The factual outline and the reasons of the primary judge
15The following outline is taken principally from the reasons of the primary judge at [49]-[197] of his reasons. Complaint was made that his Honour merely worked through the documents in a chronological way not engaging with the evidence. That criticism should be rejected. His Honour was required, as this Court is, to consider very serious allegations of malicious behaviour asserted against Ms Gale. A complete factual context must be drawn and appreciated in order to make that assessment. Thus, as his Honour did, I set out below the factual material in a coherent chronological way in order that Ms Gale's conduct be assessed in its context.
16In 1999 and 2000, Mr Maruncic planned the building of a luxury apartment development in Port Stephens on land he owned in Church Street, to be known as "Milan Towers".
17In 2000, he submitted a development application to the Council for the construction of the buildings as two five-storey residential towers with 25 apartments. The buildings were 15.7 metres above natural ground level.
18On 29 May 2000, approval was given by the Council, subject to conditions. The giving of that approval involved obtaining the approval of the Director of the Department of Urban Affairs and Planning as to the height of the building, cl 58(1) of the Hunter River Environmental Plan (the "HREP") requiring the concurrence of the Director for buildings over 14 metres.
19Demolition and construction began soon thereafter. Work ceased in March 2003 by reason of an injunction obtained by a neighbour. The injunction remained in force until December 2004.
20Meanwhile, in 2002, the Council gave approval for a nearby development at Donald Street (Nos 65-67), Nelson Bay, for 15 serviced apartments. That development has not proceeded. In February 2005, the Council, over the objection of Mr Maruncic and his companies, gave approval for a seven storey residential development called "Cote D'Azur", also in Donald Street (No 61). This comprised commercial premises, tourist units, residential units and parking. It was completed in February 2007.
21In August 2005, the Council, again over Mr Maruncic's objection, approved a third development application for another part of Donald Street (No 63) for the development of residential units, shops and parking. Mr Maruncic considered that these developments would compromise the viability of Milan Towers, unless its development was altered.
22From 2001 to 2005, the Council granted approval to eight development modification applications in respect of Milan Towers. One aspect of those approvals, which are otherwise uncontentious, should be noted. The last modification concerned the height of Milan Towers. Approval was given to a maximum height of approximately 18 metres. Ms Amanda Gale, whose conduct was at the centre of the criticisms by Mr Maruncic, had recently been appointed "Development Co-Ordinator". This modification application was her first involvement with Milan Towers or Mr Maruncic and his companies. This last modification application had been lodged in November 2004 and was approved on 21 April 2005. On 8 February 2005, Mr Maruncic wrote to the Council requesting an increase in height including one further floor and an increase in the number of apartments from 25 to 41. This proposal was the essence of the charge that was ultimately rejected and that became the subject of the proceedings.
23In May 2005, Mr Maruncic engaged Mr Warnes to assist him in the development. Mr Warnes was a very experienced town planner with experience in the private sector and the Department.
24On 23 June 2005, Mr Maruncic and Mr Warnes addressed a meeting of the Development Assessment Panel of the Council. Ms Gale was present, as were others from building and engineering departments. The minutes taken record the following (Mr Warnes' evidence being that it was Ms Gale who made these comments):
"Propose to add an additional level raising overall height by approximately 2.5 metres.
...
*Height - The proposal to increase the height by approximately 2.5 metres is considered a considerable increase and is unlikely to be supported. A SEPP1 objection to height was lodged with original Development Application and therefore, a further modification / increase in height is possible via a Section 96 modification to development consent. However, given the extent or increase in height, Council considers this would warrant a new development application.
*Density - The proposal to increase the density of this development (from 25 units to 36 units) is considered a considerable increase and is unlikely to be supported. It does not appear that the original development application included a SEPP 1 for density, therefore, if the current density approved on this site is at its limit, then Council cannot accept lodgement of a Section 96 modification to Development Consent that includes a SEPP 1 objection to density. A new Development Application would be required in this instance.
*Notwithstanding the above individual comments regarding height and density, it is advised that the proposed changes in their entirety (ie. increase in height and unit numbers) would not be considered to be substantially the same development. Therefore, on this basis a new development application would be required.
*The land is within State Environmental Planning Policy No. 71 - Coastal Protection Policy (SEPP 71). Given Council considers the changes require the lodgement of a new application, the Minister would be the consent authority. Any new development application is to be lodged with the Department of Infrastructure Planning & Natural Resources."
