[2025] NSWCATCD 152
General information, not legal advice.
NCAT Consumer and Commercial
2025-10-02
Original judgment source is linked above.
Kammoun Sukari Lawyers (Applicant / First Cross Respondent)
(1) damages for the cost to rectify the defective work or in the alternative, a work order for the removal of the frames and trusses and their instillation; and
(2) delay damages for increased construction costs to complete the project and lost rent.
(1) says it is owed money by the applicant either pursuant to the BP Contract on a quantum meruit basis; and
(2) seeks to be indemnified by SPD in respect of any relief ordered against it on the applicant's claim.
(1) Email from Arshia Jain dated 19 May (Ex. 1).
(2) Email from Nimish Mittal to Ali Mashat dated 18 December 2023 (Ex. 2).
(3) Email from Ali Mashat to Nimish Mittal dated 18 December 2023 (Ex. 3). SPD.
(4) Conclave report dated 17 February 2025 (Ex. 4).
(5) Email from Ali Mashat to BP dated 14 February 2024 attaching a quote from Crellin Carpentry (Ex. 5).
(6) Site Inspection Report of Halina Engineers (Ex. A).
(7) Extract from what was referred to as "the NASH" headed "Class 1 and10 buildings" (Ex B).
(8) Tax Invoice from Building certifies to BP dated 5 April 2023 (Ex. C).
(9) Email from the applicant to BP dated 20 July 2023 (Ex. D).
(1) A Transcript.
(2) The parties "Joint Summary of Issues for determination".
(3) The applicant's closing submissions and applicant's Chronology.
(4) BP's closing submissions.
(5) SPD's closing submissions and SPD's chronology.
(6) Applicant's closing submissions in reply.
(7) BP's reply to SPD's submissions on BP's indemnity claim.
(1) (Issue 2) The nature of and the terms of the BP Contract and more particularly:
(a) was it a term of the BP Contract that BP was to only recommend licensed contractors to be engaged to carry out the building works; or
(b) was it a term of the BP Contract that BP was to notify the applicant of any reasons why a particular contractor whose quote had been obtained was unsuitable to be selected to carry out building works, and
(c) if one or other of those terms applied, did BP breach it?
(2) (Issue 1) Whether BP was a party to the SPD Contract and if so, in what capacity, and does it mean that BP is liable for the works carried out by SPD?
(3) (Issue 3) If BP breached the BP Contract was any such breach causative of any loss suffered by the applicant.
(4) (Issue 4) The scope of the rectification work required, and more particularly, can the defective work of SPD be remedied in situ or does the work (i.e. the frames and trusses) have to be removed and replaced.
(5) (Issue 5) Is the applicant entitled to damages for defective work against BP and / or SPD? and if so, what is the sum of damages?
(6) (Issue 6) Whether a money order or a work order should be made, and if so, the form of the order and whether the order should be against BP as well as SPD. Relevant to whether a money order can be made is whether the SPD Contract has been terminated and if not, whether it is open to the Tribunal to make an order for damages
(7) (Issue 7) Whether the applicant is entitled to delay damages against BP and / or SPD? And if so:
(a) has there been a failure to mitigate? and
(b) can SPD rely on clause 18 of the SPD Contract (Consequential Loss) to limit its liability or is that clause unenforceable by reason of sections 10 and /or 94 of the HB Act or void pursuant to s 18G of the HB Act.
(8) (Issue 8) If BP is liable to the applicant, is it entitled to be indemnified by SPD?
(9) (Issue 9) Whether BP is owed any money by the applicant pursuant to the BP Contract, or on quantum meruit basis, and if so, how much?
(10) (Issues 10 and 11) - Raised by BP, but which the applicant contends are not open on the parties' pleadings. Subject to a consideration of issue 2:
(a) whether BP acted reasonably in accepting a representation from SPD that it was licensed carry out the work and,
(b) if the terms of the BP Contract included an obligation to 'check if the necessary licenses were held', did the first respondent discharge that obligation by making a direct enquiry of SPD as to whether it had the necessary licenses.
Consideration of back ground facts and the agreed issues
Contract between the Applicant and SPD and Issue 2 as to its terms
This quote is for constructing a New Double Story Dwelling with granny flat at [the Property]
...
