demolishing the walls and re-erecting them in second-hand bricks. In such circumstances the work of demolition and re-erection would be quite unreasonable or it would, to use a term current in the United States, constitute "economic waste"...We prefer, however, to think that the building owner's right to undertake remedial works at the expense of a builder is not subject to any limit other than is to be found in the expressions "necessary" and "reasonable", for the expression "economic waste" appears to us to go too far and would deny to a building owner the right to demolish a structure which, though satisfactory as a structure of a particular type, is quite different in character from that called for by the contract. Many examples may, of course, be given of remedial work, which though necessary to produce conformity would not constitute a reasonable method of dealing with the situation and in such cases the true measure of the building owner's loss will be the diminution in value, if any, produced by the departure from the plans and specifications or by the defective workmanship or materials. As to what remedial work are both "necessary and "reasonable" in any particular case is a question of fact (emphasis added).[6]
Now, it may be that, viewed objectively, it is not to the plaintiff's financial advantage to be supplied with the article or service which he has stipulated. It may be that another person might say that what the plaintiff has stipulated for will not serve his commercial interests so well as some other scheme or course of action. And that may be quite right. But that, surely, must be for the plaintiff to judge. Pacta sunt servanda. If [a party] contracts for the supply of that which he thinks serves his interests, be they commercial, aesthetic or merely eccentric, then if that which is contracted for is not supplied by the other contracting party I do not see why, in principle, he should not be compensated by being provided with the cost of supplying it through someone else or in a different way, subject to the proviso, of course, that he is seeking compensation for a genuine loss and not merely using a technical breach to secure an uncovenanted profit (emphasis added).[9]
The trial judge made the following findings relevant to the appeal: (1) the pool as constructed was perfectly safe to dive into; (2) there was no evidence that the shortfall in depth had decreased the value of the pool; (3) the only practicable method of achieving a pool of the required depth would be to demolish the existing pool and reconstruct a new one at a cost of £21,560.00; (4) he was not satisfied that the [owner Mr Forsyth] intended to build a new pool at such a cost; (5) in addition such cost would be wholly disproportionate to the disadvantage of having a pool of a depth of only 6 feet as opposed to 7 feet 6 inches, and it would therefore be unreasonable to carry out the works (I refer to these matters as the "the Ruxley considerations").[11]
Damages are designed to compensate for an established loss and not to provide a gratuitous benefit to the aggrieved party, from which it follows that the reasonableness of an award of damages is to be linked directly to the loss sustained. If it is unreasonable in a particular case to award the cost of reinstatement it must be because the loss sustained does not extend to the need to reinstate. A failure to achieve the precise contractual objective does not necessarily result in the loss which is occasioned by a total failure. This was recognised by the High Court of Australia in the passage in _Bellgrove v Eldridge..._where it was stated that the cost of reinstatement work subject to the qualification of reasonableness was the extent of the loss, thereby treating reasonableness as a factor to be considered in determining what was that loss rather than, as the respondents argued, merely a factor in determining which of [the] two alternative remedies [of remedial work, or diminution in value in Bellgrove] were appropriate for a loss once established. Further support for this view is to be found in the following passage in the judgment of Megarry V-C in Tito v Waddell (No 2)[12]:
'...if the plaintiff has suffered little or no monetary loss in the reduction of value of his land, and he has no intention of applying any damages towards carrying out the work contracted for, or its equivalent, I cannot see why he should recover the cost of doing work which will never be done. It would be a mere pretence to say that this cost was a loss and should be recoverable as damages.'
