[2025] WASAT 78
General information, not legal advice.
State Administrative Tribunal (WA)
2025-07-28
Mr AM
Original judgment source is linked above.
CITATION : LEACH and HA-DECGROUP PTY. LTD. [2025] WASAT 78
HEARD : 9-10 DECEMBER 2024, 16-17 JANUARY AND 4 MARCH 2025
Preliminary issue as to the relevant contract or contracts - Building service complaints - HBWC complaints - two building contracts and one project management agreement
Home Building Contracts Act 1991 (WA), s 3, s 14, s 20, Sch 1, cl 5
Equuscorp Pty Ltd v Glengallan Investments Pty Ltd [2004] HCA 55; (2004) 218 CLR 471
Lee and Holmes [2020] WASAT 108
Raftland Pty Ltd v Federal Commissioner of Taxation [2008] HCA 21; 238 CLR 516
(a) What were the contractual arrangements between the parties regarding home building work? Specifically:
(i) What is the status of the building contract signed by Mr and Ms Leach and HD in December 2020?
(ii) What is the status of the building contract signed by Mr and Ms Leach and HD in March 2021?
(iii) Were other building works contracts (whether oral, written or partly oral, partly written) entered into by Mr and Ms Leach, HD and/or Mr Forte?
home building work means the whole or part of the work of -
(a) constructing or re-constructing a dwelling including an existing dwelling and/or strata/community title dwelling; or
(b) placing a dwelling on land; or
(c) altering, improving or repairing a dwelling, including a strata/community title dwelling; or
(d) constructing or carrying out any associated work in connection with -
(i) any work referred to in paragraph (a) or (b); or
(ii) an existing dwelling, including a strata/community title dwelling;
associated work includes site works, swimming pools, spas, pergolas, carports, garages, sheds, fencing, retaining walls, paving, driveways, landscaping and other like works;
construct in relation to a dwelling means perform any work commencing with the preparation of the site and ending with the completion of the dwelling (including any associated work) and includes -
(a) painting where that is part of the work included in a contract; and
(b) the provision of lighting, heating, water supply, drainage, sewerage, gas and other like services;
perform in relation to home building work includes -
(a) causing the work to be performed; and
(b) organizing or arranging for the performance of the work;
(i) the 2020 building contract had not been terminated and therefore governed the rights and obligations between Mr and Ms Leach and HD;
(ii) the 2021 building contract was not intended to and did not terminate or replace the 2020 building contract; and
(iii) the parties did not enter into any other building works contracts.
(b) Until the issuing of the complaint, the actions of the parties were consistent with the 2020 building contract and not the 2021 building contract. This included the correspondence from the then solicitors of HD in late 2022.
(c) The purported termination in February 2021 was inconsistent with the parties' actions and was disputed.
(d) The 2021 building contract was not signed with the intention of altering the parties' legal arrangements but solely for the purpose of reducing the amount payable for home indemnity insurance.
(e) The communications between Mr and Ms Leach and Mr Forte did not impact the contractual relationship between Mr and Ms Leach and HD. Mr Forte attracted Mr and Ms Leach, as inexperienced clients, with a promise to locate a builder to construct the house for $335,000. Mr Forte used the spreadsheets with the intention of convincing Mr and Ms Leach to agree to increase the price without having to go through the contractual process of variations.
(f) The arrangements between the parties were unusual, and Mr and Ms Leach did arrange for contractors to perform works. The question of what building work was performed by HD or other parties was a matter to be determined at the final hearing.
(g) The evidence before the Tribunal suggested HD appointed Mr Forte as its agent or sub-contractor to perform the role of builder on behalf of HD. Whatever their arrangement, it did not alter the fact of the building contract between HD and Mr and Ms Leach.
(a) The position of HD was that the 2020 building contract had been terminated, the 2021 building contract had been abandoned by Mr and Ms Leach and there were no other building contracts.
(b) It had become apparent he was the victim of a plot whereby:
(i) his company was used by Mr and Ms Leach for the purpose of obtaining bank finance and then State and Federal building grants; but
(ii) the intention of Mr and Ms Leach was to build their house on a basis more akin to that of an owner-builder, with the assistance of Mr Forte as project manager.
