[2018] WASC 371
Supreme Court of WA
2018-11-30
Archer J
Original judgment source is linked above.
(1) It was mandatory for the panel to have 'due regard' to the amount of traffic likely to be generated by the development, particularly in relation to the capacity of the road system in the locality and the probable effect on traffic flow and safety.
(2) The panel accepted the assurances of the City of Melville that there was no need for any further traffic analysis and, in effect, that the traffic impact of the proposed development could be accommodated without difficulty.
(3) The panel was obligated to read all of the material provided to it.
(4) If the members of the panel read all of the material, it should have been obvious to them that what the City was telling them was wrong, in that there were factual disputes as to the traffic impact of the proposed development that needed to be resolved.
(5) The nature of the panel's constitution and the regulatory framework meant that it was not permitted to merely accept the City's assurance in those circumstances. To do so was to fail to have 'due regard' to the amount of traffic likely to be generated.
(6) In those circumstances, the panel acted unreasonably, and fell into jurisdictional error, in approving the development application without resolving the factual disputes.
(1) An earlier panel had deferred making a decision on the application so that further information could be obtained in relation to, among other things, the traffic impacts.
(2) The subsequent panel had to consider for itself whether the evidence the first panel had sought had been provided, given the following circumstances:
(a) there was evidence to the effect that the information sought by the first panel had not been provided; and
(b) there was no evidence as to why the subsequent panel should find that the first panel's requests were not required to be answered, or that the evidence sought by the first panel need not be provided.
(a) must a panel read all the material it is given?
(c) should it have been obvious to the panel that there were factual disputes as to the traffic impact of the proposed development that needed to be resolved and that what the City was telling them was wrong?
(d) was it unreasonable for the panel to accept the City's advice in the circumstances?
(2) Ground 1(b): did the panel have to consider for itself whether the evidence the first panel had sought had been provided?
(3) Ground 2: did the panel impose conditions based on an assumption that they would reduce congestion?
It is considered that the above impacts to Canning Highway, especially those in the [afternoon peak period] will contribute to making an existing congested situation worse. Main Roads is inclined to not object to the development, having regard to the intent to further develop the broader precinct, and the ability to prioritise movement along Canning Highway. The obvious consequence of this will be a further deterioration of the flow of traffic on and along local side roads such as Reynolds Road.
(1) Riley Consulting submitted a 'Technical Note', dated 16 June 2017.[15]
(2) The City provided a second RAR dated 30 June 2017 (City's Second Report). In this, the City recommended that the Second Panel refuse to grant development approval. This recommendation was made on the basis of issues that were not related to traffic. The City recommended refusal on the basis that the proposed development would undermine the 'Activity Centres Hierarchy'.[16]
(3) On 7 August 2017, Ms HergetLansdell provided a further report (Move's Second Report) which, among other things, referred to Riley's Technical Note.[17]
There is a jurisdictional error if the decision maker makes a decision outside the limits of the functions and powers conferred on him or her, or does something which he or she lacks power to do. By contrast, incorrectly deciding something which the decision maker is authorised to decide is an error within jurisdiction. (This is sometimes described as authority to go wrong, that is, to decide matters within jurisdiction incorrectly.) The former kind of error concerns departures from limits upon the exercise of power. The latter does not.
First, the concept of legal unreasonableness concerns the lawful exercise of power. Legal reasonableness, or an absence of legal unreasonableness, is an essential element in the lawfulness of decisionmaking.
Second, the Court's task in determining whether a decision is vitiated for legal unreasonableness is strictly supervisory. It does not involve the Court reviewing the merits of the decision under the guise of an evaluation of the decision's reasonableness, or the Court substituting its own view as to how the decision should be exercised for that of the decision maker. Nor does it involve the Court remaking the decision according to its own view of reasonableness.
Third, there are two contexts in which the concept of legal unreasonableness may be employed. The first involves a conclusion after the identification of a recognised species of jurisdictional error in the decision making process, such as failing to have regard to a mandatory consideration, or having regard to an irrelevant consideration. The second involves an 'outcome focused' conclusion without any specific jurisdictional error being identified.
...