The Cost Plus price quote is based on the plans submitted on 10/02/2023.
...
4. Frame and LVL
Standard - conventional or Frames and Trusses 90 x 45 MGP10, Pine and LVL to support roof as required as per Australian standard
...
This is a Cost plus Price Quotation for Ali Mashat, for a New Double Story Dwelling with granny flat at ...
"Quoted Price" of "$1,250,000.00 - $1,300,000.00"
Builders fees at 10%".
(1) On 25 March detailed termite treatment required, queried the timber framing to be installed, queried the piering to be installed, requested a 25 year structural warranty, advised that he need more time to read the [Estimate] and stated:
I need you to build this house as if you were building it for yourself
I am not after minimal basic just to beet national building code of Australia (NCC) requirements.
I am not after a standard home. Please do not give me the minimum.
This is my lifetime home, must be built to a high standard with high-quality items everywhere.
Why 26L GAS hot water system for big house? It is not sufficient.
Need 25 KW Air Conditioner for main house (minimum)
Why 2 drawers for wardrobes
1 Down light is not sufficient. I am looking at 200 + Downlights for main house alone, more with Granny Flat.
I need to do more reading of the contract, and we need to discuss these please.
Also, what happens of I agree to what you have put (materials / items) and change my mind and want something else. I'm talking about Costs.
(a) sought confirmation as to whether the 10% Builders fee is included in the estimate of $1.25 -$3 million?
(b) noted:
Also, there are many items in your estimate that are not mentioned, e.g The Kitchen, Type/design, Toilet/shower type etc... etc... many many items, doors, windows, fireplace etc... etc...I cannot sign contract
(c) suggested to the effect that that what could be done is that:
(i) they sign a Contract such that BP charges 10% of the build cost; and
(ii) BP tell the applicant what items are needed up front and along the way with a minimum of 4 weeks' notice and recommend "people, with their quote" with the applicant to "check or choose differently" and once agreed upon, make payment for the relevant "item / workmanship" or that part of the construction, but stating:
I also would reserve the right to change them or choose a different item if I didn't like either the looks / appealingness (sic), Quality or workmanship
(1) Neither the 25 or 27 March emails make any reference to either the house or granny flat being rented out or the time within which the work was to be performed;
(2) The 25 March appears to identify work that will be required to be added to or changed from the Estimate;
(3) The 27 March email makes clear that the applicant will be entitled to make changes to materials, the work or contractors for "looks/appealing ness, Quality or workmanship" reasons.
(4) The 27 March email makes no reference to BP's role with respect to the work to be performed by any contractors.
(5) In my view, the nature of the applicant's required involvement and that there are items to be added that are not mentioned in the Estimate, would make identification of an actual cost or time for completion difficult.
(1) The contract between the applicant and BP was entered on about 27 or 29 March 2023.
(2) The agreement was partly written, partly oral and partly implied having arisen from the Estimate, emails exchanged on about 25 and 27 March 2023 and the telephone conversation on 29 March.
(3) The contract was a cost plus contract (although the applicant was to pay contractors directly and would only be paying BP the 10%) with an estimated price of $1,250,000.00 to $1,300,000.00.
(4) To the extent written it comprised the Estimate and emails from the applicant to the BP on 25 and 27 March 2025 and included that it was in respect of "constructing a new Double Storey Dwelling with granny flat at the [Property]" which relevantly included "4, Frame and LVL".
(5) The relevant oral terms of the contract were to the effect that:
(a) BP was to inform the applicant of the work to be performed;
(b) BP was to recommend suppliers and subcontractors to be used for the work to be performed to the applicant;
(c) BP was to obtain quotes for the work by suppliers and subcontractors and provide the quotes to the applicant;
(d) The applicant could obtain his own quotes for suppliers and contractors and provide them to BP for any recommendation;
(e) BP would make recommendations to the applicant including as to a supplier or subcontractors suitability;
(f) The applicant would determine the suppliers or subcontractors to be used;
(g) The applicant's name would be placed on any contract with any contractors for the purposes of the applicant then making payment direct the subcontractors.