(c) The house as constructed was significantly larger and more complex than the single storey design of B1 Homes and the suggestion it could have been constructed for the same price 'defie[d] logic'.[3]
(d) The 2020 building contract was terminated by the 2021 building contract at the request of Mr Forte as the representative for Mr and Ms Leach. In the context of severe shortages of materials and trades, Mr Ayad accepted the representations of Mr Forte.
(e) Mr and Ms Leach set aside the 2021 building contract by engaging trades and purchasing materials directly or via Mr Forte.
(f) HD continued to invoice pursuant to the 2020 building contract because Mr Forte stated that to do otherwise could result in Mr and Ms Leach's loan being terminated.
(a) Mr and Ms Leach chose his project management agreement after having terminated a standard building contract with B1 Homes.
(b) The project management agreement took precedence over any other contracts or activities during construction.
(c) The fundamental principle of their project management agreement was an 'at cost' arrangement with no fixed price.
(d) The parties' evidence demonstrated that the events in reality had nothing to do with a fixed price building contract.
(e) The project management agreement was a non-regulated agreement and the Building Commissioner (and presumably by extension the Tribunal) had no jurisdiction to 'look into' it.
(a) The PM was engaged to provide professional project management services in relation to the construction of a house at the land.[20]
(b) The PM was to 'vet, negotiate with, supervise and approve the payments to contractors in general as well as nominated by' Mr and Ms Leach.[21]
(c) Mr and Ms Leach were to be 'responsible for the engagement of and payment of all contractors or suppliers'.[22]
(e) The PM was to take out professional indemnity insurance. Mr and Ms Leach or their contractors were to take out third party and workers' compensation insurances.[25]
(a) HD promised to construct and complete a single storey house on the land.[40]
(b) The total price was fixed at $334,990.[41]
(a) HD's scope of works was to construct only the shell or structure of a house on the land, with exterior and interior finishing to be carried out by Mr and Ms Leach.[48]
(b) The progress payments comprised the deposit, pre-slab and site works, ground floor slab, ground floor plate and roof cover.[49]
(c) The total cost was fixed at $133,996.[50]
Hi Guys,
Attached is the structure only building contract. Please sign it and return to me so we can apply for the building permit. Thank you.
Danne Forte
(a) There was never intended to be a fixed price contract for the construction of the house.
(b) Mr and Ms Leach instructed him to let them do anything they could themselves. This included their directly engaging trades and purchasing materials and constantly looking online for cheaper prices.
(c) Mr and Ms Leach did not respect any contract and so he tried to minimise the involvement of HD.
(d) For this reason, the structure only contract 'seemed plausible'. It legitimised what was happening and what was expected to happen on site.
(e) He discussed this with Mr and Ms Leach and they knew about the new contract before Mr Forte's email of 15 March 2021 which asked them to sign the 2021 building contract.
(a) Mr Leach said this document was presented to him by Mr Forte with the details already filled in and he signed it because Mr Forte asked and he did not check the document well enough.[59]
(b) Ms Leach said they had absolute trust in Mr Forte and they 'weren't checking that kind of stuff'.[60]
(c) Mr Ayad said Mr Forte prepared the application form and instructed him to sign it.[61] He understood the work had been valued at $265,000 because Mr Forte was expecting substantial additions, such as raked ceilings. In any event, it was up to Mr and Ms Leach to 'pay the gap' to the City of Stirling.
(d) Mr Forte said the amount on the building permit did not matter.[62] He said builders may start with a certain amount, but through variations or other reasons the final amount can be different. The owner or builder is obliged to inform the council and pay the difference in the applicable fee.
Called him this morning and begged on my knees!! Pheeeeeeeew! Thank God he didn't go there. I had ordered the bricks before and put them on hold as I didn't want him to see bricks on site which will immediately tell him the slabs are poured!!
(a) Ms Leach confirmed she and Mr Leach received the certificate in the post.[73] She said they did not notice the contract amount until March 2024.
