[2021] WASCA 53
Court of Appeal (WA)
2021-03-25
Buss P
Original judgment source is linked above.
(a) subject to certain specified matters, Sino must produce no less than 6 million tonnes of Product by no later than 20 March 2013;
(b) if Sino fails to do so, it must, by no later than one month following 20 March 2013, pay to Mineralogy an amount equivalent to the Mineralogy Royalty payable on the amount of Magnetite Ore required to produce 6 million tonnes of Iron Ore Concentrate.
The undertaking was given because the failure to have an early hearing of the matter would have threatened Mineralogy's solvency and the employment of its staff. I concluded that the CITIC parties were not acting in good faith and seeking to delay matters in breach of their obligations and there was no other way that the matter could proceed to trial in the short term without giving the undertaking.
The basis of the appellants' application for an adjournment - the Fulcrum Evidence[8]
In [p]roceeding CIV 2840 and during the trial, documents were discovered and tendered and testimony was given in respect of a group formed within the CITIC Respondents referred to as the 'Fulcrum Group'. The Fulcrum Group was a group of employees of the CITIC Respondents and their external lawyers. Part of its task was to try and alter and normalise the existing contractual arrangements with Mineralogy because [Sino] and [Korean] considered the commercial terms unsatisfactory.
The evidence and testimony in [p]roceeding CIV 2840 was of limited scope but still:
(a) established the existence of the Fulcrum Group;
(b) recorded the purposes and motives of the Fulcrum Group; [and]
(c) recorded the pursuit of the purposes and motives of the Fulcrum Group. (footnote omitted)
During the course of senior counsel for Mineralogy's closing submissions, it appeared then that much was sought to be made by Mineralogy of what allegedly had emerged out of Ms Rifici's evidence concerning an existence or objectives of the Fulcrum group. In particular, the admission elicited in cross‑examination from Ms Rifici about difficulties with the commercial terms of [Sino] and [Korean's] agreements with Mineralogy was heavily emphasised as suggesting something rather sinister (see ts 597).
However, I did not and do not draw any such sinister inferences from this evidence or, indeed, from any of the limited trial evidence concerning the Fulcrum group. As I indicated in my dialogue with senior counsel for the CITIC defendants during closing submissions, I do not infer anything sinister around the fact of a contracting party's desire to renegotiate over, or to revise or to amend the terms of an existing arrangement (ts 568). An issue of possible concern about such objectives might emerge, if some illegitimate or unlawful means had been suggested or resolved upon to further that end. However, I saw nothing to support such a conclusion by way of inference or otherwise from out of the evidence put before me in this trial.
There was a document relied upon by Mineralogy suggesting, it was put, a nefarious intent towards the renegotiation of contracts. The document consists of an internal Excel spreadsheet or worksheet of CITIC, which looks to be an internal CITIC document with the heading 'CITIC Risk Management Library' and displaying inputs that are seen written in both English and Chinese. In the worksheet titled 'Risk Assessment' column F is seen headed, 'Second Degree Risk Definition' and reads in general and non-specific terms.
Included in the worksheet is a sentence directed towards legal risk. Part of the risk seen as referred to is administrative liability or criminal liability risk. But nothing tangible emerges out of that, on my assessment. At column H, under a heading 'Risk Elements' (for reference only - being an English translation of the [Chinese] written column G) there is seen an input at cell H119 as follows:
'Legal Dispute Prevention Mechanism Risk
Civil or criminal suit to deal with the risk Business Partners Debt Transfer Risks (row 89)'
But again, that is simply all too broad and non‑specific, by my assessment, to be of any present forensic significance. Further seen along row 119 at column AE, under a heading, 'Commentary and description of risk management status', the worksheet input reads (cell AE119):
'Risks are currently being adequately managed. CPM has a dedicated Special Projects Team to manage the major litigations with Mineralogy.'
Again, I would assess that statement as both bland and wholly benign. Likewise, cell AG119 reads in generic terms as regards an establishment of a specialised legal team. I assess that as equally benign. Indeed, I would be very surprised if there were not specialised legal terms in place for parties on both sides of this litigation - given these parties profligate other litigation commitments as against each other. Likewise, for column AI119, I assess that as equally benign.
