[1999] NTSC 62
Supreme Court of the NT
1999-06-17
Martin CJ, Bailey JJ
Original judgment source is linked above.
STATUTES � interpretation � Workmens Liens Act � meaning of "accrued
due" in s 5 � meaning of "available" and "shall ... have become due" in s
10(1) � whether registration of lien must be effected under s10(1) within 28
days after contract price has "accrued due" under s 5, for lien to be
"available" under s10(1) � meaning of "deemed" in s10(2)(a)
Re Sneesby; Ades and Bowes Contract [1919] VicLawRp 71; [1919] VLR 497, followed
Andrew v Arthur H. Dillon Pty Ltd (1942) 59 WN (NSW) 113, followed
K & S Lake City Freighters Pty Ltd v Gordon & Gotch [1985] HCA 48; (1985) 60 ALR 509,
Sitzler Bros Pty Ltd v DKB Investments Pty Ltd (1989) NTJ 345, approved
Marriott Industries Pty Ltd v Mercantile Credit Limited (1991) 160 LSJS
The Queen v The County Council of Norfolk (1891) 60 L.J.Q.B. 379,
Metropolitan Bank Company v Haywood [1938] SAStRp 57; [1938] SASR 462, followed
Cooper Brookes (Wollongong) Pty Ltd v F.C.T [1981] HCA 26; (1981) 35 ALR 151, applied
Australian Alliance Assurance Co Ltd v Attorney-General (Qld) [1916] St R
STATUTES � interpretation � Workmens Liens Act - construction of
s10(1) and s10(2) � whether s10(2) exhaustively defines when "contract
Advanced Civil Engineering Pty Ltd v Wyara Pty Ltd (1986) NTJ 715,
Millers Lime Ltd v Royal Agricultural and Horticultural Society of South
Australia [1936] SAStRp 57; [1936] SASR 306, followed
Albert del Fabbro Pty LTd v Wilckens & Burnside Pty Ltd [1971] SASR 121,
Jennings Construction Ltd v Burgundy Royale Investments [1986] NTSC 47; (1986) 42 NTR 1,
Parob Pty Ltd v Pipeline Properties Pty Ltd and Anor (1988) NTJ 1546,
Pipeline Properties Pty Ltd v Leichhardt Development Co Pty Ltd (1989) 58
Leichhardt Development Co Ltd v Pipeline Properties Pty Ltd (1989) 62
Malady Enterprises Pty Ltd v Colstar Pty Ltd (1991) NTJ 263, overruled
Marriott Industries Pty Ltd v Mercantile Credit Limited (1991) 160 LSJS
Longreef Pty Ltd v Leighton Contractors (South Australia) Pty Ltd (1991)
160 LSJS 270, followed
STATUTES � interpretation � Workmens Liens Act � construction of s10(4)
� whether act of registration of lien under s10(4) makes it "available"
under s10(1) � whether s10(2) must be complied with despite registration
of lien under s10(4), for lien to be "available" under s10(1)
Parob Pty Ltd v Pipeline Properties Pty Ltd and Anor (1988) NTJ 1546,
Pipeline Properties Pty Ltd v Leichhardt Development Co Pty Ltd (1989) 58
Leichhardt Development Co Ltd v Pipeline Properties Pty Ltd (1989) 62
Malady Enterprises Pty Ltd v Colstar (1991) NTJ 263, overruled
Marriott Industries Pty Ltd v Mercantile Credit Limited (1991) 160 LSJS
Longreef Pty Ltd v Leighton Contractors (South Australia) Pty Ltd (1991)
160 LSJS 270, followed
STATUTES - interpretation � Workmens Liens Act -desirability of
conformity in construction of identical provisions, as between different
Camden Park Estate Pty Ltd v OToole (1969) 72 SR (NSW) 188, referred to
STATUTES � interpretation � whether Mineral Lease under Mining Act
constitutes an "estate or interest in land" under s5 of Workmens Liens Act
R v Toohey; Ex Parte Meneling Station Pty Ltd [1982] HCA 69; (1982) 158 CLR 327, applied
Thiess Contractors Pty Ltd v White Range Gold NL (1991) NTJ 1013,
National Provincial Bank Ltd v Ainsworth [1965] UKHL 1; [1965] AC 1175, followed
Stow v Mineral Holdings (Aust) Pty Ltd [1979] HCA 30; (1977) 51 ALJR 672, applied
Plaintiff: (proceedings nos 1 and 134 of 1998) M Maurice QC
Plaintiff: (proceedings nos 1 and 134 of 1998): James Noonan
The questions referred to the Court, set out in par [6], are answered as
Not applicable, but clearly the answer to the substantive question is
Jovista Pty Ltd v Pegasus Gold Australia Pty Ltd & Ors
Henry Walker Contracting Pty Ltd v Pegasus Gold Australi a Pty Ltd
CORAM: MARTIN CJ, KEARNEY, MILDREN, THOMAS & BAILEY JJ
I have had the benefit of the draft reasons and decisions of Kearney J.
His Honours extensive review of the conflicting authorities and analysis of
the issues in these matters lead me to agree with the answers he proposes to
the questions referred to this Court. This Court comprising five Judges, the
decisions of the Supreme Court contrary to the result in these matters must
On 5 February 1999 and 19 March, pursuant to s 21 of the Supreme Court
Act, Angel J (in proceedings Nos. 1 and 134 of 1998) and Bailey J (in
proceedings No. 136 of 1997) respectively referred the 4 questions of law
set out in par [6] to this Court, for determination. For that purpose certain
facts and conclusions set out in the statements of claim filed in the 3
proceedings, were assumed to be correct. As far as presently material, those
The defendant is and was at all material times the owner and
occupier of Mineral Lease No 1070 known as Mount Todd (,,the
The defendants interest in the land is and was at all material times
an estate or interest in land for the purposes of the Workmens Lien
Act [herein ,,the Act]. [This fact is not assumed to be correct, for
On 5 September 1996 the parties made a written contract mining
agreement (,,the agreement) relating to a project known as the Mt
Todd Project whereby, in consideration of various payments to be
made from time to time by the defendant to the plaintiff, the latter
agreed to perform the work and provide the materials set out in
Section 3 of the agreement, ,,Specifications and Scope of Work . [It
can be seen that the parties were in a direct contractor/client
In Section 2, ,,General Conditions of Contract, the agreement
The Contractor [ie the Plaintiff] shall be entitled to payment of
the contract value of all Work carried out in accordance with
the Contract to the date of Termination (less amounts
previously paid to the Contractor in respect thereof).
Between the time the agreement was made [5 September 1996] and
15 November 1997 the plaintiff performed work under the agreement
to the land and to fixtures thereon and provided materials under the
agreement to be used in and about work done and intended to be
done to the land and the fixtures thereon, for some of which the
The amounts outstanding under the agreement (,,the unpaid monies)
Work done and materials supplied for November 97 $2,085,677.41
By written notice dated 15 November 1997 addressed to the plaintiff,
the defendant purported to terminate the agreement with effect from
that date, on the grounds that in the defendants opinion the
continuation of the Mt Todd Project was not economically viable. In
support of this action the defendant expressly relied upon clause 31.4
of the agreement [set out in item (2) in par [4]].
On the facts set out above the unpaid monies [in item(6) above]
accrued due on or before midnight 15 November 1997 [as per item
[The plaintiff then claimed that it became entitled to liens under the Act on
the defendants estate or interest in the land, in respect of the unpaid monies
On 12 December 1997 [that is, 27 days after the unpaid monies
,,accrued due in terms of item(8)] the plaintiff demanded payment
[under s 10(2)(a) of the Act] of the unpaid monies by notices in
writing to which its corporate seal was duly affixed, posted in a
registered letter to the defendants registered office at Edith Falls
On 24 December 1997 [that is, 39 days after the date on which that
the unpaid monies ,,accrued due in terms of item(8), and 12 days
after the demand for their payment was made in terms of item(9)] the
liens were registered under the Act. [These were Liens Nos. NL366
and NL367 for the November and October 1997 amounts,
[The plaintiff then proceeded to claim, inter alia, an order under s 25 of the
Facts to the same effect as those in items 1-3, 5 and 7 in par[3] were
assumed correct. The further facts assumed correct are:
It was an implied term of the agreement [of September 1996] that,
except as expressly provided in the document, the defendant would
do nothing to hinder or prevent efficient performance of the
agreement by the plaintiff and, further, that the defendant would do
everything necessary or proper and reasonable to facilitate efficient
performance of the agreement by the plaintiff, maximise productivity
and promote the objective of ensuring that the plaintiff operated at a
In section 2, ,,General Conditions of Contract, the agreement
31.4 The Company [ie the defendant] may by written notice
addressed to the Contractor [ie the plaintiff] terminate this
Contract at any time if in the Companys reasonable opinion
the continuation of the Mt Todd Project is not economically
viable, for any reason whatsoever. If the Company exercises
its right to terminate this Contract pursuant to this Clause 31.4
the Contractor shall be entitled to payment of the contract
value of all Work carried out in accordance with the Contract
to the date of Termination (less amounts previously paid to the
[There followed in the statement of claim, claims for losses and expenses in
respect of various items of work and materials � tyres, dewatering, battens,
drill and blast, productivity and accommodation. The following facts were
The losses and expenses referred to above are moneys payable by the
defendant to the plaintiff for work done and materials furnished by
the plaintiff in connection with work so as to amount to a contract
price or contract prices (,,the contract price) within the meaning of
On the facts set out [as per item(7) in par[3]] above the contract
price [in item (3)] accrued due on or before midnight on
[The plaintiff then claimed that it became entitled to liens under the Act on
the defendants estate or interest in land; in respect of the amounts referred
to in item(3), the following further facts are assumed correct]:
On 9 June 1998 [that is, almost 7 months after the contract price in
terms of the amounts in item(3) ,,accrued due on 15 November 1997
as per item(4)] the plaintiff demanded payment [under s 10(2)(a) of
the Act] of the contract price [in terms of item (3)] by notice in
writing dated 5 June 1998 to which its corporate seal was duly
affixed, served on the defendant by its solicitors.
