in fee simple tends strongly against the view that after
the grant of a limited interest in possession land is no
longer 'vested'
in the Crown for the purposes of the
definition. In my opinion land subject to a Crown lease
in perpetuity may still be 'vested
in His Majesty'."
40. It is instructive to compare the definition of "Crown lands" in the
N.S.W. Act with the current Crown Lands
Act under which the defendant was
granted its Crown Lease. "Crown lands" is defined in s.5 of that Act as:-
"'Crown lands' means
all lands of the
Territory, including the bed of the sea within the
territorial limits of the Northern Territory, and
including
an estate in fee simple that is registered in
the name of the Territory, but does not include reserved
or dedicated lands;"
41. By way of contrast the definition of "Crown lands" in s.5 of The Crown
Lands Act 1888 (S.A.), the general Act regulating the
disposition of Crown
lands in South Australia at the time of the enactment of the Workmen's Liens
Act in 1893, so far as is relevant,
was as follows:-
"'Crown lands' shall mean and include all lands in
South Australia situated to the south of the twenty-sixth
parallel of south latitude, except -
I. Lands reserved for or dedicated to any public
purpose;
II. Lands lawfully
granted, or contracted to be
granted, in fee-simple by or on behalf of the Crown;
III. Lands subject to any lease or licence
lawfully granted by or on behalf of the Crown; ..."
42. The only difference between that definition and the corresponding
definition
in the preceding general Act in South Australia, the Crown Lands
Consolidation Act 1886, was the substitution of the words "the Crown"
for "Her
Majesty".
43. It will be noted that the Act of 1888 did not apply to what was then the
Northern Territory of South Australia.
The South Australian legislation which
regulated the general disposition of Crown lands in the Northern Territory of
South Australia
as at 1893 was The Northern Territory Crown Lands Act 1890.
Section 5 of that Act defined "Crown lands" in identical terms to that
in The
Crown Lands Act 1888.
44. Section 3 of the Crown Lands Ordinance of 1912 (Cwlth) had the following
definition, as far as
is relevant:-
"'Crown Lands' means all lands of the Crown in the
Northern Territory other than -
(a) reserved or dedicated
lands; or
(b) lands subject to any lease granted on behalf
of the Crown;"
45. It can be seen that the earlier South Australian
approach to the
exclusion of land held under Crown Lease was maintained. A significant change
of definition occurred in 1923 by
s.5 of the Crown Lands Ordinance of that
year:-
"'Crown Lands' means all lands of the
Crown in the Northern Territory other
than reserved
or dedicated lands;"
46. It will be noted that as from 1923 onwards lands the subject of Crown
Leases ceased to
be excluded from Crown lands. The present Crown Lands Act
was first introduced as an Ordinance in 1931 and contained the same definition
of "Crown lands" as the 1923 Ordinance. The definition was amended in 1956,
1970, 1978 and 1980 to reach its present expression;
it has never expressly
referred to lands subject to leases granted by the Crown.
47. It can be seen that the definition of "Crown
lands" in the general Crown
lands legislation of New South Wales and the Northern Territory are similar in
several respects; it is
clear that neither definition of "Crown lands" removes
land held under Crown lease from the category of Crown lands. This is clear
from the language used in s.5 of the Crown Lands Act, and is illustrated by
the specific exception of leased lands for the special
purposes of s.118(1) of
that Act, viz:-
"Any officer ... who has reason to believe that any
person is in unlawful occupation
of any Crown lands
(including reserved or dedicated lands but not including
any leased lands or lands occupied under licence
or
agreement), ... may make complaint before a Justice."
(underlining mine).
