[2020] WASAT 108
General information, not legal advice.
State Administrative Tribunal (WA)
2020-09-07
Original judgment source is linked above.
ACT : BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT (WA) 2011
CITATION : LEE and HOLMES [2020] WASAT 108
A person who carried out regulated building service - No evidence that the construction or any part was 'carried out' by the respondent - Applicants asserted that the respondent did not perform any regulated building service - Applicants sought an order that the respondent pay the remedial costs of the faulty and unsatisfactory regulated building service
Architects Act 2004 (WA)
Building Act 2011 (WA), s 16(j)
Hadjiloucas v Crean [1988] 1 WLR 1006
Hawke and Ennis [2018] WASAT 118
Raftland Pty Ltd v Federal Commissioner of Taxation [2008] HCA 21; (2008) 238 CLR 516
Shami and Teo [2017] WASAT 73
Shaw v McLeod (unreported, WASC, Library No 4707, 8 November 1982
Can and should the Tribunal make an order pursuant to s 36(1)(b) and s 38(1) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA) (BSCRA Act) against Mr Holmes and/or Eleven in CC 1635/19 and CC 1636/19, and if so what order should the Tribunal make?
Can and should the Tribunal make an order pursuant to s 36(1)(b) and s 38(1) of the BSCRA Act against Mr Holmes in CC 1889/19 and CC 1892/19?
Stormwater drainage/downpipe. Downpipe finished short, grate not level. Poor cutting of tiles around the drain.
Home Integrity Building Consultant Report dated 25/11/2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Downpipe not aligned centrally over the stormwater drainage grate.
Inadequate clearance from downpipe to drainage grate
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Cabinets, large gap to top scribe above overhead cabinets
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Stormwater drainage / downpipe. Grate not level. Poor cutting of tiles around the drain.
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Stormwater drainage grates / downpipes. Downpipes not aligned centrally over stormwater drainage grates.
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
i) Home Integrity Building Consultant Report dated 25.11.2019
ii) Email to Builder requesting mailbox to be in corporated
Financial settlement for remedial works by 3rd party. Cost to be advised.
Home Integrity Building Consultant Report dated 25/11/2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Outlet to balcony drain not installed as per Building permit ie:- plans show that drain discharging to southern elevation.
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Home Integrity Building Consultant Report dated 25.11.2019
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised
Drainage grate sits proud of tiles. Water is pooling.
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised.
Concrete is cracking. Expansion/control joints not installed as required
Home Integrity Building Consultant Report dated 25.11.2019
Financial settlement for remedial works by 3rd party. Cost to be advised.
The Tribunal's jurisdiction to hear and determine the disputes and the Tribunal's powers
The history of the proceedings before the Commissioner
I have attached the invoices pertaining to our order of windows and doors through Shayne Leroy for our properties and also charged for labour provided by him .... The Invoices are issued from companies owned by Shayne.
... Shayne Leroy was the person who designed our homes for us. He represented to our builder and us that he can import and supply high quality windows and doors.
A building and energy Inspector will be in touch with you within 10 working days.
The builder is believed to be Peter Holmes and the owner Yu Lian Lee.
[Ms Lee] advised that Sean O'Reilley and Mario Andreau were directors of Jetpoint Nominees Pty Ltd ... [and] ... all payments were made to Sean and Mario. Sean allegedly carried out the supervision of the site works ...
The works at the site commenced in September 2016.
[Ms Lee] entered into a HIA Lump Sum Home Building Contract with Peter James Holmes in December 2016.
[Ms Lee] first met Peter Holmes once in June 2019.
[Mr Holmes] has signed a notice of completion for both properties... which has been lodged with the City of Melville.
(Tribunal emphasis)
I advised that [Ms Lee] would need to serve a new NOPC [notice of proposed complaint] on Peter Holmes, as the registered builder, and that Peter would need to be added as the second respondent to this complaint [being CC 1635/2019 and CC 1636/2019].
Brick and tile 3 storey residence to lockup stage
to be constructed on:
23A MacLeod Road (Tribunal emphasis)
for Ms Lee and her husband. However, it is a fact that the dwelling that was constructed for Ms Lee and her husband was constructed on 23B and is a four level dwelling, including the undercroft.
Brick and tile double story residence to lockup stage
to be constructed on:
23 MacLeod Road (Tribunal emphasis),
for Ms Yong's husband (see below) which must be a reference to 23B (given the contract referred to above). However, the dwelling that was to be constructed for Ms Yong's husband was constructed on 23A.
As recently discussed, please serve the notice of proposed complaint on Peter Holmes by email (copying me in).
To allow Peter Holmes to be added as a second respondent, please write 'Peter Holmes, Second Respondent' on the attached form and return the same to me.