(1) The following warranties by the holder of a contractor licence, or a person required to hold a contractor licence before entering into a contract, are implied in every contract to do residential building work -
(a) a warranty that the work will be done with due care and skill and in accordance with the plans and specifications set out in the contract,
(b) a warranty that all materials supplied by the holder or person will be good and suitable for the purpose for which they are used and that, unless otherwise stated in the contract, those materials will be new,
(c) a warranty that the work will be done in accordance with, and will comply with, this or any other law,
(d) a warranty that the work will be done with due diligence and within the time stipulated in the contract, or if no time is stipulated, within a reasonable time,
(e) a warranty that, if the work consists of the construction of a dwelling, the making of alterations or additions to a dwelling or the repairing, renovation, decoration or protective treatment of a dwelling, the work will result, to the extent of the work conducted, in a dwelling that is reasonably fit for occupation as a dwelling,
(f) a warranty that the work and any materials used in doing the work will be reasonably fit for the specified purpose or result, if the person for whom the work is done expressly makes known to the holder of the contractor licence or person required to hold a contractor licence, or another person with express or apparent authority to enter into or vary contractual arrangements on behalf of the holder or person, the particular purpose for which the work is required or the result that the owner desires the work to achieve, so as to show that the owner relies on the holder's or person's skill and judgment.
(2) The statutory warranties implied by this section are not limited to a contract to do residential building work for an owner of land and are also implied in a contract under which a person (the principal contractor) who has contracted to do residential building work contracts with another person (a subcontractor to the principal contractor) for the subcontractor to do the work (or any part of the work) for the principal contractor.
(1) that BP was to only recommend licensed contractors to be engaged to carry out the building works; or
(2) that BP was to notify the applicant of any reasons why a particular contractor whose quote had been obtained was unsuitable to be selected to carry out building works.
Issue 3, breach, and sections 7 and 10 of the HB Act
SPD Contract and Issue 1 as to whether BP was a party to the SPD Contract
(1) made handwritten amendments, by inserting additional terms identified as A, 1, 2 and 3, and otherwise at clauses 13.2 and 14, to the terms set out in the 19 April quote;
(2) Identified Sam Ouraha as "The Builder" and inserted his name as "the Owner", so that the "Client" was identified as Sam Ouraha, as the builder and Ali Mashat as the owner;
(3) inserted his mobile number and email address; and
(4) on the last page inserted his details as "the Purchaser" and "owner", dated and signed the quote.
1.I have signed the agreement subject to the following:
2.No production is to take place unless both myself and my builder, have agreed and signed off on the shop drawings.
3.There possibly may be some changes to the first floor, and my builder would be in contact with you regarding them. They need to be taken into account and be reflected in the design, i.e., the shop drawings please.
4.Extra support would be needed for the En-suite of the Master Bed Room (1st floor) due to the bathtub. The Bath Tub will most likely be a large bathtub, and support would need to be provided to account for the weight of Water when the bathtub is fully filled with water.
4.Delivery should not take place unless all parties have agreed on a delivery date.
5.Please note that there is no column support in the inner corner of the ground floor Alfresco of the main house (where the two bifold doors meet). Thus, there will be a large span from the Left wall of the Family to the way to the Right wall of the Alfresco - A fully open span, with no walls or columns in between other than the walls clearly shown on the DA plan.
Please get quote for Slab, I am signing the contract today any delays in delivery as result of my fault will be very expensive for me,
Please get quote for Slab, I am signing the hardcore steel frame and trusses contract today any delays in delivery as result of my fault will be very expensive for me,
I have emailed the signed contract to Hardcore steel and have transferred 30% deposit ($35863.50) screen shot of transfer attached to the email.
I have CC's yourself in the email.
(1) whether BP is a party to the SPD Contract, and if so,
(2) does that mean BP is liable for the works carried out by SPD as its subcontractor.
(1) A contract may be inferred from the acts and conduct of parties as well as or in the absence of their words. The question is whether the conduct of the parties viewed in the light of the surrounding circumstances shows a tacit understanding or agreement:
(2) Acceptance of the terms of a contract may be inferred if there is no actual communication of that acceptance, where the conduct relied upon can be objectively determined to indicate that the party intended to be bound by the contract formed.