By reason of the service of the notice [of 5 June 1998] and the
defendants non-payment, [pursuant to s 10(2)(a) of the Act] the
contract price is deemed to have become due for the purposes of
section 10(1) of the Act on or about 16 June 1998 [that is, 7 days
after service of the notice of demand in item(5) above].
On 17 June 1998 [that is, one day after the contract price (in terms of
item(3) was deemed to have ,,become due in terms of item(7), some
7 months after the contract price ,,accrued due in terms of item(4)
and 8 days after the demand in item (5)], lien No. NL 372 was
[The plaintiff proceeded to claim, inter alia, an order under s 25 of the Act for
The second, third and fourth defendants to proceedings No.136 of 1997
(herein "the contractors") had jointly contracted with the first defendant
thereto (referred to in this judgment as "the defendant") to supply men and
material for the extension of the defendants mine on Mineral Lease No.
1070. Jovista Pty Ltd contracted with the contractors by 4 contracts
numbered 1073, 1075, 1077 and 1078, to carry out certain works at the mine
pursuant to the contractors contract with the defendant. (It can be seen that
it is a subcontractor, as far as the defendant is concerned). Jovista Pty Ltd
claims that the contractors have refused to pay certain monies due to it being
monies due from variations to its 4 contracts, amounts it had been underpaid
on Progress Payment Certificates, and retention monies it claims to be now
due to it under Contract 1078; these amounts constitute the balance of the
contract price payable by the contractors to Jovista Pty Ltd under the 4
contracts. These facts are for present purposes assumed to be correct, as are
[the defendant] was a lessee, tenant or occupier of land namely
the land the subject of [Mineral Lease No.1070], within the
the [Contract Nos] 1073, 1075, 1077 and 1078 Works were
undertaken by [Jovista Pty Ltd] with the assent of [the
By 9 June 1997, the following monies, or some of them, were due
and presently payable, alternatively due but not presently payable,
[by the contractors] in respect of the work undertaken by [Jovista Pty
Ltd] pursuant to Contracts 1073, 1075, 1077 and 1078: [the monies
in question referred to above as the ,,balance of the contract price
By reason of the matters referred to in paragraph (2) above as at
9 June 1997 the following monies were accrued due by [the
contractors] to [Jovista Pty Ltd] within the meaning of the Act:
[The monies set out in par (2) were then set out again]
By [separate] Notices of Demand to [the contractors] dated 9 June
1997, pursuant to s 10(2)(a) of the Act [Jovista Pty Ltd] demanded
payment of [various sums specified, in respect of ea ch of its 4
[The contractors have] failed to pay any part of the sums demanded
[2 days after the s 10(2)(a) demands] on 11 June 1997 [Jovista Pty
Ltd] lodged and obtained registration of Notices of Workmens
Liens, registered 361, 362, 363 and 364 (,,the Liens) in the General
Registry at Darwin, in respect of the monies referred to in paragraph
(2) above. [It can be seen that the liens were registered before the 7-
day period in s 10(2)(a) expired on 16 June. Proceedings to enforce
the liens commenced on 24 June, 1 day before the 14-day period in
[the defendant] was liable to make payments to [the
contractors] pursuant to the [their] Contract in respect of the
work performed by [Jovista Pty Ltd] under [its 4] Contracts,
which is the subject of [Jovista Pty Ltds] claims for payment
in these proceedings and in respect of which the monies
referred to above in paragraph [(2)] had accrued due.
Against this background of assumed facts and on the assumption that each of
the sums in pars (2) and (3) above became due (in the sense that each was
due and presently payable to Jovista Pty Ltd) pursuant to the terms of its 4
contracts with the contractors more than 28 days before the date (11 June
Court on 19 March 4 questions identical in effect to those referred by
I note that on the assumed facts demands under s10(2)(a) were made in all 3
proceedings; the part contract prices were all then payable. The liens were
all registered after the demands were made � in 2 cases after the 7 days in
s.10(2)(a) had expired, in the other case (No.136 of 1997) 5 days before that
expiry; it is the last-mentioned case which requires consideration of s 10(4).
In all cases the liens were registered more than 28 days after the part
contract prices became due under the respective contracts. In the light of
the assumed facts in pars [3], [4] and [5] the following 4 questions of law
Are the plaintiffs liens now, and were they at the time of
registration, unavailable to the plaintiff pursuant to section 10(1) of
the Act, by reason of the fact that the liens were registered more than
28 days after the contract price became due under the Contract
If ,,yes to (1), at the time of registration were the plaintiffs liens
available for the purposes of the Act, notwithstanding non-
registration within 28 days of the contract price becoming due under
the Contract Mining Agreement, by reason of the plaintiffs
compliance with the procedures set out in section 10(2) of the Act?
If ,,no [to (1)], what is the effect of unavailability [of the liens] on:
(a) the existence of a lien; and (b) the enforceability of a lien; and
Does the defendant, as grantee of Mineral Lease No. 1070 under the
Mining Act 1980 (NT), have an ,,estate or interest in land for the
I deal with Questions (1), (2) and (3) together in pars[7]-[57], and with
The answer to Question 1 entails consideration of the proper construction of
A contractor or sub-contractor shall have a lien for the contract price,
so far as accrued due, on the estate or interest in land of any owner
where the work is done, with the assent, express or implied, of
the owner or occupier to the land or to any fixture thereon;
where the materials are, with the assent, express or implied, of
the owner or occupier, used or intended to be used in or about
work done, or intended to be done, to the land or to any fixture
(1) A lien under this Act with regard to land shall be available only
if registered before the expiration of 28 days after the wages or
contract price in respect of which such lien has arisen shall for the
(2) Any wages or contract price shall for the purposes of this section
if unpaid for 7 days after the same (being payable) shall have
been demanded by notice in writing, signed by the person
claiming the same and given to the person liable to pay the
same, or posted in a registered letter addressed to him at his
if either before or after the same shall have become payable,
the person liable to pay the same shall have called a meeting of
his creditors, or committed an act of bankruptcy, or executed a
deed of assignment within the meaning of the Bankruptcy Act
1966 of the Commonwealth, or shall have taken or attempted
to take the benefit of any law relating to bankrupts or insolvent
debtors, or shall have suffered his goods to be taken in
execution or seized under legal process or distress for rent.
(3) A lien shall be registered by the person claiming the same
lodging with the Registrar-General a notice in the prescribed form or
in a form to a similar effect, which notice shall be signed by such a
person and attested, together with the prescribed fee.
(4) A lien may be registered after the wages or contract price have
become payable, although the 7 days mentioned in subsection (2)
(5) Notices of lien under this Act shall state the Court in which
action will be brought to enforce the same, and any person to whom
notice is given may deposit the amount claimed in such Court to
abide the event of such action, and thereupon the lien shall be
Courts in the Territory and South Australia have expressed different views
about the proper construction of s 10. To answer Question (1) in par [6], the
first question to be addressed is whether giving a notice of demand under
s 10(2)(a), (or the occurrence of one of the events in s 10(2)(b)), is essential
in order that a contract price ""shall ... have become due" for the purposes
of s 10(1). In other words, is s 10(1) dependent upon s 10(2), or are they
independent provisions? An associated question is whether registration of a
lien under s 10(4), without more, renders it ,,available in terms of s 10(1).
In other words, does s 10(4) provide a pathway to the availability and
enforceability of a lien, separate from that provided by registration after the
contract price has "become due" in terms of s 10(1)? Before considering the
parties submissions on these questions, it is convenient to review the
authorities where they have been discussed. First, the Territory authorities;
In Advanced Civil Engineering Pty Ltd v Wyara Pty Ltd (1986) NTJ 715
there had been a demand under s 10(2)(a) for an amount greater than the
amount certified in a progress certificate. The certificate, pursuant to the
contract, resulted in the part of the contract price so certified accruing due,
and so gave rise to a lien in terms of s 5. The s 10(2)(a) demand had been
made at a time when the certified amount, though "due", was not "payable"
in terms of the contract; for a demand under s 10(2)(a) to be valid, the
certified amount had to be payable at the time of the demand. A lien was
registered 12 days after the demand. Was the lien "available" � that is,
enforceable � in terms of s 10(1), despite the invalid s 10(2)(a) demand?
Asche J (as he then was) considered that it was, on the basis that a demand
under s 10(2)(a) was not necessary for the price to "become due" in terms of
s 10(1). He considered that it became due pursuant to the terms of the
contract, on the issue of the certificate. It can be seen that, in effect, his
Honour considered that when part of the contract price "accrued due" in
terms of s 5, it had thereby "become due" in terms of s 10(1). This is the
essence of the defendants case in this proceeding � see par [34].
At 745-7, Asche J opined that the provisions of s 10(1) are "independent" of
the provisions of s 10(2)(a), the latter being simply "one way ... of
determining when a contract price shall be deemed to have become due". In
other words, his Honour considered that a contract price could "become
due" for the purposes of s 10(1), other than via a s 10(2)(a) demand (or a
s 10(2)(b) event). His Honours opinion to that effect is the foundation
upon which the edifice of the defendants case is erected, in par [36]. Asche
J was not persuaded that the words "shall for the purposes of this section" in
both ss 10(1) and (2), point to s 10(1) being dependent on s 10(2); to the
"the repetition [of these words in s 10(2)] rather conveys the
opposite sense, that the purposes of [s 10(1)] are achieved if the
contract price is [either] actually due or can be deemed to be due".
With respect, I am unable to accept that construction of those words.
His Honour noted that his approach that ss 10(1) and 10(2) are independent
of each other, differed from that of Murray CJ in Millers Lime Ltd v Royal
Agricultural and Horticultural Society of South Australia [1936] SAStRp 57; [1936] SASR 306
at 314. Murray CJ there opined that to acquire a lien �that is, an "available"
lien, in terms of s 10(1) � payment must be due and either "the amounts due
must have been ascertained by a demand" under s 10(2)(a) and a failure to
pay the amount demanded within 7 days, or one of the events in s 10(2)(b)
had occurred "either before or after the seven days [in s 10(2)(a)] have
commenced to run or have expired (see 10(4))". It is clear that Murray CJ
saw 10(1) and s 10(2) as interdependent; Angas Parsons J agreed at 326.
