[2023] VCAT 912
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2023-08-09
Original judgment source is linked above.
Domestic building contract - Whether final payment due pursuant to the building contract - Whether building works had reached a sufficient state of completion - Incomplete and defective work - Progress payment stages and Final payment - Cardona v Brown [2012] VSCA 174; (2012) 35 VR 538 and Saath Pty Ltd v Seascape Constructions Pty Ltd & Anor [2021] VSC 358 applied.
Appliances not installed - Appliances held pending final payment - Order for installation made - Section 52(3)(h) of the Domestic Building Contracts Act 1995 (Vic).
Building contract fixed $250 per week liquidated damages for late completion - Owner's claim for delay damages capped by liquidated damages until termination - J-Corp Pty Ltd v Mladenis [2009] WASCA 157 and Hacer Group Pty Ltd v Euro Façade Tech Export Sdn Bhd [2022] VSC 373 applied.
"The Applicant (Metricon) concedes that to the extent that the installation and commission of appliances is a requirement for completion in accordance with s42 of the Domestic Building Contracts Act 1995 (Vic), the cooktop, fireplace, hot water service and rangehood have not been installed and commissioned by Metricon, and completion has therefore not been achieved".
Disputes identified by the joint report of the experts' conclave
"Agree liability." - the experts agreed on liability (whether or not item defective).
"Agree quantum" - the experts agreed quantum (if item found to be a defect).
"$ Claim Sherrard" - Mr Sherrard's estimate of the cost of rectification.
"$ Dispute" - Quantum for disputed eitems suggested by other experts.
Disputed liability items considered by the Tribunal
Item 2.2.1 - Garage roof sheeting has insufficient fall
• "SE corner outside Living (refer photos 6457 to 6458)
• South elevation outside study and kitchen (refer photos 6459 to 6461)
• West elevation outside Family (refer photos 6462 to 6466)".
These areas would "require demolition and reconstruction to achieve adequate drainage to the stormwater drains".
Items 3.2.1 - Vapour barrier, 3.2.2 - Slab short poured and 3.2.3 - Vapour shield
Item 3.2.4 - Colour and texture of concrete repair to SE corner at front of dwelling
Item 5.1-5.3 & 5.5-5.7- EPS (Expanded Polystyrene) cladding, installation and rendering; sundry issues
Render varies in colour and texture and poorly repaired
Unsealed underside of EPS bottom edge & flashing with render debris
"The EPS wall cladding measured for plumb and straight are defective. The defect - non compliant to plumbness and straight has been identified in the Blumson report. Measuring plumb and straight from a normal viewing position is not an acceptable recognised method of determining compliance. Mr Blumson has made no reference to the Guide to Standards and Tolerances for assessing the breaches in compliance. The installation of the cladding is required to meet the allowable tolerance of straight and plumb. The only method of rectification is removal of non-complying EPS installation, supply and install new, render to match existing. Description & observations: AS2 p42 & AS3 pp32-35; photos: AS2 p43 & AS3 pp36-37".
Items 6.1 - 6.3, 6.5 - Embedment and placement of stormwater pipes
"Preferred bedding materials are listed in AS/NZS 2566.2 as follows:
Suitable sand, free from rock or other hard or sharp objects that would be retained on a 13.2 mm sieve.
Crushed rock or gravel of approved grading up to a maximum size of 14 mm.
The excavated material may provide a suitable pipe underlay if it is free from rock or hard matter and broken up so that it contains no soil lumps having any dimension greater than 75 mm which would prevent adequate compaction of the bedding".
Item 7.1 - 7.7 - External wall tiling, adhesion and sealing
"Agreed defect. However, the lack of tile adhesion to the substrate and issue of the tiles not having been sealed to manufacturer's specification have not been investigated by Mr Blumson ... Description & observations: AS2 p48 AS3 p38".
"I have read over the PDFs you have sent of the Beaumonts catalogue, and having discussed with their state manager on site, they have advised the tiles are not to be sealed on the backs before laying as this would undermine the integrity of their adhesion. Beaumonts supply, install and warrant their own product and have advised the tiles were pre sealed before install on all edges and their face before being resealed".