(3) Conduct occurring after the date of a contract was allegedly formed by acceptance of an offer is admissible on the question of whether a contract has been formed as alleged.
(4) The terms to a contract should be construed so as to give them the meaning intended by the parties.
(5) Intention is (subject to limited exceptions) determined objectively; what would a reasonable person think was intended by the term. Consistent with other contract law principles, intention of the parties is determined objectively, not by reference to actual subjective intent.
(1) the BP contract;
(2) Mr Ouraha's conduct up to 20 April 2023 being consistent with BP being a party to the SPD Contract;
(3) the applicant's name being inserted next to Mr Ouraha's name on the contract and Mr Ouraha's name not being crossed out;
(4) Mr Ouraha not taking issue with being named as a party on the SPD Contract;
(5) SPD emailing Mr Ouraha in July 2023 with revised pricing;
(6) BP being named as an applicant in a claim against SPD;
(7) SPD claiming 10 % on amounts paid to SPD; and that
(1) that it did not sign the SPD contract;
(2) general discussions between the applicant and Mr Ouraha are irrelevant to the extent that they occurred before the contract was signed;
(3) the applicant took control of negotiations with SPD; and
(4) that the applicant commenced proceedings also naming BP as an applicant.
(1) rather than confirming their arrangement in a document signed by the applicant and BP that their arrangement arose from the Estimate and emails exchanged and conversations that took place after the Estimate was sent by BP and
(2) the applicant making handwritten changes to the SPD Contract and then inserting his name as a client and signing the contract.
(1) Putting to one side that it is only signed by the applicant, on the face of the SPD Contract it is between:
(a) Sam Ourimbah (or possibly BP) as the Builder and [the applicant], as the owner as the Client;
(b) and [SPD].
(2) There is no evidence that Mr Ouraha was shown the handwritten amendments made by the applicant before they were inserted and the signed contract emailed to SPD.
(3) Having said that, no issue was ever taken by BP or Sam Ouraha to Sam Ouraha being named as the "Client" and BP's email address being identified as the "Client Email" on every version of the SPD Agreement, all of which were emailed to Sam Ouraha and BP or the version signed by the applicant which was emailed to SPD and BP;
(a) arranged for the home warranty insurance certificates which identify work being carried out by "Build Property Pty Ltd" with "License number 361897C" for a contract amounts totalling $1,200,000.00 pursuant to a contract made on 27 March 2023; and
(b) engaging with SPD in respect of revised quote from SPD which it received on 26 July and emailed to the applicant on 27 July;
(1) I am satisfied that BP is a party to the SPD contract;
(2) In so far as BP is a party to the SPD Contract it is collectively with the applicant, the Client or the principal.
(3) BP would be liable for the works carried out by SPD, because that work is part of the work contemplated by the BP Contract and to which the implied warranties apply.
(1) BP and the applicant were collectively the "Client", and the SPD contract was not an orthodox builder and subcontractor contract;
(2) There is no dispute that the defective work is in respect of the instillation of the frames and trusses which BP was contacted to do and is clearly the work of SPD, not SPD and BP; and
(3) s 48MA of the HB Act provides:
A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the "responsible party") is to have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome.
Events from the entering of SPD contract on 20 April (including obtaining of a construction certificate, delivery of frames and trusses to the Property in September 2022 and issues regarding delay and defective work) up to the commencement of proceedings in November 2023
Description of construction as advised by builder: Construction of a double storey dwelling with attached secondary dwelling.
Licence number: 361897C
Carried out by: Build Property Pty ltd
Contract date: 27 March 2023.
Issue 4 Whether the appropriate rectification is to remedy in situ or remove and replace the frames and trusses
(1) Mr Prasad gave evidence to the effect that in his view the most appropriate scope of work, because of how widespread the defects were and their number, was that the existing structure be removed and the frames and trusses re- engineered and then installed;
(2) In respect of one of the more significant defects, being gaps at the bottom of studs and widespread defects:
(a) Mr Prasad suggested an in situ repair involving putting another vertical stud back to back;
(b) Mr Nguyen gave evidence to the effect that that would not work and recommended using angle brackets;
(c) Mr Prasad then gave evidence to the effect that Mr Nguyen's proposal would not work.