The relevant matters to note about this are the view then expressed of the substantial change to the development and the consequent need for a new development application. This was not ultimately how the relevant application went forward. Nevertheless, Mr Maruncic was aware of the issues of height and density to be addressed.
25Mr Warnes ceased to advise Mr Maruncic in September 2005, though he was later re-engaged. A Mr O'Connor (who had assisted in the Côte D'Azur application) thereafter began advising Mr Maruncic. Mr Warnes' view, of which he advised Mr Maruncic, was that a new development application was required and that what was proposed was not within s 96 of the Environmental Planning and Assessment Act 1979 (NSW) (the "EPA Act"). In fact the application did ultimately proceed as one under s 96. The terms of s 96 and of other relevant statutory provisions, are set out later. (The debate about this issue of the suitability of the application to be approached under s 96 was a significant issue at the hearing.)
26Mr Maruncic met officers of the Department at the site of Milan Towers in July 2005 at a meeting arranged by Mr Warnes. He was told that in order to progress his proposal he should either write to the Department or obtain a refusal to the modifications from the Council. Between June and December 2005 Mr Maruncic was in contact with the Department about his proposal.
27In October 2005, Mr O'Connor advised Mr Maruncic against an application under Part 3A of the EPA Act (dealing with major infrastructure and other projects) and that the correct approach was to do a study reviewing floor space ratio, height and density. Mr O'Connor's services were terminated in November 2005.
28In November 2005, Mr Maruncic was told by the Department by letter that his proposal may be a matter to be dealt with under Part 3A of the EPA Act. The letter also dealt with the question of how he should deal with the height of the development.
29On 22 November 2005, Mr Maruncic wrote to Ms Gale at the Council explaining the proposed changes he said were brought about by the nearby developments. The letter sought the support of Council and the Department and concluded:
"I would appreciate very much if you would advise me today or as soon as possible if Council will, or, will not, support the changes I propose."
30Two days later, on 24 November 2005, Mr Maruncic again addressed the Development Assessment Panel, which included Ms Gale. The minutes reflect the view then held by Ms Gale that the proposal fell outside a s 96 modification and that the Department was therefore the consent authority. The purpose of the Council's consideration of the matter, however, was explained to be that the Department wanted the Council's views on the proposal. Those views were negative to the proposal as follows:
"In regards to the basis for lodging a new development application (being proposed changes to height and density), Council considers these changes to be major departures from both the original approved development application, the Tall Building Study, which formed the foundation for the height limit within the area and Council's Local Environmental Plan 2000 (ie. Clause 19 development standards). Therefore, Council would not support such variations and inconsistency with Council's policy .
In regards to Council's Local Environmental Plan 2000, Clause 19 - Urban Housing developments in the Residential 2(c) Zone include: Minimum Site Area per Dwelling of 150m², Floor Space Ratio of 1:8:1 and Maximum Height Limit of 15.0m.
Whilst Council supported variations to both height and density under the original application, a further variation and extent of variation to both height and density is considered unacceptable as stated above."
31After the meeting, Mr Maruncic wrote to Ms Gale pointing out that there were different methods of height measurement (a matter that became central to the litigation):
"When (Port Stephens) Council calculate their height measurements, they measure from the floor of the basement to the top of the roof.
When the Department of Environment and Planning calculate their heights they are measured from the original land level to the top of the roof.
Therefore, there is a difference of one floor level.
According to Council my last amended plans are two floors above and according to Dept of Land & Environment I am only one floor higher.
My original approval from the basement to the top of the roof was 18.3m, my present height is 23.5m.
So the difference is 5.2m, or, according to the Dept of Land & Environment, 2.7m higher than what I had approved earlier."
This question of the different methods of measurement was to assume some importance.
32By December 2005, Mr Maruncic had the minutes of the meeting and sent them to the Department requesting a meeting with the Department to discuss his proposal. Mr Maruncic said in evidence that he was told orally by a Departmental officer that his proposal could be dealt with by the Council under s 96, a matter that he said was important and relevant to his decision to lodge such an application. On 23 January 2006, however, an officer of the Department wrote to Mr Maruncic, noting the Council's view that the proposal did not fall within s 96 and that a new approval was required, stating that given the scope of the proposal it might fall within Part 3A of the EPA Act and indicating some of the consequences of that. This view of the Department was founded on a view of the substantiality of the changes proposed. This, in substance, reflected Ms Gale's own views.