(b) Mr Leach said he did not at the time observe the contract price.[74]
(c) Mr Ayad said there must have been an oversight or perhaps a typing error by his administrative assistant, because the relevant contract was the 2021 building contract.[75] He said he was not in a fit state to check everything at that time.
(d) Mr Forte said Mr and Ms Leach had agreed to the contract figure of $133,000 on the application for a building permit and the home indemnity insurance due to the savings in fees.[76] He had explained to Ms Leach the home indemnity insurance would only cover the building structure (not the finishings) and the maximum payment was then only $100,000 regardless of the contract amount. He said in this way they saved $3,000 to $4,000.
(a) contacting neighbours to obtain their consent to works;
(b) Mr Leach performing waterproofing to retaining walls and the brick walls of the cellar;
(c) going on the site to observe progress in the construction;
(d) providing instructions to Mr Forte in relation to the construction of a cat tunnel, shower recess and barbeque areas;
(e) raising an objection at the start of the brickwork when it appeared the cat tunnel and a kitchen window were not being built to specifications;
(f) agreeing with Mr Forte to attend to retaining walls and fencing themselves to save money, obtaining quotes and providing instructions for the works to be performed;
(g) organising skip bins and cleaning the site on four occasions;
(h) organising installation of gyprock or plaster in the office, an arch to a walk-in-robe and a false ceiling to the powder room, painting and glass shower screens;
(i) arranging for boxing in from inside a raked window and finishing a wall in the office;
(j) engaging a carpenter to hang the front door, rehang the pedestrian door to the garage and install all handles and locks to external doors;
(k) going on the site to instruct where tiles should be laid and organising a tiler to lay tiles in the cellar and powder room;
(l) Mr Leach sent the City of Stirling a crossover application and they engaged a concreter to pour the driveway and repair the footpath;
(m) Mr Leach met the electrician on site and then installed medium density fibreboard to ceilings in the garage and loft so that the electrical work could be finalised; and
(n) Mr Leach with the assistance of a friend installed some external flashing.
(a) Mr Forte suggested or they agreed to undertake some things directly in order to save costs.
(b) In May 2022 they agreed to finish aspects of the building because Mr Forte was unwilling to do further works for the reason he claimed they owed him too much money.[79]
(a) He never wanted to organise any part of the work, but it was a necessity in order to get the house finished and satisfy Mr Forte's demands.[81]
(b) On 27 March 2022, he and Ms Leach emailed Mr Forte a list of things they wished to be completed whilst waiting for delivery of windows and before the internal fit-out commenced. In relation to four of the 17 items, the email stated that Mr Leach would show or discuss them with Mr Forte on site the following day.[82]
(c) On 23 May 2022 a neighbour called to complain about rainwater coming from the site to flood their courtyard. Mr Leach left work and diverted the water as best he could using spare building materials. He observed flooding in the outside storeroom and bailed out water with a bucket. He also observed water leaking from the bottom of 'each set of stairs in the house'. He stated this was due to the external render stopping at the level of the sand outside, rather than at the slab. He later dug out the sand and applied waterproofing to the bricks and slab.
(d) On 2 September 2022 he had a meeting with Mr Forte during which Mr Forte said he would complete the final works, but only issue a notice of completion and provide a handover and keys when the monies owed to him as calculated on Mr Forte's spreadsheet had been paid.
We didn't bring in any contractors. We didn't order any materials. We didn't do any of the work. So, as far as we were concerned, it was a fixed-price contract.
(a) The email of 27 March 2022 referred to at paragraph [73(b)].[84] In reply, Mr Forte emailed Mr and Ms Leach a spreadsheet for the parties to use to monitor the progress of the items.
(b) In an exchange of emails between approximately 15 May 2022 and 18 May 2022 Mr Leach and Mr Forte discussed complications regarding the manufacture and installation of windows, payment for the windows and choice of contractor to complete tiling after the windows were installed.[85] They also discussed whether it was a suitable time for Mr Leach to have office walls installed, the installation and cost of soakwells and who was responsible for organising (and the cost of) a postconstruction clean of the house.