Fourth, in assessing whether a particular outcome is unreasonable, it is necessary to bear in mind that within the boundaries of power there is an area of 'decisional freedom' within which a decisionmaker has a genuinely free discretion. Within that area, reasonable minds might differ as to the correct decision or outcome, but any decision or outcome within that area is within the bounds of legal reasonableness. Such a decision falls within the range of possible lawful outcomes of the exercise of the power.
Fifth, in order to identify or define the width and boundaries of this area of decisional freedom and the bounds of legal reasonableness, it is necessary to construe the relevant statute. The task of determining whether a decision is legally reasonable or unreasonable involves the evaluation of the nature and quality of the decision by reference to the subject matter, scope and purpose of the relevant statutory power, together with the attendant principles and values of the common law concerning reasonableness in decisionmaking. The evaluation is also likely to be fact dependant and to require careful attention to the evidence.
Sixth, where reasons for the decision are available, the reasons are likely to provide the focus for the evaluation of whether the decision is legally unreasonable. Where the reasons provide an evident and intelligible justification for the decision, it is unlikely that the decision could be considered to be legally unreasonable. However, an inference or conclusion of legal unreasonableness may be drawn even if no error in the reasons can be identified. In such a case, the court may not be able to comprehend from the reasons how the decision was arrived at, or the justification in the reasons may not be sufficient to outweigh the inference that the decision is otherwise outside the bounds of legal reasonableness or outside the range of possible lawful outcomes.
Seventh, and perhaps most importantly, the evaluation of whether a decision is legally unreasonable should not be approached by way of the application of particular definitions, fixed formulae, categorisations or verbal descriptions. The concept of legal unreasonableness is not amenable to rigidly defined categorisation or precise textural formulary. That said, the consideration of whether a decision is legally unreasonable may be assisted by reference to descriptive expressions that have been used in previous cases to describe the particular qualities of decisions that exceed the limits and boundaries of statutory power. ... The expressions that have been utilised include decisions which are 'plainly unjust', 'arbitrary', 'capricious', 'irrational', 'lacking in evident or intelligible justification', and 'obviously disproportionate'. It must be emphasised again, however, that the task is not an a priori definitional exercise. Nor does it involve a 'checklist' exercise. Rather, it involves the Court evaluating the decision with a view to determining whether, having regard to the terms, scope and purpose of the relevant statutory power, the decision possesses one or more of those sorts of qualities such that it falls outside the range of lawful outcomes.
Moreover, legal unreasonableness is invariably fact dependent and requires a careful evaluation of the evidence. That is, assessment of whether a decision was beyond power because it was legally unreasonable depends on the application of the relevant principles to the particular factual circumstances of the case, rather than by way of an analysis of factual similarities or differences between individual cases. Where reasons are provided, they will be a focal point for that assessment. It would be a rare case to find that the exercise of a discretionary power was unreasonable where the reasons demonstrated a justification for that exercise of power.
The failure of an administrative decisionmaker to make inquiry into factual matters which can readily be determined and are of critical significance to a decision made under statutory authority, has sometimes been said to support characterisation of the decision as an exercise of power so unreasonable that no reasonable person would have so exercised it.
Although decisions in the Federal Court concerned with a failure to make obvious inquiries have led to references to a 'duty to inquire', that term is apt to direct consideration away from the question whether the decision which is under review is vitiated by jurisdictional error. The duty imposed upon the Tribunal by the Migration Act is a duty to review. It may be that a failure to make an obvious inquiry about a critical fact, the existence of which is easily ascertained, could, in some circumstances, supply a sufficient link to the outcome to constitute a failure to review. If so, such a failure could give rise to jurisdictional error by constructive failure to exercise jurisdiction. It may be that failure to make such an inquiry results in a decision being affected in some other way that manifests itself as jurisdictional error.
Legislative framework Joint Development Assessment Panels
(a) have experience in one or more of the following areas of expertise -
(i) town planning;
(ii) architecture;
(iii) urban design;
(iv) engineering;
(v) landscape design;
(vi) environment;
(vii) law;
(viii) property development or management;
(i) a tertiary qualification relevant to their area of expertise and experience practising or working in their area of expertise that is, in the opinion of the Minister, sufficient to allow them to perform the duties of a specialist member; or
(ii) extensive experience practising or working in their area of expertise that is, in the opinion of the Minister, sufficient to allow them to perform the duties of a specialist member.