33After this letter, Mr Maruncic lodged, on 15 February 2006, an application under s 96. It is the consideration of this application and its refusal (in its final form) in June 2007 that is the focus of the complaints of Mr Maruncic about Ms Gale's conduct. The primary judge described the amendments to the original approval as follows at [92] of his reasons:
"(a) an increase in the total number of units from 25 to 41;
(b) an increase in the maximum height of the development by approximately five metres (from approximately 18 metres to approximately 23 metres) to accommodate an increase in the ceiling height of 100 millimetres per floor;
(c) conversion of the first-floor apartments into parking spaces; and
(d) the addition of balconies to the southern side."
34The application was lodged by Mr Maruncic personally at the counter, at which time a conversation took place with Ms Gale as recounted at [93] of the primary judge's reasons:
"GALE: I have major concerns regarding the proposed changes which are a significant departure from the original approval. I expect there will be issues with lodgement of the variations as a Section 96 application as opposed to a new development. What you are proposing is a new development.
MARUNCIC: I am going to lodge the modification application anyway and see how it progresses. I believe in the proposal. I do not want to have to lodge a new development application with the Department of Planning."
The primary judge rejected Mr Maruncic's evidence that Ms Gale said that she would personally object to the application: at [94] of the reasons.
35Ms Gale was responsible for considering the application. By April 2006, she had formed the view that it should be refused and she proposed to issue a "Notice of Intent to Refuse", but before doing so she decided to seek legal advice from the Council's legal advisors, Sparke Helmore. On 10 April 2006, she wrote to Ms Dianna Grant at that firm setting out her reasons for refusing the proposal as a s 96 application, as follows:
"1) The extent and nature of proposed modifications are not considered to relate to substantially the same development as the development for which consent was originally granted and, therefore, [are] considered outside the scope of a Section 96 modification application pursuant to the Environmental Planning and Assessment Act 1979.
2) The development does not comply with Council's Minimum Area per Dwelling (ie. density) development standard pursuant to Clause 19 of Port Stephens Local Environmental Plan 2000, with the extent of variation to the standard considered unacceptable.
3) The development does not comply with Council's Height development standard pursuant to Clause 19 of Port Stephens Local Environmental Plan 2000, with the extent of variation to the standard considered unacceptable.
4) The development is contrary to the public interests and expectations of an orderly and predictable built environment."
She described the various changes made to the original application as follows:
"The original development consent was issued for 25 Medium Density Units on 29 May 2000. The development was configured in two separate building blocks - Block A & B.
The current s 96 modification relates to:-
- an increase in no. of units (from 25 approved) to proposed 41 units (by large front units being converted into two units, some of level 4,5 & 6 units have been changed from 1 & 2 units into 3 units per floor and increase in height / level will provide for remaining extra units).
- change in height of minimum 4 metres and up to 5 metres.
- changes have affected Block A - 3 floors and Block B - 4 floors
- propose to provide adequate visitor parking by removing pre-approved units on the lower levels and replacing them with parking.
- a series of new balconies for extra open space have been proposed to Block A & Block B.
The building footprint doesn't actually change, however [the] added floors/levels and a change in roofline, along with extra balconies, I assume to provide open space for additional units, contribute to the unacceptable increase in height and density involved in this s 96 modification."
It is to be noted that Ms Gale's concerns included the substantiality of the changes taking the proposal outside s 96 (in line with the view of the Department provided to Mr Maruncic), the height and the density of the proposal.
36Sparke Helmore advised by letter of 21 April 2006. The advice principally concerned the meaning and operation of s 96, in particular the phrase "substantially the same development" in s 96(2)(a), and the question whether the application fell within s 96 or not. The advice was contrary to the apparent view of the Department, the view of Ms Gale and that which Mr Warnes had communicated to Mr Maruncic, and was expressed as follows:
"In our view, and having regard to existing case law, the current Application does not change in a 'material or essential' way the development approved by the Original Consent (as currently modified). We consider that Council would have difficulty supporting an argument before a Court that an increase in the number/height of the apartments constitutes a material or essential change to the approved development. It remains open for Council to refuse the Current Application on the merit grounds - namely non-compliance with height and density standards."
37On 28 April 2006, the Council sent a Notice of Intent to Refuse the application identifying three reasons, being the second to fourth paragraphs in the draft letter to Sparke Helmore referred to in [35] above.
38The application under s 96 was, in any event, deemed refused on 27 March 2006 by the operation of s 96(6) and the regulations. An appeal was thereupon available to MM, as a class 1 appeal under s 17(d) of the Land and Environment Court Act 1979 (NSW). At no time was any appeal lodged. This decision was made by Mr Maruncic in consultation with Mr Warnes.