That is to say, Murray CJ considered that a contract price would "become
due" for the purposes of s 10(1), only by the notice of demand procedure
under s 10(2)(a), or by the occurrence of an event specified in s 10(2)(b).
In Wyara Pty Ltd (supra) Asche J observed that this opinion of Murray CJ
on s 10 had been "gravely doubted" by Bray CJ in Albert del Fabbro Pty Ltd
v Wilckens & Burnside Pty Ltd [1971] SASR 121 at 127. With respect, that
does not appear to be so. Albert del Fabbro Pty Ltd (supra) involved a
charge under s 7 on money payable, as well as a lien under s 5. Bray CJs
"grave doubts" were as to whether it was necessary "for the perfection of the
charge ... that a demand should have been made within the meaning of
s 10(2)". This was a question of the proper construction not of s 10 of the
Act but of s 7(3), which provided that a charge under s 7(1) lapsed unless
"within 28 days after the ...contract price ... shall have become due
In Millers Lime Ltd (supra) both a lien and a charge were involved; in
addition to spelling out at 314 the "essentials" to acquire a lien Murray CJ at
315 spelled out the "essentials" to acquire a charge; he considered that s
7(3) required compliance with s 10(2) in the sense of making a demand. For
present purposes, the point is that the "grave doubts" expressed by Bray CJ
were directed at Murray CJs construction of s 7(3), not at his observations
as to the essentials to acquire an available lien under s 10. There is nothing
to suggest that Bray CJ doubted those observations, set out in par[11]. I note
in passing that in W. Curl & Sons Regd. v Buck Industries Pty Ltd [1972] 2
SASR 335 at 342 Hogarth J distinguished the position relating to a charge
claimed under s 7 from that of a lien, and disagreed with Murray CJs
Jennings Construction Ltd v Burgundy Royale Investments Pty Ltd (1986) 42
NTR 1 involved seven proceedings. In one of them a progress certificate
had issued on 22 April; under the contract, payment of the amount thereby
certified to be due was to be made within 14 days. A demand under
s 10(2)(a) was made on 2 June. The lienee contractor lodged its lien for
registration on 2 June; this was more than 28 days after the certificate
issued on 22 April. The defendant lessee submitted that the amount had
"become due" for the purposes of s 10(1) when the progress certificate
issued on 22 April; and accordingly the lien was not "available", because the
28 days time limit for registration in s 10(1) had not been met. This is the
defendants submission, in par[34]. The basis of the lessees submission was
that the price could "become due" for the purposes of s 10(1), other than via
s 10(2)(a); this had been the approach of Asche J in Wyara Pty Ltd (supra) �
see par[10]. At 12-13 I differed from the approach of Asche J to the
relationship between s 10(1) and s 10(2). I considered that s 10(2) provided
the only means for fixing the date on which the contract price had "become
due", for the purposes of s 10(1). I rejected the submission that moneys
could "become due" for the purpose of s 10(1) in ways other than those
provided for in s 10(2). There was no consideration in this case of whether
s 10(4) provided a pathway separate to s 10(2), to an enforceable lien.
In Parob Pty Ltd v Pipeline Properties Pty Ltd and anor (1988) NTJ 1546
"...the limited but important function of stipulating when time begins
to run against a sub-contractor in whose favour a lien arises under
s 5, and who has not yet lodged notice of it for registration against
I observe that this construction of s10(1) does not accord with the accepted
view in South Australia � see pars [27] and [32] � that it provides
exclusively for when a lien becomes ,,available, and does so by req uiring
registration within 28 days of a date determined by a formula set out in
His Honour considered that the 28 days for registration in s 10(1) was not
to be reckoned from when the debt became ,,due and payable in the accepted
commercial sense of those words, but only from when it was deemed by
s 10(2)to have "become due" for the purposes of s 10(1). This was contrary
to the approach of Asche J in par [9]. Maurice J considered that in its
context, the word "due" in s 10(1) did "not bear its ordinary meaning"; with
respect, I agree. As to the concepts "due" and "payable", I note authorities
such as Re Sneesby; Ades and Bowes Contract [1919] VicLawRp 71; [1919] VLR 497 at 505-6
where Cussen J observed that "money may be due, although not presently
payable"; his Honour cited authorities which show that the meaning of "due"
in a particular statute is determined by the context. See to similar effect
Andrew v Arthur H. Dillon Pty Ltd (1942) 59WN (NSW) 113 at 114. I
respectfully agree with Cussen J; though the meaning of words in an Act
may appear to be clear when they are read in isolation, it is a cardinal rule
of statutory interpretation that they must be read in their context in the Act �
see K&S Lake City Freighters Pty Ltd v Gordon & Gotch Ltd (1985) 60 ALR
Maurice J considered that ss 10(1) and (2) were interdependent when it came
to fixing the time when the "contract price ... shall ... have become due" in
terms of s 10(1). He preferred the view I had expressed to that effect in
Jennings Construction Pty Ltd (supra) � see par [13] - which he considered
to be "consistent with the weight of South Australian opinion", citing
Millers Lime Ltd v Royal Agricultural and Horticultural Society of South
Australia (supra), per Angas Parsons J at 326; Albert del Fabbro Pty Ltd v
Wilckens & Burnside Pty Ltd [1970] SASR 277 at 284, per Bright J at
instance and, on appeal, at [1971] SASR 121 at 138, per Zelling J; W. Curl
& Sons Regd. v Buck Industries Pty Ltd (supra) at 341, per Hogarth J; and
Palyaris Constructions Pty Ltd v Kauri Timber Co. [1980] 24 SASR 41 at
One argument raised was that the (first) lien registered by the plaintiff
subcontractor had been valid, though registered before a demand was made
under s 10(2)(a) on the defendant head contractor as "the person liable to
pay the same". This gave rise to a consideration of s 10(4). Consistently
with his view that the commencement of the time-limit in s 10(1) was fixed
only via s 10(2), and that s 10(1) was limited to ,,stipulating when time
begins to run, Maurice J considered that a lien could be registered under
s 10(4) without triggering the 28-day time limit in s 10(1), and that no
demand under s 10(2)(a) was ever required when a lien was registered under
s 10(4). His Honour considered that a lien "arises [that is, it comes into
existence] when the conditions of s 5 are met" but "it may only be enforced
if registered"; I observe that that now appears to be the accepted view.
Section 10(4), in his opinion, enabled a li enee to register his lien "at any
time after the lien arises [under s 5]" and the contract price becomes
payable, thereby protecting himself against "the risk that the registered
proprietor will deal with the land" and thus defeat "the statutory charge [by
way of an unregistered, though existing, lien]". I accept that. In effect,
his Honour saw s 10(4) as providing a pathway to enforcing a lien, separate
to that provided by s10(1) read with s 10(2). This does not accord with the
current approach in South Australia � see par [14] � which sees s10(1) as
providing the solitary path to lien availability and enforcement. His Honour
considered that whether a lien was registered under s 10(4), or registered in
accordance with s 10(2)(a), enforcement action under s15 had to be brought
within 14 days after registration, if the lien was not to cease; I observe that
that appears to be the accepted view, though the South Australian approach
� see par [32] � requires that a s10(2)(a) notice be given even where
In Sitzler Bros Pty Ltd v DKB Investments Pty Ltd (1989) NTJ 345, a
demand under s 10(2)(a) was made on 29 August 1988, and liens were
registered 25 days later, on 23 September. Inter alia, the defendant
contended that the monies payable had "become due" in terms of s 10(1)
more than 28 days before the liens were registered, relying on the approach
of Asche J in Wyara Pty Ltd (supra). That was the defendants argument
here, in par [34]. Martin J (as he then was) rejected that approach, holding
that for the purposes of s 10(1), the contract price will "become due" only
Pipeline Properties Pty Ltd v Leichhardt Development Co Pty Ltd (1989) 58
NTR 17 involved an application to cancel the registration of a lien. It had
been registered under s10(4) seven days before a demand was made under
s 10(2)(a); enforcement action under s 15 was then instituted before
expiration of the 7-day period in s 10(2)(a) which determined when the
contract price was deemed to have "become due" for the purposes of s10(1).
Was the enforcement action valid? I approached the matter as follows. The
contract price would "become due" for the purposes of s 10(1) only if either
par (a) or (b) of s 10(2) were complied with. That is to say, s 10(1) and (2)
were interdependent, in determining when the price would "become due" for
the purposes of s 10(1). Setting aside s 10(4), when a demand was made
under s 10(2)(a) a lien had to be registered (and thus became available for
enforcement) within the 28 day period commencing 7 days after the demand,
when the contract price was deemed to have ,,become due. Since here the 7
days had not elapsed when enforcement action was instituted, the price had
not then "become due" and registration of the lien and its availability for
enforcement were not open at that time. I considered that if ss10(1) and (2)
were the only controlling provisions the demand had to be made and 7 days
had to have expired, before the lien could be registered and action instituted
to enforce it. Since enforcement action was not open at the time it was
instituted the action would fail, unless the lienee could "rely on some other
provision of the Act". (I should say that I think Mr Maurice QC is right,
that "lienee" is the correct term for the lien holder, though the cases usually
This led to a consideration of the effect of s 10(4). I considered at 20 that a
lienee could register his lien pursuant to s 10(4), without any prior
s 10(2)(a) demand, provided the contract price had "become payable". This
was simply what s 10(4) provided, and it was what appeared to have
occurred here. I considered "with great diffidence" that no s 10(2)(a)
demand had to be made, following a s10(4) registra tion. In the result I held
that the application to cancel the registration of the lien failed, because the
question whether the contract price had ,,become payable in terms of s 10(4)
could not be determined at that time. This approach followed that of
Maurice J in Parob Pty Ltd (supra), that s 10(4) provided a pathway to
enforcing a lien separate to that of s 10(2). Implicit in this approach was the
,,single function view of s 10(1) he had expressed in par[14], and its
corollary that availability of a lien (in the sense of its enforceability)
depended simply on the fact of registration before expiration of the time
Dismissing the appeal � see Leichhardt Development Co Ltd v Pipeline
Properties Pty Ltd (1989) 62 NTR1 � Asche CJ and Angel J agreed that a
s 10(2)(a) demand was not essential to support registration of a lien.