(c) On 18 May 2022 Mr Leach sent an email to Mr Forte stating that he calculated approximately 60 sqm of tiles had been laid, that the spreadsheet indicated the tiler had been paid $8,162.70 and asking for confirmation of what the tiler had been paid for because he considered the rate to be expensive.[86]
(a) He thought he had attended once in relation to the pouring of concrete and once in relation to the roof. The concreter was supplied by Mr Forte. He asked to meet the concreter on site to see how the main slab was going to be joined to the existing bulk concrete which formed the undercroft.
(b) His supervisors had also attended site. He could not recall how often, but it was limited.
(c) His capacity to attend site was limited both due to his health and his location.
(d) It was not necessary for him or his supervisors to attend site frequently because the applicants had appointed Mr Forte as their construction manager. He fully respected the capability and capacity of Mr Forte.
OLDFIELD MS: So if your company's responsibility ended with the roof cover, why wasn't a notice of completion filed?
AYAD MR: Because, as I - as I said in the previous question, they didn't finish the roof cover in the designated time, or roof carpentry, as well. They delay and interfere a lot.
OLDFIELD MS: But weren't those works - but weren't those your works? So how can you blame anyone else if your company was responsible for the works?
AYAD MR: Yes, because - it's not blame. It's still our responsibility, but we, like, gave Mr Forte the full flexibility to deal on the site as per his and his client's requirements. But the interference here was out of our control, out of anybody's control, so again, we - we found and our structure work finish at the end, which is, that's unusual things. It's not affecting the quality of - of works, but - but it's - it's not the right sequence, like, (indistinct) did the wrong sequence. So that's why the structure delay a lot. I can't remember when we finished the roof structure, but it was - it was finished at the end of the build, or almost at the - close to the end of the build.
...
OLDFIELD MS: Now, we had spoken about that invoice from Building Renewals. And Mr Ayad had said that the roof was not finalised towards the end of the build. So, Mr Ayad, if the roof wasn't completed until quite late in the process, why was the invoice for the progress payment for the roof cover issued---
AYAD MR: Again, because they nominated the subcontractor; they instructed me when to pay and what. Invoice, like, being issued because Mr Forte, which is Mr and Mrs Leach's representative, requested this money to deposit or start the roof (indistinct) that's as far as I remember so far.
...
OLDFIELD MS: All right. So you're saying that the invoice for the roof cover, which had a date of 29 December 2021, that you were instructed by Mr Forte to issue that.
AYAD MR: Absolutely. 100 per cent; 100 per cent. Because that's their point; their management point. And, again, he may have this as a front load or whatever, but I believe, from what I can see, they delayed the roof work a bit, or roof work being delayed a bit.
...
Did you reach an arrangement where we can all have access to finish our respective jobs while keeping the house secure?
A lock box for the contractors would work or I can open doors in the morning (I usually go past around 6.30am, but could be earlier if needed).
If you would like a copy of the other keys I can arrange that as well[.]
...
There are two ways of going about this. The first is to immediately stop the presence of any tradesmen/contractors not appointed by the builder and hand over all keys to us and keep the site under lock until handed over. The second is to review and sign the attached indemnity to satisfy the insurers[.]
...
At the end of the day, we need the house to be secure, and we both need access to finish the job.
We'll go ahead and sign this and send it back to you, that should satisfy the insurers. I'll have it back to you this afternoon[.]
...
To secure the house properly we will keep it locked at all times except in the need of trades.
We will facilitate access for trades you have engaged whenever possible; however, as we both have to work, in some cases, access will need to be determined by you.
If you want to arrange a lockbox or something similar, just let us know and we'd be happy to help.
I can't remember anything about the physical keys. I remember - I remember we fight for the keys. I did argue to have the keys, and suddenly I found a set in my letterbox ... But during the (indistinct) we used to jump over the fence, especially (indistinct) We used to wait until you, like, call us and say, 'Look, the garage is open', whatever. It was - it was, like, very messy.
In fact, once the keys went - like I said before, we didn't have the new keys, you know, after the new door was installed by the owners, and I just - I never got the keys back in any case, and I have not seen the keys since.
(a) Mr and Ms Leach were in possession of keys to the house at the site; and
(b) those keys allowed Mr and Ms Leach to permit or deny access by contractors organised by Mr Forte.