48. It can also be seen that the 19th century
South Australian general
legislation relating to Crown lands, applicable in South Australia and its
Northern Territory, and the post-1911
later Commonwealth legislation relating
to Northern Territory Crown lands (until 1923), adopted a diametrically
opposite approach
and treated land held under Crown Lease as removed from the
category of Crown lands. It follows that when the Workmen's Liens Act
came
into force in 1893 s.48 did not impose a barrier in South Australia (including
its Northern Territory) to the registration of
liens against lands held under
Crown leases granted under the Crown lands legislation. While that position
apparently still obtains
in South Australia, it appears not to have obtained
in the Territory since 1923.
49. I think it is clear that because of the way
"Crown lands" is defined in
s.5 of the Crown Lands Act, s.48 of the Workmen's Liens Act 1893 currently
prevents the creation of
any lien under that Act against a Crown Lease granted
under the Crown Lands Act, because land held under a Crown Lease remains "land
vested in Her Majesty". It follows that I uphold Mr Mildren's submission on
the first "leg" of s.48 which goes to all 7 proceedings.
I will accordingly
deal more briefly with the other submissions.
50. The second argument of the defendant based on s.48 turns on
the
prohibition therein of liens which would "change the liability of Her
Majesty". The meaning of this phrase was not argued; I
respectfully agree
with Chamberlain J. that its application is "somewhat obscure"; see Readymixed
Concrete (S.A.) Pty Ltd v Construction
Broken Hill Pty Ltd (1963) SASR 340 at
p 345.
51. Mr Mildren submitted that an application to enforce a lien registered on
the Crown Lease would result in an order
for the sale of the leasehold estate;
and this in turn would "change the liability of Her Majesty" in 2 ways.
52. First, the result
of the sale would be that the covenants of the lease
would be carried out by a new lessee. I do not see how that would change the
liability of the Crown.
53. Second, the Crown's liability would be changed because of the effect of a
sale on the provisions of
the Development Agreement of 17 November 1982,
compliance with which is a condition of the defendant's Crown Lease. I set out
earlier
the gist of some of the Agreement's main provisions. It provides for
the payment of substantial sums of public monies for the construction
of the
Performing Arts Centre on part of the land held under the Crown Lease.
Mr Mildren contended that the Agreement showed that
all of the improvements
constructed on Lot 5335 (or, alternatively, that part of the improvements
which constitutes the Performing
Arts Centre) belong to the Crown until an
estate in fee simple is granted; thus, in his submission, the sale of the
leasehold would
"change the liability of Her Majesty".
54. It is clear, I think, that the beneficial ownership of the Performing
Arts Centre is
in the Crown. I accept that s.48 prevents the registration of
a lien against so much of the land held under the defendant's Lease
as will
ultimately constitute the land held under a separate title by the Darwin City
Council. I do not think that the second "leg"
of s.48 prevents a lien being
lodged against the defendant's leasehold estate in the rest of the land
because I do not think that
such a lien affects the "liability of the Crown".
55. Mr Mildren's third submission, based on the third "leg" of s.48, is that
a
lien does not lie against the defendant's leasehold estate because it is
clear from the Development Agreement of 17 November 1982
that the defendant
procured work to be done on the Performing Arts Centre "for or on behalf of
the Government". The Government paid
for the work of constructing the
Performing Arts Centre. In terms of s.48, the submission is that a lien on
the Crown Lease would
"change the liability ... of (the defendant as a) person
procuring the performance of work for or on behalf of the Government".
Mr
Mildren submitted that the result was that no lien lay against the whole of
the land held under the Crown lease; alternatively,
if not against the whole,
against that part of it on which the Performing Arts Centre is erected. The
"liability" of the defendant,
it is said, extends to the provision of a
separate title to the Performing Arts Centre, to the grant of leases over the
carpark spaces,
and to the continuing supply of water for the air-conditioning
system of the Performing Arts Centre; and its "liability" in these
respects
stems from its procuring the performance of the work of constructing the
Performing Arts Centre for the Government.
56.
I referred on p 17 to Mr Newman's submission that the purpose of s.48 was
to provide the "shield of the Crown". I consider that
the purpose of this
"leg" of s.48 is to place beyond the reach of the Act a person procuring work
to be performed for the Government,
if the effect of enforcing the lien would
be to change the liability of that person to carry out his obligations to the
Government.