Asche CJ remained of the same opinion he had expressed in Wyara Pty Ltd
(supra) - see par[10] - that s 10(1) and 10(2) were independent of each other,
not interdependent; Angel J shared that view. He considered that s 10(2)(a)
did not institute the procedure which had to be complied with before a lien
could be enforced; rather it was "facilitative", in the special sense that it
provided a procedure which enabled the contractor or sub-contractor to
convert moneys payable in the future to him under the contract to moneys
payable to him immediately, for the purposes of s 5. I observe that this
approach construes the meaning of the words "being payable" in s 10(2)(a),
as extending to "being payable in the future", a construction which, with
respect, I do not consider in their context those words can bear; cf par[28].
His Honour considered that the time limit of 28 days in s 10(1) commenced
either from the time when the moneys became immediately payable as a
consequence of the contractual arrangements, because the lien was then
"immediately registrable" under s 10(4), or from the expiry of 7 days after
service of a s 10(2)(a) notice if that procedure were used, or on the
happening of one of the events in s 10(2)(b). His Honour considered that
while the words "for the purposes of this section" in s 10(1) could
encompass the s 10(2)(a) procedure, they necessarily encompassed the
registration procedure in ss 10(3) and 10(4). Asche CJ and Angel J both
agreed with the construction of s 10(4) set out in pars[17] and [20]; I
observe that that construction sat well with their basic view that ss 10(1) and
Rice J, dissenting, considered that (apart from a s 10(2)(b) event), a demand
under s 10(2)(a) was the condition precedent to a lien becoming "available"
in terms of s 10(1), for subsequent enforcement under s 15. This had been
the approach adopted by Murray CJ in Millers Lime Ltd (supra); see
par[11]. Rice J considered that a lien becomes "available" on registration
under s 10(1), only "after [the contract price] has also ,,become due"
pursuant to s 10(2)(a). His Honour followed what Bright J said at instance in
Albert del Fabbro Pty Ltd (supra) at 284, in that regard. He said that a
demand under s 10(2)(a) was a "necessary condition precedent to the
enforcement of the lien under s 15", citing in support what I had said in
Jennings Construction Ltd (supra). In that case, I had opined that s 10(2)
exclusively determined when a contract price had "become due" for the
purpose of s 10(1); however, I did not go on to consider whether a s 10(2)(a)
demand was a condition precedent to the enforcement of the lien.
In Malady Enterprises Pty Ltd v Colstar Pty Ltd (1991) NTJ 263 a lien was
lodged for registration under s 10(4) six days before a demand under
s 10(2)(a) was served, and more than 28 days after an invoice issued for
work done. The invoice date was conceded to be the date the contract price
was ,,payable. Gray J applied the majority view in Leichhardt Development
Co Ltd (supra), to the effect that a s 10(2)(a) demand was not mandatory to
fix the time when the contract price was to "become due", for the purposes
of s 10(1). His Honour considered at 266-7 that the time limit of 28 days in
s 10(1) for registration of a lien "must be capable of running from a date
other than [that] fixed" via a s 10(2)(a) notice. He opined that the
commencement date � in terms of s10(1), the date on which the "contract
price shall ... have become due"-was when "the relevant contract fixes the
time when the contract price becomes presently payable". In this case that
time was fixed by the invoice date; so on that date the price had "become
due", in terms of s 10(1). His Honour opined at 267 that it was
"commercially unacceptable" to construe the Act in such a manner that
"where a lien has arisen under Section 5, its registration may be delayed for
an indefinite period". With respect, bearing in mind the nature of the lien
when it arises under s 5, somewhat akin to a dormant or ,,floating charge, I
do not consider that the assessment that this consequence of such a
construction would be "commercially unacceptable", is correct; see s 32,
referred to in par [38]. At 268 his Honour opined that "the Act is concerned
to require that a lien is registered within 28 days of its birth"; that is, its
,,birth under s 5. That is the defendants argument in par[34]. His Honour
held at 269 that the purported registration more than 28 days after the ,,birth
of the lien under s 5 was "ineffective by reason of the non compliance with
Section 10(1) [in that the lien was registered more than 28 days after the
contract price became presently payable and hence had "become due"] and
[that defect] has not been cured by the subsequent Section 10(2)(a) notice."
That is the current state of the law on the construction of s 10 in the
Territory; it favours the defendants submissions in par[34]. In South
Australia the construction of s10 was last considered in 2 cases in 1991; I
In Marriott Industries Pty Ltd v Mercantile Credits Limited (1990) 55 SASR
228 a notice of lien was served on 28 April, and lodged for registration on
29 April. It was not registered within 28 days after the contract price
became due. It was accepted that there had been no prior demand under
s 10(2)(a). The defendant contended that the lien was not "available" in
terms of s 10(1) because it had not been registered in compliance with s 10,
in that no demand under s 10(2)(a) had been served. Its submission was
simple: "Because no [s10(2)(a)] demand has been served, no lien arises".
The lienee submitted that while the contract price became due 7 days after
invoice, the lien had been duly registered and enforceable under s 10(4).
Prior J held that s 10 of the Act is not a Code, in that it does not provide the
only method of calculating when a contract price has "become due for the
purpose of the Act"; he agreed with the approach of the majority in
Leichhardt Development Co Ltd (supra) � see par[21] - that the Act provides
in s 10(2)(a) a method for doing so. His Honour rejected the defendants
submission; implicitly, he took the same approach to s10(4) as in pars[17]
The Full Court allowed the appeal; see (1991) 160 LSJS 288. The question
was whether the lienee subcontractor had had a valid claim to enforce the
lien, immediately prior to its cancellation. King CJ reviewed the authorities
and considered that s 10(2) should not be construed as ,,facilitative in the
sense used by Angel J in Leichhardt Development Co Ltd (supra) at par[21].
His Honour considered that "available" in s 10(1) meant "capable of
enforcement by action" and "available as a security"; I respectfully agree.
Vitally, his Honour considered that a s 10(2)(a) notice has to be given, and
the 7 days in that provision has to have expired, before a lien already
registered under s 10(4) becomes "available" in terms of s 10(1). In other
words, his Honour considered (as had Murray CJ in Millers Lime Ltd
(supra)) that, setting aside any s 10(2)(b) event, a notice under s 10(2)(a)
always had to be given, if a lien under the Act were to be ,,available and
His Honours reasoning was as follows. Placing his "own interpretation" on
the provisions of the Act because of the "great...variety of judicial
opinions" and hence lack of "any definitive guidance", he considered that
s 10(1) imposed a dual requirement for a lien to be "available". First, the
contract price had to "have become due" for the purposes of s 10(1), in
manner provided for by s10(2). Second, registration of the lien had to be
effected within 28 days after that price had "become due" in that manner. I
note, by way of contrast, the single function attributed to s 10(1) by Maurice
J in Parob Pty Ltd (supra); see par [14]. King CJs approach accorded with
the unreported decision of the Full Court of the Supreme Court of South
Australia in Giles v Jacob in 1909, referred to in Pitt Ltd v The Corporation
of the Town of Glenelg [1927] SAStRp 37; [1927] SASR 501 at 534-5. In Giles v Jacob a lien
had been registered without a demand made under s 10(2)(a), an action was
brought to enforce the lien, and then a s 10(2)(b) event occurred. Way CJ is
reported to have expressed his opinion on s 10 tersely and comprehensively,
"Two things were necessary before the lien became available [in
terms of s 10(1)]. One was that money became due, and the second
was registration. The meaning of becoming due was that the money
must be payable, and unpaid after being demanded. There was a
registration [under s 10(4)] of 4 October, which should have been
Way CJ held that because no demand under s 10(2)(a) had been made, the
lien registered under s 10(4) was not ,,available. This approach and
decision may be contrasted with those in Parob Pty Ltd (supra) at par[17],
Pipeline Properties Pty Ltd (supra) at par [20], Leichhardt Properties Pty
Ltd (supra) at par [21], and Malady Enterprises Pty Ltd (supra) at par [23].
King CJ considered that on its "natural construction", s 10(2) defined the
words "become due" in s 10(1); this is somewhat akin to Mr Maurices
approach at par [42]. Since to be the subject of a demand under s 10(2)(a)
the (unpaid) contract price, or part of it, had to have the quality of "being
payable", it must already have "accrued due", in terms of s 5; I respectfully
agree � see below and par [40]. Accordingly - and this is a vital step in his
Honours reasoning - the only "intelligible purpose" of s 10(2)(a) was to
impose "an additional pre-condition [by way of the demand, the others
being that the price had already "accrued due" and "was payable"] to the
right to enforce a lien, or to rely upon it as security" (emphasis added). I
note that this was what Way CJ meant in par [27] when he said: "The
meaning of becoming due [in s 10(1)] was that the money must be payable,
and unpaid after being demanded." King CJ observed that while money can
be "due" but not "payable", the reverse cannot obtain; I note that was also
the view of Napier J (as he then was) in Metropolitan Brick Company v
Haywood [1938] SAStRp 57; [1938] SASR 462 at 468. Money which is "payable" is money
which must be paid � "it is due, and the time for payment has arrived"; I
respectfully agree. His Honour considered that to say that money is
"payable in the future" is really to say that it is not yet payable; cf. the
approach of Angel J to the words "being payable" in s 10(2)(a) in par[21],
His Honour had then to take account of the role of s 10(4) in the general
scheme of s 10. Clearly, he considered that it was ancillary to the scheme
embodied in s 10(1) and 10(2), as he perceived it in pars[26] - [28]. He
accepted that s 10(4) permitted registration of a lien at any time after the
contract price had "become payable", even though the 7 days in s 10(2)(a)
had not "commenced to run". Vitally, he considered that such registration
under s10(4) did not mean that the lien thereby became ,,available in terms
of s 10(1). Despite registration under s 10(4), the lien could not be enforced
(that is, it was not "available"), or even operate as the ,,deemed caveat
contemplated by s 12, until a s 10(2)(a) notice had been given and the 7 day
period contemplated by s 10(2)(a) had expired. This approach to s 10(4) is
in marked contrast to that of most Judges in the Territory thus far - see
pars[17], [20] [21] and [23] � though it accords with that of Rice J,
dissenting, in par[22]. King CJ accepted that his construction of s 10(4)
presented problems in assigning any "useful purpose" to the requirement
(on his approach) that a s 10(2)(a) demand for payment still had to be made
after registration of the lien under s 10(4). However, he considered that the
difficulties in discerning the purpose of s 10(2)(a) would be greater, if it
were construed as ,,facilitative in terms of par[21].