"On 8 May 2020, ... Josh Taylor stated that he had read the Beaumont Tiles installation instructions that I had provided him and advised me that the basalt stone tiles to the front LHS Living room section had been presealed prior to installation".
a. there are deficiencies in the connections in the roof framing;
Items 9.2, 9.3 & 9.6 - Floor framing, Joist hanger installation, Balcony beams
Incorrect installation of floor joists and floor panels
Confirmation sought that cut-through timbers removed
Nail spacing and closeness to edge outside tolerance
Bracing connection to floors does not meet requirements
"There are a number of areas in the home that exceed the allowance of 4 mm tolerance over 2 m:
"In relation the above item 9.5 defects were observed. The defects observed were in relation to plaster lining exceeding tolerances in bow or plumb. The following areas were confirmed as defective by my measurements:
The defects observed are not necessarily present in the frame and can be rectified generally by reworking plaster lining and packing of wall frames where required as detailed in the attached costings for this item.
I note that the fire place walls were checked for bow and measured to be within allowable tolerances, i.e. not exceeding 5mm over 1.8m".
b. the absence of documentation of measurements of out of level areas;
d. whether the out of level areas can be rectified by fixing small areas;
e. whether the reasonable cost of rectification is $70,728.00 or $3,497.78.
I assume that the reference to the "joint inspection" is a reference to the view on 31 January 2023. Mr Radevich did not attend the view at the direction of the Tribunal. He was apparently there to assist Mr Sherrard. On that day, I observed Mr Radevich taking measurements, marking certain parts of the dwelling (including scratched windows) and spray-painting comments on the ground outside the dwelling. Mr Radevich was not asked to perform any tasks at the view by me or, I believe, by Mr Blumson. I did, however, request Mr Blumson to examine each of the scratched windows marked earlier by Mr Radevich;
At the view, I discussed with counsel and the experts what was expected at the view (to logically examine each of the matters listed in the Scott Schedule as defective). The initial task undertaken was to take levels. This was done at the direction of Mr Blumson and the agreed measurements, as shown by the laser equipment used, was agreed by the experts and recorded by Mr Blumson.
Later, during the view, measurements were also taken of levels of discrete areas in the rooms of the house by using an electronic digital level and packers. These measurements were the subject of discussion between the experts and recording by Mr Blumson.
During this process, I understood that Mr Sherrard was indicating points of significance, including areas where he had reported areas out of level.
I recall Mr Radevich taking measurements himself, separate to what was happening in the view. None of that work was directed by the Tribunal or, I believe, by Mr Blumson. I assumed that it was work carried out to assist Mr Sherrard, and at his direction. Mr Sherrard had the opportunity to raise the issues he wished at the view. Although Mr To's counsel, Mr Gray, was present for the whole of the view, his participation was largely as an observer and Mr Sherrard essentially had the conduct of the view on behalf of Mr To.
I was not aware that Mr Blumson intended to recheck "the areas marked by Sherrard's assistant, Mr Radevich" on a subsequent inspection. The need for at least one further inspection was contemplated by the Tribunal's orders dated 14 February 2023 to inspect the "plumbing defects" and "to discuss the appropriate modification of any works required to rectify defects at the property". The third visit to the property by Mr Blumson on 27 February 2023 was authorised by me;
Ground floor length: McMillan, Front entry to Fam Rm NW cnr -12 to +8; variation 20 (Surveyor, -15 to +10; variation 25).
Ground floor width: McMillan, Fam Rm mid S wall to Din Rm NW cnr -8 to -6; variation 2 (Surveyor, +10 to +5; variation 5).
First floor (length): McMillan, Leisure Rm NE cnr to BR1 NW cnr +15 to + 22; variation 7 (Surveyor, 103.905 to 103.895; variation 10).
First floor (width): McMillan, BR1 SW cnr to En suite NW cnr -15 to -16; variation 1 (Surveyor, 103.905 - 103.905; variation 0).
"11. The builder wrongly issued multiple lock-up stage invoices from 26 August 2019 and eventually issued a lockup invoice dated 11/10/19 and which was paid by the owner.
lock-up stage means the stage when a home's external wall cladding and roof covering is fixed, the flooring is laid and external doors and external windows are fixed (even if those doors or windows are only temporary);
fixing stage means the stage when all internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards of a home are fitted and fixed in position".