In this case the enforcement of the lien by sale of the leasehold
would render the defendant incapable of carrying out the obligations
to the
Government mentioned above. Its "liability" in respect thereof however
remains unchanged, despite a sale. The Crown's right
to secure the
performance of those obligations by any lessee under the Crown Lease is
untouched. The proviso - "except as between
the contractors, sub-contractors
and workmen" - applies to the third "leg" of s.48 (and only to that "leg").
For the purpose of the
argument on this "leg" the defendant is a contractor
(to the Government) and the plaintiff a sub-contractor. I see no reason why
the third "leg" of s.48 would prevent the application of the Act, and I would
reject Mr Mildren's submission on that aspect.
57.
I have dealt above with the arguments under s.48.
58. Mr Mildren submitted that in all of the proceedings other than Nos 690 of
1986 and 730 of 1986 there were deficiencies in the Statements of Claim in
that they did not clearly plead a cause of action. It
suffices to say that
the nature of the deficiencies alleged is such that I would not grant the
relief presently sought by the defendant,
if those deficiencies exist. It
would be appropriate, in my opinion, for the plaintiff to be granted leave to
amend its Statements
of Claim to meet any such deficiencies.
59. I now turn to the defendant's submissions which were directed only at
certain of the
proceedings.
Proceedings No. 436 of 1986
60. Mr Mildren submitted that the sum of $371,548 had "become due" within 28
days of 22
April, the date of issue of Progress Certificate No. 40A. The lien
was registered on 2 June, more than 28 days after the monies
had "become due".
Therefore, the submission went, the lien was not "available" because the
requirements of s.10(1) of the Act were
not met.
61. The submission was that monies can "become due" under s.10(1) of the
Workmen's Liens Act in ways other than those contemplated
by s.10(2).
62. I note that a notice of demand under s.10(2)(a) of the Act was given by
the plaintiff to the defendant on 2 June.
Mr Mildren submitted that as at 2
June the lien had ceased to be "available", and once that had happened it
could not be renewed.
63. Advanced Civil Engineering Pty Ltd v Wyara Pty Ltd(unreported judgment of
the Supreme Court, Asche J., 25 June 1986) is authority
for the proposition
that the provisions of s.10(1) of the Workmen's Liens Act are independent of
the provisions of s.10(2). His
Honour discussed the matter at pp 30-32 of the
judgment, noting that he differed in that respect from the views of Murray
C.J. in
Miller's Lime(supra) at p 314, which had been gravely doubted by Bray
C.J. in Albert del Fabbro Pty Ltd (supra) at p 127.
64. With
respect, I differ from the views of Asche J. in this respect. The
Workmen's Liens Act provides a special statutory remedy. I see
no reason why,
when a contractor seeks to avail himself of the remedy, a special regime
should not be contemplated by s.10 which
turns upon a specified date being
fixed as that on which, for the purposes of the legislation, the monies shall
be treated as having
become due. If s.10(1) is independent of s.10(2), it is
difficult to assign any meaning to the phrase "for the purposes of this
section" in s.10(1). On the other hand, if s.10(2) provides the means for
fixing the date on which monies "become due" for the purposes
of the Act, the
system of enforcement then instituted appears to accord better with what
business would require.
65. I note that
the learned author of "The Artificer's Lien", the late Mr
R.D. Elliott, also considers that the date on which the debt "becomes due"
is
an artificial point of time, for the purposes of the Act; see pp 95 and 96.
66. Taking this view, I note that the notice of demand
under s.10(2)(a) of
the Act was made on 2 June; so by virtue of ss 10(4) and 15 of the Act, the
lien was registered, and an action
for its enforcement brought within time. I
reject the defendant's argument on this ground.