(a) a recommendation as to how the application should be determined; and
(b) copies of any advice received by the responsible authority from any other statutory or public authority consulted by the responsible authority in respect of the application; and
(c) any other information that the responsible authority considers is relevant to determining the application.
In considering an application for development approval the local government is to have due regard to the following matters to the extent that, in the opinion of the local government, those matters are relevant to the development the subject of the application -
(a) the aims and provisions of this Scheme and any other local planning scheme operating within the Scheme area;
(b) the requirements of orderly and proper planning including any proposed local planning scheme or amendment to this Scheme that has been advertised under the Planning and Development (Local Planning Schemes) Regulations 2015 or any other proposed planning instrument that the local government is seriously considering adopting or approving;
(c) any approved State planning policy;
(d) any environmental protection policy approved under the Environmental Protection Act 1986 section 31(d);
(e) any policy of the Commission;
(f) any policy of the State;
(g) any local planning policy for the Scheme area;
(h) any structure plan, activity centre plan or local development plan that relates to the development;
(i) any report of the review of the local planning scheme that has been published under the Planning and Development (Local Planning Schemes) Regulations 2015;
(j) in the case of land reserved under this Scheme, the objectives for the reserve and the additional and permitted uses identified in this Scheme for the reserve;
(k) the built heritage conservation of any place that is of cultural significance;
(l) the effect of the proposal on the cultural heritage significance of the area in which the development is located;
(m) the compatibility of the development with its setting including the relationship of the development to development on adjoining land or on other land in the locality including, but not limited to, the likely effect of the height, bulk, scale, orientation and appearance of the development;
(n) the amenity of the locality including the following -
(i) environmental impacts of the development;
(ii) the character of the locality;
(iii) social impacts of the development;
(o) the likely effect of the development on the natural environment or water resources and any means that are proposed to protect or to mitigate impacts on the natural environment or the water resource;
(p) whether adequate provision has been made for the landscaping of the land to which the application relates and whether any trees or other vegetation on the land should be preserved;
(q) the suitability of the land for the development taking into account the possible risk of flooding, tidal inundation, subsidence, landslip, bush fire, soil erosion, land degradation or any other risk;
(r) the suitability of the land for the development taking into account the possible risk to human health or safety;
(s) the adequacy of -
(i) the proposed means of access to and egress from the site; and
(ii) arrangements for the loading, unloading, manoeuvring and parking of vehicles;
(t) the amount of traffic likely to be generated by the development, particularly in relation to the capacity of the road system in the locality and the probable effect on traffic flow and safety;
(u) the availability and adequacy for the development of the following -
(i) public transport services;
(ii) public utility services;
(iii) storage, management and collection of waste;
(iv) access for pedestrians and cyclists (including end of trip storage, toilet and shower facilities);
(v) access by older people and people with disability;
(v) the potential loss of any community service or benefit resulting from the development other than potential loss that may result from economic competition between new and existing businesses;
(w) the history of the site where the development is to be located;
(x) the impact of the development on the community as a whole notwithstanding the impact of the development on particular individuals;
(y) any submissions received on the application;
(za) the comments or submissions received from any authority consulted under clause 66;
(zb) any other planning consideration the local government considers appropriate.
Given the range and character of the matters to which the MRA is to 'have regard', the legislative purpose appears to be to ensure that when the MRA comes to determine a development application, it will have before it all of the information and sources of guidance which will enable it to make a sound planning decision, and that in reaching its decision, the MRA will use such of that information as it considers relevant to the application before it. That legislative purpose would be achieved if the MRA were required to give 'active consideration' to the matters listed in s 66(1), while retaining a discretion to give such weight to those considerations as it considers appropriate in the circumstances.
