Domestic Building Contract Act 1995; owner terminated major domestic building contract; dispute as to whether the contract was terminated wrongfully; consideration of the impact of the determination of this issue on the assessment of damages; declaration made that the termination of the contract was wrongful and that damages regarding the cost of rectifying or completing the works under the contract are to be assessed on the basis of what the cost would have been to the builder at the time of termination of the contract.
Nerwa Constructions Pty Ltd v Koka (Building and Property) [2023] VCAT 1137
This determination concerns a preliminary issue, which is whether the respondent owner's termination of the contract was wrongful. The impact of the determination on the issue of damages is also considered.
The rule of the common law is, that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.[3]
19.4 If the Owner without reasonable cause does not allow the Builder the opportunity to return to the Land to make good and rectify any defects or does not provide reasonable access to the Builder to allow the Builder to do so, the Builder will only be liable to the Owner for the cost which the Builder would have incurred had the Builder been permitted to rectify the defect.
(a) although the contract was executed on 27 September 2018, work could not begin straight away because the building permit was not issued until 15 October 2018.[4]
(b) Mr Koka paid the builder that the deposit due under the contract in October 2018.[5]
(c) A progress claim in relation to the base stage was issued on or about 9 November 2018 and was paid within about 10 days.
(d) The frame stage invoice was issued on or about 4 December 2018 and this was paid within about a week.
(e) Or about 15 January 2019, the builder issued an invoice in relation to the lock-up stage. This was paid within nine days. [6]
(f) Or about 8 April 2019, the builder rendered an invoice in relation to the fixing stage in the sum of $90,750. Mr Koka failed to make payment.
THE OWNER'S POWER TERMINATE UNDER THE CONTRACT
20.1 Owner's right to serve notice of intention to terminate Contract
the Owner may give written notice by registered post to the Builder:
20.2 If Builder fails to remedy breach Owner may terminate Contract
If the Builder fails to remedy the breach or breaches of this Contract as stated in any notice served by the Owner under Clause 20.1 THEN the Owner may, without prejudice to any other rights or remedies, give further written notice by registered post to the Builder immediately terminating this Contract.
20.3 Owner may not terminate Contract in certain circumstances
The Owner may not terminate this Contract unreasonably or vexatiously or if the Owner is in substantial breach of this Contract.
CIRCUMSTANCES IN WHICH THE CONTRACT WAS TERMINATED
We understand that Nerwa issued the Fixing Stage Invoice to Mr Koka on or around 8 April 2019 (being the date of the invoice). We further understand that Nerwa is refusing to continue with the Works until Mr Koka has paid the Fixing Stage Invoice. It is Mr Koka's position that the Works performed by Nerwa at the Property, pursuant to the Contract, have not reached the fixing stage (or one of the earlier stages of construction provided under the Contract and section 40(1) of the Domestic Building Contracts Act 1995 (Vic)) because they are either incomplete or defective. To that end, Mr Koka refers to and relies on the Darbecca Report, which details some of the defective and incomplete Works that exist in the Property. By reason of the above, it is Mr Koka's position that Nerwa:
(e) had no entitlement to issue the Fixing Stage Invoice because the Works were incomplete or defective;
(f) has failed to diligently progress the Works;
(g) has unreasonably suspended the Works;
(h) has refused or persistently neglected to remedy the defective work so that, by its refusal or persistent neglect, the Works are adversely affected; or
(i) is unwilling to complete the Works.
Accordingly, unless Nerwa remedies the breaches of the Contract within 14 days, it is Mr Koka's Intention to terminate the Contract.
(a) Mr Koka confirmed the fixing stage had been completed via text message sent to the builder on the 11 April 2019 and the builder, relying on this advice, continued with the final stages of the works;
(b) Mr Koka had changed the building plans on a number of occasions, and details were given;
(c) On 24 April 2019, Mr Koka contacted the builder and asked for all works to be ceased until further notice;
(d) All items detailed in the First Darbecca Report had been attended to, save for the fireplace and walls, doors and plumbing which were changed by Mr Koka;
(e) The building permit had been issued on 16 October 2018, not 1 October 2018;
(f) Mr Koka was responsible for a delay in the building works as engineering approval was required to add an extra 200mm step down in the garage;
(g) Mr Koka had breached the contract on many occasions by inviting family, friends and children to the site;
(h) Mr Koka had requested that subcontractors cease and change the scope of their works without the knowledge of the builder;
(i) The builder was entitled to suspend the works pursuant to clause 16.1 of the contract;
(j) Mr Koka had yet to pay for the fixing stage despite all requirements having been met;
(k) Mr Koka had not yet made payment for all the changes he had requested;
(l) The builder was entitled to extensions of time in relation to delays caused to the building works due to Mr Koka changing his mind and Mr Koka's "independent works" causing further delays.