67. If that view be wrong then it appears
from s.10(1) that the lien ceased
to be "available" 28 days after 22 April. What then would be the effect of the
notice of demand
of 2 June, under s.10(2)(a)? Mr Mildren submitted that it
had no effect at all, as the lien had gone and could not be renewed.
He
relied on Blythe Green and Jordain (Trading) Pty Ltd v Sienna Pty Ltd [1986] NTSC 14; (1986)
38 NTR 1. I respectfully agree with the view of Rice J. that once a lien
ceases it ceases forever. The question of the effect of s.10(2)
did not
however arise in that case. The plaintiff complied with the statutory
requirements of s.10(2)(a) on 2 June; if the words
of the statute are to be
given effect, the monies were then deemed to have become due on 9 June, and
that deeming took effect for
the purposes of s.10, including s.10(1). If so,
there may be a further period of 28 days from 9 June within which the lien
could
be registered, though s.10(4) permitted its registration on 2 June. The
question appears complex; it is unnecessary for me to express
an opinion on
it, and I refrain from doing so, as I do not accept the initial hypothesis.
Proceedings No. 690 of 1986
68. Mr Mildren
submitted that the lien was lodged prematurely. It will be
recalled that no Progress Certificate ever issued for the amount of
$26,800,668
for which on 28 August the plaintiff had claimed a Progress
Certificate. The notice of demand was made on 1 September, and a lien
was
registered on that date. The Progress Certificate which issued in response to
the plaintiff's claim of 28 August on 18 September
was for $114,161.
69. I consider that as at 1 September, the date of the notice of demand and
the registration of the lien, the
monies claimed were not due for the purposes
of the Workmen's Liens Act, because no Progress Certificate had issued. In
reaching
that opinion, I adopt with respect the views of Asche J. in Advanced
Civil Engineering Pty Ltd (supra) at pp 27-8 where his Honour
dealt with the
point arising under an identical contract, and considered that monies "became
due" on the date of issue of the Progress
Certificate.
70. Accordingly I accept Mr Mildren's submission that there was no lien in
existence on 1 September.
71. The claim
in the writ in relation to the lien referred only to a "sum ...
then due and payable under the contract", and not to any sum due
under a
quantum meruit. If a lien is to be claimed under a claim based on a quantum
meruit, the Statement of Claim may be amended
in due course.
Proceedings No. 730 of 1986
72. Mr Mildren submits that both of the liens should be cancelled. Lien No.
180977 for
$114,161 is said to be bad, because it comprises part of the sum
secured by the lien the subject of proceedings No.690 of 1986.
73.
I accept the views of Asche J. in Advanced Civil Engineering Pty Ltd
(supra) at pp 33-9, but I do not consider that their application
should result
in an order that Lien No. 180977 be cancelled.
74. As to Lien No. 181047 in the sum of $26,800,668 I think it is bad
for the
reasons earlier expressed.
75. I have borne in mind the need for caution in granting the relief sought,
on interlocutory
applications, referred to by Asche J. at pp 39-41 of Advanced
Civil Engineering Pty Ltd (supra), but am persuaded to deal with the
matter
for the same reasons as his Honour found persuasive
Orders made on 7 October 1986
(1) In proceedings 436 465, 540 and 622
of 1986, the
relief sought in paras 1 to 5 of the respective Interlocutory Summonses filed
by the defendant on 22 September 1986
in each of these proceedings is
granted.
(2) In proceedings 690 of 1986 the relief sought in
paras 2 to 5 of the Interlocutory
Summons filed by the defendant on 22
September 1986, is granted. Paragraph (b) of the Indorsement of Claim is
struck out.
(3)
In proceedings 699 of 1986 the relief sought in
paras 1 to 5 of the Interlocutory Summons filed by the defendant on 25
September
1986, is granted.
(4) In proceedings 730 of 1986 the relief sought in
paras 1 to 5 of the Originating Summons filed by the defendant
on 29 September
1986, is granted.