39Mr Maruncic wrote to the Council on 23 May 2006 listing further amendments and providing some amended plans. On 1 June 2006, Mr Warnes, by this time once again acting for Mr Maruncic, sent an email to Ms Gale saying that he had left a number of messages at the Council "over the last few weeks" for her to call him. He also stated that he had reviewed Mr Maruncic's submission and he was "concerned that he [Mr Maruncic] has not given [the Council] sufficient information to make the application competent".
40The plans were publicly exhibited by the Council in May and June 2006 and in early June the application was advertised.
41Mr Maruncic lodged further plans on 1 July 2006; and Mr Warnes supplied the Council with further plans and explanatory material under cover of letter dated 7 July 2006. Mr Warnes' letter dealt in particular with height in relation to the surrounding developments. Mr Maruncic was by this stage lobbying relevant councillors.
42On 7 July 2006, Ms Gale prepared a draft letter raising a number of concerns for Mr Maruncic to address regarding his application. It was not sent until 1 August 2006.
43On 17 July 2006, Mr Warnes wrote to the Council identifying a reduction in the number of units by two and an increase by seven of car parking spaces and stating that plans covering these would be submitted.
44On 18 July 2006, Ms Gale sent a memorandum to relevant (East Ward) councillors. The primary judge set out the relevant parts at [116] with emphasis:
"The Department of Planning have a concurrence role in respect of developments proposing a maximum height (above 15m) pursuant to a Tall Building Clause within the Hunter Regional Environmental Plan 1989. Therefore, a number of the development applications assessed by Council as identified on plan have required the Department's concurrence. In assessing and providing their concurrence to the proposed maximum heights of these buildings, the Department is measuring height from Natural Ground Level only. In contrast, Council is assessing height in accordance with the height definition pursuant to LEP 2000, whereby height is measured from either Natural Ground or Finished Ground Level (whichever is the lower). This in turn results in different maximum heights being established.
As advised previously, the extent of this proposed modification is considered unacceptable primarily in respect to increases in density and building height pursuant to LEP 2000 and relevant DCPs, which in turn raises concern that the development is contrary to the public interest .
The applicant has indicated that they wish to provide additional information to support their application and has requested Council's advice as to the deficiencies of the application and main areas of concern. This written advice is currently being finalised and essentially aligns with the reasons for refusal as outlined in the Notice of Intent to Refuse issued by Council. It is noted, however, that the applicant has been advised that whilst information submitted with the modification is deficient, the main reasons for refusal relating to proposed increase in density and building height are excessive variations, which are unlikely to be capable of justification through submission of additional information.
Recommendation/Conclusion:
Confirmation is sought as to whether the Section 96 modification is required to be forwarded to full Council for full determination.
Alternatively, if able to be determined under delegated authority within the Sustainable Planning Group, the recommendation is maintained that the modification be refused."
The issue of "concurrence", that is, the role of the Department having to approve any increase in height as well as the Council, because of the original requirement of Departmental height approval (above 15m), was important at the trial, though it fell away during the hearing of the appeal. Further, the statement that Maruncic had been advised as referred to in the third paragraph (the second emphasised portion) above was controversial at the trial and on appeal and heavily relied upon by the appellant in seeking to demonstrate Ms Gale's bad faith.
45Further plans were lodged with the Council on 20 July 2006.
46On 27 July 2006, one of the relevant councillors wrote a letter to Mr Maruncic that was sympathetic, but that reflected real concern with height (of 23 metres) "which is too far above our maximum of 15m".
47On 1 August 2006, Ms Gale sent a letter to Mr Maruncic substantially in the form of the draft prepared on 7 July, adding that discussions had been held with East Ward councillors and that height and density were the problems. The letter identified in some detail "concerns ... which need to be addressed". These are set out at [121] of the primary judge's reasons. They included height and density, as well as floor space ratio, increased traffic and a lack of shadow diagrams. Ms Gale also noted that the proposal had not yet been referred to the Department for height approval (so-called "concurrence"). As the primary judge found at [123], Ms Gale's view was that concurrence of the Department may be required. This was the first time this had been communicated to Mr Maruncic. The reasonableness of the view was a significant issue at trial. On appeal, it was accepted that her views in this regard could not be the subject of criticism.