Olsson J, with whom Mohr J agreed, observed that the "weight of decided
authority" in South Australia ran "heavily counter to the conclusion of
Asche CJ" in Leichhardt Development Co Ltd (supra) � see pars[10] and
[21] � that s 10(2)(a) was merely one method of calculating when the
"contract price...shall... have become due" in terms of s 10(1). His Honour
reviewed those authorities, which were mainly those listed by Maurice J in
Parob Pty Ltd (supra) at par[16]. He considered at 310 that the proposition
that s 10 (4) "in some way stands alone" from s 10(1) and (2) and
"authorises the enforcement of a lien otherwise than as envisaged" by those
provisions, was unwarranted both in terms of "the authorities binding upon
this court" and as a matter of construction. In his opinion s 10(4) merely
permitted "the provisional registration of a notice of lien prior to the i ssue
of a formal notice of demand" under s 10(2)(a), "so as to give notice of the
claim and to protect the position of a proposed lienor during the seven day
period envisaged by" s 10(2). This conception of registration under of
s 10(4) as "provisional" in nature stands in marked contrast to that of most
of the Judges in the Territory who have considered the matter; see pars [17],
I note that on 5 September 1991 the High Court refused special leave to
appeal from the Full Courts decision in Marriott Industries Pty Ltd (supra).
Brennan CJ observed that the Act was "generally acknowledged to raise
extreme difficulties of interpretation"; however, since its interpretation was
"largely a matter of judicial impression", his Honour considered tha t a grant
of special leave would not be "likely to lead to the elucidation of any
In Longreef Pty Ltd v Leighton Contractors (South Australia) Pty Ltd (1991)
160 LSJS 270 King CJ expressed views on the Act similar to those he had
expressed earlier that day in Marriott Industries Pty Ltd (supra).
His Honour said that he was unable to agree either with the decision in
Leichhardt Development Co Ltd (supra), or with the dictum of Angel J at
par[21] that s 10(2)(a) was ,,facilitative. At 27 6 he set out his understanding
of the relationship of ss 5, 6 and 10, and the scheme of the Act with respect
"... a contractors or sub-contractors lien can only arise when the
lienors title to the debt has accrued under the terms of his contract
(section 5), although it may arise notwithstanding that the debt,
having arisen, is payable in the future. The extent of the lien is
limited by section 6 to the amount due and presently payable by the
owner or occupier under the contract for the purpose of which the
work was done or the materials supplied. In a situation in which a
lien which has arisen because an amount has accrued due under the
contract, but there is no amount presently payable by the owner or
occupier, the lien is dormant until an amount becomes so payable.
Although a lien has arisen by reason of the contract price or part
thereof having accrued due under the terms of the contract, it is not
"available", that is to say "not capable of enforcement" or "valid as
a security", until it has "become due" for the purposes of section 10.
That will occur if one or other of the events enumerated in section
10(2)(b) has occurred, or if the price is unpaid for seven days after
notice has been given under section 10(2)(a). That notice can only
be given validly after the price is payable, that is to say after the
entitlement has arisen under the contract, thereby bringing the lien
into existence, and the time for payment has arrived. The lien, if it
has acquired a valid existence by reason of the price having accrued
due, [and if the price has become payable], may be registered
pursuant to section 10(4) prior to the section 10(2)(a) notice, but the
action to enforce it cannot be commenced until the lien is
His Honour is clearly saying in the passage last emphasized that where a
lien is registered under s 10(4) its enforcement (which s 15 requires to be
instituted "within 14 days from [that] registration" )cannot be effected until
expiry of 7 days from the essential s 10(2)(a) demand because, as
his Honour spells out in the passage first emphasized, only by the price
having "become due" by the s 10(2) procedure, does the lien become capable
of enforcement under s 15. I note that this could create some practical
I note in passing that in Ginos & Associates Ltd v Accordent Pty Ltd
(unreported, Supreme Court of South Australia (Full Court), 23 December
the Act in Longreef Pty Ltd (supra), observed that the correctness of that
authority was not challenged in that appeal "nor ... could [it] have been".
Against this review of the differing approaches in the courts, I turn to the
The ultimate submission of Mr Gee QC, senior counsel for the defendant,
was as follows. The contract price ,,accrued due on 15 November 1997. On
the proper construction of the Act the lien which thereby arose under s.5 of
the Act, had to be registered within 28 days after that date, and not within
28 days after a date determined by s 10(2). This admittedly had not
occurred. It followed, in his submission, that Questions (1)-(3) in par[6]
should be answered: (1) ,,Yes; (2) ,,No; and (3) ,,The lien is unavailable and
He submitted that because the Act had become an enactment of the Territory
in 1991, rather than, as hitherto, an Act of South Australia in force in the
Territory, ss 55, 62A and 62B of the Interpretation Act applied to its
interpretation. I accept that, assuming that it is in force.
As to the proper construction of s 10, on which his ultimate submission in
par[34] was based, he had 3 submissions. First, there was no difference in
meaning between the expressions "accrued due" in s 5, and "become due" in
s 10(1). The dueness - the quality of being due - in s 10(1) was the same
dueness which was the "essential characteristic" of the liens existence
under s 5. I note that at the heart of the opposing construction advanced in
pars [43] and [49], is the concept that "become due" in s 10(1) bears a
special and artificial meaning, quite different from the use of "due" in s 5
where it bears its usual meaning; and that that special meaning is determined
exhaustively by s 10(2) "for the purposes of" s 10(1). Mr Gee submitted that
in the authorities which suggested that there was a difference between the
meaning of "accrued due" in s 5 and "become due" in s 10(1), that
difference had simply been assumed to ex ist; however, I note the reasoning
of King CJ in Marriott Industries Pty Ltd (supra) at par [28]. Mr Gee
submitted that, lexicologically, "accrued" and "become" have the same
meaning; I observe that while that there is merit in that point in the abstract ,
these words need to be read in their respective contexts in s5 and s10(1) of
the Act. He submitted that the structure of s 10(1) also supported his
submission, because it focused on the dueness of the contract price, not on
its payability. I consider that this does not really address the opposing
submissions in pars [43] and [49] that "become due" is used in a special
sense in s 10(1); further, the price must already have been payable � and
hence already ,,due in the s5 sense - if s 10(2)(a) is utilized to deem it to
have "become due" for the purposes of s10(1), and this fact alone suggests
that the ,,dueness in s 10(1) is of a special quality, different to that in s 5.
Second, Mr Gee submitted that as a corollary of the suggested identity in
meaning between "due" as used in ss 5 and 10(1), once a contract price (or
part of it) has "accrued due" under s 5, the 28 days time limit in s 10(1) for
registration of the lien (which ex hypothesi has arisen under s 5)
immediately starts to run. I agree that if the premise is correct, this
Third, Mr Gee addressed a matter the true significance of which bore on the
role and function of s 10(4). He submitted that the availability of the lien
provided for in s 10(1) - that is, its enforceability � does not depend on the
dueness of the contract price, but only upon the fact of registration of the
lien. The dueness of the price is significant in s 10(1) only insofar as it
fixes the commencement of the time within which registration must be
effected, apart from registration under s 10(4). It can be seen that this
submission accords with the construction advanced in Parob Pty Ltd (supra)
at par [14]; see also pars [20], [21] and [46]. It is contrary to the
construction favoured by King CJ in Marriott Industries Pty Ltd (supra) and
Longreef Pty Ltd (supra) at pars[26]-[28] and [32]. King CJ saw s 10(1) as
imposing a dual requirement for a lien to be ,,available: both dueness of the
contract price (in a special sense of "due", which entailed a demand for
payment under s 10(2)(a) of a payable price, or a s 10(2)(b) event) and
registration of the lien, were required. Mr Gee rightly noted the "head-on
conflict" between the construction he advanced, and that in the passage first
He noted that it was implicit in King CJs construction in par[32]that a
lienee was under no time restriction within which to serve a notice of
demand under s 10(2)(a), so as to create the necessary dueness for the
purposes of s 10(1). As to that suggested lack of any time limit on taking
action under s 10(2)(a) to trigger the process of lien registration and
enforcement, he submitted that the Act elevated a lienee, simply an
unsecured creditor, to a special position of preference; the quid pro quo was
that it also contemplated that he would take timely steps to register and
enforce his lien, once it came into existence under s 5. On Mr Gees
construction, 28 days from ,,birth of the lien under s5 was allowed. He
submitted that if the lienee were not required to take timely steps after the
,,birth of his lien, the owner would have no timely means of testing the
validity of the lien, or clearing it off his title by depositing money under
As to this submission, I note that s32 of the Act enables the owner to take
action at any time if he claims that he has been "prejudicially affected by a
claim, lien, or charge, or by registration under [the] Act". Mr Gee noted
that all the modern authorities considered that a lien came into existence
pursuant to s 5, before it was registered; I agree - see, for example, pars [17]
and [32]. He submitted that s 10 carefully distinguished between a contract
price having "become due" in s 10(1), and its "being payable" or having
"become payable"; and that for the price to have "become due" connoted
only that the monies were owing, under the contractual arrangements. I
accept the first point but I do not consider that it necessarily assists
Mr Gees argument; as to the second � which really restates his first
submission in par [36] - I consider (as indicated in par [36]) that the "being
payable" precondition in s 10(2)(a) suggests that "become due" in s 10(1)
connotes not only that the monies ,,due are owing under the contract, but
The effect of s 10(4) is a live issue in proceedings No. 136 of 1997; see
par [6]. Mr Gee submitted that s 10(4) was subordinate to the ,,fundamental
structure of s 10, which required registration of the lien under s 10(1) if it
were to be ,,available. Registration under s 10(1) had to be effected within
28 days of the dueness of the price (in the sense of ,,dueness he had outlined
in par[36]), not of its payability; he noted by way of contrast that action
under s 10(4) turned on the ,,payability of the price. I noted in par[36] that
the fact that s 10(2)(a) required payability as a condition precedent to its use
in determining when the price "becomes due" in terms of s 10(1), is a matter
which militates against Mr Gees submission that ,,dueness is used in its
He submitted that s 10(4) had only a limited role in the Act, namely to
enable a lienee who contemplated making a demand under s 10(2)(a)
immediately to register his lien without waiting for the 7 days prescribed by
s 10(2)(a) to commence or elapse. He submitted that such a registration did
not attract availability to the lien; that quality was a creature exclusively of
s 10(1). Section 10(4) did not provide a path to availability (in the sense of
enforceability) of the lien, separate from s 10(1) and unfettered by the 28-
day time limit in that provision. In this last respect Mr Gees submission
was not in accord with views as to s 10(4) expressed in some of the
Territory cases � see pars[17], [20] and [21] � and accorded with the
approach to s 10(4) in the South Australian cases � see pars[29], [30] and
Mr Gee rightly conceded that the requirement in s 10(2)(a) that the price be
already "payable", presented problems for his submission that its function
was to provide for a "notional dueness", in the sense he attributed to
,,dueness in s 10(1) in par[36] � its ordinary sense, as in s 5. In my opinion
it is clear that if a price is "payable" it must also be "due", in the ordinary
sense of that word; see pars [15] and [28]. To my mind the requirement in
s 10(2)(a) that the price be then "payable" presents an insuperable obstacle
to Mr Gees submission as to the function of s10(2)(a). The ,,payable
requirement in s10(2)(a) requires that the price be already due (in the
ordinary sense of ,,dueness) before s 10(2)(a) can be utilized, yet Mr Gees
submission is that s.10(2)(a) is used to determine that the price has "become
due" (in the ordinary sense of ,,dueness) for the purposes of s 10(1). That
cannot be right. I consider that the requirement of payability in s 10(2)(a)
strongly favours a construction that in the phrase "shall for the purposes of
this section have become due" in s 10(1) (followed by the deeming provision
in s 10(2)) the legislature treated "due" in s10(1)as having a meaning "for
the purposes of" s 10 other than the ordinary meaning it bears in s 5.
