[2024] NSWCA 163
Court of Appeal (NSW)
2024-05-30
Meagher JA, Leeming JA, Preston CJ, Moore J
Original judgment source is linked above.
Solicitors: McLachlan Thorpe Partners (Appellant) Lindsay Taylor Lawyers (First Respondent) Mills Oakley (Second Respondent) File Number(s): 2023/00426490 Publication restriction: NIL Decision under appeal Court or tribunal: Land and Environment Court Jurisdiction: Class 4 Citation: [2023] NSWLEC 117 Date of Decision: 2 November 2023 Before: Moore J File Number(s): 2021/00292505
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] Willoughby Local Planning Panel (Panel), on behalf of Willoughby City Council (Council), granted development consent to Helm Pty Ltd (Helm) for the adaptive reuse of an existing commercial building, including the erection of an additional level and the change of use to ground level business premises, with 14 apartments above (the development) at 131 Sailors Bay Road, Northbridge (the land). Mr Lahoud brought judicial review proceedings in the Land and Environment Court challenging the development consent, which were heard and determined by Moore J (the primary judge). The primary judge dismissed the proceedings and ordered Mr Lahoud to pay 80% of Helm's costs of the proceedings. Mr Lahoud appealed against the primary judge's decision and orders under s 58 of the Land and Environment Court Act 1979 (NSW) (Court Act). Mr Lahoud's 12 grounds of appeal can be grouped in four categories: (a) the Panel's failure to be satisfied under cl 4.6 of Willoughby Local Environmental Plan 2012 (WLEP) before granting development consent to the development that contravened the height standard under cl 4.3 of WLEP (the height standard grounds); (b) the Panel's satisfaction that the development will have an active street frontage, contrary to cl 6.7(3) of WLEP (the active street frontage ground); (c) the Panel's acceptance of the development being for the permissible use of shop top housing (the shop top housing grounds); and (d) the Panel's failure to consider contamination matters under cl 7 of State Environmental Planning Policy 55 - Remediation of Land (SEPP 55) (the contamination grounds). Helm raised five contentions in its notice of contention: (a) the primary judge should have found that the validity of the Panel's decision was not capable of being challenged because the proceedings were not commenced within time (contention 1); (b) the primary judge should have dismissed the height standard ground on the basis that Mr Lahoud failed to establish that the Panel's decision was affected by the jurisdictional errors alleged (contention 2); (c) the primary judge should have dismissed the active street frontage ground on the basis that Mr Lahoud failed to establish that the Panel's decision was affected by the jurisdictional errors alleged (contention 3); (d) the primary judge should have dismissed the contamination grounds on the basis that Mr Lahoud failed to establish that the decision was affected by the jurisdictional errors alleged (contention 4); and (e) the primary judge should have considered Helm's contention that even if the Panel's decision was affected by jurisdictional error, the Court could make an order suspending the operation of the development consent and specifying the terms that could validate the consent pursuant to s 25B of the Court Act (contention 5). The Court held (Preston CJ of LEC, Meagher JA and Leeming JA agreeing): The height standard grounds (1) The height standard grounds of appeal are based on incorrect assumptions of the statutory scheme. On a correct understanding of the statutory scheme, the height standard grounds of appeal can be seen to be unfounded: at [26], [31], [36], [38]. (2) The development as required to be amended by the conditions of consent was the development for which development consent was granted. The grant of development consent to this amended development was within the power under s 4.16(1) as enabled by s 4.16(4) of the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act): at [39]. The Panel was satisfied under cl 4.6 of the WLEP with respect to this amended development: at [38]. (3) The power to determine the development application by granting consent subject to conditions was in s 4.16(1). The primary judge's finding that the Panel had exercised the power in s 4.16(1) in the way permitted by s 4.16(4)(b) did not raise a new issue in respect of which notice needed to be given to the parties and an opportunity afforded for them to be heard. There was no denial of procedural fairness in the primary judge identifying how the power in s 4.16(1) was exercised by the Panel: at [40]. The active street frontage ground (4) The question of whether the building as proposed to be redeveloped will be a building that has an active street frontage within the statutory description was not a jurisdictional fact: at [60]. The Panel's conclusion, that the building fell within the statutory description, was reasonably open to the Panel: at [67]. No jurisdictional error was involved: at [68]. The shop top housing grounds (5) The appellant's argument was based on two incorrect interpretations of the definition of "shop top housing." The first was that the phrase "ground floor retail premises or business premises" demands that the whole of the ground floor of the building be used for retail premises or business premises. The second was the conflation of the definition's use of the word "dwellings" with "residential use". The proposed development can, on the correct construction of the definition of "shop top housing", be characterised as being for shop top housing: at [78]-[81]. The contamination grounds (6) The evidence did not support the conclusion that the Panel did not consider State Environmental Planning Policy 55 - Remediation of Land (SEPP 55) or cl 7(1) of that SEPP 55 as to whether the land is contaminated: at [105]. (7) The appellant failed to discharge his onus of establishing that the land on which the development was proposed to be carried out was land specified in cl 7(4) of the SEPP 55, and therefore failed to establish that the Panel breached their obligation to consider contamination under cl 7(2): at [110], [115]. Whether proceedings were time-barred (8) The notifications given by the Council on 30 June and 1 July 2021 were not notices for the purposes of s 4.59 of the EPA Act, as they were not given in accordance with the regulations or the EPA Act. Only the 15 July 2021 notice constituted a public notice for the purpose of s 4.59 of the EPA Act. Therefore, the proceedings were not time-barred: at [126]-[128].
JUDGMENT
The height standard grounds
The active street frontage ground
The shop top housing grounds
The contamination grounds
Contention that proceedings time-barred
Conclusion and orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 10 July 2024
Lahoud
Willoughby City Council
(1987) 11 NSWLR 67
(2007) 151 LGERA 400
(2023) 256 LGERA 24
(1980) 144 CLR 1
(1956) 94 CLR 509
(2004) 61 NSWLR 707
(1982) 47 LGERA 319