(1) The applicant submits that the appropriate rectification work is the removal and replacement as first proposed by Mr Prasad and that any damages ordered, if that was the appropriate rectification work, should be $283,708.00.
(2) SPD does not rely on a scope of work proposed by Mr Nguyen including in respect of dealing with gaps at the bottom of studs, and submits that the appropriate rectification work is the scope of work identified in Mr Prasad's 6 November 2024 report for an in situ repair and that any damages ordered, if that was the appropriate rectification work, should be $138,294.63, being Mr Prasad's calculations but reducing the amount for engineering inspections from $24,000.00 to $6,000.00 and reducing the amount for accidental damages of 40% ($40,216.00) to 10% ($11,425.49).
(1) the number and extent of defects, some of which he describes as major,
(2) the alternative in situ rectification assumes that the high level of skill required and a lot of supervision can be obtained; and
(3) framing and roof trusses will have to be removed in any event so that particle board flooring that has been damaged by exposure to the weather can be removed with that involving a risk of damage to those frames and trusses.
(1) Both the applicant and SPD ultimately relied on a scope of work proposed by Mr Prasad and Mr Prasad's reasoned preferred rectification was the removal and replacement of the steel frames and trusses;
(2) Mr Prasad and Mr Nguyen were in disagreement as to how the widespread defect of gaps at the bottom of studs could be rectified;
(3) There is a likelihood of further damage to the frames and issues that are required to be removed to remove the damaged flooring board;
(4) Mr Prasad's opinion, which I accept is that the rectification in situ will require a high degree of skill and supervising, and there was no evidence of any contractors will to take on the task;
(5) The extra cost is not so much more than the estimated cost of trying to repair the frames such that it could be considered prohibitively expensive or unreasonable;
(6) The framing is required for a new house;
in my view the reasonable and appropriate rectification is the removal and replacement of the framing as provided for in the Scott Schedule at Appendix D of Mr Prasad's 5 June 2024 Report (JB p 1299 & 1300).
Issue 5 Is the applicant entitled to damages for defective work as against BP and / or SPD, and if so, what damages? &
Issue 6 Should the Tribunal make a money order or work order in respect of the defects?
(1) The general principle is to the effect that while the contract remains on foot, it is open to the builder to rectify any defect, at least as long as the owner maintains that practical completion has not been achieved, with the consequence that an entitlement to damages has not yet accrued.
(2) That principle can have no application to a claim seeking orders that a building contractor perform work required to be undertaken by the terms of a building contract, or, in relation to work governed by the HBA, to a claim pursuant to s 48O(1)(c) of the HBA for orders that the builder carry out work. ....
(3) Neither the statement of principle set out in Brewarrina Council nor the logic underlying that principle precludes the Tribunal from determining a claim for work orders pursuant to s 48O(1)(c) of the HBA while the contract remains on foot. Little v J & K Homes Pty Ltd [2017] NSWCATAP 84 (21 April 2017) (Little) at [11].
(4) Where damages are sought for delay and defective work, until such time as the contract was terminated, such an order, other than the payment of damages for delay, was not open. Little at [23].
(1) At [108], did not accept that the context in which the word 'party' is used in s48 MA, other than as noted in the section, is limited to cases where the party is the holder of a contractor licence, or that the form of order is limited to an order in terms that the responsible person do any rectification work personally.
(2) At [109], said that Section 48MA requires preference be given to orders requiring rectification by a responsible party of defective residential building work.
(3) Referred to the power to make the work orders found in s 48O of the HB Act, which states:
(1) In determining a building claim, the Tribunal is empowered to make one or more of the following orders as it considers appropriate:
...
(c) an order that a party to the proceedings:
(i) do any specified work or perform any specified service or any obligation arising under this Act or the terms of any agreement, or
(ii) do or perform, or refrain from doing or performing, any specified act, matter or thing.
(2) The Tribunal can make an order even if it is not the order that the applicant asked for.