(a) it failed to make findings of fact required to resolve disputed facts about the actual traffic situation at peak hours at the intersection of Canning Highway and Reynolds Road, and particularly on Reynolds Road south of Canning Highway, necessarily required to pay due regard to clause 67(t) of [the Deemed Provisions], as a mandatory relevant consideration; and
(b) it failed to consider for itself whether the evidence it sought at its meeting on 27 March 2017, for the reason expressed (that there was insufficient clarity about the actual traffic situation in order, implicitly, for it to properly assess likely traffic impacts for the purposes of paying due regard to clause 67(t) of the Deemed Provisions) had been provided in order for it to make the findings of fact required to resolve the disputed factual issues about the actual traffic situation described above, instead accepting (by majority) the unsupported and unreasoned assurance of the City of Melville in its Responsible Authority Report provided for the purpose of the [Panel's] meeting dated 14 August 2017 that it need not do so, when:
(i) there was evidence accompanying the Responsible Authority Report to the effect that the evidence sought by the [Panel] in answer to the request of the [Panel] at its first meeting on 27 March 2017 had not been provided; and
(ii) no other evidence appeared in the Responsible Authority Report, or accompanying it, as to why the [Panel] should find that its requests (particularly requests 4 and 5) of that first meeting were not required to be answered, or the evidence sought by it provided.
Ground 1(b) - did the Second Panel have to consider what had been sought be the First Panel?
Ground 1(a) - did the Panel have to make a finding of fact about the actual traffic situation? Milem's propositions
(1) The Second Panel had to read all the material that was before it.
(2) If the members of the Second Panel read all of the material, it should have been obvious to them that what the City was telling them was wrong, in that there were factual disputes as to the traffic impact of the proposed development that needed to be resolved.
(3) Therefore, it would be 'seriously illogical' (and would therefore be legally unreasonable) for them to conclude there was not a substantial traffic impact without resolving the factual disputes.
Should it have been obvious that the City was wrong?
(1) the minutes of meetings on 13 July 2017 and 20 July 2017, neither of which related to the Application.[81] (The minutes of the First Panel meeting were not included);
(4) a Retail Sustainability Assessment report and two information papers on this topic (not relevant to the judicial review application);[84] and
(5) extracts from the City's Local Planning Strategy document (also not relevant).[85]
It is understood that the City of Melville are satisfied that, through the additional SIDRA analysis undertaken in conjunction with MRWA, the issues raised in the Cardno review have been suitably addressed.
MRWA [Main Roads] have indicated that there is no objection raised in principle to the development as proposed, noting that road widening and the provision of a right turn pocket can be provided within the limitations of the existing road reserve subject to detailed designs being developed and approved.
(3) Further detail of the proposed off site road improvements to Reynolds Road in relation to the required road geometry including any additional road widening requirements to effect the south bound turning pocket; should that be one of options;
(4) Further traffic analysis to provide greater understanding and certainty that the vehicle access to the development for customers, delivery and waste vehicles will not be impacted by vehicles queuing in Reynolds Road at the intersection of Canning Highway;
(5) Further traffic analysis to review current traffic volumes, particularly at peak times in Reynolds Road south of Canning Highway, and the current traffic queuing that occurs in Reynolds Road having particular regard to the peer review comments of Cardno;
(6) Further detail on any potential changes required for the Canning Highway/Reynolds Road intersection to allow satisfactory traffic management around this proposed development.
Both the City and MRWA consider that further traffic analysis is not required. Substantial traffic analysis had been undertaken between consultants on behalf of the applicant (Riley Consulting), MRWA and the City's own traffic engineers in order to address the matters raised following submission of the version 2 of the TIA. The further traffic analysis undertaken by MRWA, the City and the applicant, addressed the matters raised in the peer review undertaken by Cardno on behalf of the City, and the initial comments raised by MRWA. It is noted that a third party peer review undertaken in respect of version 2 of the TIA [this was Move's First Report] was considered by the City as a submission to the initial planning application, the details of which were provided to the JDAP in the initial RAR.
To address the matters raised in points 4 and 5 of the deferral, the applicant has submitted a traffic memo [the Technical Note] that contains a chronological list of the traffic inputs provided, a summary of liaison between parties and the extent of the further traffic analysis to address the matters raised by MRWA and the Cardno peer review.
While the section 31 application has satisfied the reasons for deferral in respect of [the various matters] and clarified the position in respect of further traffic analysis being provided, the information provided in the RSA[98] has raised concerns regarding the real impacts [unrelated to traffic] that will accrue from the development if it was allowed to proceed. ...