48Mr Warnes gave Mr Maruncic advice on the 1 August 2006 letter (see [125] of the primary judge's reasons) and on 22 August sent a detailed submission to Ms Gale. In particular he addressed issues of height and density, the primary judge extracting the following at [126] (emphasis made by his Honour);
"Following upon discussions with both Council Staff and East Ward Councillors the s 96 modification has now been reduced to seek approval to 40 units, a maximum height above natural ground level of 23.15 metres (Building A) and 23.1 metres (Building B) excluding the lift over run . The design of the upper floors has also incorporated a stepping in of the building at its upper levels to reduce its scale and bulk.
The interpretation of the building from adjoining public places will not allow for a reading of the height of the buildings as 23 metre structures as they are set into the site below the street level such that Building A, the building set highest on the land, would read as a building of some 21.9 metres. It must be remembered that the measurement of height for the purpose of development is taken from natural ground level and not street level however impact is read from street level and the variation between absolute heights of 1 to 2 metres would be imperceptible to the human eye."
49Further plans were submitted a few days later. Mr Warnes maintained email contact with Ms Gale. Replacement plans were submitted. Mr Warnes stressed the relative height of the buildings, stating in an email of 4 September set out by the primary judge at [129] of his reasons:
"Michael has had new plans and elevations prepared showing the relative heights of the development as fixed by a Surveyor that show the development does not exceed 21 metres at any location and that at most other points it is lower to somewhere at the lowest it being no greater than 15 metres above natural ground."
50A letter of 5 September 2006, set out at length by the primary judge at [130] of his reasons also dealt with the height issue and methods of measurement and the reduction of the height of the development from 25m above natural ground level to 19.8m, including a one metre reduction for top soil removal.
51After further plans were lodged, on 29 September 2006, Ms Gale forwarded the latest revised plans to the Department for concurrence. The primary judge set out at [133] the text of the covering letter revealing Ms Gale's state of mind. In that she said:
"The current Section 96 Modification is the 10th modification to be lodged and the documentation submitted outlines the amendments as proposed, with the main changes relating primarily to an increase in density (ie. approved 25 units, now proposed 41 units) and increase in height (ie. approved 17.95m and proposed at maximum 21.8 metres).
The application has been tentatively called before full Council for determination. Discussions with relevant Councillors continue, in order to determine whether the modification does require referral to Council for determination with internal assessment of the modification currently being undertaken."
It can be accepted that this was Ms Gale's state of mind because of the primary judge's finding (to which I will come) about her genuine and honest involvement in the processing of the application.
52One of Ms Gale's colleagues, Mr Greenhalgh, sought concurrence on 16 October 2006. The primary judge noted at [135] the participation of other officers of the Council in the process, since the claim for misfeasance in public office was based on Ms Gale's actions alone. Mr Greenhalgh sought further information from Mr Maruncic in late October.
53On 30 October 2006, Mr Murphy of the Department, in a response to the Council's request for concurrence, stated that the Department was unable to give concurrence because it was a significant departure from the original approval and advised the Council to consider carefully whether it was appropriate to progress the application as a s 96 application. On 14 November 2006, Mr Murphy wrote again confirming that the Department was unable to provide concurrence.
54On 30 November 2006, Ms Gale once again sought the advice of Sparke Helmore. The principal reason for seeking the advice was to obtain a review of a draft set of reasons for refusal of the application. She also drew the solicitors' attention to the view of the Department contained in its letter of 30 October 2006 (referred to above) and sought confirmation of the earlier advice.
55Sparke Helmore responded promptly on the same day, 30 November 2006. They expressed disagreement with the Department's views and maintained the view that they had already expressed. The advice as to the draft reasons was short and to the point:
"We note that, in any case, the Department's failure to provide concurrence means that Council has no power to approve the application. Therefore this point should remain in the reasons for refusal. In addition, the other 'merit grounds' listed in your draft reasons are very arguable, and ought to be included."
56As the primary judge pointed out at [145] of his reasons, these communications have significance because, as he said, they indicated that Ms Gale took (and apparently followed) legal advice. The primary judge also pointed out at [146] that other officers of the Council, Messrs Anson, Broyd and Greenhalgh, were "closely involved" in the process. For instance, Mr Broyd signed the Notice to Intent to Refuse the application issued on 30 November 2006. The reasons were recorded by the primary judge at [148], as follows:
"1. The Department of Planning has not granted concurrence in relation to the height variation pursuant to Division 4, Clause 58 of the Hunter Regional Environmental Plan 1989.
2. The development does not comply with Council's Minimum Area per Dwelling (ie. density) development standard pursuant to Clause 19 of Port Stephens Local Environmental Plan 2000, with the extent of variation to the standard considered unacceptable.
