[2014] VCAT 319
Victorian Civil and Administrative Tribunal
2014-03-25
Original judgment source is linked above.
Their evidence in terms of quantum was not in issue.
"Just so the parties understand and had the best information possible what the agreement was and conclude the arrangement" (Transcript p. 278).
He added that the Owner was concerned about lack of progress on the part of the Builder.
"Pretty much they acknowledged that there was a problem and they would do whatever but I kept making the point that you need to be really thorough about it or it will come back again" (sic.)
The Builder Masterplan Builders and the Owners(s) Dina Kounelis and Dennis Beed have discussed and reviewed the foregoing list of defects on 22.12.08.
Should the Builder fail to fulfil this agreement the Owner)(s) reserve their rights with regard to costs, loss and damages.
The Builder agrees to rectify the following items to the agreed scope and conditional on reasonable access being provided. No instructions direct to contractors by owners and as discussed by (date) 8 weeks duration from 1st March 2009 (If any change to be agreed).
P. Horton...(Signed)......... G. Rossley......(Signed).........
The Owner accepts the Builder's proposed scope and offer to rectify as agreed.
D. Kounelis...(Signed).......... D. Beed......(Signed).........
Witness...(Signed) D. Cheong......Date 22/12/08" (sic.)
"The essence of accord and satisfaction is the acceptance by the plaintiff of something in place of his cause of action. What he takes is a matter depending on his own consent or agreement. It may be a promise or contract or it may be the act or thing promised. But, whatever it is, until it is provided and accepted the cause of action remains alive and unimpaired. The accord is the agreement or consent to accept the satisfaction. Until the satisfaction is given the accord remains executory and cannot bar the claim. The distinction between an accord executory and an accord and satisfaction remains as valid and as important as ever. An accord executory neither extinguishes the old cause of action nor affords a new one. ......................................An executory promise or series of promises given in consideration of the abandonment of the claim may be accepted in substitution or satisfaction of the existing liability. Or, on the other hand, promises may be given by the party liable that he will satisfy the claim by doing an act, making over a thing or paying an ascertained sum of money and the other party may agree to accept, not the promise, but the act, thing or money in satisfaction of his claim. If the agreement is to accept the promise in satisfaction, the discharge of the liability is immediate; if the performance, then there is no discharge unless and until the promise is performed."
"First, there is the mere accord executory which on the authorities, does not constitute a contract and which is altogether unenforceable, giving rise to no new rights and obligations pending performance and under which, when there is performance (but only when there is performance), the Plaintiff's existing cause of action is discharged. Secondly, at the other end of the scale is the accord and satisfaction, under which there is an immediate and enforceable agreement once the compromise is agreed upon, and the parties agreeing that the Plaintiff takes in satisfaction of his existing claim against the Defendant the new promise by the Defendant in substitution for any existing obligation. Somewhere between the two, there is the accord and conditional satisfaction, which exists where the compromise amounts to an existing and enforceable agreement between the parties for performance according to its tenor but which does not operate to discharge any existing cause of action unless and until there has been performance."
"Where the arrangement amounts to mere accord executory, it does not operate to discharge existing rights and duties unless and until the accord is performed. A compromise arises only if and when something is done. In this situation the claimant in return for abandoning its existing rights accepts an act, or agrees that he will accept an act, and there is no discharge for the other party in relation to those existing rights unless and until the act is performed".
"Owners disappointed with broken agreement re time frame and work still not complete.
Builder admitted fault and again resolved to complete within reasonable time frame to be advised depending on availability of painter.
David Good will co-ordinate and advise (by 5th June?). Painter available 22.06.09 T.B.C."
The work was to be completed within a reasonable time.
"The condition that goods are of merchantable quality requires that they should be in such an actual state that a buyer fully acquainted with the facts and, therefore, knowing what hidden defects exist and not being limited to their apparent condition would buy them without abatement of the price obtainable for such goods if in reasonably sound order and condition and without special terms."
Timber strip between wall and stringer to support new filler
107. This was agreed at $1,800. The contract provided for them to be supplied and they were not there at handover. The Owner said that she could not remember what was discussed about that. Mr Magowan said this is simply a credit and that no margin should be added. Mr Downie said that the failure to provide the flyscreens was a breach of the Contract and should be treated as damages rather than a credit. That seems right. Both Mr Paron and Mr Mackinnon allowed $1,700 in their costings for supplying the flyscreens but the two experts costed it at $1800 and that will be allowed for the flyscreens.
119. Apart from the base costings Mr Cheong assessed preliminaries at $10,252 and Mr Browning assessed it at $8,278.10. There is no reason that I can see to prefer one over the other and so I shall allow $9,250.00.
122. The Owner contends that for the works to be done it will be necessary to remove and reinstall the window furnishings, which are Roman blinds, and pelmet boxes.
123. A quotation was provided by a contractor, Active Track Installations, to carry out this work at a total cost of $3,113 and a Mr Durban of that company gave evidence that that was a fair and reasonable price for doing so.
124. In cross-examination Mr Durban acknowledged that the window furnishings could be put in bags without having to remove them, but he said that would not be easy to do so. He agreed that they could be covered in plastic but said that if the remedial work involved working under the architraves they would have to come off. According to Mr Good's evidence, during the rectification works the window furnishings were rolled and wrapped and stored on site. He said that that work was done by "...the people that installed them originally."
"26. The Owners also claim loss of use and enjoyment and amenity and inconvenience.
27. Where there is a breach of contract, the party in breach is only responsible for resultant damage which he ought to have foreseen or contemplated when the contract was made as being not unlikely or liable to result in his breach, or of which there was a serious possibility or a real danger (see Halsbury Laws of England, 4th edition, Vol 9, para 1174).
28. It has been held that substantial physical inconvenience and discomfort caused by a breach of contract will entitle the party to damages (see Burke v Lunn [1976] VR 276 at 285-286; Clarke v Housing Guarantee Fund Limited (1998) 13 VAR 19 at p. 21-22.) Loss of amenity generally is also recognised as a head of damages (see for example Ruxley Electronics and Construction Limited v Forsyth [1995] 3 All ER 268. I was also referred to Wilshee v Westcourt Limited [2009] WASCA 87 to a similar effect.
29. However, damages for personal injury are not recoverable (Domestic Building Contracts Act 1995 s. 54(2)) nor are damages for disappointment, hurt feelings or damage of any other kind that was not reasonably foreseeable at the time the contract was made.
30. In the present case, the Owners claim damages for having lived in a wet house for 2 ½ years. That is a loss of amenity which is compensable. They will also face the inconvenience of having to move out while repairs are effected. However, Ms Doughty's claims for headaches said to have been caused by having to work long hours to pay for the House and lack of sleep and stress resulting from both the defects themselves and this dispute are not compensable. Insofar as any such claim amounts to damages for personal injury, it is barred by s 54(2). Otherwise, I do not believe that it is reasonably foreseeable."
Kounelis
Ross Horton Homes Pty Ltd
(1973) 1 ALR 497