What constitutes the aggrieved party's loss is in every case a question of fact and degree. Where the contract breaker has entirely failed to achieve the contractual objective, it may not be difficult to conclude that the loss is the necessary cost of achieving that objective. Thus if a building is constructed so defectively that it is of no use for its designed purpose the owner may have little difficulty in establishing that his loss is the necessary cost of reconstructing. Furthermore, in taking reasonableness into account in determining the extent of loss it is reasonableness in relation to the particular contract and not at large. Accordingly, if I contracted for the erection of a folly in my garden which shortly thereafter suffered a total collapse it would be irrelevant to the determination of my loss to argue that the erection of such a folly which contributed nothing to the value of my house was a crazy thing to do. As Oliver J said in [Radford[13]]:
'If he contracts for the supply of that which he thinks serves his interests, be they commercial, aesthetic or merely eccentric, then if that which is contracted for is not supplied by the other contracting party I do not see why in principle, he should not be compensated by being provided with the cost of supplying it through someone else in a different way, subject to the proviso, of course, that he is seeking compensation for a genuine loss and not merely using a technical breach to secure an uncovenanted profit.'
However, where the contractual objective has been achieved to a substantial extent the position may be very different (emphasis added).[14]
[the Ruxley considerations are all set out, in terms, by the Court].
Their Lordships quoted and referred to various passages in Bellgrove v Eldridge and Radford v De Froberville without dissent. Although they reversed the Court of Appeal, in which the leading judgment, that of Staunton LJ, quoted various passages from Radford v De Froberville, they did not disagree with what those cases said as a matter of principle, and seemed to consider that their decision was consistent with the principles stated by Oliver J. The result at which their Lordships arrived is on one view inconsistent with those principles, but for present purposes it is sufficient to say that the facts of [Ruxley], which their Lordships evidently saw is quite exceptional, are plainly distinguishable from those of the present appeal.
(a) Where the work and materials are not in conformity with the contract, the prima facie measure of damages is the amount required to rectify the defects complained of and so give to the owner the equivalent of a building which is substantially in accordance with the contract (Bellgrove); > > (b) The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt (Bellgrove); > > (c) Reasonableness is a question of fact (Bellgrove) and the onus of proving unreasonableness so as to displace the prima facie measure is upon the builder. It is the builder who is seeking to displace the prima facie position (Tabcorp per Rares J.); > > (d) In considering whether it would be unreasonable to award the cost of rectification, the tribunal should consider all the circumstances of the case before it. The nature and significance of the breach should be looked at in terms of the bargain the parties had and the relative importance of the breach within the context of the contract as a whole. The decision in Ruxley suggests that account can be taken of the following matters at least: > > > (i) whether and to what extent the work, although not in conformity with the contract, is nonetheless serviceable; > > > > (ii) whether and to what extent the defect has affected the value of the work or the building as a whole; > > > > (iii) the cost of rectification, the proportion that the breach bears to the cost of rectification and whether the cost of rectification would be wholly disproportionate to the real damage suffered by reason of it;[20] > > > > (iv) the likelihood that, if rectification cost is awarded, the sum so ordered will actually be spent on rectification. Obviously, a successful plaintiff can spend his damages as he sees fit but this may be a useful indicator of whether the amount sought is greater than the real loss suffered.
Quite obviously, this list is by no means exhaustive. Other matters might be relevant according to the facts of the particular case. For example, the innocent party might have elected to accept the non-conforming work, whether by taking the benefit of it or otherwise; the owner might have waived the breach or so acted after becoming aware of the breach as to create an estoppel or to make rectification impracticable. There might also be many circumstances in which it could be argued that an award of rectification cost would give the innocent party an uncovenanted profit (Radford).
(e) If it would be unreasonable in the circumstances to award rectification cost, what damages will compensate the owner for the breach? Matters to be taken into account might include:
(i) the magnitude of the breach;
(ii) the significance of the breach to the owner;
(iii) whether the owner, after becoming aware of the breach, has acted unreasonably so as to make rectification more expensive;
(iv) whether and to what extent an owner might have accepted a benefit from the non-conforming work that should be taken into account;
(v) since the breach is not to be rectified, the reasonable cost of mitigating the effect of it;
(vi) compensation for any lesser appearance or functionality;
(vii) loss of amenity;
(viii) if it appeared likely that less than complete rectification would be undertaken, the cost of that.