Once 14 days have passed from the service of the notice of proposed complaint on Peter Holmes, I will transfer this complaint to the Building Commissioner's delegate for consideration of acceptance.
I am more than happy to look at any issues that you may have with the mention properties, but as documented in Notice of Completion letter sent, dated 16th June 2019, all monies need to be paid first, as per contract.
... I was directed by the Judge to file in a complaint to the Building Commission with regards to License Lending by our builder Peter Holmes and the third party builders who were actually the responsible ones in building the houses.
Please advise me what is required of me to lodge this new complaint.
Lastly, for the second set of NoPC [notice of proposed complaint] that is going in do I name both the registered builder (Peter Holmes) and the third party builders who used his registration to build our houses OR just the registered builder ie:- first and second respondents.
(Tribunal emphasis)
23B across all four proceedings.The hearing concerning CC 1635/2019 and CC 1636/2019
(a) Item 1 - Al fresco (item 1(i) on consolidated Scott Schedule)
The second respondent is to remedy the defective bifold doors in a proper and proficient manner making good all affected surfaces
(b) Item 2 - Al fresco (item 1(ii) on consolidated Scott Schedule)
The second respondent is to install missing handles and screws to the bifold doors and remedy the defective door handles in a proper and proficient manner making good all affected surfaces.
(c) Item 3 - Alfresco (item 1(iii) on consolidated Scott Schedule)
The second respondent is to remedy the badly fitted rubber strips in a proper and proficient manner making good all affected surfaces.
(d) Item 6 - Al fresco (item 2 on consolidated Scott Schedule)
The second respondent is to remedy the bifold doors which open to the wrong side (to the right instead of the left) in a proper and proficient manner making good all affected surfaces. The remedial work for this item is to be completed by 31 July 2020. Within seven days of receiving a tax invoice from the second respondent setting out the labour cost for completing the remedial work for this item, the first respondent must pay to the second respondent the total amount set out in that tax invoice.
(e) Item 7 - Dining area (item 3 on consolidated Scott Schedule)
The second respondent is to remedy the aluminium strip to match the window frame in a proficient manner making good all affected surfaces.
(f) Item 9 - Bedroom ground floor (item 4 on consolidated Scott Schedule)
The second respondent is to remedy the defective window frame in a proper and proficient manner making good all affected surfaces.
(g) Item 10 - East side French windows (item 5 on consolidated Scott Schedule)
The second respondent is to remedy the defective aluminium and rubber strips around the frame in a proper and proficient manner making good all affected surfaces.
(h) Item 11 - West side French windows (item 6 on consolidated Scott Schedule)
The second respondent is to remedy the defective doors in a proper and proficient manner making good all affected surfaces.
(i) Item 12 - West side French windows (item 6 of consolidated Scott Schedule)
The second respondent is to remedy the defective door lock and latches in a proper and proficient manner making good all affected surfaces.
(a) Item 1 - Ground floor front corridor (item 1 on the consolidated Scott Schedule)
The second respondent is to frost the full length of the windows. All works to be undertaken in a proper and proficient manner making good all affected surfaces.
(b) Item 2 - Master ensuite (item 2 on the consolidated Scott Schedule)
The second respondent is to frost the windows. All works to be undertaken in a proper and proficient manner making good all affected surfaces.
(c) Item 3 - Powder Room (item 3 on the consolidated Scott Schedule)
The second respondent is to frost the windows. All works to be undertaken in a proper and proficient manner making good all affected surfaces.
(d) Item 4 - Master Bedroom (item 4 on the consolidated Scott Schedule)
The second respondent is to remedy the defective fly screen on the right side window in a proper and proficient manner making good all affected surfaces. In addition the second respondent is to supply the window keys to the right side window.
(e) Item 5 - Living room (item 5 on the consolidated Scott Schedule)
The second respondent is to remedy the defective window on the far left so that it opens properly. In addition the second respondent is to remedy the faulty fly screen. All works to be undertaken in a proper and proficient manner making good all affected surfaces.
(f) Item 6 - First floor landing (item 6 on the consolidated Scott Schedule)
The second respondent is to remedy the defective window on the right so that it opens properly. In addition the second respondent is to remedy the faulty fly screen and supply the window keys. All works to be undertaken in a proper and proficient manner making good all affected surfaces.
(g) Item 7 - Bedroom 4 (item 7 on the consolidated Scott Schedule)
The second respondent is to remedy the defective fly screen in a proper and proficient manner making good all affected surfaces.
(h) Item 8 - Bedroom 3 (item 8 on the consolidated Scott Schedule)
The second respondent is to remedy the defective stained window and faulty fly screen in a proper and proficient manner making good all affected surfaces.
(i) Item 9 - Bedroom 2 (item 9 on the consolidated Scott Schedule)
The second respondent is to remedy the defective fly screen in a proper and proficient manner making good all affected surfaces.