(a) had no entitlement to issue the fixing stage invoice because the works were incomplete or defective;
(b) had failed to diligently progress the works;
(c) had unreasonably suspended the works;
(d) had refused or persistently neglected to remedy the defective work so that, by its refusal or persistent neglect, the works were adversely affected; and/or
(e) was and remained unwilling to complete the Works.
As the builder had not remedied the breaches of the contract identified in the notice of intention to terminate within 14 days, Mr Koka terminated the contract. The letter went on to revoke the licence granted to the builder under clause 7.2 of the contract to enter the property, with immediate effect.
WAS THE TERMINATION OF THE CONTRACT WRONGFUL?
"fixing stage" means the stage when all internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards of a home are fitted and fixed in position.
In the present case, the processes in the building contract anticipate the likelihood of defective and incomplete work being found during the processes, and the possibility of differences of opinion between the builder and the owner about what is defective or incomplete work.
However, protections are provided. So long as the owner complies with their responsibilities under the processes, the builder must rectify the defects identified by the owner and the final claim is not payable until 7 business days after the builder gives notice that it has completed the listed defective or incomplete work. Further, neither party, by following the processes, concedes conclusiveness of, or admits the description of, the listed works. These matters do, therefore, anticipate that the processes themselves may give rise to disputes or leave some matters unresolved, even if the processes are followed.
The builder's submissions regarding the fixing stage payment
By 7 April 2019, everything for the fixing stage was finished except the toilets(Ayad had changed it three times) and some other basins he had agreed to bring. I had arranged for the plumber to attend site to install the remaining bathroom fixings, but Ayad didn't bring the rest of fittings. As a consequence, I paid the plumber in full as he sent three plumbers on Monday 7 April 2019 to finish all the works.
On 8 April 2019, I submitted a claim for the fixing stage of the works, as the fixing stage was effectively complete (but for items Ayad had prevented me from installing by failing to provide the required fixings).
The toilet, as I said was changed three times by Mr Koka changing his mind. So the toilet wasn't there to be put.[19]
Was the builder not entitled to submit a fixing stage invoice because of defects in the works?
(a) the vapour barrier had been allowed to fall below the finished ground level ('FGL');
(b) downpipes had been installed to most of the gutter pops, but some had come away from the pops or had been removed by trades, and some of the downpipes did not have the stormwater point available as yet;
(c) no articulation joints have been provided to the front face of the dwelling;
(d) the water lead in enter the dwelling at the base of the brick wall did not follow the recommended method of installation through the slab footing, exiting within the perimeter timber wall frame;
(e) there were areas around the dwelling with a non-compliant slope toward the slabs footing;
(f) perpends failed to meet the minimum requirements mandated by AS 3700 which calls for 10 mm, but allows maximums of 20 mm and minimums of 5 mm;
(g) there were some voids and numerous small holes in the finished faces of the mortar joints around the house and garage;
(h) there were numerous areas of the brickwork around the dwelling where mortar smears were evident;
(i) most of the articulation or control joints in the dwelling had non-compressive material (mortar) still in the joints;
(j) all external power points must be sealed to the top and sides of the connection to the brickwork, as per AS 3000, clause 1.7.1;
(k) the weep holes on the dwelling appear to have excess mortar to a number of areas;
(l) the dwelling's down pipe installation breaches the requirement of AS 3500.3 that a downpipe cannot be installed within 100 mm of an electrical cable;
(m) the builder is using black plastic flashing as a DPC;
(n) internal corners (of brickwork) were constructed with unnecessary straight joins;
(o) there are open concrete voids to the slab edge, showing exposed reinforcement bars;
(p) the brick overhang to the dwelling needs to be supported, as the BCA, part 3.2.2.7 calls for a maximum overhang of 15 mm and all areas exceeding 15 mm must be reworked and supported in accordance with AS 2870 prior to handover;
(q) the brickwork has a small number of bricks that are chipped in excess of a reasonable level;
(r) the Colorbond down pipes, fascia and gutter to the dwelling have been damaged during construction;