In a linked submission, Mr Gee submitted that the word "deemed" in s 10(2)
is used to create a "fictional dueness" in the ordinary sense he attributed to
,,due in par[36]. I consider that there is no scope for such a construction of
"deemed", again because a price which is "payable" as required by
s 10(2)(a) must in reality already be due, in the ordinary sense of ,,due; see
par[40]. In my opinion, the word "deemed" in s 10(2) in its context is
equivalent to the word "adjudged". It does not create a statutory fiction of
the type discussed, for example, in Loizos v Carlton United Breweries Ltd
(1993-94) 94 NTR 31 at 32-3. It extends the denotation of "become due" in
s10(1) to what those words would not in ordinary parlance denote; it infuses
"become due" in s 10(1) with meaning, by designating what that term there
comprehends. I consider that "deemed" is used in s 10(2)(a) in an
exhaustive, rather than an inclusive, sense; adapting the words of Cave J (as
he then was) in The Queen v The County Council of Norfolk (1891) 60
L.J.Q.B. 379 at 381, it points to an intention in the legislature to confine
"become due" in s 10(1) to what it specifies in s 10(2), and not to go beyond
that. See generally on ,,deeming Muller v Dalgety & Co Ltd (1909) 9 CLR
693 at 696, per Griffith CJ; Hunter Douglas Australia Pty Ltd v Perma
Blinds [1970] HCA 63; (1969-70) 122 CLR 49 at 65-7, per Windeyer J; and Rowe v Hughes
[1974] VicRp 7; [1974] VR 60 at 68.
The submissions of the plaintiff Henry Walker Contracting Pty Ltd
The major submissions of Mr Maurice QC, of senior counsel for this
plaintiff, were as follows. The meaning of s 10(1) and s 10(2) was clear; it
was ascertainable simply from the words of those provisions, which were
used in their natural and ordinary meaning, a usage which did not lead to
any manifest absurdity. I note that many judges have not found the
language of the Act to be so clear. See Brennan CJs reference to its
"extreme difficulties of interpretation" in par [31]. In Parob Pty Ltd (supra)
the learned judge referred to "a chorus of judicial protest about the
ambiguities and uncertainties attending many aspects" of the Act, which he
characterized as a "thoroughly discredited piece of legislation". In Pipeline
Properties Pty Ltd (supra) I referred to the Acts "fuliginous obscurity". In
Marriott Industries Pty Ltd (supra) Olsson J noted that the Act "has become
notorious for its difficulties of rational construction". In his judgment of
26 November 1998 leading to these proceedings Angel J referred to "the
enigmatic language of the Act", and "the muddy state of the authorities";
and in his judgment of 4 February 1999 Bailey J referred to "the obscure and
unsatisfactory nature of the antiquated" Act. That is a small sample of
adverse judicial comment on the Acts Delphic drafting.
Mr Maurice submitted that s 10(1) stipulated that a lien was not "available"
until it had been registered; this had to be effected in a timely way. Section
10(2) determined this timeliness, by fixing the date from which the 28-days
limit for registration under s 10(1) commenced, by determining when the
"contract price shall for the purposes of this section have become due".
"Become due" in s 10(1) was determined solely by s 10(2), and thus in
s 10(1) it was an artificial and technical concept. Sections 10(1) and 10(2)
were interdependent in that sense; this was made clear by the use of the
words "for the purposes of this section" in both provisions. The only
purpose of specifying a commencing time in 10(1) via 10(2), however, was
to fix the outer time limit within which the lien had to be registered.
Section 10(1), in providing for the commencement of that time -limit,
expressly contemplates that the "lien has arisen" with respect to the contract
price. That is clearly a reference to s 5. Thus s 10(1) proceeds on the basis
that the contract price has already "accrued due" in terms of s 5, when
setting out a formula to determine the commencement of the 28-days time
limit. It follows that since s 10(2) determines the time of commencement of
the 28-days limit "for the purposes of" s 10(1), in terms that require the
price already to have been "payable" (and hence ,,due in its s5 ordinary
sense), the 28 days could not begin to run from the earlier date when the
contract price had "accrued due" pursuant to s 5. Once s 10(2) is treated as
fixing the commencement of the s 10(1) time limit for registration, to
construe "become due" in s 10(1) as equivalent to "accrued due" in s 5 is not
I consider that this line of reasoning is compelling.
Mr Maurice submitted that the 28-days grace in s 10(1) for the lienee to
register his lien, commencing 7 days after a s 10(2)(a) demand, had not been
shown to cause any great inconvenience in practice. This was in contrast to
what would be the practical effect if the construction advanced by the
defendant in par[34] obtained. That would require any prudent unpaid
contractor or subcontractor first to register his lien within 28 days of each
instalment of the contract price accruing due under s 5, and then to issue a
court writ to enforce it within 14 days of such registration. I accept that
submission, and consider that such a nonsensical procedure could ne ver have
been intended by the legislature. As Jordan CJ said in Hall v Jones (1942)
[1942] NSWStRp 22; 42 SR (NSW) 203 at 208, a court should assume that the legislature
"intended to enact sense and not nonsense". The consequences of giving a
particular meaning to a provision in an Act are taken into account when
interpreting it; see Cooper Brookes (Wollongong) Pty Ltd v F.C.T. (1981) 35
ALR 151 at 169-170, per Mason and Wilson JJ. This consequence militates
against the construction of "become due" advanced by Mr Gee. Mr Maurice
noted that on the defendants construction of "become due" in s 10(1),
s 10(2) served no useful purpose; I accept that. He also submitted that the
only function of s 5 was to bring the lien into existence; I accept that.
Mr Maurice pointed out a further practical consequence of the defendants
construction of s10. A contract price which had "accrued due" in terms of
s 5, might often not be "payable" for more than 28 days thereafter. In such
a case, if the 28 days for registration were to commence from the date on
which the contract price had "accrued due", as the defendant contended, that
time would have expired before a lienee could lawfully register his lease
under s 10(4), or issue a demand under s 10(2)(a), since each of those
provisions required that the contract price first be "payable", in the sense
used by King CJ in par [28]. That is to say, in such a case, on the
defendants construction of s 10, the lienee could never register his lien
within time. I consider that this obvious practical consequence of the
defendants construction is one the legislature could never have intended to
occur. It also militates against the defendants construction of "become
Mr Maurice submitted that s 10(4) was unnecessary, in the scheme of
s 10(1) and (2). Its function was to enable a lien to be registered after the
contract price had "become payable" (and hence after it had also ,,accrued
due in terms of s 5), even though no s 10(2)(a) demand had been made.
When the lienee adopted this course, th e lien became immediately
"available" in terms of s 10(1), following its registration, because
,,availability under s 10(1) turned only on the fact of registration; cf the
approach of the defendant on this point in par [39], and of Jovista Pty Ltd in
par [50]. For this reason, after registration had been effected under s 10(4),
there was no need - and no requirement - that a demand under s 10(2)(a)
then be made, before the lien became ,,available under s 10(1). It was
It can be seen that Mr Maurice agreed in this last respect with Mr Gees
third submission, in par[37]; the submission also accords with the approach
in pars [17], [20] and [21]. It will be recalled that he had submitted that the
commencing date for the s 10(1) time-limit could only be determined
pursuant to s 10(2); see par[43]. He now submitted that a registration
pursuant to s 10(4) would necessarily have been effected before the 28-days
time limit in s 10(1) would have expired, had the s 10(2) procedure been
adopted. That is to say, a registration under s 10(4) would always be within
the s 10(1) time limit for registration; a s 10(4) registration must always
occur "before the expiration" of the time limit, as required by s 10(1).