(b) Progress payments and variable outgoings: $396,177;
(c) Total paid by them to Mr Forte and HD: $471,177;
(e) Payments received by them from Mr Forte: $22,747.73.
(a) deposit - $21,774 - invoice dated 11 February 2021;[139]
(b) pre-slab and site works - $45,000 - invoice dated 19 April 2021;[140]
(c) ground floor slab - $45,000 - invoice dated 20 July 2021;[141]
(d) ground floor plate - $55,000 - invoice dated 20 September 2021;[142]
(e) roof cover - $55,000 - invoice dated 29 December 2021;[143]
(f) lock up - $35,000 - invoice dated 23 March 2022;[144]
(g) finishing - $35,000 - invoice dated 4 April 2022;[145] and
(h) cabinets and fit out - $30,000 - invoice dated 20 May 2022.[146]
Hi Guys
Attached are the variations. I have sent them to Ha-Dec and am awaiting their confirmation. These come to $154,064.39. Please don't send them just yet. Thank you.
Hi Danne
Please find attached as discussed. Also please note I checked all dates as some were on a Sunday so have changed those too.
I increased the inclusions (V1) and reduced the amount for the 45 days.
Upgrade to bathroom fixtures, tiling floor to ceiling, kitchen fitout and electricial inclusions as requested by client
Revised DA application, BP, CDC and energy assessment
Extra over for price adjustment starting 45 days beyond contract signature and site conditions
Extra over PS for retaining walls and Waterproofing
Extra over for increase in Bricks and cartage and Bricklayers' rates at cost (can include crane costs in this??)
Extra over for increase in roof costs includes timber prices, roof carpenters and steel
(a) Variation 1 in the amount of $18,872, paid in full. The date of the variation was said to be 8 February 2021, and the date of payment 9 February 2021.
(b) Variation 2 in the amount of $2,750, paid in full. The date of the variation was said to be 4 May 2021, and the date of payment 9 May 2021.
(c) Variation 3 in the amount of $3,251, paid in full. The date of the variation was said to be 14 May 2021, and the date of payment 16 May 2021.
(d) Variation 4 in the amount of $520, paid in full. The date of the variation was said to be 24 May 2021, and the date of payment 29 May 2021.
(e) Variation 5 in the amount of $5,780, paid in full. The date of the variation was said to be 23 May 2021, and the date of payment 25 May 2021.
(f) Variation 6 in the amount of $25,257, paid in full. The date of the variation was said to be 28 June 2021, and the date of payment 2 July 2021.
(g) Variation 7 in the amount of $22,580.39, paid in full. The date of the variation was said to be 25 May 2021, and the date of payment 28 May 2021.
(a) dated 16 November 2021, described as '[e]xtra over for increase in Bricks and cartage and Bricklayers' rates at cost including cranage and site handling', in the sum of $38,402.00; and
(b) dated 4 February 2022, described as '[e]xtra over for increase in timber prices, roof carpenters and structural steel', in the sum of $36,001.00.
'Danne Forte Extra fees for variations Joondanna Variations table"
'variations ... as per the reconciliation ... with Danne Forte'
(a) the invoices evidenced at paragraphs [113], [117] and [118] above were paid by or on the instructions of Mr and Ms Leach; and
(b) HD paid a significant portion of the funds so received to BR.
(a) By an email dated 20 April 2021 from Ms Leach to Mr Forte:[158]
The bank has their instructions to release the payment. Money will be received within 2-3 business days ...
Please organise, as discussed, for money to be paid back to us.
(b) In an email exchange on 5 January 2022, Ms Leach wrote:[159]
[W]e will send you 10k this week and 10k next week. Hopefully in 2 weeks' time we will be at a point to invoice the bank for the lockup payment.
(c) Mr Forte's reply dated 5 January 2022 included:
...
Please note the $55,000 of the roof payment is not received yet and my loan still stands at just over $147,000 ...
What I suggest you do is after the lock up, you get a valuation and refinance for another say $100,000 and cover yourself[.]
Total Build $569,689.35
Less Contract Price $334,990
Difference $234,669.35
15% Builder Allowance $35,204.90
Less previously received $19,536.93
Due to be paid $15,667.97
What were the contractual arrangements between the parties?