Item 28 - Bushfire Attack Level rating of 12.5 Report (STB91-94)
Item 29 Installation of appliances, fixtures and fittings including HWS
"14 The builder wrongly issued final stage invoices on 10/6/20 and 17/6/20 when the works were not complete".
"14 It denies paragraph 14 and says further and in the alternative that the only works which were not complete was the installation of appliances at 69 Bayview Road, Officer, Victoria (the Property).
Metricon refers to the Joint Report of Alan Sherrard, Bob Lorich, Robert Quick & Sunny Blumson dated 22 May 2023 (the Joint Report). The items expressed as defects in the Joint Report by Mr Blumson, as well as the non-installation of appliances, were trivial failures or alternatively failures borne of impracticalities which do not preclude effective and satisfactory completion. As expressed by Mr Blumson (pg 62), 'It is standard practice for builders to hold delivery of such items until same day as final payment is receive and keys are handed over. This is to avoid the possibility of theft'".
"22. As a consequence of the builder failing to repair the defects and complete the incomplete items as described in the reports of the owner's experts the final payment did not ever become due to the builder under the building contract".
Mr To's counterclaim accepting Metricon's repudiation of the building contract
"24. The owner in his Points of Counterclaim dated 16 July 2021 filed and served in this proceeding at paragraph 12 the owner described the builder's repudiation and accepted the repudiation as terminating the contract".
Provisions of the building contract relevant to "completion"
Metricon's obligations to complete the building works
"The Applicant (Metricon) concedes that to the extent that the installation and commission of appliances is a requirement for completion in accordance with s42 of the Domestic Building Contracts Act 1995 (Vic), the cooktop, fireplace, hot water service and rangehood have not been installed and commissioned by Metricon, and completion has therefore not been achieved".
"It is necessary for there to be 'effective and satisfactory' completion of the required stage ... [as] a condition of any instalment payment and while trivial failures, or failures borne of impracticalities, do not preclude effective and satisfactory completion, it is noteworthy that the dispute in relation to the trusses was not resolved until the first day of the hearing before VCAT. That resolution involved work being done on the trusses to strengthen them in accordance with the recommendations of a consultant engineer. The 'final approval' was not given until Mr Kidd undertook a personal inspection on 13 March 2007" [emphasis added].
At Mr To's request, Mr Loomes inspected the works completed on site and reported.
Email from Metricon to Mr To enclosing "Notice of Completion", and claim for "Completion Stage payment" of $77,662.00 (TB 425). Notice of completion requested Mr To to "attend a final inspection of the dwelling to identify and list any defects and those defects are to be rectified before the Completion Stage payment is paid and the house is handed over".
Final inspection scheduled by Metricon. Mr Loomes attended and later Mr To. Mr Taylor prepared "a report of defect items to be completed prior to completion" (TB 481) All items on the list were, according to Mr Taylor, subsequently rectified by Metricon and "ticked-off" the list. Mr To said that, at the inspection, he was "continuously pressured to leave" and that it was agreed with Metricon that it would not be treated as a "final inspection" and that Metricon would do a "thorough paint and plaster review".
Mr Loomes' report from the inspection (TB 429). Mr To said Loomes told him he would provide a "general" rather than a "final report", that the site was "defective and not clean" and that, "when I received the report, I should have the builder complete the items listed".
Mr Loomes' report provided to Metricon after it requested a copy in order that the report could be treated as part of the "client list" from the "final inspection".
Occupancy permit issued (TB 1155). The permit was provided to Mr To on 20 February 2020.
Metricon issued a notice to Mr To advising that, "defects notified had been rectified and final payment was due within 7 days" (TB 445). Payment was not made by Mr To.
Mr To issued a notice of dispute with Domestic Building Disputes Resolution Victoria ("DBDRV") and advised Metricon on 5 March that the dispute had been issued.
Further "final inspection" agreed to by Metricon after a request by Mr To. Mr To said Mr Taylor and Mr Sutton told him that the rectification work was not finished. Following the inspection, Mr To provided Metricon with a "207 page document [noting] a further 417 items of alleged defects" (TB 507). Items on the list were claimed by Metricon to have been subsequently rectified by Metricon and letters of warranty were obtained from product suppliers. Mr To's defects list with Mr Taylor's notations of work undertaken is at TB 715. Mr Taylor said that Mr To asked him to "mark each brick that [Mr To] considered to be defective". Photographs of the marked bricks are at TB 923. Metricon determined that, "no further work was required to be carried out in respect of the brickwork".
