Consideration regarding documents sought from HMT Construction
15 The first element of r 7.23(1) is a reasonable belief that NAE may have the right to obtain relief from HMT Construction. This matter is dealt with in [72]-[85] of Mr Rydquist's first affidavit, and confirmed in his third affidavit. Mr Rydquist's belief is summarised in [72] of his first affidavit as follows:
I believe that since my exclusion from the business of HMTP, opportunities belonging to HMTP or work which ought to have been undertaken by HMTP may have been diverted instead to HMTC. This belief, if substantiated would mean that HMTP, and NAE as a shareholder, are being deprived of its share of the profits for these projects.
16 On the basis of the material presently before the Court, that belief appears to have been justified in respect of the Woodside Project (as defined in [23] of Mr Rydquist's first affidavit). Mr Tracey (at [127]-[133] of his first affidavit) gives evidence that HMT Pilbara has novated the contract for the Woodside Project to HMT Construction. The terms of the Novation and Indemnity Agreement disclose that HMT Pilbara was to receive the sum of $10 in consideration for that novation.
17 NAE relies on a number of provisions of the Company Agreement in support of the proposition that it may have a right to obtain relief from HMT Construction. In particular, NAE relies on clause 3.2 (good faith), clause 3.3 (general obligations) and Schedule 2 (company objectives).
18 One of the issues between the parties on the present application concerns the geographical scope of the Company Agreement. NAE's position is that the agreement provided for HMT Pilbara to carry out works in all areas other than the Kimberley region (this being the area in which HMT Construction was already carrying on business). NAE relies on the wording of Schedule 2 to the Company Agreement to support its position. On the other hand, HMT Construction contends that HMT Pilbara was established primarily to conduct works in the Pilbara region. This contention derives support from Recital B of the Company Agreement, the definition of "Projects" in clause 1.1, and the subsequent references to Projects in other clauses of the Company Agreement (for example, clauses 2.2, 3.4 and 4.2). It may be accepted that there is a tension, if not a conflict, between the parts of the Company Agreement relied on by NAE and the parts relied on by HMT Construction. I do not consider it possible or appropriate to resolve this matter on the present application. Resolution of this matter is likely to require further evidence as to the circumstances surrounding entry into the Company Agreement. I will therefore proceed on the basis that NAE's position is at least arguable. In proceeding in this way, I also note that, even if it is correct that HMT Pilbara was established to conduct works primarily in the Pilbara region (as the name of the company suggests), the definition of "Projects" also refers to "such other areas as the Directors may unanimously agree". It was therefore envisaged that the company may undertake works in other areas as well.
19 Another issue raised in connection with the novation of the Woodside Project to HMT Construction concerned the need to obtain certain insurance. It was contended on behalf of HMT Construction that HMT Pilbara was unable to obtain the required insurance due to the failure on the part of Mr Rydquist to arrange registration as a builder. It is also not possible or appropriate, on the basis of the material presently before the Court, to resolve this aspect of the matter. It suffices to note that I am not satisfied that the material relied on by HMT Construction contains a complete answer to NAE's potential right to obtain relief from HMT Construction in relation to the Woodside Project.
20 The circumstances of the Woodside Project support a reasonable belief that, at least in relation to that project, NAE may have a right to obtain relief from HMT Construction (whether on the basis of breach of the Company Agreement or breach of fiduciary duty, if it could be established that such duties were owed). I am therefore satisfied that, at least in relation to the Woodside Project, NAE has a reasonable belief that it may have the right to obtain relief from HMT Construction.
21 Mr Rydquist refers in his first affidavit to other projects that he is concerned may have been diverted from HMT Pilbara to HMT Construction. Specifically, he refers to the Onslow Aircraft Hanger project for the Shire of Ashburton at [79(a)] of his first affidavit, and the Royal Flying Doctor Service - Jandakot project (RFDS Project) at [79(b)] of that affidavit. In relation to the Onslow Aircraft Hanger project, Mr Rydquist states that, "[t]o the best of my knowledge, this project was contracted to HMTP and HMTC was awarded the construction subcontract on behalf of HMTP". This is confirmed by Mr Tracey in his first affidavit at [54] and [67]. While Mr Tracey states that the funds were paid to HMT Pilbara (at [73]), no reconciliation has been provided.
22 In relation to the RFDS Project, Mr Rydquist states that this was discussed by the directors of HMT Pilbara "as an HMTP project". Mr Tracey does not address this allegation in his affidavits. Rather, Mr Tracey simply states that HMT Construction was awarded the project and performed the work (at [57] of his first affidavit).
23 The material suggests that there may have been a lack of clarity as to the respective roles of HMT Pilbara and HMT Construction in relation to a number of projects. HMT Pilbara is a small company and did not secure its first project until 2017. In contrast, HMT Construction is a larger company and has been carrying on construction projects for some time. In these circumstances, it seems that HMT Construction acted as the contracting party or Head Contractor on behalf of HMT Pilbara: see Mr Rydquist's first affidavit at [20]. This blurring of the lines between HMT Pilbara and HMT Construction makes it difficult, on an application such as this, to conclude that NAE does not hold a reasonable belief that it may have the right to obtain relief from HMT Construction in respect of other projects, that is, projects other than the Woodside Project. Having considered the material before the Court, including the material to which I was taken by counsel for HMT Construction, I consider that NAE does have a reasonable belief that it may have the right to obtain relief from HMT Construction (whether on the basis of breach of the Company Agreement or breach of fiduciary duty) in respect of other projects.