(s) a large number of roof tiles are sitting proud of the other tiles;
(t) the gutters all need to be fully cleaned;
(u) the valley iron tiles have not been cut straight as required by AS 2050, part 3.6;
(v) the dwelling is not watertight as flashings, infill panels over windows and cladding over the porch have not been installed:
(w) the fascia to the dwelling has damage to the coating;
(x) the roof tiles to the dwelling are presenting with damaged chipped sections which require cleaning or replacement prior to handover;
(y) the boundary garage wall will need to be reworked to include fire protection;
(z) The metal transfer flashings around the dwelling are showing fall backwards towards the wall frames;
(aa) all of the perimeter window and door architraves need to be gapped to the plaster as per the energy rating requirements and NCC 3.12.3.3;
(bb) all cabinet door margins and drawer fronts need to be reworked to ensure that all are aligned;
(cc) the shower wastes are presenting with an amount of builder's waste which must be removed to comply with AS 3500.2, part 4.3.1(g) before commissioning of the site;
(dd) there are a number of areas in the home that exceed the allowance of 4 mm tolerance over 2 mm;
(ee) the bath has been used as an on-site rubbish bin during construction and the internal surface will have to be polished to remove any scratches or indentations;
(ff) as per AS 3958.1, the cutting of tiles must be smooth and of an even width and some tiles will need to be reworked;
(gg) some of the bottom window reveals are too wide and present with significant fall back towards the window;
(hh) the insulation in the ceiling has not been completed and requires installation in accordance with AS 3999;
(ii) the approved plans showed a step down between the dwelling and the garage of 86 mm, but on site the step down is in excess of 300 mm;
(jj) associated rework will be required due to the additional site cut and step down to the garage and the builder must provide an engineer's design for waterproofing and drainage of the garage boundary wall;
(kk) a window in the corner of the master bedroom was not fitted in accordance with the plans;
(ll) a cavity sliding door to the pantry is missing;
(mm) there is a defect in the double wall in the bathroom;
(nn) the master bedroom doors are the wrong way around;
(oo) the spacing of the bathroom sinks requires correction;
(pp) the fireplace exhaust is in an incorrect location.
I was instructed to inspect the client's new home to write a report as to the overall installation of all items required to construct a new home to completion stage.[34]
Did the builder fail to diligently progress the Works?
Did the builder unreasonably suspend the works?
Good morning happy easter please stop don't do nothing in the house until I'll Bring the inspector call me when you have spare time please thank you. (Sic).[49]
Did the builder refuse or persistently neglect to remedy any defective work so that, by that refusal or persistent neglect, the works were adversely affected and/or was the builder unwilling and remained unwilling to complete the works?
Under AS 2124-1992 on substantial breach by the contractor, the principal is not entitled by the contract to immediately elect to terminate the contract or take the work out of the hands of the contractor. The right to take either course of action does not automatically follow failure to rectify the breach after the service of a notice. The contractor has the opportunity to influence the principal's choice about its response to its substantial breach by showing reasonable cause to the notice that the principal had served. The process affords to the contactor an opportunity to show cause why the principal should not exercise those rights at all.
Clause 44 does not contemplate that the contractor's response needs to be to rectify the breach that is the subject of the notice. The clause is primarily concerned with future performance, not rectification. AS 2124-1992 requires that the principal name expressly, or mention definitely, the alleged substantial breach. It does not require that the principal detail or particularise each matter constituting the default. The response expected is not necessarily an activity-based response, remediation within the time permitted, not less than 7 days. The clause contemplates that the notice will require the contractor's response in writing, at a place nominated by the notice and by a time and date specified by the notice. The process of showing cause under cl 44 requires communication, not necessarily just rectification.
it permitted the principal to serve a notice that it intended to determine the employment of the builder under the agreement unless the substantial breach specified in the notice was remedied in terms consistent with the contract within 10 days. The contract provided that the principal's notice specify and detail the default relied upon.