That appears to be correct, accepting the notional element involved : absent
a s 10(2)(a) notice or a s 10(2)(b) event, there is no actual commencing date
for the 28-days time limit for registration in s 10(1) (on Mr Maurices
approach in par [43]), and hence no actual period of time within which
s 10(1) requires registration. It is implicit in the present submission as to
s10(4) that ss 10(1) and 10(2) do not require that the process which they
spell out in detail, designed to determine the commencement of the 28-day
period which s 10(1) specifies, actually be carried out, before a lien
becomes ,,available. Mr Maurice rightly conceded that on this construction
I note that this approach to the function and effect of s 10(4) follows that
spelled out in some of the Territory cases, in pars[17], [20] and [21]. It
does not accord with the current South Australian view, expressed in
pars[30] and [32], to the effect that before a lien can be "available"
following registration, the contract price m ust also have "become due", via
the deeming provision in s 10(2). I note that in Pitt Ltd (supra) at 521 and
534, Richards J appeared to take the same approach to s 10(4) as that
advanced by Mr Maurice. Mr Maurice conceded that the reference to
s 10(2)(a) in s 10(4) might suggest, implicitly, that s 10(4) contemplated
that a s 10(2)(a) demand must issue, following registration under s 10(4).
Mr Collins QC of senior counsel for this plaintiff submitted generally that
the Act made it clear that the mere fact that a contract price was not paid on
the day on which it was payable, did not permit the lienee immediately to
enforce his lien. Rather, the Act contemplated that a lien was not
enforceable unless notice was first given. The rationale for this was that by
creating the statutory lien the Act elevated the right in personam of an
unpaid contractor or sub-contractor to a security right, and required as a
quid pro quo of that elevation that notice be given.
Mr Collins approach was broadly that adopted by King CJ in par [32 ]. He
submitted that, setting aside s10(4), the Act contemplated the existence of 3
steps in a time continuum, and its provisions proceeded upon that basis; I
note the similar reference to ,,sequence by Bright J in Albert del Fabbro Pty
Ltd (supra) at 284. First, in time, the lien for the contract price arises under
s5, so far as it has then "accrued due". Second, the price which has
"accrued due", becomes "payable". These first and second steps could be
coterminous; that depends on the particular contractual provisions. In s 10
"payable" is used in the sense of "presently payable"; I agree. He submitted
that ,,payability in this sense is a precondition to availability of the lien in
terms of s 10(1), unless a s 10(2)(b) event occurs � in which event
registration must be effected within 28 days from that event.
He submitted that apart from a s 10(2)(b) situation, the lienee is under no
compulsion as to the time within which he must re gister his lien (to enforce
it, to obtain the price presently payable to him). He may choose to register
under s10(4) immediately the price becomes payable, to avoid the risks
referred to in par[17]; he may choose to issue a demand under s 10(2)(a). I
note that, on this approach to the construction of ss5 and 10, the lienee may
choose to do nothing at all, and his lien (which has arisen under s 5) would
He submitted that bearing in mind the need for notice to be given be fore
enforcement (as per par [48]), the Act required that this (presently payable)
contract price "become due" in s 10(1) before the lien could be registered.
The Act then proceeded "for the purposes of" s 10, to spell out in s 10(2)
what "become due" means, the third and final step in the time continuum
leading to lien enforcement. The word "deemed" as used in s 10(2)
emphasizes that "become due" in s 10(1) is used in a special sense "for the
purposes of" that provision. Once the price has "become due" in this special
sense, the lienee has to register his lien within 28 days, and enforce it within
14 days of registration if it is not to cease. As I have already sufficiently
indicated, I am persuaded that this is the proper construction of ss 10(1) and
Mr Collins submitted that the sole purpose of registration under s 10(4)
served a purpose ancillary to that of s 10(1) and 10(2): to enable speedy
registration, so as to secure the priority which s 9 gave to a registered lien.
Section 10(4) was not concerned with the availability of the lien; that was
provided for in s 10(1), and could only be triggered by action under s 10(2).
The practical result was that a lienee who had registered his lien under
s 10(4), had of necessity to make a prompt s 10(2)(a) demand to avoid
cessation of the lien. The practical effect of this construction of ss.10(4)
was to reduce the 14-day period in s 15 to 7 days (or less). I note, for
example, that if the lienee did not make a s 10(2)(a) demand until 8 days had
elapsed after his s 10(4) registration, the further 7 days which s 10(2)(a)
required then to elapse would mean that he could not take enforcement
action within 14 days of the registration, as required by s 15, and his lien
would then cease. It will be noted that this construction of s 10(4) differs
markedly from that of Mr Maurice in par[46]. Mr Collins submitted that the
concluding words in s 10(4) � "although the 7 days mentioned in subsection
(2) shall not have commenced to have run" � expressly recognised the
central importance of the notice under s 10(2)(a) for the purpose of fixing
the commencement of the 28-day time limit in s 10(1), and hence (on his
approach) for determining the availability and enforceability of the lien.
Against the background of these submissions, Mr Collins submitted that the
concept of "become due" was the mainspring of s 10(1), including the
availability of the lien provided for therein. It can be seen that the
construction of s 10 advanced by Mr Collins accords generally with that of
Mr Collins submitted that even if the Court did not favour this construction,
in the interests of comity it should now adopt it, to maintain uniformity with
the construction of the Act in South Australia in Marriott Industries Pty Ltd
He submitted that the defendants construction meant that many words in
s 10 could not be assigned a meaning. Further, in effect, that construction
not only equated "become due" in s 10(1) with "accrued due" in s 5, but also
He submitted that this plaintiffs liens were validly registered and available,
because the 28-day period in s 10(1) begins to run only after the contract
price has "become due" under s 10(1), via s 10(2). On the assumed facts in
par[5] the price had "accrued due" and become payable on 9 June; a
s 10(2)(a) demand was then made on 9 June; the "accrued due" price had
accordingly "become due" 7 days later on 16 June, for the purposes of
s 10(1); and on 11 June registration of the lien had been effected under
s 10(4), before the 28 days time limit commencing 16 June expired on
14 July. The fact that under the contractual arrangements, the price was due
and payable by the contractors more than 28 days before the registration on
11 June, was simply irrelevant. Accordingly, he submitted that Questions (1)
� (2) in par [6] should be answered: (1) ,,No; and (2) ,,Provided notice was
given in accordance with s 10(2) of the Act, yes. Mr Collins did not
The various submissions show that what is in issue is the construction of
provisions in the Act which are susceptible of more than one meaning. No
construction of s 10 is wholly satisfactory. It will always be possible to say:
"If construction X is adopted, section Y has no work to do". So it is for
example, with s10(2)(a), if the construction of s 10(4) in par [46] is adopted;
cf. pars [28] and [29]. In general, a statute s hould be so interpreted as to
give all its provisions some meaning and effect. Nevertheless, this may on
occasion be impossible; this is one of those occasions. The duty of the
Court in such circumstances is to give the Act the construction, fairly open,
which produces the more reasonable result; that is, the construction which
"produces the greatest harmony and the least inconsistency" as Cooper CJ
put it in Australian Alliance Assurance Co Ltd v Attorney-General (Qld)
[1916] St R Qd 135 at 161.
I adopt that approach. I have already sufficiently indicated when going
through the submissions, the general view I take. I consider that the better
construction of s10 is that favoured by King CJ in Longreef Pty Ltd (supra),
set out in par[32]. I think that this construction best expounds the Act
according to the intent of the legislature, best promotes the underlying
purpose of s 10, and results in a fairer and more convenient operation of the
Act as a whole, bearing in mind its general object and purpose. There is
nothing novel about this construction; it was tersely and accurately stated by
Way CJ 90 years ago in Giles v Jacob; see par [27].
As to Mr Collins point on comity, in par[52], I consider that it is generally
desirable that there be conformity in the construction of an Act which is in
identical terms in both the Territory and South Australia; see Camden Park
Estate Pty Ltd v OToole (1969) 72 SR (NSW) 188 at 190. However, on the
approach I take, that aspect does not arise. I consider, with respect, that the
construction of ss 10(1) and (2) favoured in Wyara Pty Ltd (supra), by the
majority in Leichhardt Development Co Ltd (supra), and in Malady
Enterprises Pty Ltd (supra), is erroneous; so is the limited construction of
s 10(1) in Parob Pty Ltd (supra); and so also is the construction of s 10(4) in
Parob Pty Ltd (supra), in Pipelines Pty Ltd (supra) and, on appeal, by the
majority in Leichhardt Development Co Ltd (supra). I would answer
Questions (1) � (3) in par[6]: (1) ,,No; (2) ,,Not applicable, but clearly the
answer to the substantive question is ,,Yes; (3) ,,This question does not
require answer. I deal next with Question (4), in pars [58] to [66].
Mr Gee submitted that neither the Mining Act nor the Mt Todd Project
Agreement Ratification Act 1993 (herein "the Ratification Act") expressly
provided that a Mineral Lease involved the grant of an ,,estate or interest in
land. I accept that. I note that the Ratification Act was a special Act which
ratified an Agreement between the Territory and a company for the
He submitted that exclusive possession of the land was a characteristic of a
proprietary right, citing R v Toohey; Ex parte Meneling Station Pty Ltd
[1982] HCA 69; (1982) 158 CLR 327 at 344, per Mason J. I note that his Honour said that
the issue did not take "the applicants very far, even if it be the case that
exclusive possession is very often a characteristic of a proprietary right."
Mr Gee submitted that neither ML1070, nor the Mining Act, nor the
Ratification Act gave the defendant exclusive possession of the land the
subject of ML1070. He submitted that the decision in Thiess Contractors
Pty Ltd v White Range Gold NL (1991) NTJ 1013 was distinguishable, on
this point. I note that that case involved applications to enforce liens over
two Mineral Leases. Martin CJ held that no monies had "accrued due"
within the meaning of s 5 of the Act, and that that was "enough to dispose of
the applications". However, his Honour went on to consider other points
which had been argued, including whether a Mineral Lease under the Mining
Act conferred an estate or interest in land. He considered at 1034 that "it
clearly does", noting the description and incidents of such Leases.