Again, this is not intended to be an exhaustive list. It must not be forgotten that the object is to fully compensate the innocent party for the breach but not provide him with an "uncovenanted profit".
[249] While itself concerned with breach of a negative covenant, the decision of the High Court in Tabcorp Holdings confirmed the continued operation of the general rule in Bellgrove v Eldridge in cases involving defective building work. It also confirmed the qualification to that general rule.
[250] In so doing, the Court emphasised the primacy to be afforded to the plaintiff's performance interest in assessing damages for breach of contract. While identifying that this will result in the "unreasonableness" test underpinning the qualification to the general rule being satisfied and only "fairly exceptional" cases, the Court's reasons provide little guidance in relation to the application of the qualification.
...
[254] ...However, as the law currently stands, there has been no express identification in the Australian case law of any principal or policy underpinning the notion of unreasonableness. Certainly there has been no express adoption of the principal or policy preferable to fairness to the defendant. The matter has been largely left as a question of fact and degree to be determined by reference to the circumstances of the individual case.
[255] In determining what is a reasonable, the issue is one to be determined objectively, there being no suggestion that the plaintiff should be the arbiter of his or her reasonableness. However, the determination must take place in the context of the relevant contract, and hence by reference to the plaintiff's needs and desires reflected in the bargain he or she struck.
[256] Consistent with this general approach, my survey of the authorities has identified several matters that will be relevant in determining the reasonableness of the rectification costs claimed.
[257] The first [matter] is the proper identification of the plaintiff's performance interest; that is, the benefit bargain for. Often this will involve going behind express contractual standard or specification relied upon in order to determine whether the benefits sought to be achieved by the standard or specification was merely functional or economic in nature, or a matter of aesthetic choice or amenity on the part of the plaintiff. If the true contractual objective was purely functional or economic, then a departure from the contractual standard that does not compromise the functionality or value of the building work may not reasonably require an award of rectification damages to adequately protect the plaintiff's performance interest ["the Stone first consideration"].
[258] [His Honour here cite number of decisions in support of his propositions in paragraph [257]. Consistent with the propositions, his Honour pointed out that in Wilshee, the Court held that the contractual objective sought to be achieved by the specification of high-quality limestone was more than a merely functional one].
[259] The second matter is a consideration of the extent to which the defendant has, despite departure from the contractual standard, nevertheless achieved the contractual objective, and hence provided the plaintiff with the benefit he or she bargain for. In Tabcorp Holdings, the defendant completely ignored the plaintiff's contractual desire to control alterations to its premises. Similarly, in the incorrect paint colour and garden folly examples given in the authorities there was a complete failure to achieve the contractual objective. In Wilshee v Westcourt it was relevant that the defendant's use of inferior quality limestone involved a significant and substantial departure from the benefit contracted for by the plaintiff. On the other hand, in [Ruxley], the House of Lords was influenced by the relatively minor, if not technical, departure from the contractual objective and hence relatively minor benefit to the plaintiff from carrying out the rectification work proposed ["the Stone second consideration"].
[260] The third matter is any lack of proportionality between the proposed work and cost, and the benefit to be achieved by the plaintiff through this work. I do not understand the High Court's reasoning in Tabcorp Holdings to exclude consideration of any disproportion between the rectification work proposed and the benefit to be obtained...["the Stone third consideration"][25]
...
[263] Finally, it will be relevant to consider the plaintiff's intention and ability to carry out the rectification work. For the reasons explained in the authorities that I have summarised...these considerations are not usually decisively relevant in their own right. Rectification costs may be reasonable and recoverable even though plaintiff does not intend to, or is not able to, carry out the rectification work. One cannot say more without knowing the reasons why the plaintiff does not intend to, or is not able to, carry out the contemplated rectification works. Alternatively, rectification costs may be unreasonable and irrecoverable despite the plaintiff intending to, and being able to, carry out the contemplated rectification work. As the authorities make plain, the plaintiff's intention and ability to carry out the works are relevant only insofar as they shed light on the issue of the true nature of the plaintiff's loss, or the reasonableness or otherwise of the contemplated rectification works.["the Stone fourth consideration")
[265] ...I am not aware of any authority that has expressly taken into account the nature and quality of the defendant's breach. However, it may be that in cases where the defendant's breach is intentional, or profit driven, that the Court may be more reluctant to deprive the plaintiff of rectification damages designed to protect his or her performance interest. Indeed, the intentional and flagrant breach by the defendant in Tabcorp Holdings may have influenced the Court in that case and its preparedness to award rectification damages (emphases and definitions added for the purpose of these Reasons).