3. The development does not comply with Council's Height development standard pursuant to Clause 19 of Port Stephens Local Environmental Plan 2000, with the extent of variation to the standard considered unacceptable.
4. The development is contrary to the public interests and expectations of an orderly and predictable built environment."
57Issue was taken on appeal with the extent of the involvement of other Council officers. It can be accepted that Ms Gale was principally responsible for the day to day handling of the application and the drafting of relevant memoranda. The evidence did not, however, permit any conclusion that the other officers did not pay proper attention to their responsibilities in the handling of the application, or that Ms Gale could assume from their passivity that her asserted intention to harm Mr Maruncic would go unnoticed.
58Mr Maruncic sought legal advice and on 4 December 2006 his solicitor wrote to the Council. He challenged the need for Department concurrence; he also challenged the other reasons as unsatisfactory. The matter was said to be urgent. The urgency was explained in a letter three days later. The property was to be sold by auction on 13 December 2006 in a mortgagee sale. The property had been mortgaged in May 2004. In July 2005, notices under s 57(2)(b) of the Real Property Act 1900 (NSW) and statutory demands under the Corporations Act 2001 (Cth) had been served. The mortgagee took possession of the property on 13 November 2006. Mr Maruncic's solicitor said in his letter:
"... The only way our client can stop the sale is to re-finance the mortgage, and the only way this can be done is if council provide him with the development consent that he has sought. The situation is therefore urgent.
As indicated in previous correspondence, our client will look to council for any damages which he suffers as a result of the council failing to properly consider his application."
59The auction took place on 13 December 2006 and the property was passed in.
60Ms Gale sought advice from Sparke Helmore about the threat of legal action. She also prepared a draft response to Mr Maruncic's lawyer that was not sent. The primary judge used it as evidence of Ms Gale's state of mind: [154] of the reasons. Once again, the legitimacy of this was based on his acceptance of her evidence about her bona fides and honesty. On this basis, the draft revealed her view that the concurrence requirement was based on the height issue and that the variation as to density was unacceptable.
61Correspondence then followed as discussed in [155]-[158] of the reasons. On 30 January 2007, shortly prior to a meeting of the Council scheduled for 5 February 2007, Mr Warnes wrote to members of the Council urging them to attend and to hear Mr Maruncic. He said this about Mr Maruncic and the development:
"Mr Maruncic is unlike most developers in that this project is his sole development and is the culmination of his ... work which is to see a building of significant Architectural merit and high private amenity constructed at Nelson Bay where he will live out his retirement years. Unfortunately due to the significant delays that have been encountered in this matter Mr Maruncic now faces the prospect of having his financiers sell him up if he cannot get this matter resolved as quickly as is possible."
62On 5 February 2007, Ms Gale sought further clarification from the Department about its view that concurrence would not be issued, based on the Department's view that the application was not properly to be dealt with under s 96. She stated that the advice she had was that the matter could be dealt with under s 96. A response was received on 12 February 2007 from the Department that reiterated its view that this application was a substantial departure from the original approval; but that if the application was to be dealt with under s 96 the Council did not require concurrence from the Department. The primary judge discussed the significance of this correspondence with the Department at [164] as follows:
"Thus, the Department of Planning indicated (contrary to views in earlier correspondence) that concurrence was not required for the Plaintiffs' s 96 application. That said, the Department of Planning response did not suggest that there was a clear-cut and obviously favourable outcome which should result for the Plaintiffs' s 96 application. To the contrary, the Department of Planning used guarded language and expressed concern about the scale of the application. It might be thought that this would have the effect of maintaining a degree of caution on the part of officers of the Defendant, including Ms Gale. Given the Plaintiffs' causes of action, this is a pertinent consideration."
63By mid-February 2007, the application had been called to the Council for decision; and on 13 February 2007, Ms Gale sent a long email to all councillors to advise them of the current status of the application. In it she asked that the application be refused under delegated authority, rather than by the full Council.
64In anticipation of the matter going to Council, on 14 February 2007, Ms Gale once again sought confirmatory advice from Sparke Helmore about two matters:
"- the validity of lodgement of the s 96 application as opposed to a requirement to lodge new DA;
- clarification of the concurrence role requirements for s 96 applications."
65Within five days, Sparke Helmore responded, once again stating their view that the application fell to be considered under s 96. Their view was supported by reference to a number of court decisions. The subject of concurrence was also dealt with. The solicitors advised that no separate concurring approval from the Department was required under cl 58 of the HREP by reason of the height of the buildings. Thus, the application was for the Council only to approve or not pursuant to the power in s 96 of the EPA Act.