(4) At [111] and [112], found that the powers are cast in wide terms, not limited to ordering a party to perform a contractual obligation or to do any rectification work personally and would include:
(a) ordering a party who is liable for defective building work to engage another person to perform rectification work and for the party who is liable, to pay for such work, or
(b) to require a party to take steps to cause a subcontractor to carry out rectification work, including any specialist work which may require a particular authority.
(5) At [113] and [114], that there is no reason the power under s 48O should be construed in a manner which confines its scope or to interpret s48MA as having that effect on the general powers and that doing so would mean that anyone who was liable for work of a subcontractor or third party and who had not done the work themselves may be liable to pay compensation, rather than have the benefit of the preferred outcome principle and an order which enabled them to rectify the work at their cost and/or require the subcontractor or third party who had done defective work for the responsible party to return to the site to rectify the defects at no cost to the person who was primarily liable to a homeowner or successor in title.
(6) At [117] and [118], that the expression "work by a party to the proceedings" used in s 48MA concerns work both work done personally or for which the person was responsible.
(7) At [119] and [120] that by its terms, s 48MA makes clear that a court or tribunal in determining a claim for defective work is to have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome and that liability for defective residential building work can be imposed upon a party by a contract, under common law or by legislation and each of these may give rise to a building claim within the meaning of Part 3A of the HBA.
(1) SPD's Contract was with the applicant and BP as the Client, and SPD was not BP's subcontractor the orthodox way, but was BP and the applicant's contractor;
(2) both BP, and significantly the applicant were involved in giving direction to SPD;
(3) there is no dispute that the defective work was the work SPD was contracted to performed and which SPD by its subcontractors performed and
(4) that even if an order was made against BP, it would be entitled to require SPD to return to the site to rectify the defects.
(1) Pursuant to Section 48O of the Home Building Act 1989 (NSW) the Tribunal makes the following work order in relation to the performance of remedial work to the Applicant's premises against the Second Respondent, SPD St Mary's Pty Ltd (SPD).
(2) SPD is to arrange for suitably qualified and licensed subcontractors to perform the remedial work identified in the Scott Schedule at Appendix D - pages 62 and 63 of the Report of Mr Prasad of Inhouse Engineers Pty Ltd dated 5 June 2024, (JB 1299 to 1300) (the Scott Schedule) subject to and in accordance with Orders (3) to (8) below (Work).
(3) The Work is to:
(a) be commenced within 1 month of these orders;
(b) be completed within 4 months of these orders;
(c) be undertaken by appropriately licenced and insured subcontractors and tradesman;
(d) be performed with due care and skill; and
(e) comply with, the Building Code of Australia; all relevant codes, standards and specifications; and any other law.
(4) The applicant and SPD are to jointly appoint a supervising engineer to be chosen by the applicant (the Supervisor) to perform the inspections referred to at Item 8 of the Scott Schedule.
(5) The Supervisors costs of and incidental to the inspections required by Item 8 re to be paid by SPD capped at $5000.00.
(6) The parties are at liberty to apply for an extension of the time referred to in order 2, such application to be supported by brief submissions and evidence.
(7) For the avoidance of doubt, SPD is responsible at its cost for the preliminary and miscellaneous works, including "Scaffold" identified at Item 10 of the Scott Schedule.
(8) The applicant is to give reasonable access to the Property to SPD and its contractors so that the Work can be performed.
(9) The applicant has leave to renew these proceedings if order 2 is not complied with within the period specified.
Issue 7 Is the Applicant entitled to delay damages as against BP and / or SPD and if so, has there been a failure to mitigate.
(1) Because the SPD Contract did not provide a set time it is therefore implied that the works will be performed within a reasonable time.
(2) The unchallenged expert evidence of Mr Moises Lopez in a report dated 21 June 2024 was that a competent contractor would complete the contracted scope of works within three months.
(3) Because the construction certificate was issued on 1 August 2023, the three-month period would ordinarily commence from that date.
(4) Given the tribunal was not in a position to assess conclusively which party was responsible for the delay in the finalisation of shop drawings, a reasonable time to allow for the works to be completed would be to 1 January
(5) SPD and BP should therefore be responsible for damages from that date until three months after the decision in these proceedings on the basis that that will be sufficient time for a new contractor to be engaged to complete the works that SPD were originally contracted to complete.