(a) Poor quality non-compliant bricklaying throughout (GST[29] Table 3.04)
General comment-some of the defects identified in the Thorne report were defects under AS3700-2001, but are not defects under AS3700-2011.
(b) Voids and holes in mortar, viewed from a normal standing position (GST 3.0).
No defect. Voids and holes in the mortar are minimal, and most have been addressed. Voids and holes are difficult to locate from a normal viewing position.
(c) 'Throughout the brickwork' over 2 mm deviation or 'step' of exposed masonry surfaces from adjacent masonry surfaces (GST3.04 F).
No defect. Was a defect under AS3700-2001, but is not defect under AS3700-2011.
(d) Mortar bed widths exceed 3 mm [taken to be a reference to 13 mm] 'in some wall sections' (GST 3.04 H).
No defect. Unable to locate any mortar bed joint exceeding 13 mm.
(e) Perpend widths exceed 8 mm 'in some wall sections' (GST 3.04 I and J).
No defect. Perpends exceeding 8 mm was a defect under AS3700-2001, but is not defect under AS3700-2011 where perpends between 5mm and 30mm wide are allowed.
(f) Colour variations 'throughout brickwork' in mortar repairs do not match existing mortar colour (GST 3.05).
No defect. In some areas where brickwork appeared to have been replaced, a small change in mortar colour appears, which is unexceptional.
(g) Mortar smears on masonry facing visible 'throughout brickwork' (GST 3.07).
(h) Perpend alignment 'in some wall sections' exceeds the allowable 20 mm per 2 m of wall height.
No defect. Was a defect under AS3700-2001, but is not defect under AS3700-2011.
(a) $1,100 for the selected removal and replacement of about 100 bricks (upon which cost the experts agreed); and
(b) a full treatment of NAWKAW, a masonry staining technology designed to correct the appearance of faulty or mismatched bricks and mortar, at a cost of $8,294.40.[30]
(a) The plaster cornices are defective, because they deviate from a straight line greater than 4 mm over a length of 2 m and are visible from a normal viewing position (GST 9.17).
AS 2589 (2007) Part 4.2.2 and Table 4.2.2 specifies an allowance of 5 mm over 1.8 m.
Two cornices in the bedroom should be rectified together (even though one has a deviation no greater than 5 mm over 1.8 m) and one cornice in the kitchen should be rectified.
(b) Plaster ceiling in the garage has been adversely affected by a water leak during construction, with potential collapse possible.
Insufficient lead flashing installed in roof. Builder defect. Resulted in leak affecting the first 1200 mm wide section of plaster at front internal corner of garage. This section and cornice requires replacement.
(c) Ceiling plaster peaking or waviness and its jointing is visible from a normal viewing position (GST 9.18)
$14,160 for supply and installation of new plaster ceiling lining throughout dwelling, including metal battens, when cornice defects can also be rectified.
The alleged defects in the ceiling plaster is not apparent in a non-critical light.
Paintwork is defective if the application has blemishes such as paint runs, paint sags, wrinkling, dust, bare or starved painted areas, colour variations, surface cracks, irregular and coarse brush marks, sanding marks, blistering, non-uniformity of gloss level and other irregularities in the surface that are visible from a normal viewing position.
During my inspection I took special note of the painting of the dwelling. I noted five small defects to the whole of the internal of the dwelling and one defect to the alfresco area. To find these defects, I had to look extremely hard. There was no light used and the inspection was from a normal viewing position.