On that basis, it is the reconsidered opinion of the City that the development the subject of this section 31 reconsideration should be refused planning permission for the reasons stated.
A Road Safety Design Audit should be undertaken to identify the [sic] any roadside and onsite safety and conflict points and any modifications to existing median islands and road seal, line marking and signage which may be required to accommodate site-generated traffic. It is our understanding that Council at its meeting of 14th March 2017 resolved to amend Condition 22 of the RAR approval to include the requirement for a Road Safety Audit, prior to the issuance of a building permit.
Prior to the commencement of the development an independent Road Safety Audit (RSA) shall be undertaken. The recommendations of the RSA shall be included in the final detailed design, and implemented prior to the initial occupation of the development.
The further traffic analysis undertaken by MRWA, the City and the applicant, addressed the matters raised in the peer review undertaken by Cardno on behalf of the City, and the initial comments raised by MRWA.
Move suggest that the 35% passby reduction has been applied to the site access. This is not true. 100% of the forecast traffic is applied to the site access. Passby reductions have only been applied to the external road network.
(1) If optimal traffic signal time was not used, there would be a 50% probability of blockage in the afternoon peak period.
(2) Riley should have considered the impact of nonoptimal timing.
(3) The issues raised by the First Panel included the use of optimal signal timing.
Further traffic analysis to provide greater understanding and certainty that the vehicle access to the development for customers, delivery and waste vehicles will not be impacted by vehicles queuing in Reynolds Road at the intersection of Canning Highway.
Obviously the adequacy to accommodate the localised road widening on Reynolds Road to accommodate transfer to the driveway safely. The issue of ongoing congestion and operations in the area generally and then what's going to happen at the intersection itself.
The traffic impacts of the proposed Woolworths store and medical centre have been peer reviewed and they've been thoroughly assessed by professional officers at the City of Melville and at Main Roads.
The peak hour assessment of the local road network shows acceptable levels of service are maintained with no changes to the current traffic signal timings of Canning Highway. During the morning peak period the level of traffic generated by the development is not so significantly greater than the existing use of the subject land and as such the proposed development has minimal impact on peak queues and delays at that time.
During evening peak hour, queues are shown to increase on Reynolds Road northbound ... [b]ut are shown not to extend to interfere with the proposed access. This is because the access has been relocated to the most southern point of the subject land and allows ample stopping length before the traffic signals. The location of the access has been endorsed by Main Roads. Longterm queuing issues have been confirmed by Main Roads to be general traffic growth issues and are not a direct consequence of the proposed development. For the benefit of the new JDAP members, there was a letter from Main Roads back to the City that ... indicated that significant queueing would occur in the very longterm, ah, scenarios. But again, this is not as a result of this development.
Since the last meeting of the Joint Development Assessment Panel, further discussions and meetings have been held with the City of Melville and Main Roads, to clarify the matters raised and the reasons for deferral. Now as shown on pages 11 through to 13 of the Responsible Authority Report the reasons for deferral have been addressed and the report concludes, and I will summarise here. The section 31 application has satisfied reasons 2, 3, 4, and 5 of the deferral. Those reasons were traffic ground related and therefore in my opinion there are no real reasons why the development should be refused in terms of traffic requirements.
Whilst respecting the special control area, planning control area that is ... applied to this intersection which allows Main Roads to do a major upgrade at some point or another; that's all been considered in a lot of detail. And the City and Main Roads are comfortable with that configuration on Reynolds Road. ... [F]rom a road safety perspective, I think we all acknowledge that it's ... I lived in [the] area, it's a congested intersection. [B]ut in terms of this development and what it brings, there's a level of acceptance amongst the agencies.
Yes the City's representative is not here today but was involved in the mediation of the SAT and has been involved in the correspondence that we have been going to from, including Main Roads and are happy that the offside works of roads improvement can take place within the road reserve.