Metricon sent an email enclosing notice of completion and advising that, "defects identified by you ... were completed on the 10 June 2020 [and] final payment is due within 7 days" (TB 447). Payment was not made by Mr To.
Inspection on site. Metricon wished to check-off defective items as complete. Mr To wished to examine the property. Mr To was told to leave, and later, he was informed that the police had been called. Metricon claimed that Mr To was not entitled to a "re-inspection".
Email from Metricon to Mr To advising that final payment was required to be paid (TB 1597).
Metricon received a copy of Mr To's complaint from DBDRV. The document listed 105 items of defective work and 8 further general complaints.
Metricon issued a notice advising that Mr To was in "substantial breach" of the building contract by failing to make the final payment. The notice requested that Mr To "rectify the breach" (including the payment of interest) within 10 days (TB 1159). Mr To did not make a payment. Metricon said it "decided not to terminate the Contract and to retain possession of the house until the full contract price had been paid by Mr To" (TB 939 paragraph 28).
Metricon responded to Mr To's complaint to DBDRV item by item, generally responding by indicating that the item "has already been fixed", "no issue "identified" or "no defect visible from normal viewing distance". (TB 1600)
Metricon denied further access until final payment was made and stated that, "After settlement, you can submit further reports or lists to us which will be addressed at the end of the 3 month defect liability period" (TB 1625).
Mr To visited the site and was critical of what he found. He said, "It was clear that Metricon was suspending building works and only returned to carry out sub-standard work on site to support its fraudulent demands for final payment and interest for late payment" (TB 1200).
Building Consultant, Tony Croucher, after inspecting the property at Metricon's request on 19 October 2020, reported on 27 October that, "It is my opinion the home is finished to a very good standard with some minor adjustments and repairs required" (TB 372).
Counterclaim filed by Mr To alleging acceptance of Metricon's repudiation of the building contract.
"40.0 If the Building Works have not reached Completion by the end of the Building Period the Owner is entitled to agreed damages in the sum set out in Item 9 of Schedule 1 for each week after the end of the Building Period to and including the earlier of:
40.1 The Owner may deduct the amount of any such damages from the Final Payment".
"35 It is clear that the parties to an agreement may, as part of their agreement, fix an amount that is to be payable by way of damages in the event of a breach of the agreement. Provided the amount so fixed is a genuine pre-estimate of the damage that would arise from the breach, and not so out of all proportion as to be by way of a penalty, that amount is recoverable without proof of the actual loss caused by the breach. It is immaterial that the amount of the actual loss turns out to be less than the amount specified. Equally, if the actual loss turns out to be greater than the amount of the liquidated damages, the claimant cannot ignore the liquidated damages clause and sue for unliquidated damages: Diestal v Stevenson [1906] UKLawRpKQB 92; [1906] 2 KB 345; Talley v Wolsley-Neech (1978) 38 P & CR 45 (CA). That is, ordinarily a valid liquidated damages clause fixes the amount that is recoverable in the event of a breach, regardless of whether the claimant's actual loss is greater or less than the amount specified.
"179 If the actual loss turns out to be greater than the amount of liquidated damages, the claimant cannot ignore the liquidated damages clause and sue for unliquidated damages. That is, ordinarily, a valid liquidated damages clause fixes the amount that is recoverable in the event of a breach, regardless of whether the claimant's actual loss is greater or less than the amount specified.
(a) if a positive sum of liquidated damages has been stipulated under the contract. In this case, Schedule E of the Subcontract sets out a positive sum for liquidated damages in relation to each milestone date of $9,500.00 per day capped at 5% of the contract price; and > > (b) if the liquidated damages clause is mandatory.
a. extra interest incurred on the investment construction loan
"Thank you for allowing Century 21 Preferred to provide a rental appraisal on your above-mentioned property. Given the current rental market conditions, we believe you could achieve a rental amount of approximately $650 per week. Should you require any further information ...";
"Thank you for your email. The property looks amazing. Thank you for the photos. In regards to the rental, there is only one property in the area that has achieved a price of $700.00. I have attached a rental report for your perusal, with most properties sitting below $500.00. In saying that and now seeing what the property has to offer, I believe you could achieve somewhere in the 600.00's however, the market will tell us where the property is sitting once it goes live. Let me know your thoughts". [the "photos" and the "rental report" referred to were not in the Tribunal Book];
"Thank you for allowing me the opportunity to appraise your abovementioned property. We estimate the property could lease for $650 per week. This appraisal has been conducted as a desktop appraisal only. Considerable care has been taken to provide you with the most accurate estimate possible based on our professional knowledge of the area, prevailing market trends and recent lettings of comparable properties. Should you have any further queries please do not hesitate to contact our office".