66The primary judge remarked on the course of events to this point and the roles of Sparke Helmore and the Department in their provision of advice to Ms Gale at [169] of the reasons, as follows:
"I note that it was not until this point that the Defendant was provided with legal advice from Sparke Helmore that Department of Planning concurrence was not required. Whatever may be said concerning the views of the Department of Planning which had been expressed, and the legal advice which had been provided by Sparke Helmore to the Defendant up to this time, it is difficult to see that the course of events up to this point materially assists the Plaintiffs in their causes of action against the Defendant based upon the suggested acts and omissions of Ms Gale. Ms Gale, who was not a lawyer, had taken independent legal advice and communicated with the Department of Planning. It is difficult to see how the fact that the legal advice changed, and the Department of Planning altered its view on the need for concurrence, may be (in some way) sheeted home to Ms Gale."
67At [170]-[172] of the reasons, the primary judge described some of the communications among Ms Gale and the other Council officers about preparing a report for a March meeting that was described as a "deadline". The correspondence reveals a degree of business-like attendance to the processing of the application for a decision in March.
68Meanwhile, Mr Warnes enquired about progress.
69On 26 February 2007, solicitors acting for the mortgagee in possession purported to withdraw the s 96 application. Sparke Helmore advised the Council that its consideration should continue whilst seeking evidence to assess the legitimacy of the actions by the mortgagee's solicitor. This development brought a defensive response from Mr Maruncic, which was dealt with by the primary judge at [177]-[179] of the reasons.
70On the evening of 13 March 2007, the application was considered by the Combined Strategic/Operations Committee of Council. On that very day, Mr Warnes sent an email to all Councillors which included a letter of three pages that he described as "a last desperate plea". This letter refers to a report to be considered by the Committee. That report was dated 9 March 2007 and was sent to "All Councillors & Executive Group" under Mr Anson's name, although Ms Gale was involved in its preparation. Also on 13 March, Mr Warnes sent additional information to Mr Anson and Ms Gale. This material in March can be seen to have been made available to Mr Warnes to comment upon. Consideration of the application was deferred because of the receipt of this further information to allow for its assessment.
71On 20 March 2007, further plans were lodged by Mr Maruncic for a 38 unit proposal and a height reduction. These plans were then publicly exhibited from 29 March to 11 April 2007.
72Meanwhile, on 30 March 2007, contracts were exchanged for the sale of the property by the assignee of the mortgagee in possession. It was accepted on appeal that from this date there was no causal relevance of any impugned conduct of Ms Gale. It assumed only an evidential significance, throwing light upon her earlier alleged conduct of delay and deliberate refusal to examine the application honestly.
73On 5 April 2007, Mr Warnes wrote to the Council concerning information that Mr Maruncic was delivering that day to the Council which concerned the height of the buildings. It was information from the surveyors Fagan Mather Duggan. The primary judge referred to Mr Warnes' letter at [187] of the reasons. The letter included the following:
"The information relates to survey and height deduction undertaken by local Survey firm Fagan, Mather Duggan Pty Ltd in relation to the amended plans and the height of the proposed development in respect of natural ground and that of the adjoining approved development.
In summary the information provided by the Survey firm confirms that the heights of the development now proposed by Michael Maruncic are 22.17 metres for block A (closest to Church Street) and 22.93 metres for Block B.
These reductions in heights are achieved from the earlier proposals by the reduction in floor to ceiling heights and the removal of the lift overrun by including the lift motor within the lift itself using the latest design of lift available that does not require lift tower placement above the last habitable floor.
These heights when compared to the development already approved and which adjoins the subject land to the east show that Building A is lower than the already approved adjoining building and that Building B whilst nominally higher than the adjoining building at 22.93 metres is likely to be lower than that adjoining building as the only plans available to the Survey Firm of that adjoining building indicate the Lift Tower as a half height overrun whilst the completed development has a lift that now exits on the roof level deck area and is therefore likely to be some 2 metres higher than both of Mr Maruncic's proposed buildings.
I understand that the number of units has been also been reduced to 38 and that the provision of car parking now exceeds Council's requirements."