...The paintwork as a whole is exceptional and well above the requirements of AS 23112 most parts. There is a very small number of areas that could be considered as being outside... the Standard however, as stated they are limited.
Please note that [before my inspection on 6 November 2019, being the basis of my observations in the Thorne report] I [inspected] the dwelling on 9 October 2018 and had marked up the paintwork at that time with numerous blue tape markings. When I re-attended on 23 October [2018] I noted that all of my defects had been rectified.
... I noted a large amount of painting equipment in the garage with used trays that had dry paint in the same colour as the internal walls and ceilings. I also noted drop sheets that had drops of paint that were the same colour as the walls. Further, there were two large cans of wall paint which had been opened in the area noted in the garage that appeared to be the same colour as the wall paint.
When I was inside the dwelling, standing in the kitchen, I noted that the fridge wall have been painted in a manner that had half of the cornice covered in a different paint to that applied on all other parts. It is my... opinion that the homeowner may have repainted sections of the home at some stage from the time of taking the dwelling over to the time of this latest inspection.[34]
(a) alleged misalignment through the hinge lines of, and visible damage, marks and scratches to the cupboards forming the kitchen cabinetry;
(b) a cabinet door that is cut short; and
(c) replacement of an allegedly incorrect single pantry door for a double pantry door, thus creating separately accessible top and bottom pantry internal shelving.
Replace section of kitchen cabinets installed not as per plan. Replace damaged doors and panels. Replace previously poor fitting cabinet doors to balance gaps.
Bench tops, cabinet doors and drawer fronts
Unless otherwise specified, cabinet door and drawer fronts are defective if they are not aligned, or do not have consistent gaps between them at handover, and can be seen from a normal viewing position.
Where the time limit for defects in bench tops, cabinet drawers, drawer fronts and similar joinery is not documented, it is to be taken as six months from completion.
(a) the elevation described as '01 KITCHEN ELEVATION' in INTERNAL ELEVATIONS drawing A6.0 (showing the panty door from the front); and
(b) the elevation described as '02 KITCHEN ELEVATION' in INTERNAL ELEVATIONS drawing A6.0 (showing the pantry from the side)
show a double pantry door, as contended on behalf of the owners.
Cracked, pitted, chipped, scratched or loose tiles
Tiles are defective if they are correct, pitted, chipped, scratched or loose at handover.
After handover, tiles are defective where the builder's workmanship causes details to become cracked, pitted, chipped or loose within 24 months.
Alleged defect 7-structural support of the bath in bathroom 1
Bath installation has not [been] fully supported from underneath...the manufacturer's installation guide is to install a full bed of mortar below the bath...[the builder] will need to rework this bath installation with the correct support"
Remove and replace architraves.
Remove and replace broken, damaged and scratched sliding door frames and fixed panels.
Remove and replace damaged and scratched aluminium framed window.
A & L Windows and Doors, Materials $14,254.00
Labour 4 people 16 hours @$66.00 per hour $4,224.00
$18,478.00
Remove and relay some sections of roof tiles. Repair pointing throughout.
Including safety rail hire.
2 people x 8 hrs @$66 per hour $1,056.00
Hire charge inc install and removal $440.00
$1,496.00
6.03 Roof Tiles
Roof tiles are defective if they do not conform to the manufacturer's sample. Irregularities in tiles are defects if they are visible from a normal viewing position at ground or upper floor level...
3.4 BEDDING AND POINTING
Bedding and pointing may be used to hold down, align, weatherproof, infill, and decorate the verge, eaves and junction of tiles and accessories. Where bedding and pointing is used, all mortar used shall be in accordance with Clause 2.3.
NOTES:
Roof tiles are not sitting flat in some areas, ridge and hip pointing , finish, has visible cracks throughout. Some tile relaying and pointing repairs required.
Repair/re rendering as required. Repair to front letter box.