Firstly ... these reasons, these additional reasons, reflect some of the concerns of the residents nearby the development and I certainly acknowledge that those concerns represent the ... at least the perceived impacts of the development. Against that we have to weigh the issues in regards to the evidence about those impacts to confirm whether they are likely to be significant or not. [I]n this case, the advice from the City Administration, and also the Main Roads and the context of the traffic impact, notwithstanding that we did have some experts from the deputations which raised these concerns. On balance, I believe that I cannot find significant enough evidence to justify the refusal on these grounds, on these 2 grounds, based on the evidence that the City has provided with the Main Roads. So the City, the Design Advisory Panel, the Main Roads Department have said that these impacts are manageable and for that reason I can't support the amendment. So I am voting against them.
Mr Chair I would like to speak against the recommendation on the basis that I was at the previous JDAP and it was clear that the deferral was on the basis of 3 items and they were traffic, amenity and the retail sustainability assessment. Having had due regard to all the papers that were received and the reports, previous reports, reports before us, I'm not supportive of the refusal ...
Main Roads and the City have confirmed the suitability. There is obviously going to be a traffic impact from this development, but there already is an issue on Reynolds Road which needs to be addressed. I don't see, and the reports confirm, that there is an undue impact on traffic and there are conditions in the alternative which actually address that.
So with that I'm going to vote for the approval with conditions. I've been through those conditions. I think they are sound conditions. There is room for further work in respect to some of the traffic issues which are important to refine. Condition 22. So, and I believe that there is a sufficient control in the construction management plan to deal with this operation.
The Panel in the majority formed the view that the application could be approved having regard for the range of views being expressed and the advice provided through deputations and the RAR Report. Some of the deputations raised concerns about the amenity and traffic impacts of the proposal however these were not supported by technical advice from the City of Melville or Main Roads WA.
The design modifications to the proposal were considered to satisfactorily ameliorate the development to adjoining neighbours noting that the City's design review panel were satisfied with the previous design.
A concept design for a righthand turn pocket in Reynolds Street by the applicant has been presented. Main Roads WA and the City were satisfied that the design demonstrates that the works are feasible and will not have an impact on the functionality of the intersection. The righthand turn pocket has been designed in such a manner to accommodate delivery and waste vehicles safely into the site without impact by vehicles queuing on Reynolds Road. The detailed design of this improvement is included in a condition of approval.
...
In summary it was agreed that whilst Panel Members might prefer the supermarket to be located in a larger activity centre it could not be said that the proposal before the Panel could be refused on that basis having regard for its acceptable amenity and traffic impacts.
(1) The Second Panel imposed conditions 21 and 22 for the purpose of easing congestion.
(2) The Second Panel simply assumed that those conditions would ease congestion.
(3) On the material available to the Second Panel, it was not open to the Second Panel to make that assumption because:
(a) the material showed there was a dispute about the traffic;
(b) in those circumstances, the Second Panel was not permitted to simply accept the City's views;
(c) the Second Panel had the power to seek more information; and
(d) if the Second Panel had sought more information, it would not have been a fruitless inquiry.
(4) In those circumstances, it was legally unreasonable to make the assumption (and therefore legally unreasonable to impose the conditions).
Did the Second Panel impose the conditions for the purpose of easing congestion?
Prior to the commencement of the development an independent Road Safety Audit (RSA) shall be undertaken. The recommendations of the RSA shall be included in the final detailed design, and implemented prior to the initial occupation of the development.
In accordance with the detailed traffic information supplied in support of the development and prior to the commencement of the development, a detailed design for the provision of off site road improvements to facilitate access into the development from Reynolds Road south bound, shall be provided to and approved in writing by the City. The agreed measures shall be implemented and made available for use prior to initial occupation, and shall be provided at the applicant's expense.
So with that I'm going to vote for the approval with conditions. I've been through those conditions. I think they are sound conditions. There is room for further work in respect to some of the traffic issues which are important to refine. Condition 22. So, and I believe that there is a sufficient control in the construction management plan to deal with this operation.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[3] Affidavit of Gregory Ian Brindle sworn 14 February 2018 (Brindle Affidavit), page 266.
[4] See under the heading 'Legislative framework'.
[7]Affidavit of Mark Andrew Etherington sworn 2 May 2018 comprising 313 pages (Etherington First Affidavit), pages 151 152.
