McDaid v The Owners - Strata Plan No. 60346
[2023] NSWCATCD 134
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2023-05-16
Before
Palmhide P
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
Introduction
- This is an application by Peter McDaid (the Lot Owner) for 16 orders under the Strata Schemes Management Act 2015 (NSW) (the Act), which include an order that would require The Owners - Strata Plan 60346 (the Owners Corporation) to pay him damages, being lost rent, he contends he continues to suffer due to the Owners Corporation's alleged failure to repair common property in his Lot, an order that would require the Owners Corporation to effect such repairs, and orders that would either appoint a compulsory Strata Manager to manage the Owners Corporation's affairs or remove a current member of the Strata Committee from office. This application was made to the Tribunal on 29 December 2022 (the application).
- For reasons explained in greater detail following I have determined that the application must be dismissed. While it may be accepted that the common property associated with the Lot, being the water proofing, has been in a state of disrepair since at least May 2022, the Lot Owner has failed to substantiate his damages claim in respect of lost rent from that date. Neither party has placed before the Tribunal a final scope of works which could provide the basis for a work order, and the Lot Owner, who bears the onus of doing so, specifically rejects the possibility that a 'preliminary scope of remediation works' recommended by the Owners Corporation's building consultant, Mr Thorburn, dated 22 May 2023 could provide an adequate foundation for such an order. The appointment of a compulsory Strata Manager and the removal of a Strata Committee Member are very serious steps that can only be taken in the clearest cases of persistent dereliction of an Owners Corporation's functions. There is no evidence of this in this case.