24 I note for completeness that the Company Agreement contains a dispute resolution clause (clause 13). It appears that the requirements of that clause have not been complied with by NAE. It was submitted on behalf of HMT Construction that in these circumstances I should not be satisfied that NAE held a reasonable belief as referred to in r 7.23(1)(a). Counsel for HMT Construction referred me to nearmap Ltd v Spookfish Pty Ltd [2014] NSWSC 1790 at [59]-[62]. In the circumstances of this case, and given the wording of the dispute resolution clause, the apparent failure to comply with that clause does not alter my view that NAE has a reasonable belief as required by r 7.23(1)(a).
25 The second element of r 7.23(1) is that, after making reasonable inquiries, NAE does not have sufficient information to decide whether to start a proceeding to obtain that relief. I am satisfied on the basis of the material before the Court (in particular, Mr Rydquist's first affidavit at [86]-[98]) that NAE has made reasonable inquiries and that, having made those inquiries, it does not have sufficient information to decide whether to start a proceeding to obtain that relief.
26 The third element of r 7.23(1) is a reasonable belief that the prospective respondent has or is likely to have documents directly relevant to the question whether the prospective applicant has a right to obtain the relief, and inspection of the documents would assist in making the decision. Subject to considering the scope of the categories of documents sought, I am satisfied that this element is established. The basis for NAE's reasonable belief that the documents are within the control of HMT Construction is set out in [106] of Mr Rydquist's first affidavit. In particular, the documents sought are documents that would have been produced by HMT Construction in the course of its business. Similarly, the matters listed in [107]-[109] of Mr Rydquist's first affidavit support the conclusion that NAE holds a reasonable belief that the requested documents will assist NAE in making a decision whether to issue proceedings against HMT Construction.
27 In relation to the scope of the categories sought, I consider the documents relating to the general financial affairs of HMT Construction to go beyond what is necessary to achieve the objects of r 7.23, at least at this stage. It appears that HMT Construction is a substantial business and it appears likely that many aspects of its business are unconnected with NAE's potential claims. In the circumstances, I do not consider it appropriate, at least at this stage, to require HMT Construction to discover its general financial documents. I appreciate that this may affect NAE's ability to quantify any damages which it may be able to claim (and that this may be necessary to make a responsible decision about whether to commence a proceeding). Nevertheless, on the basis of the material currently before the Court, and in the circumstances to which I have referred, I do not consider it appropriate to require discovery of the general financial documents. Accordingly, I will not order discovery of categories 1.1, 1.2, 1.3 and 1.4. It may be that, after production of documents in the other categories, a further application for preliminary discovery of categories 1.1, 1.2, 1.3 and 1.4 could be made.
28 In relation to category 1.5, I do not consider it appropriate to order discovery of paragraph (b) of this category, which is concerned with tenders by HMT Construction. I do not consider this part of the category to be sufficiently connected with the potential right to relief. However, I do consider paragraph (a) to be appropriate.
29 In relation to category 1.6, which also relates to tenders, for the same reason as category 1.5(b), I do not consider it appropriate to order discovery of this category.
30 Category 3.5 is confined by the general heading for category 3, namely documents relating to existing contracts between Woodside and HMT Construction. This category is appropriate.
31 Category 4 refers to projects carried out by HMT Construction outside the Kimberley region. A number of projects are listed but the category is more general, and relates to the period since 2 December 2014, when the Company Agreement was entered into. Insofar as the sub-categories relate to actual contracts, I consider the categories to be appropriate. I do not accept the submission that these sub-categories should be limited to the projects identified in Mr Tracey's second affidavit. To the extent that the sub-categories relate merely to tenders, for the reasons already indicated, I do not consider it appropriate to order discovery of the sub-categories. Accordingly, I will order that categories 4.4 and 4.5 be provided, but not categories 4.1 and 4.3.
32 The basis for category 5 is explained in [82] of Mr Rydquist's first affidavit, namely a concern that HMT Construction may be relying on HMT Pilbara facilities and presence in the Pilbara to secure work. That paragraph is not addressed in Mr Tracey's affidavit. I consider it appropriate to order discovery of category 5.1 on this basis. Category 5.2 is rather broad and goes beyond the Pilbara region. It is also unconfined by a date period. I am prepared to order discovery of this category, but confined to the Pilbara region and confined to the period since HMT Pilbara was established (i.e. 22 May 2014).
33 I note for completeness the submission that NAE is seeking preliminary discovery for a collateral purpose. I am not satisfied on the material that this is the case. I accept that the application for preliminary discovery is brought for the reasons articulated in Mr Rydquist's affidavits.