(b) the actions of HD evinced an intention to be bound by the 2020 building contract because its actions were inconsistent with the 2021 building contract but consistent with the 2020 building contract.
(a) As discussed at paragraph [143] below, the actions of the parties were inconsistent with the terms of the 2020 building contract.
(b) The manner in which their contract with B1 Homes was terminated indicated to me that Mr and Ms Leach understood the process of a builder issuing a variation in order to vary the cost of construction under a fixed price contract. They did not attempt to follow that process with HD.
(c) Mr and Ms Leach knew B1 Homes had obtained a building permit from the same local government in relation to the same land, without requiring a 'structure only' contract.
(a) It was the evidence of Mr and Ms Leach that Mr Forte's email dated 15 March 2021 by which he sent them the 2021 building contract caused them to believe that contract was to be used in applying for a building permit.[169]
(b) It has not been alleged, and there is no evidence, that Mr or Ms Leach communicated their intention to HD.
(c) It has not been alleged and there is no evidence that HD made any representations to Mr and Ms Leach in relation to the 2021 building contract.
(d) It was suggested that Mr Forte was effectively acting as agent for HD.[170] However even if that were accepted, there is no evidence Mr or Ms Leach communicated their intention to Mr Forte.
(a) The terms of the project management agreement appear in conflict with the terms of either or both of the 2020 and 2021 building contracts. In other words, it is unclear how the project management agreement could have operated in conjunction with either of the 2020 or 2021 building contracts. In their evidence, Mr and Ms Leach were vague regarding the expected role of Mr Forte in the context of a fixed price building contract.
(b) The evidence of the parties' activities on site and engagement with the City of Stirling appears inconsistent with HD being in control of the site and the building works pursuant to either the 2020 or 2021 building contract.
(c) The preparation and use of the spreadsheets by Mr and Ms Leach and Mr Forte, to track the actual cost of labour and materials, is inconsistent with the concept of a fixed price building contract and inconsistent with the terms of the 2020 and 2021 building contracts. It is notable the first spreadsheet was prepared and shared on 15 December 2020 whereas the 2020 building contract was signed on or about 24 December 2020.
(d) It seems to me the payment by HD of funds received from Westpac to BR would only be consistent with the 2020 or 2021 building contracts if BR[176] had been engaged by HD to supervise and carry out the building works on behalf of HD. I am not satisfied the evidence established that arrangement. Indeed, the situation appeared more consistent with arrangements commonly known as 'licence lending' where a registered builder allows their name and builder's registration to be used by someone else.
(a) Mr and Ms Leach were in effect owner-builders who had engaged Mr Forte or Resiservices to provide advice and assistance in managing the construction; or
(b) Mr Forte or Resiservices was in effect the builder operating on a cost-plus basis (albeit in breach of s 14 of the HBC Act).
(a) What were the contractual arrangements between the parties regarding home building work? Specifically:
(1) What is the status of the building contract signed by Mr and Ms Leach and HD in December 2020?
On the face of the documents, the 2020 building contract was rescinded by the 2021 building contract. However, the 2020 building contract was a pretence which did not represent the true agreement between the parties.
(2) What is the status of the building contract signed by Mr and Ms Leach and HD in March 2021?
On the face of the documents, the 2021 building contract was the subsisting contract between Mr and Ms Leach and HD. However, the 2021 building contract was a pretence which did not represent the true agreement between the parties.
(3) Were other building work contracts (whether oral, written or partly oral, partly written) entered into by Mr and Ms Leach, HD and/or Mr Forte?
Yes, there was an agreement which was partly recorded in the project management agreement whereby:
(i) home building work would be performed by Mr and Ms Leach and by Mr Forte and/or Resiservices;
(ii) HD, in exchange for monies paid, would allow its name and building licence to be used for purposes which included obtaining home indemnity insurance and a building permit.

I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
[1] Applicants' Outline of Submissions (AOS) dated 15 April 2025.
[2] Exhibit 1, pages 1653 - 1658; HD's Closing Submissions dated 15 April 2025 (HDCS).