(j) Item 10 - Bedroom 2 ensuite (item 10 on the consolidated Scott Schedule)
The second respondent is to remedy the defective fly screen and loose rubber seals in a proper and proficient manner making good all affected surfaces.
(k) Item 11 - Laundry door (item 11 on the consolidated Scott Schedule)
The second respondent is to remedy the defective rubber seal in a proper and proficient manner making good all affected surfaces.
(l) Item 12 - Al fresco (item 12 on the consolidated Scott Schedule)
The second respondent is to remedy the defective sliding and bifold doors and install missing door handles in a proper and proficient manner making good all affected surfaces.
The evidence of the dispute in CC 1889/2019 and CC 1892/2019
He [Mr O'Reilly] said his partner Mario Andreo (sic), also from Jetpoint Nominees, would be the supervisor for the project. But Sean [O'Reilly] would be overseeing the whole project, if we appointed Jetpoint to do it.
He was the builder. He and Mario [Andreou] was the actual builders, because Peter James Holmes were never never came to site. We have never met him. We have never seen him, except for that his name was on the contract.
Then Sean [O'Reilly] negotiated a contract together with Mario [Andreou] whereby we were to build with him, him meaning Jetpoint, based on cost of build plus 300,000 in fees.
We did not write out a contract, but we have a payment -- progress payment schedule which was prepared by prepared by Mario [Andreou] and Sean [O'Reilly] and given to us. In there was the breakdown of the required progress payments that we had to pay from the beginning of the build right through to practical completion.
So Sean [O'Reilly] convinced us that he could do the job quicker, better and cheaper. We trusted him fully as he was a good friend. He told us that the build was not going to be longer than 18 months for the whole development.
So we agreed with Sean [O'Reilly] that his company, Jetpoint Nominees, trading as Ace Construction, was to build our development, which consisted of two houses with a basement, a tennis court, and landscaping areas. It was a seamless development, as shown in the drawing plans by Shane Leroy.
Things were moving quite quickly from 2016 onwards, and all negotiations and meetings were conducted by Sean and the architect, Sean [O'Reilly] and the engineers, Sean [O'Reilly] for earthworks and Sean [O'Reilly] for piling. At this point, there was never a doubt that Jetpoint Ace was the builder. However, in December 2016, we were told to sign a standard, off-the-shelf build contract with a Mr Peter James Holmes whom we had never met in our lives.
Yes. So we were meant to sign with - of course, we are meant to sign with the actual company, right. But then the name on the contract was a Mr Peter James Holmes. So I asked Sean [O'Reilly], 'Who are we signing with? You know, why are we signing with this guy?' you know. So he said that he was a business associate and his friend, and the reason we are signing with him was because his company, Jetpoint Ace, did not have enough insurance indemnity or indemnity insurance.
Yes. So he assured us that he [O'Reilly] will be in charge of the project, and he was still going to do it. We, at that point, thought that this sort of arrangement was quite normal in Australia.
We didn't know. We didn't know that at that point, we didn't even know that you have you need a building licence to build. We didn't even know that, you know.
Mario [Andreou]? He was the supervisor and the builder. He has a building licence. So during the course of the construction, from 2016 to 2019 June 2019, all quotes, payments and operation were handled by Sean [O'Reilly] and Mario [Andreou], fully and exclusively.
When the quotes were given of course, the quotes were given to us, me and Ms Yong, yes, at that point. And we look at it. We say 'Okay' or 'Not okay'. 'Proceed'. 'Work done'. And all the quotes were what do you call that all the quotes were given out to Ace Construction, not Peter Holmes. It was addressed - addressed to Ace Construction. Yes. And when they presented it and the work was done, we paid for it. There was an account that was set up, and that account is an account my husband is a holder. Mario [Andreou] is a holder of the account. And Peter [Holmes] was also a holder of that account. It was a tri-account, we call it. So whenever we will put in money into the account for payments with regards to the project work. And that account was set up by Sean [O'Reilly].
Mr Ling puts in the money, basically deposits the money into the account. And Mario [Andreou] would pay for all payments. The person who handles the account is Mario's wife.
It's only one signature, and that is Mario [Andreou].
(The Tribunal shall refer to that bank account as the 'joint account' for the purposes of these reasons).
Never met him [Mr Holmes]. Never paid him. He has never claimed any money throughout the two year three years, sorry. Yes.
I asked Mario [Andreou]. At that point, I asked Mario, 'What is all this about?' You know, I said, 'I am not aware that I had to pay any more. I know that I have to pay 300,000, which I did'. And I said, 'I do not understand'. I was not very happy, of course, and he [Mr Andreou] basically couldn't explain himself. And he just shrugged his shoulders and said he doesn't know.
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.