[9] Move's First Report par 1 (in Brindle Affidavit, page 315), the Brindle Affidavit [1] and Affidavit of Mark Andrew Etherington sworn 2 May 2018 comprising 61 pages (Etherington Second Affidavit), page 20. Milem referred to Move as 'the Applicant's consultant' in its submissions - see Applicant's Outline of Submissions in Reply filed 28 June 2018 (Milem's Reply Submissions) [18(c)].
[11] The composition of Joint Development Assessment Panels is explained in the next section.
[12] Affidavit of Heidi Herget-Lansdell sworn 14 February 2018 [3].
[13] Brindle Affidavit, pages 223 - 224.
[16] The State Government planning policy 'Activity Centres for Perth and Peel', 'SPP4.2', advocates a hierarchical approach to 'Activity Centres' to allow for the planning, management, and control of Activity Centres. Activity Centres are 'community focal points'. They include activities such as commercial, retail, higher density housing, entertainment, and medical services. Activity Centres are ranked according to the existing or planned role and function of that centre, the needs of the community it serves, and the accessibility to employment opportunities it provides. So, for example, a development with a large shop floor area should ordinarily be placed within a 'District Centre' level Activity Centre, not a 'Local Centre' level Activity Centre. See Etherington First Affidavit, pages 170 182 and SPP4.2.
[18] Some minor changes were made to conditions 14, 16 and 17 - see Brindle Affidavit, page 364.
[20] Order 56 r 2 of the Rules of the Supreme Court 1971 (WA).
[21] Milem did not allege errors of law on the face of the record.
[22] Re Refugee Review Tribunal; Ex parte Aala [2000] HCA 57; (2000) 204 CLR 82 [163]. This statement was applied in Forrest & Forrest Pty Ltd v The Honourable William Richard Marmion, Minister for Mines and Petroleum [2017] WASCA 153; (2017) 51 WAR 425 [86] [88].
[23] Hossain v Minister for Immigration and Border Protection [2018] HCA 34; (2018) 359 ALR 1.
[24] Hossain [23], [27] (Kiefel CJ, Gageler & Keane JJ).
[26] Minister for Immigration and Border Protection v SZVFW [2018] HCA 30; (2018) 357 ALR 408 [4] (Kiefel CJ), [53] (Gageler J), [89] (Nettle & Gordon JJ), and [134] (Edelman J).
[29] Mohammadi v Bethune [2018] WASCA 98 [31]. See also all of [31], and [32] [36].
[30] Australian Unity Property Limited as responsible entity for the Australian Unity Diversified Property Fund v City of Busselton [2018] WASCA 38 [77] [85].
[31] Minister for Immigration and Border Protection v Eden [2016] FCAFC 28; (2016) 240 FCR 158 [58] [60], [62] - [65], cited by Buss P in Western Australian Planning Commissioner v The Board of Valuers [2018] WASCA 145 [172].
[33] Minister for Immigration and Citizenship v SZIAI [2009] HCA 39; (2009) 259 ALR 429.
[37] Minister for Immigration and Citizenship v Dhanoa [2009] FCAFC 153; (2009) 180 FCR 510 [50].
[38] Minister for Immigration and Border Protection v SZRTF [2013] FCA 1377 [40].
[40] Panel Regulations regs 35(1) and 37(1).
[42] Panel Regulations reg 35(2) and the definition of 'department' in reg 3(1).
[46] Panel Regulations reg 12. The period is either 48 or 78 days after the application was made or 12 days before the application would be deemed to be refused, depending on the circumstances.
[50] Planning and Development (Local Planning Schemes) Regulations 2015 (WA) pt 2 reg 10(4) and the Planning and Development Act 2005 (WA) s 256 and 257B.
[52] ts 141 142. See also ts 104 108, 110 111, 115 116, 129 and 143 145. I give more detail of Milem's final position in dealing with ground 1(a).
[54] Marshall v Metropolitan Redevelopment Authority [2015] WASC 226.
[58] S & L Lenz Pty Ltd v The Shire of Serpentine Jarrahdale [2017] WASC 191.
[60] ts 43 and 171. See also Milem's Reply Submissions [11], [15], [18(h) - ''realistic consideration'].
[61] Second Respondent's Outline of Submissions and List of Authorities filed 25 June 2018 [32].
[62] See the discussion of ground 1(a) below.
[66] See under the heading 'Due regard'.