Min charge 10 sqm @ $88 per sqm $880.00
Scaffold hire inc delivery and pick up $260.00
$1,140.00
...there is [within the meaning of the GST paragraph 9.04] cracking and other blemishes in rendered or hard plastered surfaces on masonry substrate. Cracking, blemishes and poor quality finished (sic) noted from the normal viewing position.
Permanent staining note throughout carpet.
When viewed from normal viewing position.
Carpet replacement required.
Bed one, Bed two, Bed three, Bed four, Sitting room.
Heating system not installed as per specifications.
Add additional zone controllers.
Add additional outlet.
Refer to sheet A5.0 and Sales Quote page 3
Heating zoned areas (zone 1 to the bedrooms and zone 2 to the living areas)
2 additional outlets have been added, 1 to the living room and 1 to the Study...
Provide Site Cut and fill not exceeding 300mm overall with excess soil spread or stockpiled on site.
Liability of the builder, as determined or agreed.
[3] Robinson v Harman (1848) 1 Ex Rep 850.
[7] Any exclusion of the right of the builder to contend, as it does here, here that certain of the damages claimed by the owners are not necessary and reasonable would appear to have been required to be expressly stated in clause 44 of the building contract: Gilbert-Ash Northern Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689.
[12] [1977] 3 All ER 129 at 316.
[15] [2009] HCA 8, Judgment 12 February 2009.
[18] See, for example Doyle J in Stone v Chappel (infra) at [261]-[262].
[20] It will be seen that Senior Member Walker's observations in paragraph 165 (d)(i)-(iv) of Clarendon Homes were indeed harbingers of the same considerations considered by Doyle J to be relevant to the question of assessing whether claimed rectification costs are unreasonable; see Stone v Chappel [2017] SASCFC 72 at [256]- [263], upon which his Honour provided a fuller exemplification (see further below).
[21] [2009] WASCA 87, Judgment 18 May 2009.
[22] Ibid. Taken from the judgment at [67].
[24] Per Doyle J (with Kourakis CJ(in part) and Hinton J agreeing)
[25] His Honour then cited a number of decisions of the New South Wales Court of Appeal where the issue of disproportion was considered relevant.
[26] See also the similar analysis of Kourakis CJ in Stone v Chappel (ibid) at [28]-[71].
[28] See Stone v Chappel (ibid) per Doyle J at [263] quoted above.
[29] Guide to Standards and Tolerances (2015), issued by Victorian Building Authority (the "GST 2015").
[30] A NAWKAW total treatment would cost $10,368, but the owners seek only 80% of this amount, being the amount of affected brickwork as a proportion of the whole.
[32] See GST 2015 page 14 and AS 2589.1 (1997) (superseded in other respects) Notes to Section 6 "Levels of Finish".
[33] Such as the finish required to be provided here-see page 19 of the Specification forming part of the building contract.
[35] Mooney v Hery Boot Construction Ltd (1966) 80 BLR 66 at 83; Bovis Lend Lease Ltd v Cofely Engineering Services [2009] EWHC 1120 (TCC) at [23(a) and [26]. See also Construction Law 3rd ed 2020 [3.177].
[36] See s 43(3) Domestic Building Contracts Act 1985 and Clarendon Homes (ibid) at [104].
[37] See page 46 of the Love report, at TB 136.
[39] I accept the builder's evidence that Revision T of Drawing A1.1 SITE PLAN did not specify a retaining wall (unlike Revision F that formed part of the building contract).
Nostra Homes and Developments Pty Ltd
Komuves
Bellgrove v Eldridge [1954] HCA 36; [1954] 90 CLR 613; Radford v De Froberville [1978] 1 All ER 33; Ruxley Electronics and Construction v Forsyth [1996] AC 344; Tabcorp Holdings Ltd v Bowen Investment Pty Ltd [2009] HCA 8; Clarendon Homes v Zalega [2010] VCAT 1202 Wilshee v Westcourt Limited [2009] WASCA 87; Stone v Chappel [2017] SASCFC 72 considered.