[4] Mr Forte's Closing Submissions on the Preliminary Issue dated 15 April 2025 (FCS).
[5] BSCRA Act, s 3; Building Services (Complaint Resolution and Administration) Regulations 2011 (WA), reg 5A.
[9] BSCRA Act, s 5(2); Home Building Contracts Act 1991 (WA) s 20 and Sch 1, cl 5.
[12] For example, Exhibit 1, pages 2, 1480, 1508 and 1522.
[18] Exhibit 1, pages 492 and 532; Exhibit 2, pages 777 - 778.
[20] Project management agreement clauses 1(2) and 2.1 and the definition of 'Project' in clause 1.1.
[26] Exhibit 2, pages 769, 773 and 930. See Annexure A attached.
[27] For example, Exhibit 2, pages 1321, 1322, 1325, 1337, 1338 and 1361.
[28] Exhibit 2, pages 1730; ts 24, 47, 49, 50, 51, 52, 62, 90, 93 and 95, 17 January 2025.
[29] Australian Government, 'HomeBuilder', (Web Page, 27 April 2021)
[30] Government of Western Australia, 'HomeBuilder Program to assist with renovations and new builds', (Web Page, 4 June 2020) .
[32] Government of Western Australia, 'HomeBuilder grant extensions', (Web Page, 4 May 2023)
[33] Australian Government, 'Australian Government HomeBuilder grant', (Web Page, 5 June 2025)
[34] Government of Western Australia, 'Building Bonus to support economic recovery and create WA jobs', (Web Page, 7 June 2020)
[35] Government of Western Australia, 'Building Bonus grant', (Web Page, 1 July 2025)
[37] Government of Western Australia, 'Building Bonus extension to provide WA job certainty', (Web Page, 20 October 2020)
[38] Government of Western Australia, 'About the first homeowner grant', (Web Page, 19 June 2025) .
[42] Exhibit 1, pages 495 and 533; ts 14, 67 - 68, 9 December 2024; ts 158, 10 December 2024.
[56] Exhibit 1, page 1716; ts 52 and 98 - 99, 17 January 2025.
[57] Exhibit 1, pages 499 and 534; ts 50 and 81 - 82, 9 December 2024; ts 6, 10 December 2024.
[64] Exhibit 1, pages 501 and 535; Exhibit 2, pages 865 - 867.
[69] Exhibit 1, pages 426 - 428 and 592.
[78] Exhibit 1, pages 50, 209 - 510, 515 and 516; ts 56, 9 December 2024.
[88] Exhibit 2, page 1733; ts 24, 17 January 2025.
[93] Exhibit 2, page 1731; ts 50, 17 January 2025.
[101] ts 90, 17 January 2025; ts 213 - 214, 4 March 2025.
[102] Exhibit 2, pages 1730 - 1731; ts 47 - 49, 17 January 2025.
[109] ts 123 and 134, 10 December 2024.
[110] Exhibit 1, pages 1617 - 1618 and 1719.
[112] Exhibit 1, pages 1715 - 1716; Exhibit 2, pages 1730 - 1741.
[116] ts 277 - 278 and 279, 16 January 2025.
[134] For example, Exhibit 2, pages 359, 846, 929 and 933.
[135] For example, Exhibit 2, pages 462, 490, 501 and 1092 - 1095.
[152] The variations listed at [118] and the variations the subject of the receipts listed at [117].
[154] Exhibit 1, pages 1566, 1568, 1574, 1575, 1578, 1579 and 1580; Exhibit 2, pages 1628 - 1634.
[157] Exhibit 1, pages 513 and 539 - 540.
[167] SA Christensen and WD Duncan, The Construction and Performance of Commercial Contracts (3rd ed, 2023) The Federation Press at [15.3.2.4].
[168] JW Carter, Contract Law in Australia (8th ed, 2023) at [12-03].
[169] Exhibit 1 pages 499 and 534; ts 50 and 81 - 82, 9 December 2024; ts 6, 10 December 2024.
[176] Or arguably Mr Forte or Resiservices.
[178] More accurate than the 2020 building contract or 2021 building contract.
(2004) 218 CLR 471