Consequently, the endeavour of Mineralogy to suggest some sinister background underlying conspiracy involving the Fulcrum group as it was established by the CITIC defendants and towards some illegitimate or unlawful end directed against Mineralogy, in my view, is unsupportable. Ultimately, I assess it to be an irrelevant distraction in the present litigation.
...
Mineralogy also advances a view that the CITIC defendants, through their attempt to replace Mineralogy as trustee, are strategically attempting to fundamentally alter the [Agreements'] contractual relationship and bargain subsisting between the parties, so as to achieve an outcome that better suits their commercial ends. Such a strategy is referred to by [Mineralogy] as being the sinister function of a comprehensive and targeted taskforce - the aforementioned 'Fulcrum group'.
Under Mineralogy's closing (at pars 217 - 226), various submissions and allegations are put concerning illegitimate activities of the Fulcrum group. I have previously outlined the basis of this argument and concluded, in my opinion, that the allegations of illegitimate or sinister activities are not established and are a distraction in this litigation. (footnotes omitted)
The CITIC parties' response to the appellants' adjournment applications[15]
(a) the documents in relation to the Fulcrum Evidence were discovered in CIV 2840 in May 2020;
(b) the listing of these appeals occurred on 10 August 2020;
(c) the documents were the subject of evidence at the hearing of the trial in CIV 2840 in November 2020; and
(d) Mr Palmer held suspicions about the existence of the Fulcrum Group as early as December 2012.[16]
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
Research Associate to the Honourable Justice Murphy and the Honourable Justice Mazza
[1] Mineralogy Pty Ltd v Sino Iron Pty Ltd [2020] WASC 40 (primary decision).
[6] Mineralogy Pty Ltd v Sino Iron Pty Ltd [No 16] [2017] WASC 340. An appeal against that decision was dismissed: Sino Iron Pty Ltd v Mineralogy Pty Ltd [2019] WASCA 80; (2019) 55 WAR 89.
[7] C Palmer affidavit affirmed 8 May 2019, par 57; GB 423 - 424.
[8] The appellants relied on an affidavit of S Iskander sworn 9 March 2021 in CACV 29 of 2020, and an identical affidavit in CACV 27 of 2020.
[9] Appellants' outline of submissions, pars 17 - 18.
[10] Tyne v UBS AG [2016] FCA 241; (2016) 338 ALR 624 [31] - [34]; Re Luck [2003] HCA 70; (2003) 203 ALR 1 [9].
[11] Mineralogy Pty Ltd v Sino Iron Pty Ltd [2021] WASC 45.
[12] Mineralogy Pty Ltd v Sino Iron Pty Ltd [2021] WASC 45 [211] - [217], [549] - [550].
[13] Appellants' submissions, pars 28 - 31, 34 - 38.
[14] Reference was made to Mount Lawley Pty Ltd v Western Australian Planning Commission [No 2] [2008] WASCA 1 [5].
[15] The CITIC parties relied on the affidavit of H Chan affirmed 17 March 2021.
[16] Exhibit HC‑1 annexed to the affidavit of H Chan affirmed 17 March 2021.
[17] CITIC Ltd v Mineralogy Pty Ltd [No 4] [2020] WASC 439.
[18] JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [2020] WASCA 38 [3] ‑ [4]; La Mela v Franklexis Pty Ltd [2020] WASCA 83 [53].
[20] See, eg, Bailey v Marinoff [1971] HCA 49; (1971) 125 CLR 529; Burrell v The Queen [2008] HCA 34; (2008) 238 CLR 218 [19] ‑ [20]; Wentworth v Woollahra Municipal Council (No 2) [1982] HCA 41; (1982) 149 CLR 672, 683 ‑ 684; Mount Lawley [5] concerned an appeal where the orders had not been perfected.
(1971) 125 CLR 529
(1982) 149 CLR 672
(2019) 55 WAR 89
(2016) 338 ALR 624
(2003) 203 ALR 1
(2008) 238 CLR 218