[67] ts 141 142. See also ts 104 108, 110 111, 115 116, 129 and 143 145.
[73] Planning and Development Act s 171A(3) and Panel Regulations regs 8(1)(a) and 16.
[79] See the discussion under the heading 'Jurisdictional error'.
[80] Etherington First Affidavit, pages 153 313.
[81] Etherington First Affidavit, pages 157 169.
[82] Etherington First Affidavit, page 200.
[83] Etherington First Affidavit, page 222.
[84] Etherington First Affidavit, pages 235 307.
[85] Etherington First Affidavit, pages 308 313.
[86] Letter from the State Solicitor's Office dated 16 November 2018.
[90] Brindle Affidavit, pages 332 - 333.
[92] Brindle Affidavit, pages 331 332 and 333 334.
[93] Etherington First Affidavit, pages 170 182.
[95] The concept design is in the Etherington First Affidavit, page 199.
[96] Etherington First Affidavit, page 181.
[97] Etherington First Affidavit, pages 181 - 182.
[100] Applicant's Written Submissions filed 12 June 2018 (Milem's Written Submissions) [39] and [40(c)(ii)].
[102] Milem's Written Submissions [39].
[103] Milem's Written Submissions [35].
[104] Brindle Affidavit, pages 340 355.
[105] See under the heading 'The meeting'.
[106] See under the heading 'The meeting'.
[107] The topic was also mentioned on pages 6 and 10.
[108] See, for example, the second last sentence above the first bullet point on page 8 of the report, Brindle Affidavit, page 347.
[109] See under the heading 'Milem's criticisms of Riley's response'.
[110] Milem's Written Submissions [60(d)] and [61].
[112] Brindle Affidavit, page 215 - 216.
[113] Milem's Written Submissions [61].
[121] Brindle Affidavit, pages 331 and 332.
[131] Etherington First Affidavit, pages 180 - 181.
[133] Mr Hall and Mr Doyle referred to traffic, but not substantively - see Etherington Second Affidavit, pages 16 and 19.
[134] See under the heading 'Move's Second Report'.
[135] Etherington Second Affidavit, page 20.
[136] Etherington Second Affidavit, page 20.
[137] Etherington Second Affidavit, page 21.
[138] Etherington Second Affidavit, pages 20 21.
[139] Etherington Second Affidavit, pages 21 22.
[140] Etherington Second Affidavit, page 25.
[141] Etherington Second Affidavit, page 26.
[142] Etherington Second Affidavit, pages 26 27.
[143] Etherington Second Affidavit, page 27.
[144] Etherington Second Affidavit, page 26.
[145] Etherington Second Affidavit, page 36.
[146] Etherington Second Affidavit, page 38.
[147] Etherington Second Affidavit, pages 42 48.
[148] Etherington Second Affidavit, page 43.
[149] Etherington Second Affidavit, page 48.
[150] Etherington Second Affidavit, pages 50 51.
[151] Etherington Second Affidavit, page 53.
[152] Etherington Second Affidavit, page 53.
[153] Etherington Second Affidavit, page 54.
[154] Etherington Second Affidavit, page 54.
[155] Etherington Second Affidavit, page 55.
[156] Etherington Second Affidavit, pages 55 56.
[157] Etherington Second Affidavit, page 56.
[158] Etherington Second Affidavit, page 58.
[159] Etherington Second Affidavit, page 59.
[160] Etherington Second Affidavit, page 59.
[161] Some minor changes were made to conditions 14, 16 and 17 - see Brindle Affidavit, page 364.
[162] Brindle Affidavit, page 367. The conditions are set out later in these reasons, under the heading 'The conditions'.
[163] Etherington Second Affidavit, page 60.
[164] Brindle Affidavit, page 368 - 369.
[165] Eden [64]. See also SZVFW [84].
[166] Reid v Western Australian Planning Commission [2016] WASCA 181 [26], [35], [37] and [40].
[169] ts 140 141, 146. See also ts 137 139, 167 168, 170, 211 212 and Milem's Written Submissions [52], [64].
[171] Etherington First Affidavit, page 181.
[173] See under the heading 'The meeting'.
[175] This was accepted by Milem - see ts 119.
[176] See under the heading 'The meeting'.