His Honour appears to have treated the fact that no other mining tenements
could be granted over the land the subject of the Mineral Leases, as vesting
in the lessee "exclusive possession of the land ... by virtue of the statute",
subject to the provisions in the Leases. Whether that be so or not, I do not
consider that a right to exclusive possession is one of the essential
characteristics of a proprietary right in land; see par [60].
Mr Gee noted that clause 7 of the Agreement ratified by the Ratification Act
preserved the power of the Territory under the Lands Acquisition Act
compulsorily to acquire the land the subject of ML1070. He submitted that
the preservation of this power caused ML1070 to lose its "degree of
permanence or stability". This phrase has significance in terms of
Lord Wilberforces classic description of the four essential characteristics of
a proprietary right, in National Provincial Bank Ltd v Ainsworth [1965] AC
"Before a right or an interest can be admitted into the category of
property, or of a right affecting property, it must be definable,
identifiable by third parties, capable in its nature of assumption by
third parties, and have some degree of permanence or stability."
I do not consider that the reservation by the Territory of its statutory power
of eminent domain has the effect for which Mr Gee contends, any more than
it can, for example, affect the "degree of permanence or stability" of an
estate in fee simple in land. I note further that Clause 7(2) of the
statutorily-ratified Agreement provides that apart from specified public
purposes set out in Clause 7(1), any compulsory acquisition for other public
purposes can only be effected by the Territory with the written consent of
the company, though the consent is not unreasonably to be withheld. This
puts the Lessee in a somewhat stronger position as regards the Territorys
power of eminent domain than that of the ordinary person holding, for
Mr Gee submitted that ML1070 was different from the usual mineral leases
granted under the Mining Act. The Ministers only function was to receive
the rent. The fee simple in the land was vested in the Jawoyn Association
Aboriginal Corporation or its nominee, so all that the Minister could do
under the Lease was to sell the minerals in the land. I consider that
examination of the Agreement, the Ratification Act and the Mining Act
under which ML1070 was granted, show that there is no substance in this
The submissions for the plaintiff Henry Walker Contracting Pty Ltd
Mr Maurice submitted as follows. ML1070 had a term of many years; the
Lessee had extensive rights under the Mining Act, including the power to
assign with the Ministers consent, under s 173. The Mining Lease was in
its legal nature a species of profit � prendre, in the sense that it conferred on
the Lessee a right to enter anothers land to take some portion of the soil.
Mr Maurice submitted that a profit � prendre was unquestionably an ,,interest
in land; he relied on R v Toohey; ex p. Meneling Station Pty Ltd (supra) at
341-4 per Mason J and at 351-4 per Wilson J. He also relied on the views of
Aickin J on this point in Stow v Mineral Holdings (Aust) Pty Ltd (1977) 51
"In my opinion the ordinary meaning of the compound expression
,,estate or interest in land is an estate or interest of a proprietary
nature in the land. This would include legal and equitable estates
and interests, for example, a freehold or a leasehold estate, or
incorporeal interests such as easements, profits � prendre, all such
interests being held by persons in their individual capacity."
I accept that a profit � prendre constitutes an "estate or interest in land" for
Mr Collins submitted as follows. The defendant was an ,,occupier of the
land under ML1070, for the purposes of s 5 of the Act; I note that that is
accepted. The authorities showed that the ordinary meaning of "estate or
interest in land" was an estate or interest of a proprietary nature in the land;
I accept that � see par[62]. Accordingly, the question was whether the
Lessees right to occupy the land was a mere personal right, or arose
because it had a proprietary right in the land. I accept that approach.
Mr Collins referred to the essentials of a proprietary right as set out by Lord
Wilberforce in par [60]; he posed as the ultimate question for answer
whether the defendants rights under its Lease under the Mining Act, taken
as a whole, are of a proprietary nature. He then referred to the extensive
rights spelled out in ss 60-69 of the Mining Act, dealing with the grant of
Mineral Leases. These include provision for the term not to exceed 25
years; and extensive rights of user (granted in the Lease), as set out in
ss 54(1), 60(1)(a)-(g), and in the other provisions of s 60. I note that the
nature of many of the rights of user granted under the Mining Act is such as
necessarily to imply a right in the Lessee to exclusive possession of parts of
the lease area. Section 61(3) provides for renewal of a Lease for up to 25
years, provided the lessee has complied with the provisions of the Act and
the conditions of his Lease. In this case, ML1070 is for a term of 25 years,
with a right to renew for a further term of 25 years; see Clause 4(6) of the
statutorily-ratified Agreement. The long term nature of the rights granted is
emphasized by Clause 8 of ML1070; the Lease cannot be cancelled; it may
be forfeited only in the limited circumstances set out in s 171 of the Mining
Act. No other mining tenements may be granted over the Lease area; see
Mr Collins supported Mr Maurices submission that the totality of the
Lessees legal rights in the land amounted to its having a profit � prendre in
the land; he cited in support In re Caveat of Gamboola Cabonne Phosphates
Ltd [1919] NSWStRp 38; (1919) 19 SR (NSW) 227 at 229-230, where an exclusive right to mine,
with other important rights of user, was held to confer an estate or interest
in the land; Ex p. Henry; re Commissioner of Stamp Duties (NSW) [1963]
NSWR 1079 at 1084-5, affirmed at [1964] HCA 4; (1963) 114 CLR 322 at 333, 337-8;
Mills v Stokman [1967] HCA 15; (1966) 116 CLR 61 at 71-2, 75, 77 and 79; and Unimin Pty
Ltd v The Commonwealth (1974) 22 FLR 299 at 306, 308.
In terms of Lord Wilberforces analysis at par [60], he submitted that the
lessee had assignable rights of a nature which gave them a considerable
,,degree of stability or permanence. See generally s 173 of the Mining Act,
As to Question (4) it is sufficient to say that I consider that the submissions
of Mr Maurice and Mr Collins are persuasive and must be upheld; they point
overwhelmingly to the Lessee of ML1070 having a proprietary interest in
the land the subject of that Mineral Lease, and hence as having an "estate or
an interest in land" for the purpose of s 5 of the Act. Accordingly, I would
I have had the advantage of reading a draft of the judgment of Kearney J
with which I generally agree. However I wish to add a few short
First, I note that the majority judgment in Longreef Pty Ltd v Leighton
Contractors (South Australia) Pty Ltd (1991) 160 LSJS 270 was delivered
by Olsson J with whom Mohr J agreed. I see no point of difference between
the majority judgment and that of King CJ on the question of the
construction to be given to the Act. With one minor reservation, I consider
that the passage in the judgment of King CJ set out in para 32 of Kearney Js
judgment most clearly sets out in a short and simple way what is the true
construction to be given to ss 5 and 10 of the Workmens Liens Act.
The reservation I have is the view of King CJ that the writ to enforce a lien
registered pursuant to s10(4) cannot be validly issued until the seven days
has run. His Honours view seems to be based on the consideration that
until the lien is available under s10(1) by both registration and the giving of
a valid notice under s10(2), the lien is not enforceable, and therefore any
action brought before the seven days has run would be premature: see
Marriot Enterprises Pty Ltd v Mercantile Credits Limited; Maesbury
Plumbers Pty Ltd (Intervenor) (1991) 160 LSJS 288, at 293. The
consequence of this line of reasoning is to create another trap for the unwary
which serves no useful purpose. As that point does not arise for
determination in this case and was not commented upon by Olsson J in
either Marriotts case or Longreefs case, I would prefer to reserve that
There is one other matter I feel I should mention. In relation to s10(4), the
same Court in Marriotts case (supra) held that the purpose of s10(4) was to
permit provisional registration of the notice of lien prior to the issue of a
formal notice of demand, so as to give notice of the claim and to protect the
position of the lienor during the seven day period envisaged by s10(4): (see
Olsson J at 310). King CJ expressed it thus, (at 160):
A lien may be registered pursuant to subsection (4) after the contract
price has become payable, although the seven days mentioned in
subsection (2) has not commenced to run, that is to say before the lien
is "available". Until the seven day period expires, the lien as it is not
available cannot be enforced, in my opinion, and does not operate as a
caveat pursuant to s12. It is true, as Zelling J pointed out in the Del
Fabro case at p 138, that a caveatable interest under the Real Property
Act must be an existing interest in land. That does not appear to me to
present a difficulty. This Act represents a departure from that rule and
allows the registered lien to operate as a caveat to protect the statutory
right which is inchoate as a lien until it becomes available under s10.
Except in one respect I agree with these observations; it must be
remembered that this Act may apply to both registered as well as
unregistered land. This supports the conclusions reached above. However, I
do not necessarily accept King CJs observation that such a lien does not
operate as a caveat under s12. That point is not touched on by Olsson J, and
does not have to be resolved in this case. I would prefer to leave that
As to the question of whether or not the mining lease is an estate or interest
in land, the definition of "estate" in s29 of the Interpretation Act supports
the conclusion that a profit � prendre is an estate in land within the meaning
of the Workmens Liens Act. That definition provides that ",,estate includes
any estate or interest, charge, right, title, claim, demand, lien or
encumbrance at law or in equity". I agree that a profit � prendre is also an
interest in land: R v Toohey; ex p. Meneling Station Pty Ltd (1982) 158 CLR
327 at 341 � 344; 351 � 354; Stow v Mineral Holdings (Aust) Pty Ltd (1997)
[1979] HCA 30; 51 ALJR 672 at 674. In my opinion the mining lease is clearly a profit �
prendre, and an estate and interest in land, and that this is so irrespective of
whether or not the lessee has exclusive occupation of the land for the
I would answer the questions in the manner proposed by Kearney J.
I have read in draft the opinion prepared by Kearney J. I agree with
his Honours proposed answers to the questions referred to this Court, and
I am in complete agreement with Kearney Js analysis of the issues and
(1985) 60 ALR 509
(1981) 35 ALR 151
(1982) 158 CLR 327
(1977) 51 ALJR 672
(1985) 60 ALR
509
(1990) 55 SASR
228
(1909) 9 CLR
693
(1977) 51
ALJR 672
(1963) 114 CLR 322
(1966) 116 CLR 61
(1974) 22 FLR 299
(1982) 158 CLR
59
(1997) 51 ALJR 672
(1990) 55 SASR 228
(1909) 9 CLR 693