Here, the drafter of the notice has sought directly to provide details of the substantial breach by specific reference to other documents. It is not a requirement for validity that the notice be completely accurate in every particular. What is required is to convey what is amiss for the purposes of showing cause. While it might be prudent to annex or otherwise provide copies of documents that provide the particulars of the substantial breach, in my view incorporation of documents, properly identified by reference in the notice, is sufficient to unequivocally convey what the principal considers to be amiss and provide the opportunity intended by the contract for the contractor to show cause.
Plainly the requirement imposed by cl. 12. 01 that the notice must not only "specify" but also "detail the default relied on" was intended to ensure that the builder was adequately informed of the allegations of breach of contract made by the proprietor. It is only if the notice descends to such particularity that the builder could avail himself of the opportunity cl. 12.02 provides to remedy the default "in terms consistent with this Agreement" and avoid the proprietor's determining the contract, with all the serious consequences that step involves. Considerations of this sort mean that a notice is not effective as a cl. 12.01 notice unless the detail of the default is clearly identified. So the notice must be "unequivocal in order to convey what was amiss", ....[54]
The present notice does not clearly identify any document or other matter that might provide the detail the notice itself ignores. As it happens, the administration of this contract involved a substantial. number of complaints and disputes to which the general words of the letter might relate: ... Cl. 12.01 does not envisage that the builder can be required to pick and choose among unidentified site instructions, minutes of site meetings or conversations to which the letter could be referring. That letter is therefore not a notice which meets the requirements of cl. 12.01. Accordingly, it could not support the attempt in late September, 1989 to terminate the contract.
Was the builder unwilling to complete the works?
Did Mr Koka act unreasonably in issuing the notice of intention to terminate?
The Owner may not terminate this Contract unreasonably or vexatiously or is the Owner is a substantial breach of this Contract.[57]
Was Mr Koka himself in substantial breach of the contract at the time he issued the notice of intention to terminate?
Relevance of this finding on the assessment of damages
[1] The address has been withheld for privacy reasons.
[2] (2009) 83 ALJR 390; [2009] HCA 8, [13].
[3] [1848] EngR 135; (1848) 1 Exch 850 at 855 [154 ER 363 at 365].
[5] Mr Kasho in his witness statement, at [18], says this occurred on 30 October 2018, not on 1 October 2018 as alleged.
[6] The lock-up stage invoice dated 15 January 2019 is endorsed "Paid on 24/01/2019". See TB 647.
[16] Transcript ('TS') 14 August 2023 (14/8), (page) 89: (lines) 1-90:2.
[20] TS 16/8, 14: 19-2; 15: 7-11; 15: 15-19.
[26] TS 14/8, 94: 7-12; TS 16/8, 17: 29-18: 12.
[27] TS 16/8, 18: 11-12; and 18: 20-23.
[31] First Darbecca Report, TB 866, at Summary, page 2.
[32] This is contestable, as the builder disputes some of the defects.
[34] First Darbecca Report, under "Client Brief", TB 867.
[37] Builder's submissions on termination, [13].
[41] See the contract, at [15.1], TB 1733.
[42] An example of a notice of delay arising from variations is to be found in an email sent by Mr Kasho to Mr Koka on 17 January 2019, TB 638
[51] Mr Koka's submissions on termination, [13].
[53] Dixon J used (1991) 7 BCL 200 as the citation for White Industries. The case is also reported at [1990] QSC 010.
[59] Kasho witness statement, [38(b)], [14].
[61] In his witness statement, at [37] Mr Kasho says that Mr Koka "started going to site every day before going to work and complaining about things not being finished yet."
[63] Kasho witness statement, [38(a)]; contract specification, TB 537 at "HEATING AND COOLING, TB 540.
[65] Kasho witness statement, [38(c)].
[67] Ibid, [38(e)]; see also the letter at TB 670 from the kitchen cabinet maker Selwan Putrus dated 8 September 2021, confirming that Mr Ayad (Koka) had come to his factory and asked him to do a new design which was different to that on the architectural plans.
[68] Kasho witness statement, [38(f)].
Nerwa Constructions Pty Ltd
Koka
(2009) 83 ALJR 390