74The primary judge referred at [188] of the reasons to the letter of the surveyors of 4 April 2007 and the controversy as to whether the Council and Ms Gale had it in their possession, as follows:
"In this letter, Mr Warnes referred to information provided by Fagan Mather Duggan Pty Limited. The evidence demonstrates that Mr Maruncic and Mr Warnes had been provided with a letter dated 4 April 2007 from Mr Mather (Exhibit E, Tab 45). There is controversy as to whether Mr Mather's letter was provided to Ms Gale and the Defendant or whether Mr Warnes' letter of 5 April 2007 was the only source for this information. I accept the evidence of Ms Gale that it was not received by the Defendant. The letter is not contained in the Defendant's records and Mr Warnes' letters do not assert that he supplied Mr Mather's letter to the Defendant. The real issue, however, concerns the relevance and the utility of the information conveyed by Mr Warnes (based upon Mr Mather's document) to the process of determination by the Defendant with respect to the Plaintiffs' application."
There was no appeal from the finding that Ms Gale and the Council did not have Mr Mather's letter of 4 April in their possession.
75The questions of the height of the building, and the comparative height of the building compared with Côte D'Azur and the effect of these matters on the decision of the Council, including by reference to the letters of early April 2007, were the subject of focus both at trial and on appeal. In this context, the findings at [189]-[190] should be noted:
"[189] What is clear is that Mr Mather's letter did not purport to be a survey of either 'Milan Towers' or 'Cote D'Azur'. Mr Mather agreed that there was no survey involved, with his involvement being 'just a review of plans' (T571.49). Mr Mather explained the process which he undertook in his evidence. I accept the submissions for the Defendant that, in light of his evidence, Mr Mather did not purport to undertake an accurate height measurement of the size of 'Cote D'Azur'. Mr Mather's letter dealt with the size of 'Cote D'Azur' from basement to the top of the lift overrun, without regard to relevant LEP definitions of 'height' in accordance with the decision of the Court of Appeal in Port Stephens Council v Chan Industrial Pty Limited [2005] NSWCA 232; 141 LGERA 226. The size of 'Cote D'Azur' was estimated by Mr Mather to be 22.7 metres high. He achieved this figure by a process of assumption and additions so as to give rise to an estimate.
[190] Although a considerable amount of time was taken up at the hearing, and in submissions, addressing the role of Mr Mather's letter in this case, I do not, in the end, consider that it plays any significant part. In particular, I do not think that the letter demanded the approach submitted for the Plaintiffs. It was not essential that the information contained in Mr Warnes' letter (by reference to Mr Mather's letter) be included in papers that were provided ultimately to Councillors as part of the decision-making process. I am certainly not persuaded that the omission of reference to Mr Warnes' letter supports a conclusion that Ms Gale was, in some way, seeking to suppress this information from Councillors."
76On 10 April 2007, further plans were received by Council, otherwise unexplained by any correspondence. On 11 April 2007, a letter from the Council to Mr Warnes (drafted by Ms Gale) stated that the Council was in the process of finalising consideration of the matter. The letter sought confirmation of the relevant information, stating:
"During the preparation of this supplementary information, a further revised set of plans has been submitted (received 22nd March 2006) which is the revised plan that is being reviewed for the purposes of Council's request and is the revised plan which is currently being re-exhibited. This set of plans generally incorporated changes to density (now 38 units), height, removal of the lift overrun and carparking, and included revised documentation (received 5th April 2007) confirming by survey the maximum heights for this development.
Council is in the process of finalisation [of] the supplementary information required to be completed by the end of this week and forwarded to Councillors for their consideration of this item at the Ordinary Meeting of 24th April 2007.
However, on the 10th April 2007 a further set of revised plans has been received without a covering letter explaining the changes (noted in red) on plan. There would appear to be only several small changes (noted in red) which are difficult to read.
As outlined above, Council is concerned with the numerous revised sets of plans received over time for this proposal and the difficulty in assessment and preparation of information for Council. Given the timeframes associated with finalising this information and re-exhibition of the proposed plans, Council requests your confirmation of the relevant plans for this proposal. Further, it should be noted that submission of further revised plans may result in deferral of this matter beyond the Ordinary Council Meeting in April."
77Mr Warnes responded that the plans that had been advertised were those that were relevant.
78Objections were received in April and May 2007: [191] and [194] of the reasons. Mr Maruncic wrote directly to Council members about these objections and about supporting his application: [195] of the reasons.
79The application came before the Combined Strategic/Operations Committee on 12 June 2007. A report of Mr Anson was before the Committee. It can be taken to have been prepared by Ms Gale. It recommended that Council not support the application and that it be delegated to the general manager for decision. On 12 July 2007, Mr Maruncic was advised that the application was refused, the reasons being stated to be its height, density, public interest and parking and traffic aspects.