(6) The applicant's evidence that he intended to rent the house and granny flat out and that he would move in once married should be accepted.
(7) The loss of rent claim should be calculated $1,100.00 per week for the house and $520.00 per week for the granny flat from 1 November 2023, being $101,597.77 to 14 March 2025 and continuing at $231.43 per day.
(8) Relying on the report of Mr Lopez, the delay has resulted in an increase costs of labour and materials for the completion of the building (i.e. the rest of the work) from the original construction programme by $185,049.75.
(1) It has no contractual or other liability to the applicant for delay damages.
(2) It has done all in its power to assist the applicant to enforce its contractual rights against SPD and to mitigate its loss.
(3) The evidence as to rental for the granny flat contains assumptions of fact that were not made out on the evidence and is simply speculative.
(1) Mr Lopez does not explain why he has estimated the 2023 costs at $1.123 million when the BP Contract estimate was $1,250,000.00 to $1,300,000.00, and mindful that the applicant's case was that there were items missing from the estimate, the true cost would be higher than the estimate.
(2) Mr Lopez and the applicant's claim generally ignores the fact that the contract was costs plus, which are often used because the precise nature and extent of the work is not known and therefore cannot be priced accurately.
(3) The applicant agreed that the Estimate was a guide and that a number of items were missing from the Estimate.
(4) Having regard to the above, the total cost to undertake the work was not known and could fluctuate.
(5) Further, because the works were in their infancy, there were to many variables that would affect identifying the price increases.
(6) The applicant has not discharged the onus of satisfying the Tribunal and the Tribunal would not be satisfied that the applicant intended to rent the house or the granny flat out;
(1) negotiate with contractors directly;
(2) determine the contractors to be used; and
(3) engage with contractors to obtain invoices and pay them directly.
(1) The BP Contract was a cost plus contract which only included an estimate;
(2) The evidence made clear that there were items missing from the Estimate;
(3) Having regard to, for example the handwritten amendments made by the applicant to the SPD Contract, the exact extent of the work was not known and would be varied; and
(4) The level of active involvement the applicant had in dealing with the contractors with respect to the work completed to date and mindful of the form the BP Contract ultimately took with the applicant being able to change materials or contractors or choose a different item if he didn't like "either the looks / appealingness (sic), Quality or workmanship".
(1) None of the 25 or 27 March emails of the applicant responding to the Estimate provided by BP make any reference to an intention to rent the house or the granny flat out;
(2) Despite several emails and text messages being exchanged between the applicant and BP or the applicant and SPD following the making of the BP Contract, including up to November and December 2023 when the applicant and BP were raising concerns about delays and defective work by SPD, I have not been taken to:
(a) any email or text message where the applicant indicates an intention to rent out either the house or the granny flat;
(b) any contemporaneous record, consistent with an intention to rent out either the house or the granny flat.
Issue 8 If BP is liable to the applicant, is it entitled to be indemnified by SPD.
Issue 9 Is BP owed any money by the applicant pursuant to the BP Contract or on a quantum meruit basis.
(1) $2,339.70 incl GST for direct construction costs incurred but not paid for by the applicant;
(2) $7,700.00 pursuant to a separate oral agreement to prepare and lodge a construction certificate;
(3) 10% builder's fee of $29,464.19; and
(4) in the alternative to (1), (2) and (3), $39,503.76 on a quantum meruit basis as the fair value of the work performed.
(1) identify when the amounts of $850.00 and $277.00 were paid;
(2) mindful that the arrangement ultimately made was for BP to be paid 10% of costs paid by the applicant, identify any basis on which the payment of the costs was incurred;
(3) identify any arrangement or agreement for the hire of the skip bin;
(4) provide any documentary evidence supporting the payment of the costs in relation to the project or the hire of the skip bin; and otherwise
(5) mindful that the claim can only be made on a quantum meruit basis, how the amounts of $850.00, $277.00 or $1000.00 are the reasonable value of t work performed by BP or benefit to the applicant.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Mashat
Build Property Pty Ltd [2025] NSWCATCD 152;