Mr To seeks payment of the amount of $19,588.00 for the following non-delivered Contract items:
Undermount rangehood, 900mm Elica IXGL/A/90 Hidden S/Steel White Glass
InAlto MC25BF Convection Microwave w/integrated trim kit
InAlto DWI62CS 600mm Integrated Dishwasher with cutlery trays
4 x Legrand Arteor Mirror White/White Double Powerpoints ($190 each)
2 x Methven Aio Aurajet Rail 228563 8 chrome shower outlet (Ensuite, Item 142)
Pair of Southern Star Windows, 'Commercial D' handles for Family and Outdoor room sliding door
Additional Dulux Acrashield Advance finishing coat (Item 29)
Item 6 - 4 x Legrand Arteor Mirror White/White Double Powerpoints
"incorrect double powerpoints in the kitchen. 4 x Legrand Arteor Mirror White-White Double Powerpoints not installed as required by the Contract. Page 3 of the Contract's electrical upgrades list dated 29/01/2019 (Tribunal book at page 1704) specifies an upgrade from four standard Powerpoints to four Legrand Arteor Mirror White-White Double Powerpoints. The Applicant charged the Respondent $760 for four of the upgraded Legrand Arteor Mirror White-White Double Powerpoints. The Applicant has not installed the four Legrand Arteor Mirror White-White Double Powerpoints. The contract's ground floor electrical floor plan shows the locations where the four Legrand Arteor Mirror White-White Double Powerpoints were supposed to be installed. (Tribunal book at page 1091)".
Item 8 - Methven Aio Aurajet Rail 228563 8 chrome shower outlet
"2x Handheld Methvan Aio Aurajet Rail chrome shower outlet not installed as required by the Contract. Item 142 at page 18 of the Contract (Tribunal book at page 1014) shows that two handheld Methvan Aio Aurajet Rail chrome shower outlets are to be installed in the Ensuite. The Applicant charged the Respondent $1360 for two of the upgraded handheld Methvan Aio Aurajet Rail chrome shower outlets. The Applicant has not installed the two handheld Methvan Aio Aurajet Rail chrome shower outlets".
Item 9 - Pair of Southern Star Windows, 'Commercial D' handles for sliding doors
Due to a design fault/oversight by the Respondent, a pair of door handles to one of the alfresco sliding doors has not been possible to install. The Respondent refuses to refund the cost of the handles despite multiple requests by the Applicant without fair reasoning. The total for the door handles (a pair of Southern Star Windows, 'Commercial D' handles) as quoted by the Respondent in the Contract quote is $720.00. which is to be reimbursed".
"I have been advised that the Alfresco sliding door handles installed are as per your Contract. I have also looked at the Studio M doors and window quote and cannot see any item priced at $720.00 as per your letter. Could you please provide me with further information as to what you believe you should have, as opposed to what has been installed, and a photo if you have one. If it is proven that the door handles are incorrect and not in accordance with the Contract, we will either replace them or credit you back the cost, whichever you prefer".
Item 10 - Powder room 1, Polished edge Mirror 1250mmx 850mm
Item 11 - Additional Dulux Acrashield Advance finishing coat (Item 5)
Interest from the mid-point of the period 28 May 2020 to 16 July 2021 (21 December 2020). Interest from 21 December 2020 to 9 August 2023 ($14,785.71 for 961 days @ 10% p.a.)
Interest from the mid-point of the period 16 July 2021 to 29 October 2021 (6 September 2021). Interest from 6 September 2021 to 9 August 2023 ($7,481.25 for 702 days @ 10% p.a.)
Interest from 16 December 2019 to 9 August 2023 ($2,258.57 for 1,334 days @ 10% p.a.)
Metricon Homes Pty Ltd
To
(2012) 35 VR 538